Professional Documents
Culture Documents
Form Estimasi Rework BFWP: Kebutuhan Jasa
Form Estimasi Rework BFWP: Kebutuhan Jasa
Consumable
No Nama Barang Jumlah Satuan Harga satuan Harga Total Keterangan stock
Rp 1 Gas LPG (50kg) Rp 1 Tabung Rp 1,250,000 Rp 1,250,000 OK
Rp 2 Gas Oksigen Rp 1 Tabung Rp 277,500 Rp 277,500 OK
Rp 3 Gasket Tombo Lembaran thickness 1 mm Rp 1 Lembar Rp 1,850,000 Rp 1,850,000 UKURAN? (Stock 0) ORI
Rp 4 Gasket Tombo Lembaran Thickness 3 mm Rp 1 Lembar Rp 3,920,000 Rp 3,920,000 UKURAN? (Stock 0) ORI
Rp 5 Gasket Tombo Lembaran Thickness 5 mm Rp 1 Lembar Rp 4,220,000 Rp 4,220,000 UKURAN? (Stock 0) ORI
Rp 6 Gasket Klingeride 1000 (1 x 1 mtr) Rp 1 Lembar Rp 6,658,600 Rp 6,658,600 Tidak Ada Stock
Rp 7 O-ring Casing ID 385 mm x OD 399 mm x Thickness 7 mm Rp 11 pcs Rp 382,880 Rp 4,211,680 Tidak Ada Stock
Rp 8 Red Silicone Rp 15 pcs Rp 48,000 Rp 720,000 Stock 1, -14 pcs
Rp 9 Sand Paper Gr 180 Rp 5 Meter Rp 15,000 Rp 75,000 OK
Rp 10 Sand Paper Gr 400 Rp 5 Meter Rp 15,000 Rp 75,000 Tidak Ada Stock Stock wh Lembaran
Rp 11 Sand Paper Gr 1500 Rp 5 Meter Rp 15,000 Rp 75,000 Tidak Ada Stock Stock wh Lembaran
Rp 12 Majun Rp 5 kg Rp 10,000 Rp 50,000 OK
Rp 13 Wire Brush Rp 3 pcs Rp 36,300 Rp 108,900 Tidak Ada Stock
Rp 14 Flap Disk 4" Rp 3 pcs Rp 9,500 Rp 28,500 OK
Rp 15 Blue Cel Liquid Rp 2 pcs Rp 121,975 Rp 243,950 Stock 1, -1 pcs
Rp 16 White Marker Rp 1 pcs Rp 69,266 Rp 69,266 Ok
Rp 17 Scotbret Rp 5 Pcs Rp 9,000 Rp 45,000 Stock 2 (-3 pcs)
Rp 18 Thinner Rp 1 Galon Rp 222,000 Rp 222,000 Ok Cobra
Rp 19 Liquid Penetrant Developer Rp 1 Kaleng Rp 175,000 Rp 175,000 OK
Rp 20 Liquip Penetrant Red Rp 1 Kaleng Rp 175,000 Rp 175,000 OK
Rp 21 Liquid Penetrant Cleaner Rp 1 Kaleng Rp 175,000 Rp 175,000 OK
Rp 22 Sim Plate Lembaran (stainless/Steel; Ukuran 0.1) Rp 1 Lembar Rp 375,000 Rp 375,000 OK
Rp 23 Sim Plate Lembaran (stainless/Steel; Ukuran 0.4) Rp 1 Lembar Rp 470,000 Rp 470,000 OK
Rp 24 Sim Plate Lembaran (stainless/Steel; Ukuran 0.6) Rp 1 Lembar Rp 850,000 Rp 850,000 OK
Rp 25 Sim Plate Lembaran (stainless/Steel; Ukuran 0.8) Rp 1 Lembar Rp 1,050,000 Rp 1,050,000 OK
Rp 26 Sim Plate Lembaran (stainless/Steel; Ukuran 1.0) Rp 1 Lembar Rp 1,150,000 Rp 1,150,000 OK
Rp 27 Sim Plate Lembaran (stainless/Steel; Ukuran 2.0) Rp 1 Lembar Rp 1,250,000 Rp 1,250,000 Tidak Ada Stock
Rp 29,770,396
Tools
No Deskripsi Jumlah Satuan Harga satuan Harga Total Keterangan stock
Rp 1 Inner Pack 50 ton Rp 1 Unit Rp 27,336,192 Rp 27,336,192 Tidak Ada Tools
Rp 2 Bunner tip Rp 1 pcs Rp 87,500 Rp 87,500 on stock
Rp 27,423,692
Kebutuhan Mobilisasi
No Nama Barang Jumlah Satuan Harga Satuan Harga Total Keterangan stock
Rp 1 Delivery Site to Ws Rp 1 Lot Rp 30,000,000 Rp 30,000,000
Rp 2 Mobilisasi for Balancing Rp 1 Lot Rp 4,000,000 Rp 4,000,000 biaya sewa truk pulang pergi
Rp 3 Delivery WS to Site Rp 1 Lot Rp 35,000,000 Rp 35,000,000
Rp 69,000,000
Kebutuhan Lain-lain
No Nama Barang Jumlah Satuan Total
Rp 1 Kebutuhan Takterduga Rp 1 lot Rp 18,677,040
Mengetahui
Rev. 4
WOR : 22006 (Rework BFWP)
Project : Rework BFWP
Tanggal : 10 Agustus - 31 September 2023
Kebutuhan Jasa
No Deskripsi Jumlah Satuan Harga satuan Harga Total
1 Fabrikasi Dummy Shaft (Roundbar Ø 100 mm x 615 mm ST 41) 6 Pcs Rp 2,400,000 Rp 14,400,000
Individual Balancing Impeler
2 1 Lot Rp 60,000,000 Rp 60,000,000
- Individual Impeller Balancing (11 impeler), Total Balancing
3 Fabrikasi/ Machining Impeller (11 Impeller) 1 Lot Rp 6,600,000 Rp 6,600,000
Rp 81,000,000
Consumable
No Nama Barang Jumlah Satuan Harga satuan Harga Total
1 O-ring Casing ID 385 mm x OD 399 mm x Thickness 6 mm 11 pcs Rp 382,880 Rp 4,211,680
2 Red Silicone 15 pcs Rp 48,000 Rp 720,000
3 Prisian Blue Check 1 pcs Rp 140,000 Rp 140,000
4 Scotbrite Merah 5 Pcs Rp 9,000 Rp 45,000
5 Sim Plate Lembaran (stainless/Steel; Ukuran 0.1-2.0) 1 Lembar Rp 3,000,000 Rp 3,000,000
6 Kertas Karkil A3 20 Lembar Rp 5,000 Rp 100,000
7 O-ring Ø3mm x ID 87mm 3 Pcs Rp 100,000 Rp 300,000
8 Dynabolt Ø 16mm x 180mm 48 Pcs Rp 220,000 Rp 10,560,000
9 Bolt M 16mm x 200 mm (Grade 8) 16 Pcs Rp 100,000 Rp 1,600,000
10 Snap Ring Ø 6mm x 95mm (Spring Seal) 2 pcs Rp 500,000 Rp 1,000,000
11 Bromus 5 Ltr Rp 300,000 Rp 1,500,000
12 Baut tanam SUS M10x20 50 Pcs Rp 10,000 Rp 500,000
Rp -
Rp 23,676,680
Tools
No Deskripsi Jumlah Satuan Harga satuan Harga Total
1 Hydrolic Jack + Hand Pump 100 Ton 1 Unit Rp -
2 Bunner tip 1 pcs Rp 87,500 Rp 87,500
3 Vibrasi Analysis 1 Unit Rp 12,000,000 Rp 12,000,000
Rp 12,087,500
Kebutuhan Mobilisasi
No Nama Barang Jumlah Satuan Harga Satuan Harga Total
1 Delivery Site to Ws 1 Lot Rp 30,000,000 Rp 30,000,000
2 Mobilisasi for Balancing 1 Lot Rp 4,000,000 Rp 4,000,000
3 Delivery WS to Site 1 Lot Rp 35,000,000 Rp 35,000,000
4 Mobilisasi For Machining 1 Lot Rp 500,000 Rp 500,000
Rp 69,500,000
Kebutuhan Lain-lain
No Nama Barang Jumlah Satuan Total
1 Kebutuhan Takterduga 1 lot Rp 17,417,668
Mengetahui
WOR : 23010
Project : APH Cleaning Unit #1
Tanggal : 25 September - 02 Oktober 2023
Kebutuhan Jasa
No Deskripsi Jumlah Satuan Harga satuan Harga Total
1 Manpower Saudi 16 orang Rp 2,500,000 Rp 40,000,000
2 Rp -
Rp -
Rp -
Rp -
Rp -
Rp 40,000,000
Consumable
No Nama Barang Jumlah Satuan Harga satuan Harga Total
1 Cutting Whaeel Tebal 5 pcs Rp -
2 Cup Brush 5 pcs Rp -
3 Karung 10 pcs Rp -
4 Face Shield 8 Pcs Rp -
5 Sarung Tangan 5 Lusin Rp -
6 Majun 10 Kg Rp -
7 Full Body Hardness 4 Set Rp -
8 Masker Respirator 20 Pcs Rp -
9 Baju Plastik Anti Debu 200 Pcs Rp -
10 Rp -
11 Rp -
12 Rp -
Rp -
Rp -
Tools
No Deskripsi Jumlah Satuan Harga satuan Harga Total
1 Vacuum Truck 1 Unit Rp -
2 Vibrator Electrik 2 Unit Rp -
3 Blower + Ducting 4 Set Rp -
4 Hand Grinder 4 Unit Rp -
5 Kunci Ring Set 1 Set Rp -
6 Kabel Power + Terminal @20 Meter 6 Set Rp -
7 Lampu 8 Pcs Rp -
8 Special Tools (Panjang 2,5 Meter) 2 Pcs Rp -
9 Jet Hummer Drill Elektrik 6 Unit Rp -
10 Selang Angin Set (Include Conector & Hose @50 Meter) 4 Set Rp -
11 Besi Panjang 4m Ø 10 mm 8 Pcs Rp -
12 Pipa PVC 3/4 Inch 6 Meter 8 Pcs Rp -
13 Terpal 6x15 Meter 2 Pcs Rp -
Rp -
Rp -
Rp -
Kebutuhan Mobilisasi
No Nama Barang Jumlah Satuan Harga Satuan Harga Total
1 Delivery Tools Ws to Site 1 Lot Rp -
2 Mobilisasi Man Power To Site 1 Lot Rp -
3 Mobilisasi Man power to WS 1 Lot Rp -
4 Mobilisasi Man Power Saudi To Site 1 Lot Rp -
5 Mobilisasi Man Power Saudi To Surabaya 1 Lot Rp -
6 Delivery Tools Site to Ws 1 Lot Rp -
7 Rp -
Rp -
Kebutuhan Lain-lain
No Nama Barang Jumlah Satuan Total
1 Kebutuhan Takterduga 1 lot Rp 4,000,000
Jumlah Anggaran Total Total sebelum PPN
Rp 44,000,000
Mengetahui
Hari Ke-
No Activity Durasi 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
1 Bongkar Bearing dari box pengiriman 1 8
2 Inspeksi Dimensi Awal 1
3 NDT UT & PT 1
4 Machining (Skin Cut) 8
5 Babbit Weld 8
6 NDT 1
7 Machining (Finishing) 4
8 Polishing 3
9 NDT Final 1