Qts Manpower Steam Turbine 8.5kw Padang
Qts Manpower Steam Turbine 8.5kw Padang
3 Adm,Safety Officer
Upah Hari biasa 3 org x 10 hr x Rp 600,000.00 = Rp 18,000,000.00
Upah Hari Libur 3 org x 5 hr x Rp 1,200,000.00 = Rp 18,000,000.00
Lembur Hari biasa 3 org x 3 jam x Rp 75,000.00 = Rp 675,000.00
Lembur Hari Libur 3 org x 3 jam x Rp 150,000.00 = Rp 1,350,000.00
Akomodasi/makan 3 org x 15 hr x Rp 450,000.00 = Rp 20,250,000.00
Mob & Demob 3 org x 2 Lot x Rp 2,000,000.00 = Rp 12,000,000.00
Rp 70,275,000.00
4 Helper / Tooling
Upah Hari biasa 4 org x 10 hr x Rp 500,000.00 = Rp 20,000,000.00
Upah Hari Libur 4 org x 5 hr x Rp 1,000,000.00 = Rp 20,000,000.00
Lembur Hari biasa 4 org x 3 jam x Rp 50,000.00 = Rp 600,000.00
Lembur Hari Libur 4 org x 3 jam x Rp 100,000.00 = Rp 1,200,000.00
Akomodasi/makan 4 org x 15 hr x Rp 450,000.00 = Rp 27,000,000.00
Mob & Demob 4 org x 2 Lot x Rp 2,000,000.00 = Rp 16,000,000.00
= Rp 84,800,000.00
6 Insurance
Accident & health Personil 23 org Rp 500,000.00 = Rp 11,500,000.00
Rp 11,500,000.00
Note:
Rp 665,235,000.00