You are on page 1of 1

Customer : PT Semindo Gemilang

Schedule : 15 days /12 Hours


Manpower : 23 Person
Location : Palembang
Project : Overhaul Steam Turbine 8500kW
and Condensing Turbine
No Rate Turbine Time Schedule 15 days , two shift
1 Supervisor
Upah Hari biasa 2 org x 10 hr x Rp 1,280,000.00 = Rp 25,600,000.00
Upah Hari Libur 2 org x 5 hr x Rp 2,560,000.00 = Rp 25,600,000.00
Lembur Hari biasa 2 org x 3 jam x Rp 160,000.00 = Rp 960,000.00
Lembur Hari Libur 2 org x 3 jam x Rp 360,000.00 = Rp 2,160,000.00
Akomodasi/makan 2 org x 15 hr x Rp 450,000.00 = Rp 13,500,000.00
Mob & Demob 2 org x 2 Lot x Rp 2,000,000.00 = Rp 8,000,000.00
= Rp 75,820,000.00

2 Teknisi Mekanik / Electrical / Welder


Upah Hari biasa 10 org x 10 hr x Rp 700,000.00 = Rp 70,000,000.00
Upah Hari Libur 10 org x 5 hr x Rp 1,400,000.00 = Rp 70,000,000.00
Lembur Hari biasa 10 org x 3 jam x Rp 90,000.00 = Rp 2,700,000.00
Lembur Hari Libur 10 org x 3 jam x Rp 180,000.00 = Rp 5,400,000.00
Akomodasi/makan 10 org x 15 hr x Rp 450,000.00 = Rp 67,500,000.00
Mob & Demob 10 org x 2 Lot x Rp 2,000,000.00 = Rp 40,000,000.00
= Rp 255,600,000.00

3 Adm,Safety Officer
Upah Hari biasa 3 org x 10 hr x Rp 600,000.00 = Rp 18,000,000.00
Upah Hari Libur 3 org x 5 hr x Rp 1,200,000.00 = Rp 18,000,000.00
Lembur Hari biasa 3 org x 3 jam x Rp 75,000.00 = Rp 675,000.00
Lembur Hari Libur 3 org x 3 jam x Rp 150,000.00 = Rp 1,350,000.00
Akomodasi/makan 3 org x 15 hr x Rp 450,000.00 = Rp 20,250,000.00
Mob & Demob 3 org x 2 Lot x Rp 2,000,000.00 = Rp 12,000,000.00
Rp 70,275,000.00

4 Helper / Tooling
Upah Hari biasa 4 org x 10 hr x Rp 500,000.00 = Rp 20,000,000.00
Upah Hari Libur 4 org x 5 hr x Rp 1,000,000.00 = Rp 20,000,000.00
Lembur Hari biasa 4 org x 3 jam x Rp 50,000.00 = Rp 600,000.00
Lembur Hari Libur 4 org x 3 jam x Rp 100,000.00 = Rp 1,200,000.00
Akomodasi/makan 4 org x 15 hr x Rp 450,000.00 = Rp 27,000,000.00
Mob & Demob 4 org x 2 Lot x Rp 2,000,000.00 = Rp 16,000,000.00
= Rp 84,800,000.00

5 Inspector / NDT /Reager /Opr Head Crane


Upah Hari biasa 4 org x 10 hr x Rp 700,000.00 = Rp 28,000,000.00
Upah Hari Libur 4 org x 5 hr x Rp 1,400,000.00 = Rp 28,000,000.00
Lembur Hari biasa 4 org x 3 jam x Rp 90,000.00 = Rp 1,080,000.00
Lembur Hari Libur 4 org x 3 jam x Rp 180,000.00 = Rp 2,160,000.00
Akomodasi/makan 4 org x 15 hr x Rp 450,000.00 = Rp 27,000,000.00
Mob & Demob 4 org x 2 Lot x Rp 2,000,000.00 = Rp 16,000,000.00
= Rp 102,240,000.00

6 Insurance
Accident & health Personil 23 org Rp 500,000.00 = Rp 11,500,000.00
Rp 11,500,000.00

7 Tools and Measurement


Tools Standart 1 lot Rp 55,000,000.00 = Rp 55,000,000.00
Akomodasi 2 PP Rp 5,000,000.00 = Rp 10,000,000.00
Rp 65,000,000.00