Museum Expansion - Langley Graham
Museum Expansion - Langley Graham
Both the Store and the Lecture hall will be entirely completed within 66 days. Between the two, they account for 32
workers are now untasked. These resources could now be utilized to contribute to the overtime (64hrs) necessary to
(712). By incentivizing the over at 1.5x normal hourly, the contractors may be motivated to complete the overtime.
there are no dependencies that conflict with the workers scheduling, and assuming the workers can complete the w
hours of overtime.
Museum Expansion Project
30 million budget & additional 3 million for expedite
10 laborers & 25 contractors
81 days - 15 days 66
Original Budget
30,000,000.00
33,000,000.00
Hours
8
10
12
HRs
8
11
14
9.5
Makeup 64hrs
81 days (648 HR)
43
38
81
81
81
30,000,000.00 337078.65169
33,000,000.00
Hours
8 712
10 890
12 1068
HRs
8 337078.65169
9 400280.89888
10 463483.14607
9 400280.89888
89 Days 88 Days 81
340909.09091 370370.37037
704 648
880 810
1056 972
42613.636364 46296.296296
340909.09091 370370.37037
404829.54545 439814.81481
468750 509259.25926
404829.54545 439814.81481
63920.454545 69444.444444
15
17
32
63202.24719101
89 HR 81 88
27303370.78652 648 30000000 27613636.36
4044943.820225 64 4444444.4444 4090909.091
31348314.60674 712 34444444.444 31704545.45
1,651,685.39 -1,444,444.44 1,295,454.55
te the times taken with a weighted average, we immediately reduce the Critical Path by 1 day due
estimate on Activity 17 being 9 days instead of 10. Now, If we utilize the cost per hour of work
al, or original corrected critical path, we can find if we meet the financial constraint of
e or not. If we take the original baseline of 89 days and multiply that with an assumption of 8
er day, we receive 712 hrs of total work. By taking the baseline schedule for HOURS(712) and then
total amout of hours available in the 81 day compression(648), you know how many hours you'd
o the schedule (64) to equal the 89 days total of 712. Utilize the 89 Day Critical Path cost per day
the most up to date information we can work from for cost. Now we can utilize a cost per hour
or 712 hours of work to find out the additional cost for the 64 hours of overtime and complete an
ere our overall 33 Million budget will be at based on the total costs per hour type. Now we know
nder budget within time but it comes down to scheduling constraints of the workers.