Week1 Week2 Week3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13
Task ID
Objecti
linked
ves
Task Description
1 Project Planning
2 Looking for sponsor 7
3 Discussing requirements with Sponsor ###
6 M
4 Produce a Project Proposal ###
5 Acceptance of Project Proposal 6 6
6 Planning on Terms of Reference, Schedule & Gantt Chart ###
9 ### 2
7 Discussing Terms of Reference(TOR) with Sponsor ###
### M
8 Discussing Terms of Reference(TOR) with Supervisor ###
### M
9 Finalised Schedule and Gantt chart ### 6
10 Finalised TOR with supervisor ### 5
11 Terms of Reference signoff by Supervisor and Sponsor ### ### M
12 First Review Submission ###
13 1 Relevant Literature and Research on topic ###
### ###
9 ### M
14 1 Finalising Relevant Literature on topic ### ###
9 ###
### M
15 2 Evaluation on relevant Literature to project ###
9 ###
###
### M
16 2 Preparation of Draft Research Chapters ###
###
###
###
### M
17 2 Finalising Research Chapters ###
###
###
### M
18 3 Design for Solution as per Requirement ### ###
### M
19 3 Discussing Design with client ###
###
###
20 3 Implementation for solution ###
###
###
### M
21 3 Discussing Implementation with Client ###
###
22 3 Finalised Implementation to client ###
###
23 4 Evaluation on Implementation Results ###
###
### M
24 4 Implementation Results to sponsor ###
25 5 Critical Evaluation on solution with Client Requirements ###
###
26 5 Critical Evaluation Against Client Requirements ### M
27 5 Dissertation Chapters Outline Preparations 6
28 5 Second Review Finalising 6
29 5 Second Review Submission to Supervisor
30 5 Research Chapters Review
31 6 Draft Dissertation Preparations
32 6 Interim Deliverables To Sponsor
33 6 Study On Overall Dissertation
34 7 Finalising Deliverables With Sponsor
MSc ITM project Schedule A.Student
Weeks
Task Objective Task Description Hours Start date End date Covered
planned actual planned actual
1 Project Planning 29/04/10 29/04/10 29/04/10 29/04/10
2 Looking for sponsor 7 30/04/10 30/04/10 1/5/2010 1/5/2010
3 Discussing requirements with Sponsor 12 2/5/2010 2/5/2010 4/5/2010 4/5/2010 WEEK-1
11 Terms of Reference signoff by Supervisor and Sponsor 9 23/5/2010 23/5/2010 25/5/2010 25/5/2010
12 First Review Submission 9 26/5/2010 26/5/2010 27/5/2010 27/5/2010
13 1 Relevant Literature and Research on topic 40 28/5/2010 28/5/2010 31/5/2010 31/5/2010 WEEK-4
14 1 Finalising Relevant Literature on topic 40 1/6/2010 1/6/2010 4/6/2010 4/6/2010 WEEK-5
15 2 Evaluation on relevant Literature to project 40 5/6/2010 7/6/2010 11/6/2010 11/6/2010 WEEK-6
16 2 Preparation of Draft Research Chapters 40 12/6/2010 14/6/2010 18/6/2010 18/6/2010 WEEK-7
17 2 Finalising Research Chapters 34 19/6/2010 21/6/2010 24/6/2010 24/6/2010 WEEK-8
18 3 Design for Solution as per Requirement 24 27/6/2010 28/6/2010 30/6/2010 30/6/2010
19 3 Discussing Design with client 15 1/7/2010 1/7/2010 4/7/2010 4/7/2010 WEEK-9
20 4 Implementation for solution 28 5/7/2010 5/7/2010 7/7/2010 7/7/2010
21 4 Discussing Implementation with Client 11 8/7/2010 8/7/2010 11/7/2010 11/7/2010 WEEK-10
22 4 Finalised Implementation to client 12 12/7/2010 12/7/2010 14/7/2010 14/7/2010
23 4 Evalaution on Implementation Results 25 15/7/210 15/7/2010 18/7/2010 18/7/2010 WEEK-11
24 4 Implementation Results to sponsor 8 19/7/2010 19/7/2010 20/7/2010 20/7/2010
25 5 Critical Evaluation on solution with Client Requirements 12 21/7/2010 21/7/2010 22/7/2010 22/7/2010
26 5 Critical Evaluation Against Client Requirements 6 23/7/2010 23/7/2010 24/7/2010 24/7/2010 WEEK-12
27 5 Dissertation Chapters Outline Preparations 6 25/7/2010 25/7/2010 25/7/2010 25/7/2010
28 Second Review Finalising 6 26/7/2010 26/7/2010 27/7/2010 27/7/2010
29 Second Review Submission to Supervisor 5 28/7/2010 28/7/2010 28/7/2010 28/7/2010
30 5 Research Chapters Review 12 29/7/2010 29/7/2010 31/7/2010 31/7/2010 WEEK-13
31 6 Draft Disseration Preparation 40 1/8/2010 1/8/2010 5/8/2010 5/8/2010
32 6 Interim Deliverables To Sponsor 2 6/8/2010 6/8/2010 6/8/2010 6/8/2010 WEEK-14
33 6 Study On Overall Dissertation 11 8/8/2010 9/8/2010 10/8/2010 10/8/2010