Stop type

Fatal
Flash Report of Accident
D
(Fatal)
Case : Contractors go up to work at high places. Replace the pipes on the roof that are deteriorating But he fell to the bottom and died.
Location : On the roof of the factory Date & Time : January 28, 2023 at about 11:45 Injury Level : Death

Detail of accident Factors


1. The documents necessary for the implementation of the work were not
The ducts on the roof had deteriorated and were about to be submitted to the construction planning department, and the work was
replaced. The victim and worker A were carrying a replacement duct performed without a construction permit.
(approx. 10 kg) on the roof. When they reached the duct to be 2. He was wearing a fall prevention device, but he did not hang a hook on to
replaced, the victim was left to carry the rest of the duct, and worker A the main rope and did not use foot boards.
took a break. When the victim was carrying the duct, he collapsed
through the roof and crashed to the factory floor. Countermeasure
1. The construction work is to be carried out only after the necessary
procedures and after a safe work plan has been established
2. Always take measures to prevent falls when working at height.

Essence : Failure to comply with standards for working at heights

Yokoten point :
1. There is a request for work permit before working at high place ?
2. Do you have point check in Work permit working high place as detail below?
2.1 Seat belts are in ready-to-use condition.
2.2 There is a clear, strong and safe way up and down.
2.3 Scaffolding / stairs / X-lift / Boom lift / scissor lift etc. on safety standards.
2.4 There is a clear boundary / safety net to prevent falling / a life-saving rope is installed.
2.5 The weather is not windy or rainy.