Professional Documents
Culture Documents
Petroci CI-11 Pipeline Pigging - Options Presentation August 9th
Petroci CI-11 Pipeline Pigging - Options Presentation August 9th
Original Plan
Budget Actuals
Phase 1 - Pathfinder Campaign $439,769 $494,223
Phase 2 - Standard MFL Campaign $559,978 N/A
Total $999,747 $494,223
Contingency $1,099,722
Remaining Funds on current GTA Addendum $605,499
2
Options
• Pigging Strategy Options
‒ Option 1 – Continue with current plan. A progressive cleaning campaign followed by a MFL ILI however, tools will be more bespoke and trials may
be required. Additional cost in addition to approved GTA Addendum = $271,110.
Enabler 1: Propipe water trial to confirm bore passage of mechanical pigs.
Enabler 2: Rosen input to confirm MFL modifications to pass restriction.
Risk: Dent length is not known. For trials we would assume dent length equal to tool length. This will be sufficient for confirming bore passage
but not sufficient to confirm no MFL speed excursions which would have an impact on data quality and tool damage. Risky option, hence not
preferred.
‒ Option 2 – As above, plus inclusion within the same campaign of a high resolution calliper tool before the MFL ILI tool. Additional cost in addition to
approved GTA Addendum = $428,410.
Enabler 1: Same enablers as option 1.
Enabler 2: Rosen input to confirm standard High Resolution Calliper tool can pass restriction.
Risk: Effort and cost may be wasted redesigning the MFL tool if the dents / restrictions are not as aggressive as recorded by the pathfinder.
Risk of wasted effort, cost is high compared to other options. Option considered but not preferred.
‒ Option 3 – Run a high resolution calliper tool as a stand alone campaign. Increase accuracy on measured restrictions and dent geometry. Then use
this information to downscale the level of modifications required on the MFL tool and requirement for trials. Additional cost in addition to approved
GTA Addendum = $393,197.
Enable 1: Rosen input to confirm standard High Resolution Calliper tool can pass restriction.
Risk: Increase in schedule in comparison to option 1 and 2. Also it assumes no significant modifications to the MFL. Less risk and cost is
comparable to other options. This option is preferred.
3
Option 3
• Option 3 Budget
Option 3 Additional Cost
Phase Total Comments
Phase 1 - Pathfinder Campaign $494,223 Completed
Phase 2 - Standard High Res Calliper Tool $453,986 New Campaign
Phase 3 - Standard MFL Tool $544,711 Standard MFL Tool
Project Total $1,492,919 N/C
Additional Cost to Addendum $393,197 N/C
Threat: This cost estimate assumes the use of a standard MFL tool for Phase 3.
• Worst case budget if threat materialise i.e. MFL modifications and trials required.
Option 3 (MFL Modifications and Trials required)
Phase Total Comments
Phase 1 - Pathfinder Campaign $494,223 Completed
Phase 2 - Standard High Res Calliper Tool $478,689 New Campaign
Phase 3 - Modified MFL Tool + N2 Trials $903,154 MFL Mods + Trials
Project Total $1,876,066 N/C
Additional Cost to Addendum $776,344 MFL Mods + Trials
4
Opportunities and Prerequisites
• Opportunity
‒ Phase 2 includes the launch of a gauge plate pig. It is proposed to launch this pig ahead of mobilising the high resolution tool to potentially reduce
conservatism in the restriction picked up by the pathfinder. This could remove the requirement for the calliper tool to be used if the restrictions are in
fact debris on the bottom of the pipeline and save approximately 70% of the cost for Phase 2.
5
Schedule
CI-11 Pipeline Pigging & ILI
Campaign
1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6
ITEM Jan-23 Feb-23 Mar-23 Apr-23 May-23 Jun-23 Jul-23 Aug-23 Sep-23 Oct-23 Nov-23 Dec-23 Jan-24 Feb-24 Mar-24 Apr-24 May-24 Jun-24
Phase 1 - Foam Pigging and Phase 1 January to July 23
Status
Pathfinder Survey
Ship Pathfinder Tool to CDI (ATA Carnet) Complete
Phase 1 Pigging - Foam and Pathfinder Complete
Run Pathfinder service tool for data collection Complete
Assess data from Pathfinder tool for input into
mechanical pig design and ILI tool design.
Complete
MILESTONE Activity
ACTIVITY / DELIVERABLE PREP
Critical Path Activity
Activities to be progressed by temp support
6
PROVEN EFFECTIVE STRATEGY