Professional Documents
Culture Documents
Table of Contents
1.1Introduction: ................................................................. 3
002
1.1 Introduction:
The framework adopted in the Planning criteria and Design philosophy
is to deliver one of the key Asset Management functions, which is a
‘Systematic and Co-ordinated activities and practices through which
ADDC optimally manages its assets, and their performance, risks and
expenditures over asset lifecycle for the purpose of achieving its
Organizational Strategic objective. Where the Organisational Strategic
Plan is defined as:
‘The overall long-term action plan for the organisation that is derived
from and embodies its vision, mission, values, business policies,
objectives and the management of its risks’
The objective is ‘to ensure and to be able to demonstrate that the assets
deliver the required function and a level of performance, in a
sustainable manner, at an optimum whole-life cost basis without
compromising health, safety, environmental performance, or the
organisation’s reputation.’
003
As part of the planning process and new Price Control regime starting
January 2006 (and with appropriate modification to License), ADDC is
required by the Bureau to produce annually Five (5) Year Planning
Statement. The planning statement give a forward view on the
proposed expansion of infrastructure, new connections and the
associated capital expenditure requirements that will meet the forecast
demand growth and support the growth and development of Abu Dhabi
Emirate. Condition 29 of Distribution License requires ADDC to
develop and review Security Standards from time to time for the
distribution system. ADDC must plan and develop its distribution
system to a Standard not less than that set out in the Distribution
System Security Standard.
004
1.2 Planning Process:
The planning process adopted by ADDC can be easily understood with
the help of the process flow chart (Figure-1.1) depicted below. The
process begins with the demand/load forecasting that determines the
future demand. A reality check will be done with forecasted
load/demand to evaluate the system capabilities. The system should be
capable of catering to the future demand without compromising the
supply security standards and the quality of power supply or any other
requirement that are defined by the regulator. The system evaluation
will be done with the help of simulation software by carrying out load
flow, short circuit and stability studies and requirement of
reinforcements for the existing system will be identified and finalized
based on the system performance reports available. All the risks
associated are clearly identified and if the risks cannot be managed
with the existing system, new proposals are recommended for
implementation.
005
Total & Spatial Load
Load
Forecast
Forecast Supply Security
Total & Spatial
Standards
Evaluation
EvaluationofofSystem
SystemCapabilities
Capabilities
System Model/
Identifying System
Identifying Deficiencies
System Deficiencies System Model
Performance
Reports
Adequacy
Adequacy&&Security
Security NO
Concerns
Addressed.?
Addressed?
Evaluate Risks & Constraints
YES
YES
“Do
“DoNothing”
Nothing” Can
CanRisks
Risksbebe
Managed?
NO
Evaluate
Evaluate System
System
Implement Projects
Performance Implement Projects
Figure- 1.1
006
1.2.1Inputs/Factors for Planning:
Load
Load Forecast
Forecast
Total System& Spatial SupplyCSS Security
Load Forecast; How
much.., Std. S
Interruption
Interruption duration/
Where..& When.. Restoration
Duration/
Restoration timing/
Refurbishme
Refurbishment Power/Service
Power service quality
timing/
nt&&Under Quality.
Old
Old under performing
Assets.
performing
assets
Recommendatio
KEMA
n.
Operational
Operational Concern
System
System
Concern
Expansion Operational
Plan Abu
CostDhabi Plannin
Expansion
Planning &Operational flexibility,
Ease of Switching
Flexibility
Ease of switching &
Load
&
2030
s
LeastCost
g Load transfers
Transfer
Urban Structure
SolutionPlan
Framework
s.
Environment
Environment,&
Best Practices
Best Safety & Safety
Health
Environment,
Practices
International & Local
International Community
safety,
Environment, safety
Standards/
Advanced
Standards to& be
concerns
Community concerns
Advanced Utility Practices/ addressed.
Practice
Utility
s.
Figure- 1.2
007
1.2.2 Load Forecasting:
008
a. Trend analysis.
b. Multivariable regression (Econometric).
c. End use method.
d. Scenario approach.
Trending methods are widely used as a tool for forecasting that works
with historical data, extrapolating past load growth patterns into
future. Trending techniques involve fitting trend curves to basic
historical data adjusted to reflect the growth trend itself. With the trend
curve the forecast is obtained by evaluating the trend curve function at
the desired future point. Although it is a very simple procedure, it
produces reasonable results. Such a technique is to be classified as a
deterministic extrapolation, since no attempt is made to account for
random errors in the data or in the analytical model. Some eight to ten
standard analytical functions are used in trend curve fitting.
009
important explanatory variables. In addition, it should be simple in
order to make it easier to use and interpret.
Multi-variable regression analysis can be used to establish the
correlation between selected socio-economic-energy variables and
energy consumption data using the past sample data. The relation
obtained will be then used to estimate the energy consumption data for
the future years using the trend/modified trend values for the
regression variables for the future years.
010
(C) End-use Technique:
The end-use method determines energy demand through total kWh use
from all of the electrical appliances used in the households. The
forecast is "built from the sum of end-using activities”. End-use
models must include kWh consumption data by type of equipment or
process.
011
1.2.4 Approaches Adopted by ADDC:
012
Load Forecast Methodology
Define Variables
Modify the
Trend to
reflect LDN
Data
Test and Validate Results
(Compare with Consolidated LDN
Report for short term forecast)
Are Results
O.K?
NO
YES
Prepare Load
Forecast Report
013
ADDC has adopted the trending technique to forecast the area wise
demand. The process flow chart given above explains the process in
brief.
014
1.3 Planning Criteria:
This section broadly outlines the criteria to be followed by the planning
section while planning the distribution system configuration. This
chapter considers and explains the significance of each and every
individual criteria/aspect that is to be taken into consideration while
developing the network. The planning criteria have been developed
based on Security of Supply Standard for the Electricity Distribution
Code approved by the Regulation and Supervision Bureau (RSB) and
the best utility practices that focus on developing and operating a
secured, reliable and economical power system.
Class
Range of Min Demand to be met after
of
Group Demand First Circuit Outages
Supply
Demand within repair time
A1 Up to 1.5 MVA
following first circuit outage
Demand within repair time
A2 Up to 3.0 MVA
following first circuit outage
50% of the Group Demand within
20 minutes (if Circuits are
B1 3.0 to 6 MVA equipped with remote/auto
switching capability)
Group Demand within 2 Hours
B2 3.0 to 6 MVA Group Demand within 2 Hours
015
Class
Range of Min Demand to be met after
of
Group Demand First Circuit Outages
Supply
Class A1:
Class A2:
Class B1:
016
distribution substation the demand of that substation may be excluded
from the Group Demand and for which the restoration criteria of Class
A1 will apply
Class B2:
Class B3:
Class B4:
Class C1:
017
restored within 3 hours, by closing the open points on the 11 kV
feeders. Following a Second Circuit Outage (at either package
substation) the power will be restored after the repair time or the time to
restore the planned first outage
Class C2:
Class D1:
Class D2:
A: Voltage Levels:
018
Nominal Voltage Normal Operation Voltage Band
400 V +10%, -6%
*as per Supply Regulations 2007
019
1.3.3 Design Philosophy:
Drawing 1.1 to 1.3 presents the detailed map of Central region, Eastern
region and Western Region. Drawing 1.4 presents the entire map of
Abu Dhabi Emirate. The total area of Central Region is 92 Sq. km
(excluding Islands) and 255 Sq.km (including neighboring Islands).
Central Region is densely populated area with skyscrapers and hub for
major commercial activities in the Emirates. The total area of Eastern
region is 12,522 Sq.km and Western region is 43,700 Sq.km. Eastern
Region and Western Region is comparatively less populated and
dispersed. Eastern Region is a mix of high density and low density load
whereas Western Region is predominantly a low density typical rural
load. Each area load characteristics depicts its own traits in terms of
peak load, load density, load characteristics and developmental/growth
avenues.
In urban areas, the load densities are very high with expected high
demand growth whereas in rural area the load growth is low and
dispersed over a very large area. Urban areas would require large
capacity substations and a number of distribution substations within a
very small reach. As the feeders are not very long, voltage regulation is
not a constraint in urban areas and invariably loading of an asset is a
limitation.
020
The design is specified by the engineering design guidelines and
includes guidelines for the following areas of the electric distribution
network:
Primary Substations
Sub-transmission and Distribution Network
Distribution Equipment
Low-Voltage Network and Equipment
021
The standard substation capacity/configuration of 132/11 kV
substation is as depicted in the Table below:
Rating 40 MVA
022
Standard 132/11 kV Substation Configuration
Equipment
SN Rating/specs Value
description
feeder Breakers Continuous Current
630/1250 A
Rating
Rated Breaking
31.5 kA
Capacity (Icn)
S.C Withstanding
31.5 kA for 3 Sec
Capability
Type GIS
Continuous Current
6 Bus Bar -11 kV 2500 A
Rating
S.C Withstanding
31.5 kA for 3 Sec
Capability
TRF Firefighting Automatic fixed water
7 --
equipment spray systems
Incoming Feeders 2500A- 4Nos.(1No.per Bus
Section)
630A-40 Nos. (10Nos. per
Outgoing Feeders
Bus Section, (CT: 600-
400/1A) – Note-1
1250A-8Nos. (2Nos. per
Outgoing Feeders
Bus Section, (CT: 1250/1A)
8 Feeder Details
– Note- 1 &2
Bus-Section Feeders
2500A-4Nos.
Capacitor Bank Feeders 1250A-4 Nos. (1 No. per
Bus-Section )– Note-3
Auxiliary Transformer 630A-2Nos.(1 No. per 2
Feeders Bus-Sections (CT: 100/1A)
* Note:
1) The outgoing cable feeders shall be suitable for termination of two
cables
2) The 2 Nos. 1250A outgoing feeders in each bus-section shall be
located on either side of the bus-section breaker 1 & 3, which are
normally closed. While terminating the outgoing feeders with 2
Nos. of cables, the destination of the feeder shall be at the same
panel.
3) The 1250A capacitor bank circuit breaker identified for capacitor
bank shall be suitable for capacitor switching duty.
023
The operation philosophy of all new 132/11 kV substations are as
follows:
All the mega developments that are expected to have a very high load
density, have been planned with 132/22 kV substation configuration
only to cater to such development on standalone basis.
024
Standard 132/22 kV substation configuration
Equipment
SN Rating/Specifications Value
description
Voltage Ratio 132/23kV
Rating 60 MVA
025
Standard 132/22 kV substation configuration
Equipment
SN Rating/Specifications Value
description
S.C Withstanding
31.5 kA for 3 Sec
Capability
Type GIS
Continuous Current
2500 A
Rating
6. Bus Bar -22 kV
S.C Withstanding
31.5 kA
Capability
Single (4Nos.)-22kV Bus
Configuration
shall be a ring formation
TRF Firefighting
7. Deluge System --
equipment
Incoming Feeders 2500A- 4Nos.(1No.per Bus
Section)
630A-32Nos.(8Nos.per
Outgoing Feeders
Bus Section, (CT: 600-
400/1A) – Note-1
1250A-8Nos.(2Nos.per
Outgoing Feeders
Bus Section, (CT:
8. Feeder Details
1250/1A) – Note- 1 &2
Bus-Section Feeders 2500A-4Nos., CT:2500/1A
Capacitor Bank Feeders 1250A-4Nos. (1 No. per
Bus-Section )– Note-3
Auxiliary Transformer 630A-2Nos.( 1 No. per 2
Feeders Bus-Sections (CT: 100/1A)
* Parameters as per the tender document of TRANSCO
The specific protection functions shall be as per latest ADDC/ADWEA
specifications and standards.
* Notes:
026
1. In normal operating conditions, 2 Nos. transformers will be
operated in parallel as presented in Drawing 1.8.
2. In case of failure of one transformer, three transformers will be
operated in parallel, for a duration, estimated by M/s EDF to be 30
minutes, as presented in Drawing 1.9.
3. Auto bus-coupler closing facility to close the bus couplers in the
event of outage one transformer.
4. 22 kV systems will operate in open loop and DMS controlled as
presented in Drawing 1.10.
In most parts of Eastern and Western Region the loads are distributed
over large area. Due to the low load density, the load will be catered
through a conventional 33/11 kV system. The substation
transformation capacity will be decided based on the expected load.
In some cases where the load is very small and located remotely,
suitably sized 33/11kV package units can be used initially and
replaced by permanent 33/11kV substation as the load grows.
027
Standard 33/11 kV Substation Configuration
Equipment
SN Rating/Specifications Value
Description
Voltage Ratio 33/11.5 kV
Rating 20 MVA
80/60/40 MVA,
Total S/S Capacity
4/3/2 x 20 MVA
FIRM Capacity 60/40/20 MVA
Transformer
1
33/11 kV
Impedance % Z 12.0 %
028
Standard 33/11 kV Substation Configuration
Equipment
SN Rating/Specifications Value
Description
couplers
Continuous Current Rating 2500 Amps
Rated Breaking Capacity
31.5 kA
(Icn)
S.C Withstanding
31.5 kA for 3 Sec
Capability
Type Gas(SF6) or Air Insulated
029
2. In case of failure of one transformer, three transformers will be
operated in parallel refer to Drawing 1.12.
3. Auto bus-coupler closing facility to close the bus couplers in
the event of outage of one transformer as mentioned above.
4. 11 kV system will be operated in open ring, refer Drawing 1.13.
Can contain the voltage drop and improves the voltage profile in
the rural distribution system.
030
1.3.5 Sub-transmission and Distribution Network:
The configuration and size of the network feeder is based on the peak
load served by the feeder and the least cost configuration that satisfies
the security standards.
1.3.5.1 33 kV Feeders:
33 kV Feeder Configuration:
SN Description Criteria
1 Substation with 4 transformers Four (4) feeders
2 Substation with 3 transformers Three (3) feeders
3 Substation with 2 or 1 transformer(s) Two (2) feeders
33 kV Feeder Size:
The capacity of the above underground cable and the overhead line
conductor is around 20 MVA after considering possible de-rating.
031
1. The creepage distance for 33 kV line will be as per the standard
practice of 50mm/kV
2. Silicon rubber insulators to replace the conventional porcelain
insulators in coastal areas and where the insulators are
subjected to high level of pollution and humidity. Normally, it is
preferred that the entire length of 33 kV line would be of Silicon
rubber insulators as the incremental cost between the two
options has narrowed down due to the new manufacturing
techniques and wide spread use of polymer insulators.
3. Insulated conductors to be used in areas where the lines are
susceptible to corrosion, large vegetation, and high wind velocity
and in the middle of desert with likely formation of sand dunes
that can impact ground clearances.
4. Sectionalizers to be installed at every 5 km distance (as a
standard) to isolate the faulty portion of the line in the event of a
fault. However, the same needs to be studied with respect to each
line tap-offs.
5. Fault locators to be installed at regular intervals to avoid
extensive patrolling to identify the faults and for quick
restoration.
6. Auto re-closing facility to close (Charge) the line after a transient
fault from a remote end will also be part of the 33 kV line design.
A schematic diagram explaining the philosophy of fault detection
and sectionalizing process is attached in Drawing 1.20.
7. The poles that are normally used in 33 kV OHL design is iron
poles and the grounding of these poles is by running a separate
ground wire throughout the length of the line and grounding at
each and every pole to limit the resistance to 5 ohms as per the
standard practice. The same would be adopted for all the new
designs.
8. It is ADDC general policy to minimize to the most possible extent
the use of OHL T-offs in order to simplify the network and avoid
unnecessary load shedding.
9. The present standard and specifications for OHL is currently
under major review by ADDC to include full details for every
component and introduce new elements that would improve the
overall reliability and performance of the OHL systems.
33 kV Feeder protection:
032
Differential protection using Fiber Optic cable or Pilot wires is
used as a Primary or Main Protection function to protect the
cable feeder, while over current and earth fault functions will be
used as a backup protection for the primary or the main
protection function.
Voltage Drop:
033
The voltage drop of 5% is acceptable for any proposals being prepared
and if the voltage regulation is more than that the proposal, it will be
revised to be restricted to 5% voltage regulation in 33 kV system.
1.3.5.2 11 kV Feeders:
11 kV Feeder Configuration:
The maximum loading on each feeder will be limited to 50% of its rated
capacity. Refer to Drawings 1.7, 1.13, 1.16 and 1.19 for typical
arrangements.
034
primary transformers and if possible, from different primary
substations.
11 kV Feeder size:
035
11 kV OHL
The choice of whether to use overhead line (OHL) or underground cable
(UGC) must be consistent with safety, reliability and operational
constraints to ensure that the capacity of the sending end efficiently
matches the supply and demand of electrical energy. The choice
between OHL and UGC is driven by technical, environmental and
economic considerations; for instance:
1. Inhabited areas i.e. residential/industrial areas where the right of
way is already established and well defined it would be brodant
for ADDC to establish UG services.
2. OHL may cause hazardous Risks that impact the
surrounding environment
3. Performance improvement initiative to the existing network that
technically/commercially justify the underground system
investment.
Rating
SN Description Size
(Amp)
1 Overhead Line - Main 200 Sq. mm AAAC Poplar 267
2 Over Head Line - Spur 150 Sq. mm. AAAC Ash 230
036
2. Silicon rubber insulators to replace the conventional porcelain
insulators in coastal areas and where the insulators are
subjected to high level of pollution and humidity. Normally, it is
preferred that the entire length of 11 kV line would be of Silicon
rubber insulators as the incremental cost between the two
options has narrowed down due to the new manufacturing
techniques and wide spread use of polymer insulators.
3. Insulated conductors to be used in areas where the lines are
susceptible to corrosion, large vegetation, and high wind velocity
and in the middle of desert with likely formation of sand dunes
that can impact ground clearances.
4. Sectionalizers to be installed at every 5 km distance (as a
standard) to isolate the faulty portion of the line in the event of a
fault. However, the same needs to be studied with respect to each
line tap-offs.
5. Fault locators to be installed at regular intervals to avoid
extensive patrolling to identify the faults and for quick
restoration.
6. Auto re-closing facility to close (Charge) the line after a transient
fault from a remote end will also be part of the 11 kV line design.
Similar to 33 kV OHL, the schematic diagram explaining the
philosophy of fault detection and sectionalizing process typical to
the attached in Drawing 1.20.
7. Copper Clad steel wire to be used as pole earth wire for remote
areas to avoid thefts
8. On load vertical mounted switch fuse installation for PMT and
GMT HV protection to be used.
9. It is ADDC general policy to minimize to the most possible extent
the use of OHL T-offs in order to simplify the network and avoid
unnecessary load shedding.
10. The present standard and specifications for OHL is currently
under major review by ADDC to include full details for every
component and introduce new elements that would improve the
overall reliability and performance of the OHL systems.
11 kV Feeder protection:
Voltage Drop:
037
The voltage drop of 5% is acceptable for any proposals being prepared
and if the voltage regulation is more than that the proposal, then it will
be restricted to 5% voltage regulation in 11 kV system.
1.3.5.3 22 kV Feeders
22 kV Feeder Configuration:
22kV power cables shall be associated with dedicated FOC loop and the
number of fibers shall be specified on case to case basis in accordance
with DMS requirement.
Compared to the existing 11kV feeder, 22kV feeder will have double the
loading capacity, accordingly it will solve the space constraints to some
extent since the number of feeders will be less.
038
22 kV Feeder Size:
The underground cable of 3Cx300 Sq. mm, Cu. XLPE will be used as
the main cable, which can carry up to 335 Amps (13 MVA), in order to
utilize the full feeder capacity. 300 Sq. mm cable is optimally selected
for distribution based on various constraints including cables bending
radius, spacing between cables for heat dissipation and service
reservations availability.
22 kV Feeder protection:
Voltage Drop:
039
validate/revise the demand factors and diversity factors to be used for
sizing of the distribution equipment.
The below DF’s are adopted to estimate the Demand Load at the LV
side of the Distribution Transformer. However, additional Coincidence
factors should be applied to estimate the Demand load at upstream
levels to reach feeder level and primary substation level.
NOTE: These factors can be used in absence of actual factors and the factors will be
revised based on the result of proposed study currently in progress.
040
1. Permanent Distribution Substation with Two Transformers:
Permanent substations with two transformers (2x1500kVA) are
recommended in both urban and rural areas to serve multiple
customers where the load requirement exceeds 1.5MVA and to be
located in the load center.
Permanent Distribution Substation with Single Transformer:
Permanent substations with single transformer (1x1500kVA) are
recommended in areas planned for low load density type of
development and defined load is less than 1.5MVA. Also for areas
where additional capacity in the existing substation cannot be
utilized due to geographic conditions, plot locations, service
corridor facilities etc.
041
Street Lighting – Package units are recommended in long
highways through rural and remote areas. But for any new
developments in rural or urban areas, the street lighting
network to be fed from the Ring Main substations.
3. 11/0.4 kV RMU:
A typical RMU based substation located in a typical 11 kV loop will
comprise of the following:
The RMU shall be fitted with 2 Nos. Earth Fault Indicator with
remote indication at both incomer/ring outgoing feeder.
The RMUs will have the facility to monitor and control from
remote. The Feeder rating would be 630 Amps and the
Transformer Circuit Breaker rating would be 200 Amps. The
042
RMUs will be fitted with Self powered numerical O/C and E/F
Relay.
043
The incomers will be off-load isolator and the outgoing will be Fuse
based. In case of two transformer substations, a combined LVDB
will be installed with two (2) bus-sections with bus-section
isolator.
** The specified short circuit level at 22kV for distribution system emanating from
132/22 kV Primary substation with 4x80 MVA transformers is 25kA for 1second
and distribution system emanating from 132/22 kV Primary substation with 4x60
MVA transformers is 20kA for 1 second. This specified level of short circuit is
irrespective of its location in the loop.
These RMUs shall be of Metal enclosed type. The RMUs shall have
circuit breaker rated 630A for both Ring feeders (incomer and
outgoing feeders) and transformer feeders. The Ring feeders will
have the facility to monitor and control from DMS.
The RMU shall be fitted with 2 Nos. Earth Fault Indicator with
remote indication at both incomer/ring outgoing feeder.
044
The transformer feeder will be fitted with Self powered numerical
O/C and E/F Relay. The RTU for remote operation will be powered
by auxiliary supply of 24V DC, which will be part of the RTU panel.
Distribution Transformers:
LV Distribution Boards:
1Cx630sqmm 6+1(Spare)+
3 1000 1800 1800 630/400
-7Runs (2 x 1(Space)
3ph + 1 N)
The incomers will be having off-load isolator and the outgoing will be
Fuse based. In case of two transformer substation, a combined LVDB
045
will be installed with two (2) bus-sections with bus-section isolator. This
interconnection facility at the LV level will result in additional security
of supply, in case of a failure of one of the transformers and also during
periodical maintenance.
Total Demand
Diversity Factor
Connected Factor
Overall
load incl.
Demand-cum-
Among SSs
S Cooling
Land use Diversity
Among
Among
FP/ST
Loops
N Specific within Factor
Consumption the Plot (@ PRY Level)
(W/Sqm)
046
1. Maximum number of villas/buildings can be constructed in each
plot based on plot size and GFA as permitted by DMA/Town
Planning Department or UPC.
It is to be ensured that the new added load is not going to over load any
of the upstream elements. The feeding scheme prepared to supply
electricity to new consumer would consider the following:
047
to service turret (ST). Service cable to consumer’s metering panel
from the FP or ST to be restricted to 100m.
3. In few cases where there are no sources nearby and the load has to
be fed from a farthest sources then the cable will be upgraded to the
next size to increase the load transfer capability, reduce voltage drop
and loses to an extent.
The low voltage (LV) cable size is based on the load on the cable, voltage
drop and voltage flicker caused by the starting of larger loads such as
an air-conditioner.
The maximum low voltage (LV) cable length is limited by the voltage
drop and voltage flicker. The maximum voltage drop that is accepted to
meet the voltage standards is 6% for the LVDB including LV cable and
service cable.
The maximum total circuit length of LV cable from the LV panel of the
S/S to the building service entrance should be less than 450 meters
(from LVDB to FP & to Consumer metering point) in order to maintain
the voltage drop minimum.
048
meters from the substation will require a bigger cable size than normal
to be installed in order to provide adequate voltage to the consumer.
The LV cable should be sized based on the peak load and not the
connected load for the distribution network and the selection of service
cables to individual plots are based on respective demand load. The
voltage drop is required to be calculated to ensure the service will
supply the proper voltage.
Voltage Drop:
Voltage drop calculations will be computed for all the LV proposals. This
calculation will determine the percentage voltage regulation to supply
demand load to a given distance with particular conductor.
Minimum permissible voltage at a consumer connection point is 400V
less 6 % (376 V).
049
DERATING FACTOR- PARAMETERS
SN Factors Considered Rating factors
With 30 cm spacing between cables
Table -2
MAXIMU LV CABLE ROUTE LENGTH
SN Description Max.Length
From Distribution Substation LVDB to the
1 250 m
Feeder Pillar
Table – 3
SN Description %Vd
From Distribution Substation LVDB to the
1 3%
Feeder Pillar
050
LV CABLE CURRENT CARRYING CAPACITY
Current Carrying Capacity Recommended Loading of
S Cable Type/Size
(A) (as per manufacturer’s Cable (A) (after applying de-
N (Sq. mm)
catalogue) rating factors)
4 4Cx50 215 127
5 4Cx70 265 157
6 4Cx95 315 187
7 4Cx120 360 213
8 4Cx150 405 240
9 4Cx185 460 273
10 4Cx240 530 314
Table -5
LV FUSE RATING & CABLE SIZE CORRESPONDING TO LOAD
Max Load
Sl Demand Load Recommended Recommended
Current range (A)
No. Range (kW) Cable Size mm 2 Nearest Fuse Rating
@0.9pf
1 0-40 64 16 80A
2 40-55 88 25 100A
3 55-70 112 50 125A
4 70-90 144 70 160A
5 90-115 184 95 200A
6 115-125 200 120 224A
7 125-140 244 150 250A
8 140-170 272 185 300A
9 170-200 320 240 355A
400A-Direct from
LV Panel/separate
10 200-250 400 2x120/2x185
fuse O/G with
lower capacity
051
LV Feeder Pillars:
Services with total peak demand less than 250 kW shall be fed from
feeder pillars. The feeder pillar bus bar shall be rated for 800A, it has
two in-coming cables of 4Cx240 Sq. mm size from two different outgoing
fuses of LVDB and connected through 630A solid link and all the
outgoings are fuses.
There are two types of feeder pillars based on the number of outgoings
(Type-A and Type-B). Following standard types are utilized in the
network.
160A- Up to
Type 3Nos 4cx70
630A 2x4Cx240
B 800A 2 6+1Space 250A Up to
(8Way) 200A-
4cx120
3Nos
052
It is proposed to have two cables (240 Sq.mm) from different outgoings
of Substation LV panels to each feeder pillar for the optimal utilization
as the feeder pillar is rated for 800A.
Note: For planned areas with defined residential load of very low density,
Feeder pillars with single incoming cable of 4Cx240 mm2 cable can be
considered under the following conditions together:
LV Service Turret:
Power supply for small shops, farms, street lighting control cabinets etc.
is fed directly from the service turret. The service turrets bus bar shall
be rated for 400A; it has one incoming connected through 630A solid
link with provision for terminating XLPE cables up to 4x240 mm² sizes
and four outgoing fuses.
The outgoing services are usually fused with 125 or 160 amps fuses.
125A- Up to
250A
4Cx70/120 4Nos 4cx70
ST
400A 1 4 630A /185/240
(4 Way) 300A- Up to
400A 1No(Loop 4cx185
out)
053
distribute LV power, shall be installed on a suitable concrete foundation
or fixed at metallic structures below Pole-Mounted 11/0.4 kV
Transformer.
The housing shall consist of only one compartment with two doors and
shall be of heavy- duty hot molded glass reinforced plastic (GRP) with a
reinforced lockable door.
LV DISTRIBUTION CUBICLE
054
The earthing scheme as per the prevailing practices shall have three
separate earthing grid / pits for System earthing (Transformer Neutral),
Safety earthing (HV), Safety earthing (LV).
The earthing practice adopted for the overhead lines is presented here:
Steel work in wood poles shall be earthed at all sections, "H"poles and
other "H"poles which are fitted with transformers, cable boxes or other
apparatus. At such "H"poles all steel work will be bonded and earthed.
Earthing and bonding wire of 70/35mm2 will be stapled to poles at
intervals < 30cm. At Pole mounted transformer location, two
Earthing points are to be provided. One Earthing point for LV System
LV Cut out and LV Cables, The other point should be for HV system
separated by a distance of not less than 5 meters. Transformer body
and all Steel Works, Lightning Arrester on the pole should be connected
to main HV Earthing point. It is being taken care that no connection
between these two points exists.
Earthing will be done by boring and installing earth rods to reach the
required resistance value (less than 10 Ω). It will be ensured to add only
approved suitable environmental friendly material to enhance
the resistance value. If required more earthing points will be created
and connect them together by suitable Conductor to achieve the
minimum acceptable earth resistance.
055
The system performance reports with the reliability indices published
regularly, would give the information about such bottle necks in the
system affecting the reliability/security of supply. Although the system
is already designed to meet such criteria/guide lines in the beginning,
it may deviate from those criteria during the actual operation due to
some other factor or changes in reference conditions. The reliability
indices along with the other parameters would be monitored
continuously by the planning team to identify the reasons for outage or
deviation in the supply standards. Based on such inputs, system
augmentation/expansion would be proposed to improve the system
performance.
Personnel safety.
Condition monitoring results.
Performance statistics such as failure frequency, outage duration
and number of occurrences.
Criticality of Assets (based on type of customers).
Network criticality (such as N-1 compliance)
Life cycle cost
Age of assets.
Obsolescence.
Feedback from field staff.
Environmental hazard if any
056
Assets will be replaced considering above mentioned points and a
standard table is attached for reference.
Less than
*ARRC (%) 60% 70% 80% 80-100%
50%
Include in the
Include in the Include Urgent
Replacement No plan in 5 5 year plan
5 year plan next year Execution
Plan year with least
higher priority CAPEX required
priority
*ARRC-Asset risk report code created as per replacement template.
Purpose of procedure:
057
Step 1: Determine useful life cycle of an asset based on estimated
length of time during which the asset is able to deliver a
given level of service.
Step 5: Analysis
Asset Life cost analysis can be completed to help determine whether the
asset should be maintained or replaced, taking into various factors
contributing to Asset efficiency.Asset condition evaluation is based on:
The factors considered also involves the health and safety risk, risk to
assets, risk to the company’s reputation, financial impacts and
potential effects on the environment. The final project prioritisation list
(that incorporates scoring based on conditions and performance as well
as risk assessment), along with budgetary estimates and optioneering
form the basis of the annual replacement budgets for each fiscal year. It
is essential to capture and maintain adequate information on the
performance of assets in the field in order to undertake accurate
assessments.
058
1.6 Risk Management:
ADDC aims to increase awareness of the need of risk management and
provide a common risk management framework to manage all business
risks across the enterprise. ADDC Risk Management policy forms part
of ADDC’s internal control and corporate governance structure and is
an integral part of good practice asset management.
The policy aims to:-
059
6. Ensuring there is continuous improvement of the risk
management system to the benefit of ADDC.
060
1.7 Safety Requirements:
Safety is of Paramount importance in electricity distribution. Safety
requirements are to be met without any exception to safeguard human
life, property and environment. The prerequisites for safe operation and
maintenance of the electricity distribution system are enumerated in
ADDC System Safety Rules document. All the aspects/requirements of
the General safety adopted by ADDC are enumerated in brief below.
2. ADDC shall safeguard its staff, other workers, and the general
public, from its Electrical Apparatus when in normal use and
under all other reasonably foreseeable circumstances.
061
7. Overhead lines shall be installed at an adequate height so as to
prevent Danger. As a minimum, the height of overhead lines for
LV will be 6 m and for HV will be 7.5 m. Poles, towers and
supports for overhead lines will be marked with a warning label.
062
063