You are on page 1of 1

Project No: Rev

Doc. No:
PRPD CHKD APVD
Date:

FIELD INSPECTION AND TEST PLAN FOR PIPING WORK


RESPONSIBILITY
METHOD OF LEVEL OF ACCEPTANCE /
No. INSPECTION ACTIVITY VERIVICATION RECORD Remarks
INSPECTION REFERENCE Contractor Owner

1 Painting Over Concrete


1.1 Paiting Material
a. Batch / RAL / Expired Date Painting Material Specification FI-CM-01 RP,W SW
visual & review
Painting Material Specification FI-CM-01 RP,W W
b. Quantity / Quality Inspection visual & review

1.2 Before Painting


a. Temperature visual & Meassured SSPC Vol 1 & 2 FI-M-02 RP,W SW
b. Humidity visual & Meassured SSPC Vol 1 & 2 FI-M-02 RP,W SW

1.3 After Painting


a. Coating Thickness visual & Meassured SSPC Vol 1 & 2 FI-M-02 RP,W SW