Professional Documents
Culture Documents
Excavation Itp
Excavation Itp
REV 00
INSPECTION & TEST PLAN PAGE 1-2
ITP Title INSPECTION & TEST PLAN FOR ROAD ITP NO. SEP-WAD-CIV-ITP-0001
1.2 Third Party Laboratory Inspection Laboratory Acceptance Certificate H/R H/R H H/R
1.3 Review of Soil Analysis Report 3rd party test report H/R H/R H H/R
calibration certificates for measuring
1.4 Calibration certificate H/R H/R H H/R
instruments
Procedures (with safety precautions
1.5 Risk assessment H/R H/R H H/R
recommendations)
2 Survey Works
Acceptance of the survey establishment and Approved Drawings, Approved Method
2.1 H/R H/R H/R R
references. Statement & Specs
3 EARTHWORKS
Clearing and grubbing
Removal and satisfactory disposal of trees,
3.1 H/R W/R W/R R
stumps, roots, vegetation, logs, rubbish and
other unsuitable material
3.2 Topsoil Removal and Stockpiling H/R W/R W/R R Photographic Report
Classification and review of excavated
3.3 3rd party test report H/R W/R W/R R
materials
Disposal of unsuitable materials
3.4 3rd party test report H/R W/R W/R R
Backfilling/Placement of Fill
3.5 Approved Method Statement H/R W/R W/R R
LEGEND
H: Hold Point W: Witness Point R: Document Review S: Surveillance
H: For Hold point, SEPCO will raise and submit RFI to owner, if owner did not attend the inspection then SEPCO will proceed the work to next stage through owner permission.
W: For witness point, SEPCO will raise and submit RFI to owner, if owner did not attend the inspection then SEPCO will proceed the work to next stage without owner permission.
Description
Location
Item No: Rev
ITP NO
Note:
Signature
Name
Title
Date
Excavation Checklist
Department RFI No.
Description
KKS No. Drawing No.
Location
ITP NO Item No: Rev:
SN Description Accepted Rejected Remarks
1 Removal of stumps, roots, vegetation, logs, rubbish and other unsuitable material
2 Excavation shall be carried out to the lines and levels shown on the drawings. Slopes and
formation surfaces shall be trimmed to the required profiles
5 Excavated material from the Works which is approved for re-use shall either be placed in
its final position or stockpiled on site
6 shall carry out excavation in a safe and careful manner such that the excavation is
adequately supported and stable
Note:
EPC
ISSUED BY Sub-Contractor SEPCO QC Owner
Construction
Signature
Name
Title
Date
3 Backfill fill material obtained from excavations or by dredging within the Site shall be
deposited in its final location as soon as practicable
Note:
EPC
ISSUED BY Sub-Contractor SEPCO QC Owner
Construction
Signature
Name
Title
Date
Note:
EPC
ISSUED BY Sub-Contractor SEPCO QC Owner
Construction
Signature N/A
Name
Title
Date