016 - SAS Redundancy
016 - SAS Redundancy
Switch OFF the GTW_B. After few second the HMI should
have an alarm for GTW_B disconnection.
Go on HMI. Go to Alarm page. Check the GTW_B
disconnection alarm is active.
Go on HMI. Go to System view. Check the GTW_B
representation is RED.
Check you can navigate on all the pages. On system view
check all the equipment is still active.
At this stage you can validate Redundancy is activated.
Switch ON the GTW_B in SAS panel. After few minutes, the
alarm should be inactive.
Go on HMI. Go to System view. Check the GTW_B
representation is GREEN.
condition.
Plug in the AC power supply.
Remove the DC power supply.
Go on HMI. Check the alarm. “AC power supply Failed” is not
active
Check an alarm is display. DC power supply Failed. During this
condition the switch should be in operational condition.
Plug in the DC power supply.
Go on HMI. Check the alarm. “DC power supply Failed” is not
active
4.0 REFERENCES
This document shall comply in accordance with the existing Company’s Rules and Regulations.
Any modifications therein found not conformance with the document shall be declared invalid.
For clarification and verification on this document, contact the following:
Substation
SAS Panel Name
DeviceType Serial No
In case of Substation Server failure the connected HMI Servers must switch
to the healthy Server.
__________________ __________________
Date Date
Commissioning Services Department
Company Name: Contract No : SAS Redundancy Test Formats
Project Title:
Indix DS-NG-6460-002-016 Date: Page:2
__________________ __________________
Date Date
Commissioning Services Department
Company Name: Contract No : SAS Redundancy Test Formats
Project Title:
Indix DS-NG-6460-002-016 Date: Page:3
Station- Station-
Function Remarks
GATEWAY-1 GATEWAY -2
Redundancy of SCADA communication
links
IEC-101 Link-1
IEC-101 Link-2
1.
IEC-101 Link-3
IEC-101 Link-4
IEC-104 Link-5
IEC-104 Link-6
Redundancy of GATEWAY
Switching to Gateway-2 when
communication of Gateway-1 fails
2. with SAS.
Switching to Gateway-1 when
communication of Gateway-2 fails
with SAS.
3. Coherency of Gateway data
__________________ __________________
Date Date
Commissioning Services Department
Company Name: Contract No : SAS Redundancy Test Formats
Project Title:
Indix DS-NG-6460-002-016 Date: Page:4
Not
Test Case Checked Approved
Approved Remarks
Operator Workstation 1 Faulty
Shutdown HMI 1 from LAN and generate
new inputs (events and alarms) on one
typical BCU. Initiate control of any
switching device.
Check functionality of connected
operator workstation 2(HMI-2)
Check updating of information
event/alarm/analogue appearance
on HMI 2
Check execution of command
Check appearance on dot printer
Check fault indication of HMI 1
Repeat the Procedure in case
when HMI-1 Application is
stopped.
Repeat the procedure in case
when LAN is removed.
__________________ __________________
Date Date
Commissioning Services Department
Company Name: Contract No : SAS Redundancy Test Formats
Project Title:
Indix DS-NG-6460-002-016 Date: Page:5
__________________ __________________
Date Date
Commissioning Services Department
Company Name: Contract No : SAS Redundancy Test Formats
Project Title:
Indix DS-NG-6460-002-016 Date: Page:6
__________________ __________________
Date Date
Commissioning Services Department
Company Name: Contract No : SAS Redundancy Test Formats
Project Title:
Indix DS-NG-6460-002-016 Date: Page:7
__________________ __________________
Date Date
Commissioning Services Department
Company Name: Contract No : SAS Redundancy Test Formats
Project Title:
Indix DS-NG-6460-002-016 Date: Page:8
__________________ __________________
Date Date
Commissioning Services Department
Company Name: Contract No : SAS Redundancy Test Formats
Project Title:
Indix DS-NG-6460-002-016 Date: Page:9
Not Remar
Sr. Check
Test Chec N.A ks
No ed
ked
Check the redundancy of the Ethernet
1. switches located on the rear of IED by
failing communication link/Channel. The
redundant Ethernet switch shall carryout the
communication without any
interruption(Zero Switch-Over).
__________________ __________________
Date Date