Field Inspection and Test Plan For Civil Work (ITP CIVIL WORK)
Field Inspection and Test Plan For Civil Work (ITP CIVIL WORK)
: REV
CONTRACTOR OF :
PT. CIPTA BANGUN NUSANTARA 20000312-OS-10103 B
DOC. NO. :
RESPONSIBILITY
LEVEL OF
METHOD OF VERIFYING
No. INSPECTION ACTIVITY/TEST ITEM ACCEPTANCE / REMARKS
INSPECTION DOCUMENT CBN SERD
REFERENCE
1. EARTH WORKS
1.1. SURVEY
(1) Survey Tools and Equipment Review/Visual Calibration Certificate Valid Certificate R R
FI-S.0.01, FI-S.0.02,
Bench Marks (BM), Coordinates and Elevation, Marking and
(2) Dimension & Survey IFC Drawing FI-S.0.03, FI-S.0.04 W SW
Stake Out, Location, number, stability and protection
1.2 EXCAVATION
A. Preparation
(2) Set out location, based on IFC drawing and endorsed Bench mark Survey IFC Drawing FI-C-0.01 W SW
B. Excavation Work
(1) Depth and width of excavation Survey IFC Drawing FI-C-0.01 W SW
Line, Slope and Grades according to approved drawing
(2) Survey IFC Drawing FI-C-0.01 W SW
1.3. BACKFILL
A. Preparation
(3) Clearing & grubbing before filing Visual Engineering Spec. FI-C-0.03 W R
B. Placement of Backfill
(1) Cleaning (removal of trash debris, etc.) in soil Visual Engineering Spec. FI-C-0.03 W SW
(2) Sand filling around underground pipe and cable (if any) Visual Engineering Spec. FI-C-0.03 W SW
(4) Uniformly in layers depth for soil backfill Visual Engineering Spec. FI-C-0.03 W SW
(5) Fill shall be Spreading Thickness per Layer and compacted Dimension Engineering Spec. FI-C-0.03 W SW
(8) Retaining Wall / Slope Protection Dimension Engineering Spec. FI-C-0.03, FI-S.0.02 W SW
C. Testing / Monitoring
(1) Compaction test by Field Dencity Test (Sand Cone) Test ASTM D1556 FI-C.0.04 W SW
(2) Compaction test by for Sand gravel by DCP or CBR Test ASTM D4429 FI-C.0.02 W SW
2 FOUNDATION
A. Preparation
Method Statement
(1) Construction method Review Work Method Statement R R
Approval
B. Bored Pile
(1) Location and numbering the drill point Visual IFC Drawing FI-S.0.03 W SW
FI-C.2.04, FI-C.2.05,
(8) Pouring Concrete Visual Engineering Spec. W SW
FI-C.1.04
(10) Cut off Bored Pile Head Visual Engineering Spec. FI-C.1.04 W SW
Verification Checklist
(11) Bored pile -construction verification checklist Visual Engineering Spec. W SW
Report
(12) Bored Pile - Drilling Log Visual Engineering Spec. Drilling Log Report W SW
C. Test
Method Statement
(1) PDA Test Engineering Spec. Approval, FI-C.1.03, W W
S/C Inspection report,
2.2. GROUTING
A. Preparation
(1)
Method Statement
Construction method Review Work Method Statement R R
Approval
B. Installation FI-C.3.01
(1) Mixing & Placing Visual Engineering Spec. FI-C.3.01 W SW
Visual, Dimension,
(4) Dimension, alignment & stability of form work Engineering Spec. FI-C.3.01 W SW
Survey
(5) Top elevation of form work Dimension, Survey Engineering Spec. FI-C.3.01 W SW
(9) Ensure that sleeves around anchor bolt are complete Visual IFC Drawing FI-C.3.01 W SW
(10) Check that shim / wedgewhich are fix Visual IFC Drawing FI-C.3.01 W SW
(2) Material (conformity to specification and drawing) Visual, Test,Review Engineering Spec. FI-C.5.02 W SW
(3) Checking of existing sub-grade bearing capacity Visual Engineering Spec. FI-C.5.02 W SW
B. Installation FI-C.5.02
Visual, Dimension,
(5) Location , dimension, Elevation, as per drawing IFC Drawing FI-C.5.02 W SW
Survey
(6) Finishing Visual Engineering Spec. FI-C.5.02 W SW
Method Statement
(1) Construction method Visual Work Method Statement R R
Approval
(2)
Cement type, quality and compliance with applicable standard Review Engineering Spec. FI-CM.0.01 W SW
b) Specific Gravity Test of Aggregates Test, Review ASTM C 127 Laboratorium test W SW
c) Mud Test of Aggregates Test, Review ASTM C 127 Laboratorium test W SW
(4) Mortar finishing (level, chamber, crack, mortar proportion, etc.) Visual Engineering Spec. FI-C.2.02 W SW
(5) Dimensional inspection for completed casting Dimension Engineering Spec. FI-S.0.01, FI-S.0.02 W SW
3.2. FORMWORK
A. Preparation
(1) Quality and shape of material Visual Engineering Spec. FI-C.2.02 W SW
B. Installation
(1) Location, dimension, alignment, plumb and elevation Dimension, Waterpass IFC Drawing FI-C.2.02 W SW
(2) Compliance of material with standard Visual & Dimension, Engineering Spec. FI-CM.0.01 W SW
(3) Handling and storing Mill Cert.
Visual Engineering Spec. None W SW
(4) Workmanship in cold bending operation Visual Engineering Spec. None W SW
(5) Surface cleaning (to be free from mud, dirt, grease, loose mill, Visual Engineering Spec. FI-C-2.03 W SW
B. scale, etc.)
Installation
IFC Drawing / Barbending
(1) Location, shape, sizes, numbers, cleaning and spacing of bars Visual & Dimension FI-C-2.03 W SW
Schedule
(5) Length and Location of Development Visual & Dimension Engineering Spec. FI-C.2.02 W SW
(6) Final inspection for rebar arrangement (Pre-pouring) Visual & Dimension Engineering Spec. FI-C.2.02 W SW
(1) Material (conformity to specification and drawing) Visual Engineering Spec. FI-C.5.01 W SW
B. Installation
(2) Location , dimension, Elevation, as per drawing Visual & Dimensional IFC Drawing FI-C.5.01 W SW
(3) Finishing Visual Engineering Spec. FI-C.5.01 W W
(4) Engineering Spec. / IFC W SW
Subgrade and or foundation Visual FI-C.5.01
Drawing