You are on page 1of 14

Employers’ Claims and Remedies

James Bremen and Mark Grasso


Quinn Emanuel Urquhart & Sullivan LLP

19 October 2021

Print article

This is an Insight article, written by a selected partner as part of GAR's co-


published content. Read more on Insight
Introduction
The majority of construction disputes proceeding to arbitration are commenced
by contractors. This is not to suggest that it is only contractors that have claims
on most projects, as that is clearly not the case. It goes without saying that
employers have interests in the projects they are commissioning, in particular,
the interest in having their project delivered on time, on budget and in
accordance with the contractual specifications. The main difference between a
contractor’s position and that of an employer that causes a contractor to refer its
claims to arbitration first is that, generally speaking, a contractor will feel financial
pressure earlier than an employer in the form of non-payment of sums to which it
considers it is entitled, and will turn to arbitration in order to recover such sums.

Nevertheless, employers often bring claims against contractors, sometimes as


claimant, but more often by way of counterclaim after an arbitration has been
commenced against them by a contractor. This chapter begins by considering
the range of claims employers most frequently pursue in arbitration, which
revolve around four issues:

 the time for delivery of a project;


 the quality of what is being delivered;
 termination; and
 payment
Other matters in respect of which an employer might, in theory, have a claim
against a contractor are then briefly addressed.
Claims concerning the time for completion
In almost every construction contract, even for a simple project, there will be a
specified date by which the project must be completed. On larger and more
complex projects, the work may be divided into milestones and the contractor
may be required to complete each milestone by the associated ‘milestone date’
specified in the contract. There may also be additional milestones and milestone
dates for matters, such as testing and commissioning and handover of the whole
project.

However, even if a contract specifies a completion date or one or more milestone


dates, the question arises as to the nature of the remedies available to the
employer if the contractor fails to complete part or all of the work by the
associated milestone or completion date. As a matter of principle, the employer
would have a claim against the contractor for damages for breach of contract.
However, it is then necessary to consider the damage that it will have suffered as
a result of the delay to the project, or part thereof, and how such delay can be
quantified.

Consider the case of a construction project where the first milestone is the
completion and approval of the design for the project. If the design is not
completed or approved by the milestone date specified in the contract, has the
employer suffered any loss? In most cases, the answer will probably be no. Even
in a scenario where delay has occurred to a milestone that is capable of being
used on its own (e.g., part of a shopping centre) or to a project as a whole (e.g.,
a new road), the monetary loss to an employer as a result of delay may be a
relatively small sum or may be very difficult to quantify.

In light of this, the usual practice is for construction contracts to provide that the
contractor will be liable for liquidated damages (that is, damages in a fixed
monetary amount) for each day or some other period for which it is late in
completing a milestone or the project as a whole. If the project has been divided
into milestones, there may be different liquidated damages rates for each
milestone. The liquidated damages payable in respect of each milestone and the
project as a whole will also probably be capped.

An example of a liquidated damages provision is Clause 8.8 of the FIDIC Silver


Book, which provides that:

If the Contractor fails to comply with Sub-Clause 8.2 [Time for Completion], the
Employer shall be entitled subject to Sub-Clause 20.2 [Claims For Payment
and/or EOT] to payment of Delay Damages by the Contractor for this default.
Delay Damages shall be the amount stated in the Contract Data, which shall be
paid for every day which shall elapse between the relevant Time for Completion
and the relevant Date of Completion of the Works or Section. The total amount
due under this Sub-Clause shall not exceed the maximum amount of Delay
Damages (if any) stated in the Contract Data.

Clause 8.8 goes on to provide that liquidated damages are the employer’s sole
remedy for delay on the part of the contractor. Provisions of this nature are also
commonly found in construction contracts containing liquidated damages
provisions.

As is also illustrated by Clause 8.8, most liquidated damages provisions provide,


in effect, that the contractor is, prima facie, liable to pay the employer liquidated
damages for all delays in completing the project (up to the value of any caps). In
other words, the employer is not required to establish that the contractor is at
fault before being entitled to recover liquidated damages. Put another way, in an
arbitration, an employer’s claim for liquidated damages would, at least in the first
instance, simply be a mathematical calculation of the number of days (or other
period for calculating liquidated damages) from the scheduled milestone or
completion date to the date on which the milestone or completion was actually
achieved multiplied by the applicable liquidated damages rate.

However, the fact that liquidated damages provisions prima facie make
contractors liable for delay, however caused, gives rise to two questions: first,
how does the contractor obtain relief from this liability for liquidated damages
when it has not been responsible for the delay to the project; and second, what
are the legal implications of a clause that provides that the contractor is liable for
liquidated damages even if the employer is at fault?

In relation to the first question, a contractor would be extremely unlikely to sign


up to a contract that would make it contractually responsible for all delays, even
delays outside its control. While there may be some risks that a contractor is
prepared to accept (e.g., risks associated with bad weather), most contractors
would refuse to assume responsibility for force majeure events and delay events
caused by the employer’s acts or omissions. For these reasons, most
construction contracts contain terms that provide that the contractor will be
entitled to an extension of a milestone date or the completion date if it
establishes that it has been delayed in achieving the milestone or completion of
the project by certain events. In the FIDIC Silver Book, such a provision is found
in Clause 8.5.

Claims concerning extensions of time in construction arbitrations can be very


complex. In most jurisdictions, the contractor carries the burden of establishing
that it is entitled to an extension of time and associated relief from the employer’s
claim for liquidated damages – that is, that the project was delayed by matters
that the construction contract specifies are the employer’s responsibility. Strictly
speaking, an employer is not obliged to positively demonstrate that the contractor
was the cause of delay in order to be able to recover liquidated damages.
However, when faced with a claim by a contractor for an extension of time, many
employers will proceed to seek to do so as it is the best means of defeating the
contractor’s claim for an extension of time.

In relation to the second question noted above, the risk associated with a
liquidated damages clause that does not provide relief for the contractor when
the employer is at fault is that, if the employer causes delay to the project, the
employer will not be permitted, under the law governing the contract, to hold the
contractor to the contractually agreed milestone dates or completion date as it
has prevented the contractor from achieving them. Under English law, the
principle is known as the ‘prevention principle’. Similar principles exist in most
legal systems. If the prevention principle (or equivalent principle) applies because
an employer has caused a contractor delay in achieving a milestone or project
completion, the consequence generally is that time will be ‘at large’. The effects
of time being at large are that the contractor is no longer obliged to complete the
milestones or the project by the associated milestone dates or completion date,
but only in a reasonable time, and that the employer will no longer be able to
claim liquidated damages if the milestone dates or completion date are not met.
In theory, an employer might still have a claim for general damages if the
contractor does not achieve a milestone or completion within a reasonable time,
but, as discussed above, the employer is likely to have difficulty in establishing or
quantifying its actual losses in such circumstances. However, the risk of the
prevention principle coming into play is limited if a contract provides that a
contractor is entitled to an extension of time and associated relief from the
employer’s claim for liquidated damages for matters for which the employer is
responsible. Liquidated damages clauses that provide no relief when the
employer is responsible for delay are extremely rare.

Nevertheless, because of the potential advantage of time being set at large,


contractors often attempt to argue that time is at large because of alleged failures
on the part of the employer in awarding extensions of time as and when they are
due as a project is progressing. However, the mere failure to administer an
extension of time clause is generally insufficient to set time at large, and
arguments by contractors based on any such failings causing time to be at large
almost inevitably fail.

In summary, where there has been delay to a construction project, an employer


will generally have a claim against the contractor for liquidated damages. Such a
claim is likely to form a significant part of any claims that an employer brings
against a contractor in a construction arbitration. However, any such claim will
almost certainly be met with a counterclaim by a contractor for an extension of
time, and the employer will need to be prepared to meet the contractor’s
counterclaim with evidence showing why the employer is not contractually
responsible for the delay. An employer may also want to lead evidence
demonstrating that the contractor has caused the delay, although this may not be
necessary if the contract provides that the contractor is only entitled to an
extension of time in specific circumstances (as is generally the case) as in such
circumstances the contractor is prima facie responsible for all delay, and the
employer would only obliged to prove that it has no responsibility for any delay.

Assuming that a contractor’s claim for an extension of time has failed in whole or
in part and the contractor is contractually liable for liquidated damages, it is often
thought that in some civil law jurisdictions, the contractor will not be liable for
liquidated damages if the employer has suffered no loss as a result of the
contractor’s delays or its actual losses are less than the value of the liquidated
damages that would be payable under the contract. However, such arguments
are based on a misunderstanding of the treatment of liquidated damages clauses
under civil law systems. The circumstances in which contractors are able to
persuade arbitral tribunals to exercise any power to reduce the contractually
agreed amount of liquidated damages are, in practice, extremely rare.

Finally, it is also worth noting that many construction contracts provide that if a
contractor has not been proceeding with the works with reasonable diligence or
some other measure required by the contract, or is otherwise in delay, the
employer may instruct the contractor to accelerate the works or take other steps
to recover the delay. In practice, however, employers are generally hesitant
about exercising such powers as there is a risk that, if the contractor is
subsequently found not to have been in breach of contract or not responsible for
the delay, the employer’s instruction would be found to amount to a variation and
the employer would then be liable to the contractor for the additional costs of the
acceleration or other steps it has directed.

Claims concerning the quality of the works


Under most construction contracts, the contractor’s primary obligation is to
deliver the project in accordance with the employer’s specifications by a specified
date. On a strict reading of such contracts, it might be argued that the quality of
the works as they are being undertaken is irrelevant, as all that matters is that,
when the project is handed over to the employer, everything is in accordance
with the contractual specifications. This gives rise to a question as to whether
there can be defects in a contractor’s works prior to handover. This question has
been debated by commentators in several jurisdictions, and the legal position is,
perhaps surprisingly, generally unclear.

From a practical perspective, it would be unsatisfactory to an employer if, in


circumstances in which it has observed a deficiency in the manner in which the
contractor is carrying out the works or has identified a serious defect in part of
the works, it has no remedy against the contractor until handover. In order to
overcome this in circumstances where it may be unclear whether the employer
would have a legal remedy against the contractor prior to completion, many
construction contracts contain provisions that entitle the employer to inspect the
works as they are proceeding (e.g., Clause 7.3 of the FIDIC Silver Book) and to
issue a notice to the contractor prior to completion requiring the contractor to
remedy a deficiency in the works (e.g., Clauses 7.5 and 7.6 of the FIDIC Silver
Book). Clause 7.6 of the FIDIC Silver Book provides that, should the contractor
fail to remedy the work following such a notice from the employer, the employer
may instruct others to remedy the work at the contractor’s cost.

In addition, the generally worded Clause 15.1 of the FIDIC Silver Book provides
that:

If the Contractor fails to carry out any obligation under the Contract the Employer
may, by giving a Notice to the Contractor, require the Contractor to make good
the failure and to remedy it within a specified time (‘Notice to Correct’ in these
Conditions).

This has the potential to be a powerful remedy for an employer while construction
works are progressing. However, it needs to be accompanied by a provision
expressly giving the employer a remedy if the contractor does not comply with
the employer’s notice as the employer may not otherwise have a claim against
the contractor in such circumstances, particularly if the contractor’s failure to
comply with the notice does not cause the employer any immediate financial
loss.
The employer may also have a right to withhold a portion of the payments
otherwise due to the contractor until the deficiency in the work is rectified, even
before the project is complete. In such circumstances, the amount that the
employer will be entitled to withhold will generally be limited to the cost of
rectifying the defect (see, e.g., Clause 14.6 of the FIDIC Silver Book).

Insofar as the quality of the works at completion is concerned, construction


contracts for large projects will generally contain a structured regime concerning
completion and handover of a project.

Typically, when the contractor considers that it has completed (or, if applicable,
substantially completed) the works:

 the contractor issues a written notice to that effect (under the FIDIC Red Book,
this notice is to be issued to the engineer appointed by the employer);
 the works are inspected (by the engineer, in the case of a project governed by
the FIDIC Red Book);
 if the works are complete (or substantially complete as the case may be), a
Taking-Over Certificate is issued (again, this is the responsibility of the
engineer under the FIDIC Red Book); and
 if not, the contractor is notified (by the engineer, under the FIDIC Red Book) of
the works it must complete or correct before the Taking-Over Certificate can
be issued (see, e.g., Clause 10.1 of the FIDIC Red Book).
Similar mechanisms are found in other standard form contracts.

Pursuant to Clause 10.1 of the FIDIC Red Book, the Taking-Over Certificate may
identify minor aspects of the work that are outstanding or need to be corrected by
the contractor, although they do not affect the handing over of the project to the
employer. In such circumstances, the contractor will generally be required to
complete all snagging items and remedy any outstanding defects at its own cost
within a specified period of time, known as the defects liability period, after
completion (see Clause 11 of the FIDIC Red Book). Should any other defects be
identified during that period, the contractor will also be obliged to remedy them by
the end of the defects liability period.
The rectification of defects during the defects liability period is the contractor’s
right. Unless the contract specifically provides to the contrary, where a contract
provides for a defects liability period, the employer is unlikely to have any right to
sue the contractor for damages for breach of contract until the end of this period,
unless the contractor has failed to carry out any rectification work it is required to
carry out during the defects liability period within a reasonable time. If a contract
does not provide for a defects liability period, or if defects remain unremedied or
other works remain incomplete within a reasonable time of them being identified
during the defects liability period or, in the worst case, at the end of the defects
liability period, or if the employer subsequently identifies further defects, the
employer will have a claim against the contractor for breach of contract. The
measure of damages recoverable by the employer will be the costs of rectifying
the defects.

Depending upon the number and complexity of defects on a project after


completion and the costs of rectifying them, a defects claim may not be so
significant as to warrant an employer commencing an arbitration against a
contractor bearing in mind the costs of arbitration. Of course, there will be
exceptions to this. In any event, a defects claim is likely to form a reasonably
substantial part of an employer’s counterclaim if an arbitration is commenced
against it by a contractor.

In order to succeed in a defects claim, the employer will need to identify the
relevant contractual specification (which may be a specification relating to the
particular works in question, a specification concerning the quality of the works
generally or a general fitness for purpose warranty), the reasons why the
contractor’s works fail to meet the specification and the costs of rectifying the
defect. An employer is not limited to recovering the costs of rectifying the defect
in the cheapest manner possible, but would be expected to act reasonably in
engaging a third party to undertake the rectification works.

Termination
The most powerful remedy that an employer has against a contractor is the right
to terminate its contract, particularly when the contractor is in default.

An employer will always be well advised to check carefully that it is contractually


and legally entitled to terminate a contract before doing so, and that it complies
with any notice or other procedures set out in the contract before serving a
termination notice. The consequences of a wrongful termination of a contract can
be serious and can expose the employer to a substantial claim for damages from
the contractor, extending to the profit that it claims to have lost as a result of the
wrongful termination. In addition, from a practical perspective, termination of a
partially completed project may cause disruption to the overall completion of the
project, bearing in mind the time required to identify and engage a replacement
contractor, and will almost inevitably lead to increased costs because a
contractor will charge a premium for taking over a project and accepting liability
for another contractor’s partially completed works (although the additional costs
of completing should be recoverable from the original contractor if it was properly
terminated for default).

At the same time, termination is a remedy that is perhaps considered too


infrequently by employers. Although it may appear surprising, many construction
contracts, even contracts for large projects, provide the employer with broad
scope to terminate the contract for any default on the part of the contractor. If a
contract provides that it may be terminated for any default, such a provision
should be given effect by an arbitral tribunal. Even in jurisdictions in which the
parties may be obliged to carry out their contractual obligations in good faith,
there is no reason why a clause permitting termination for any default should not
be construed according to the ordinary meaning of the words used in the clause
so long as the employer is not acting maliciously or capriciously in exercising its
termination right.

Contracts based on standard forms, however, may not be so favourable to the


employer. For example, the FIDIC series of contracts effectively requires the
contractor to be in serious breach of the contract before the employer will be
entitled to terminate their contract. Nevertheless, the proof required to satisfy the
termination provisions of such contracts is not insurmountable. Depending upon
the precise wording used in the termination provision, multiple breaches of a
smaller scale may together amount to a serious breach justifying termination.

If it validly terminates a contract for default on the part of its contractor, an


employer will generally be entitled to recover from the contractor the additional
costs of completing the contract with another contractor (that is, the costs over
and above those it would have incurred if the original contractor had completed
the project in accordance with its contractual obligations), which are likely to be
substantial, plus any other amounts it would have been entitled to irrespective of
the termination, such as liquidated damages for the delays that had occurred up
to the time of termination.

However, termination will have a significant financial impact upon a contractor. If


an employer does not promptly commence an arbitration against a contractor
following termination, the employer is likely to find that the aggrieved contractor
will institute arbitral proceedings very shortly after termination. In either case, the
employer will bear the burden of establishing that the termination was valid under
the contract. In some jurisdictions, local law may impose additional preconditions
to termination, which must also be satisfied if the termination is to be upheld by
an arbitral tribunal.

Another remedy available to employers, which has some conceptual overlap with
termination, is descoping – that is, removing part of the original scope of works
from the contractor. The wording of variation provisions in most contracts will
permit an employer to add to or omit from the contractor’s scope of works,
effectively at its discretion. On the face of such provisions, it may appear that an
employer would have the right to omit substantial portions of the contractor’s
works for any reason (e.g., if the employer is dissatisfied with the contractor’s
performance generally). However, this may be prohibited by the express terms of
the variation provisions. Even if it is not, most legal systems limit the ability of an
employer to make substantial omissions from a contractor’s scope of works. In
common law systems, it is generally held that an employer cannot take work from
the original contractor in order to give it to another contractor unless the variation
provision of the original contract permits the employer to do so. In some civil law
jurisdictions, particularly those in the Middle East, local law prevents government
employers from changing a contractor’s scope of works by more than 10 per cent
without retendering the works. In practice, this has the effect of preventing a
government employer from reducing the contractor’s scope of works by more
than 10 per cent.

Payment
As noted earlier, an employer will be concerned to see that its project is delivered
on budget. Disputes about price often arise as a result of claims made by
contractors for additional payment, as considered in Chapter 4. Insofar as such
claims are concerned, the employer will generally be the respondent – that is, it
will be defending claims made by the contractor and arguing that the contractor is
not entitled to the extra costs it is claiming.

Leaving contractors’ claims aside, an employer will otherwise generally be


required to pay the contractor pursuant to the contract as the contractor is
carrying out its works in accordance with the terms of the contract. There are
three main exceptions to this. First, an employer may be entitled to withhold
amounts claimed by the contractor where the corresponding work has not been
completed or has not been carried out in accordance with the contract. Second,
many contracts will provide that the employer is entitled to retain a percentage of
all payments (usually around 5 per cent) until the project is complete, at which
point it must return half of this retention, and that it may continue to hold the
remainder of the retention until the defects liability period has come to an end
and all outstanding works have been rectified, at which point the remainder of the
retention must be paid to the contractor (see, e.g., Clause 14.9 of the FIDIC Red
Book). Third, the employer will generally be entitled to set off amounts it is owed
by the contractor against payments it would otherwise be required to make to the
contractor. If a project is in delay and the contractor has a substantial liability to
the employer for liquidated damages, this can significantly reduce the net
amounts actually payable by the employer to the contractor. Set-off provisions
are therefore a powerful remedy available to employers.
Other potential claims and remedies
The difficulties that an employer will often face in establishing that it has suffered
actual losses as a result of delay to a project have been discussed above. The
same difficulties may arise in other circumstances as well. Consider the scenario
where a contractor abandons a project and removes all of its staff and perhaps
even materials and equipment the employer has paid for from the site. The loss
and damage to an employer in such a scenario is likely to be viewed by a court
or arbitral tribunal as (at best) purely economic such that the employer will have
virtually no prospects of obtaining an order for specific performance or the like
requiring the contractor to resume the works, even if the contractor is in serious
default. For this reason, it is uncommon for employers to obtain injunctive relief in
connection with construction projects where the dispute relates to time, quality of
the works or money.

A contractor’s breach of other provisions may also leave an employer without any
practical remedy. For example, if a contractor fails to employ a specific
subcontractor or key personnel named in the contract or identified by the
employer, or if it does not make project documents available when an employer
exercises its audit rights, the employer is unlikely to be able to do anything about
this. A claim against the contractor for damages for breach of contract will fail
unless the employer is able to identify a quantifiable financial loss from the
contractor’s breach.

The final remedy potentially available to an employer that is worth noting is an


employer’s right to call on the bank guarantees or other forms of security that a
contractor will often be required to provide, particularly on larger projects.
Although the practice of providing such security has been questioned by some
commentators, it is not uncommon for contractors to be required to provide a
bank guarantee, bond or similar security for somewhere between 10 per cent and
20 per cent of the contract price at the beginning of a project. The provision of
such security may be as a quid pro quo for the employer making an advance
payment of a corresponding amount to the contractor. However, the terms of the
construction contract or the security may permit the employer to call on the
security if the contractor is in default. In addition, or alternatively, a contractor
may be required to post a bond as a form of security against its performance of
the contract. The value of such bonds is generally also between 10 per cent and
20 per cent of the contract price.

In some contracts, particularly government contracts in the Middle East, an


employer has an absolute right to call on the full amount of the contractor’s
securities on demand and for any default, and without proving that the contractor
is in default. In other jurisdictions, the employer’s right may be limited to making a
call for an amount equivalent to the cost of remedying the contractor’s default
and after the employer has established that the contractor is in default (e.g., by
way of a court judgment or arbitral award). In any case, it is important for
employers to bear in mind that the right to call on a contractor’s security is not a
right to obtain extra compensation from the contractor even if the contractor is in
default. The employer will ultimately need to account for the amount it has
recovered from calling on a contractor’s security in any subsequent arbitration
and establish that it has suffered losses equal to or exceeding the amount
recovered, otherwise it will have to return the excess part of the proceeds of
calling on the contractor’s security.

You might also like