SP-2065 Technical Data Management
SP-2065 Technical Data Management
Document ID SP-2065
Security Restricted
Revision 6.0
This document is the property of Petroleum Development Oman, LLC. Neither the whole nor any part of this document
may be disclosed to others or reproduced, stored in a retrieval system, or transmitted in any form by any means
(electronic, mechanical, reprographic recording or otherwise) without prior written consent of the owner.
Petroleum Development Oman LLC Revision: 6.0
Effective: Jun-18
I Document Authorization
Authorized For Issue – June 2018
Page 2 of 38 SP-2065: Document Management in Engineering Projects and Operations Printed: June 25, 2018
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Jun-18
II Revision History
The following are brief revision summary of this document. Details of all revisions prior to
these are held on file by the issuing department.
Revision Date Authors Scope / Remarks
No.
Revision Mar- Mike Turberville 1. Updated numbering requirements. Aligned with
2.0 11 UEPI/1 changes to SP-2047
2. Roles and Responsibilities moved to Section 2
3. Definitions and Abbreviations moved to
Appendices
4. Updated some text to reflect changes in PDO
Doc management strategy for Projects
5. New Owner and Custodian.
Page 3 of 38 SP-2065: Document Management in Engineering Projects and Operations Printed: June 25, 2018
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Jun-18
The related CMS Documents can be retrieved from the CMS Business Control Portal:
Page 4 of 38 SP-2065: Document Management in Engineering Projects and Operations Printed: June 25, 2018
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Jun-18
Table of Contents
1. INTRODUCTION ........................................................................................................................... 7
1.1. Purpose................................................................................................................................... 7
1.2. Scope ....................................................................................................................................... 7
1.3. Distribution / Target Audience ....................................................................................... 7
1.4. Review and Improvement ................................................................................................ 8
1.5. Step-out Approval ............................................................................................................... 8
1.6. Abbreviations ........................................................................................................................ 8
1.7. Definitions .............................................................................................................................. 9
2. DOCUMENT MANAGEMENT ................................................................................................ 11
2.1. General Requirements.................................................................................................... 11
2.2. Project Initiation ................................................................................................................. 11
2.3. Document Planning Strategy ....................................................................................... 11
2.4. Design Document Planning .......................................................................................... 12
2.5. Vendor Information Planning ........................................................................................ 13
2.6. Document File Format .................................................................................................... 16
2.7. Review and Return of Comments .............................................................................. 17
2.8. Document Approval ......................................................................................................... 20
2.9. Documents Reviewed/Approved in 3D Model ....................................................... 21
2.10. Demolition Works .............................................................................................................. 22
2.11. Document with Hold Point ............................................................................................. 22
2.12. Cancelled and Superseded Documents .................................................................. 22
2.13. Suspended Project ........................................................................................................... 23
2.14. Construction Work Packs .............................................................................................. 23
2.15. Design and Construction Changes ............................................................................ 23
2.16. Red-Line Mark-Up (RLMU) ........................................................................................... 23
2.17. Final Information Deliverables Handover ................................................................ 24
2.18. Check-out and Check-in Requirements ................................................................... 26
2.19. Correspondence Numbering and Control ............................................................... 26
2.20. Quality Management ....................................................................................................... 27
3. DOCUMENT NUMBERING STRUCTURE ....................................................................... 28
3.1. Document Taxonomy ...................................................................................................... 28
3.2. Issue and Status Code ................................................................................................... 30
3.3. Revision Convention and Control ............................................................................... 31
3.4. Renumbering of “Old System” Documents ............................................................. 31
3.5. Vendor Documents Numbering ................................................................................... 32
3.6. Project ID and Project Code Administration ........................................................... 32
4. DOCUMENT EXCHANGE ....................................................................................................... 33
4.1. Collaboration Media ......................................................................................................... 33
4.2. Exchange of Documents ................................................................................................ 33
5. ROLES AND RESPONSIBILITIES ....................................................................................... 35
6. APPENDIXES ............................................................................................................................... 38
6.1. Appendix 1 – User Feedback Form ........................................................................... 38
Page 5 of 38 SP-2065: Document Management in Engineering Projects and Operations Printed: June 25, 2018
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Jun-18
Page 6 of 38 SP-2065: Document Management in Engineering Projects and Operations Printed: June 25, 2018
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Jun-18
1. INTRODUCTION
Information Management (IM) is one of the key requirements of Engineering and Operations
CoP (CP-117 and CP-115) within the Opportunity Realization CoP (CP-223). Within the
framework, project design deliverables need to be generated, reviewed and approved before
they are translated into physical assets that can be procured, constructed, commissioned
and operated.
Poor management of information has resulted in missed opportunities, higher costs, process
safety issues and even litigation. Engineering and Operations functions have adopted a
common framework for Information Management practice for PDO and their contractors that
ensure documents/drawings generated are delivered in a format compatible with PDO
systems. This document specifies the standard for document management in Engineering
and Operations, which shall be used in conjunction with PR-1666: Document, Drawing and
Data Control Procedure.
1.1. Purpose
The purpose of this specification is to define requirements for document management that
would support creation of documents suitable for use to support operations. These
requirements comprise:
Documents requirement planning
Document numbering taxonomy
Document development, issue, review, approval and update
Control hardcopy requirements
Document templates, exchange and tools
Document exchange process refers to the flow of documents within the project team, as well
as between the project team and external parties.
1.2. Scope
This document specifies the document management standard to be implemented in
engineering projects, which would deliver quality information deliverables for Operations. It
covers the general strategy for document management, vendor requirement, review and
exchange method, and numbering taxonomy. It defines the relationships, roles and
responsibilities of project team members, IM team, contractors and vendors during the
implementation.
1.3. Distribution / Target Audience
This document shall be used by PDO project delivery teams comprising of a project
manager, project engineers, technical discipline engineers and designers, operations and
project services personnel, as well as external project delivery partners: vendors, suppliers,
consultants and contractors.
Page 7 of 38 SP-2065: Document Management in Engineering Projects and Operations Printed: June 25, 2018
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Jun-18
Users of this Document who identify inaccuracy or ambiguity should notify the custodian or
his/her delegate, and request changes to be initiated. The Requests shall be forwarded to the
custodian using the “User Feedback Form” provided in the Appendix 1.
1.6. Abbreviations
In addition to the glossary and definition in the EIS, the following specific definitions of
abbreviations apply:
AIC Asset Information Centre
AI-PS Asset Integrity Process Safety
ARV Asset Register Verification (SP-2213).
CSV Comma Separated Values, a document format that allows data exchange
between different applications.
CSR Concept Selection Report
CMMS Computerized Maintenance Management System
DCC/DC Document Control Centre / Document Controller – Office / individual(s) that
provides all document control services as outlined on this document.
DCAF Discipline Control and Assurance Framework
DCS Document Control System – System set up and used by DCC/DC to provide
document control services during the life of a project.
DDR Document Deliverables Register – list of all project deliverables to be delivered
in a project.
DDM Document Distribution Matrix – distribution of all project deliverables as listed on
the DDR
EDMS Electronic Document Management System (Livelink) – PDO system used for
document storage/retrieval
EIS Engineering Information Specification
EPC Engineering Procurement and Construction
EMC Engineering Maintenance Contract
EOIM Engineering and Operations Information Management
ERP Enterprise Resource Planning
EPC, External Project Contractor responsible for all or part of the Design,
EMC, Engineering, Procurement, Construction, Commissioning or Management of a
Page 8 of 38 SP-2065: Document Management in Engineering Projects and Operations Printed: June 25, 2018
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Jun-18
1.7. Definitions
number revision.
Controlled / PDO E&O documents are controlled electronically in the document
Uncontrolled management system (ASSAI/Livelink), and become uncontrolled when
printed except when printed with Watermark/stamped “Control Hardcopy”.
Deliverable(s) Product(s) of an activity (ies) or undertaking(s). The product can be a
document, data or just an activity.
DCAF Discipline Control and Assurance Framework, that specifies TA level
required to review and approve discipline deliverables.
Document Manuals, drawing, reports, datasheet, etc
Document Project deliverables are managed electronically. Access to these
Security documents is on the “need-to-know” basis. All commercially sensitive
contract, project management and tender document will be retained in a
secure location on Livelink.
Electronic Electronic file created by scanning or direct rendition through software.
Image
IM deliverables Documents; drawings; MRBs; Engineering Data; SPIR; Asset
Register/CMMS; SPI/INTOOLS; Corrosion Data; Tag Register; 3D Model
IM Focal Point Information Management (IM) Staff: IM Lead, Document/Data Controller,
EDS Lead and or EDS Specialist, assigned to provide IM service
IM Kick-off Form Form used during project initiation, to request support information: Area
code, Tagging convention, EDS requirements, IM requirements existing
asset drawing/documents, etc
Inter-Discipline Contractor review cycle involving team members/disciplines outside the
Check originating discipline/team.
Livelink PDO corporate EDMS.
May The word ‘may’ is to be understood as a possible course of action.
MRB Document delivery format for vendor documentation, identified for delivery
as a result of manufacturing, installation, integration, commissioning and
handover of a piece of equipment.
Native File Editable Electronic File Format.
Petroleum Initiates the project and ultimately pays for its design and construction.
Development
Oman (PDO)
Project Team PDO staff assigned to deliver project scope (usually through contractor).
Shall The word ‘shall’ is to be understood as mandatory.
Should The word ‘should’ is to be understood as strongly recommended.
Start-up Introduction of hydrocarbon to a facility
Registers and Electronic copies of documents and drawings will be logged and filed by the
Filling DCC using appropriate document control tools (eg ASSAI) and in
accordance with the Project filing scheme.
User Any person who applies this standard.
Page 10 of 38 SP-2065: Document Management in Engineering Projects and Operations Printed: June 25, 2018
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Jun-18
2. DOCUMENT MANAGEMENT
2.1. General Requirements
Follow PR-1666: Document, Drawing and Data Management Procedure for document
reviews and approval process
Documents not yet issued should be kept in team work-in-progress work area (e.g.
livelink), while issued documents should be stored and controlled in a secured document
management system. Keeping work related files on the Desktop PC or any other storage
media outside dedicated work-in-progress team area is not allowed.
PDO TAs shall review revisions but only approve key milestone stages of a document
development e.g. AFD and AFC
Upon notification that a new member has joined the project team, IM on boarding shall be
conducted before granting access to Information Management system.
Project deliverables review/approval status report shall be issued by the project IM team
periodically to show performance of project IM KPIs
IM resource shall be in place to support project document management from Select
Phase.
PDO’s standard drawing symbol and digitizing menus shall be employed, as well as data
files for existing drawings which will be provided to assist the consultant/contractor during
detailed design, refer to SP-2099 for details.
The custodian of IM deliverables during project is the project manager. During operation,
the custodian of electronic master information from project is UOI2 (AIC) but the owner is
the Asset Operation Manager (CP-115).
The selected milestone dates shall be as contained in the project planning system (e.g.
Primavera), and be determined as part of project initiation and applied to develop project
DDR (for design deliverables) and VDDR (for vendor deliverables).
2.3.1. Existing Document Dependency
Where project scope includes modification of existing Asset documents, the project team
shall follow the Dependency Matrix requirements contained in SP-1131 and evaluate the
impact of the modification on the dependant deliverables.
The dependant documents shall be included by default in the project information delivery
scope of DDR and be verified/updated as part of project. Just like any existing document
identified by the contractor for modification in project, these documents shall be obtained for
reference during project and verified for impact by designated doctype design engineer.
Where project scope “impacted” any of the dependant documents it shall be checked out/in
from AIC for final update. In a “no impact” situation, the doctype discipline engineer shall
update the DDR indicating that the documents were “Verified for project scope, no impact”.
This is a key information deliverables handover assurance requirement that could impact
project closeout.
2.4. Design Document Planning
Design document planning requires each discipline to define a set of document deliverables
against each work package defined in the project planning system (e.g. Primavera). These
identified documents shall be used to create the document deliverables register (DDR).
2.4.1. Document Deliverables Register (DDR)
The DDR contains listing of information deliverables doctypes selected from PLIP, with their
tentative milestone delivery plan; click here for DDR project template. As part of project
initiation the contractor discipline engineer shall agree discipline scope with project team and
identify DDR doctypes from PLIP to become the high-level discipline DDR. The contractor
shall collate DDR discipline scope into one master DDR and issue to IM Lead and discipline
engineered for review/approval In line with DDM. The actual documents are generated
against doctype, added as new record in the DDR and shared with project team periodically:
Information development milestones defined and applied in the DDR shall be assigned a
planned start date and a planned end date (according to data from the planning system), and
shall be loaded into the project document control system with status “PLN”. The milestone
planned date for a doctype like PEFS shall be obtained from the planner and be applied for
all PEFS generated in the project unless advised differently.
The documents maturation progress can be measured as a percentage at each new
milestone attained. Contractor shall submit to PDO every two weeks the DDR progress
Page 12 of 38 SP-2065: Document Management in Engineering Projects and Operations Printed: June 25, 2018
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Jun-18
report indicating Contractor’s forecast dates of issue for review/approval of all relevant
documents/drawings.
2.4.2. Document Distribution Matrix
The DDM is a PDO business process for internal project document distribution which shall be
concluded as part of project initiation using template of appendix 12. It shall be applied each
time a project document created by a contractor, requires PDO review input and/or approval.
The PLIP contains default document distribution which shall be referred by the project team
to produce the project specific DDM. The DCC team shall apply the project specific DDM in
distributing project documents and will not accept distribution request outside the DDM.
The contractor shall develop and formalize their document distribution, as part of project
initiation, and shall be a key reference document for assurance reviews and audits.
Page 13 of 38 SP-2065: Document Management in Engineering Projects and Operations Printed: June 25, 2018
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Jun-18
Page 14 of 38 SP-2065: Document Management in Engineering Projects and Operations Printed: June 25, 2018
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Jun-18
review shall be distributed according to the VDDM as attached in appendix 11, and could be
adopted for use by the contractors involved in procurement.
2.6. Document File Format
2.6.1.General Format
Each electronic file shall be self contained, i.e. will not require or call in any other project
delivered electronic files for viewing or updating other than agreed reference files. It is not
acceptable for non-standard (Korean or Cyrillic) character set to be required to be installed
on user machine to allow the file to be used. All project documents shall be produced in
compliance with ISO standard A1, A3, and A4 sizes.
Where hardcopy submission forms part of the deliverable in the Project, the issue, review,
approval and “Control Hardcopy” requirement is the same as specified in this document but
the following requirement shall also be met as a minimum:
Hard copy prints to be submitted in collated sets.
Hard copies shall be submitted in a clearly legible paper format.
Documents shall be scanned at their original size directly from the original hard copy.
Images shall be scanned in an orientation that allows viewing without rotation.
Paper copies submitted in a size over A3 should be fan folded such that the title block will
be visible and allows easy insertion into plastic wallets.
A4 documents to be stapled or bound dependent on size.
Standard number of copies to be submitted for review should be agreed with project
team.
Unless specifically requested by project team to deliver native file for review, and when
review cannot be effectively performed electronically in pdf format, external party shall submit
review files in pdf (made from the rendition of native file). However the following document
types shall always be submitted in native format at all revision: all schedules, ASCI files and
all business process data files (registers, EDS seed files etc).
Where dates are held in databases the format shall be DD-MM-YYYY e.g. 05-10-2010 while
dates used on correspondence, etc shall be e.g. 12 December 2007.
2.6.2. Sets and Sizes of Files
File size for each design and vendor document (VDRL record) shall be a maximum of
200MB. Larger files and document delivered in multiple renditions (e.g. doc and PDF), shall
be split into smaller files and assembled into sets for delivery against a single document
number revision.
When splitting lager files into smaller files, the following shall apply:
Split the document at natural section breaks (indicated by section markers).
If the document has no natural section breaks but exceeds the allowable file size, the
document shall be split into allowed file-size limit.
When assembling split files into sets of files, the following shall apply:
Zip files are highly discouraged unless it is agreed with IM Focal point.
Page 16 of 38 SP-2065: Document Management in Engineering Projects and Operations Printed: June 25, 2018
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Jun-18
Nominate the primary document and treat it in the same way as any other document,
giving it a document number and revision.
Assign the same document number and revision to all other files in the Set, but name
each with a Document Title reflecting the sequence of the files as they should appear
in the complete document.
Acceptable examples are:
1. Vendor Manual Centrifugal Pump Model XYZ Sections 1 to 5
Vendor Manual Centrifugal Pump Model XYZ Sections 6 to 10
Vendor Manual Centrifugal Pump Model XYZ Appendix 1
Vendor Manual Centrifugal Pump Model XYZ Appendix 2
2. Compressor Station Layout PDF(Page 1-50 of 250)
Compressor Station Layout dwg (Page 51 – 180 of 250)
Compressor Station Layout xls (Page 181 - 250)
Page 17 of 38 SP-2065: Document Management in Engineering Projects and Operations Printed: June 25, 2018
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Jun-18
Some documents may not require updates after a certain point for the duration of their
lifecycle, it is expected that the originating discipline will remain aware of the state of the
documents for which they have responsibility.
Every document/drawing shall go through at least one review cycle before it is approved
except for standard or typical drawings. Standard and typical drawings that will be applied in
the project shall be identified in the DDM.
2.7.1.Project Team Document Review
Documents/drawings generated by contractor and identified in the DDM for project team
review and comments shall follow the following requirements:
ASSAI is the application through which project document deliverables are controlled
(reviewed and approved) while the actual electronic files are stored in Livelink (PDO
corporate EDMS).
All documents issued shall be accompanied with a transmittal indicating clearly the
purpose of issue (e.g. IFI, IFR). The default review cycle time is 10 working days but can
be adjusted to suit the requirement of the project.
Contractor shall ensure that adequate IDC review is undertaken to confirm technical
adequacy and quality before issue to PDO. Any delay or rework associated with low
quality information issued to PDO shall be the contractor’s responsibility.
For information that does not require PDO review, contractor shall ensure that document
is reviewed internally by contractor’s engineer with commensurate technical capability.
Documents or drawings issued for review/comment in pdf format shall be made from the
direct rendition of native file (‘comment-enabled’).
PDO shall comment and return to Contractor within 10 working days all requested
documents which are issued in accordance with the forecast dates in the DDR. PDO
shall not be obliged to return within 10 working days any documents that are not issued
in accordance with the forecast report issued by the Contractor.
In the event documents have not been returned to Contractor within ten working days
after issue, Contractor shall advise PDO in writing of their intention to proceed with the
Work, detailing the relevant documents. If PDO does not return the documents within the
next (….timing to be agreed with project team….), Contractor shall issue the relevant
documents at the next stage in document development and mark them with the following:
“PDO Comment Default”;
Number of transmittal under which the documents were submitted for
comment;
Reference and date of reminder written advice.
Contractor will implement all comments made by PDO unless the Contractor disagrees
with the comments, in which case the comments in question shall be discussed and the
follow up requirements agreed with PDO prior to their implementation.
The Contractor shall maintain a Comment Response Sheet to trace comment history.
Page 18 of 38 SP-2065: Document Management in Engineering Projects and Operations Printed: June 25, 2018
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Jun-18
Page 19 of 38 SP-2065: Document Management in Engineering Projects and Operations Printed: June 25, 2018
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Jun-18
PDO system would hold the review and approval version of the document revisions. Records
of IDC shall be maintained, to show contractor internal review/approval outcome, which could
be required during assurance reviews and audits.
2.8. Document Approval
Typical or Standard drawings can be issued approved at revision 1 as long as these
drawings are identified as typical/standard drawings on the DDR. Single discipline (no RTA
from other discipline) deliverables already reviewed in IDC (copied PDO IFI) should issued
AFC, as long as the recorded evidence of IDC TA input/review is attached to the Assai.
Checking of Final As-Built drafted against authorized RLMU should be done by contractor
engineer with capability to validate the outcome of the drafting work.
2.8.1. Project Team Document Approval
The following requirements shall be followed for documents/drawings identified in the DDM
for project team approval:
These documents shall be issued for approval after project team review was completed;
refer section 3.2 for issue cycle guide.
Documents shall be approved electronically first by the designated TA or document
owner and, or PM (or delegate) using the electronic document management system
(ASSAI), with sufficient audit trail.
When new revision of document existing in hardcopy is issued, the hard copy custodian
shall replace existing hardcopy at all the places where they are located.
Project team shall return to Contractor within 10 working days all documents which are
issued in accordance with the forecast. Project team shall not be obliged to return within
10 working days any documents that are not issued in accordance with the forecast by
the Contractor.
If documents have not been returned to Contractor within 10 working days after issue,
Contractor shall advise PDO in writing of Contractor’s intention to proceed with the Work,
detailing the relevant documents. If PDO does not return the documents within the next
(….timing to be agreed with project team….), Contractor shall issue the relevant
documents at the next stage in document development and mark them with the following:
“PDO Approved by Default”;
Number of transmittal under which the documents were submitted for
approval;
Reference and date of reminder written advice.
If the documents issued for approval are returned to Contractor with comments, the
documents shall be treated as if they were issued for comments and after
implementation of the comments, be re-Issued for Approval.
To approve a document, the approver shall log-on to Assai system and after confirming
all comments are incorporated, type "No Comment" on Assai comment template and
select appropriate return code to close the approval cycle.
Page 20 of 38 SP-2065: Document Management in Engineering Projects and Operations Printed: June 25, 2018
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Jun-18
Page 21 of 38 SP-2065: Document Management in Engineering Projects and Operations Printed: June 25, 2018
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Jun-18
Page 22 of 38 SP-2065: Document Management in Engineering Projects and Operations Printed: June 25, 2018
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Jun-18
drawing blocks shall be scanned to sit in front of the cancelled document/drawing and the
status shall change to “CAN” in ASSAI. Cancelled document numbers shall on no account be
re-allocated to newly created documentation.
2.12.2. Superseded Documents
Documents are superseded when document metadata is updated (e.g. change of doctype,
etc), and when a document is replaced with a new document. The document status is
changed to SUP, and for the second case the party superseding shall clearly identify on the
document and in the document control system, which document it has been superseded with.
2.13. Suspended Project
When a project is placed on hold, the PDO Project Engineer shall recall and freeze all the
AFC documents/drawings (electronic and hardcopy) for the Project. The Contractor shall
ensure that the status of all project documents/drawings produced, including vendor
documentation is updated in the CSV load file as “SUS” and forwarded to the IM Lead. The
IM Lead shall retain these documents in the project document management system with the
status “SUS”.
2.14. Construction Work Packs
The design Contractor (if different), shall prepare and agree the construction Work packs with
PDO Project Engineer and deliver to the construction Contractor. Copy of the transmittal
shall be delivered to PDO IM Delivery Lead
Unless stated differently in contract, at the end of construction, the construction contractor
shall generate and deliver the final RLMU drawings to design contractor to produce As-Built.
2.15. Design and Construction Changes
Follow PR-1247: Project Management of Change for design and construction change
management. Once design change is approved the drawings/documents shall be updated
and issued, and the latest revision shall sent to site.
The contractor shall maintain proper documentation of construction changes. Markups
generated as a result of different construction activities on same drawing shall be collated to
produce the master RLMU.
2.16. Red-Line Mark-Up (RLMU)
RLMU is generated: by the asset operation team when reference master document/drawing
does not reflect physical installation and as a result of project delivery of new asset or
modification of existing asset.
2.16.1. Project Delivery RLMU
After commissioning, the construction contractor accumulates all changes and prepares the
master “red line” mark-ups, which shall be checked and authorized by contractor.
The construction contractor shall obtain signatures from designated CSR and commissioning
engineer/team. The RLMU produced for different systems, etc, contained on same drawing
shall be assembled into one Master RLMU under one document number
The Contractor shall produce 2 (two) hardcopies of signed final red-line mark-up drawings,
make a clean scanned copy and distribute as follows:
Page 23 of 38 SP-2065: Document Management in Engineering Projects and Operations Printed: June 25, 2018
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Jun-18
Page 24 of 38 SP-2065: Document Management in Engineering Projects and Operations Printed: June 25, 2018
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Jun-18
Page 25 of 38 SP-2065: Document Management in Engineering Projects and Operations Printed: June 25, 2018
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Jun-18
contractually and grammatically correct. For those activities provided by a sub-vendor, the
sub-vendor contact data shall be clearly documented and included in the MRB.
MRB delivery scope shall be as contained in the equipment list of appendix 15.
2.18. Check-out and Check-in Requirements
Master Deliverables are checked-out from AIC only for As-Building (not for project duration).
The contractor is required to transfer the content of the project drawings/RLMUs on to the
master and return back to AIC within the checkout timeline of 25 days for EMC/ODC, Well
Completion, Integrity and FCP projects. After this period, the check-out activity is cancelled to
make deliverable available for another project.
The contractor handover will not be accepted by PDO and they will be required to check-out
the master again. Contractor can obtain approval from the Project IM Lead to extend check-
out timeline for some deliverables that could not be delivered within the standard timeline.
2.19. Correspondence Numbering and Control
Formal Correspondence relates to any communication medium containing project
management communication or business information that may be retained for project close-
out, legal, operational, fiscal or other critical business purposes. It is the intention that formal
correspondence shall be managed through PROCON Contract Management System but
where official dispensation has been obtained for PROCON not to be used on a project, and
then each correspondence will be produced containing the following minimum attribute:
o Unique number (showing sender/receiver) in the upper left corner
o the author of the correspondence
o recipients
o if reply is expected and expected reply date
o email address of the originating party
o Maintain Project Correspondence Control Registers, (Incoming / Outgoing)
o Signed original shall be delivered via surface mail to the current address of project
DCC (to be advised separately)
o Maintain hardcopy master files of all correspondence received (clearly stamped
with date-received).
o Expedite all indicated responses for correspondence received and issue
Correspondence Status Reports
Originator of any outgoing correspondence shall be responsible for ensuring that:
It is processed through the Document Control Center.
The content of the correspondence is contractually and grammatically correct
Where electronic mail is used to provide instruction to Contractor or Supplier, it shall be
followed-up with a formal writing using minutes of meeting or formal correspondence as
appropriate, and registered in DCC. Until this is done, the instruction shall not be binding.
Such confirmation shall be forwarded within five (5) working days.
2.19.1. Document Exchange in FEED Office
FEED Office is the PDO design team that provides design services for project team (Asset
team and CPD), and often provide document review and approval support on behalf of
Page 26 of 38 SP-2065: Document Management in Engineering Projects and Operations Printed: June 25, 2018
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Jun-18
project team when designated. For a project to be executed in FEED Office, the authorized
project IM Plan shall show clearly the document review and approval strategy for project (if
FEED Office will review (IDC/IFR)/approve on behalf of project team or project team (IFR) by
themselves).
Internal document review cycle in FEED Office shall be completed as part of IDC. For
documents that require project team review/approval, the IDC shall be completed before the
document is circulated for review/approval. Where FEED Office is designated to review/
approve on behalf of the project team, IDC/IFR could be combined as part of revision 1.
2.20. Quality Management
Follow the assurance requirements as contained in SP-2122. The Contractor shall confirm
understanding of contract IM scope of work in line with GU-691: Engineering Information
Quality Management Framework.
The Document Controller will ensure that the correct template, document number, revision
status and title are on a document prior to issue or distribution, and will facilitate the timely
document review turnaround.
The responsible Engineer shall ensure that document is developed using the correct
template and that all meta-data are populated on the document.
Page 27 of 38 SP-2065: Document Management in Engineering Projects and Operations Printed: June 25, 2018
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Jun-18
Area Code: As defined in Corporate ERP System (SAP FLOC Level 5 Location code).
This code will be derived in line with SP-2152 section 2.3 and supplied by the Asset
Information Centre (AIC) via the “IM Kickoff Form”, see Appendix 2.
Process (system) Unit Code: As contained in SP-2152: Specification for Tagging and
FLOC Level 5 appendix II. For drawing/document cutting across the whole facility (e.g.
Overall Plot Plan, Operation HSE Case), or drawing of an area in which an equipment
was not installed, the code shall be “00”.
Originator Code: A 6-10 character code assigned to identify the party generating the
document in relation to the overall project. Every activity undertaken by a contractor or
vendor is governed by the provisions of the contract or purchase order (PO). The contract
and PO number allocated shall be used as originator code for “design” & “vendor” IM
deliverables respectively, to identify and relate a piece of equipment IM deliverable to a
particular project/asset. The code shall apply as follows:
Even when the same vendor is delivering service to more than one project, the PO
number assigned for each procurement activity would be different. During operation,
each piece of equipment would be associated to the project that delivered it (not
vendor) using the unique PO number.
When a vendor is engaged directly by PDO, to procure equipment and the equipment
would be allocated to a known ongoing project (e.g. in EMC project), the “originator
code” shall be the 6-10 character contract number of party receiving the equipment for
installation (allottee).
When a vendor is engaged directly by PDO, to procure equipment and the equipment
would be allocated to a not-yet-known project (e.g. in EMC project), the “originator
code” shall be the 6-10 character PO number issued by PDO to the vendor. As
defined in Corporate ERP System (SAP) for existing organizations/entities registered
as vendors (i.e. SAP vendor list).
When PDO engage an EPC or EP&C contractor, and the scope includes procurement
of one or more equipment, then the “originator code” for both the design and vendor
deliverables shall be the PDO contract number with the main Contractor. This code
shall be 6 character for design IM deliverables, and 6-10 character (the 6 character
Page 28 of 38 SP-2065: Document Management in Engineering Projects and Operations Printed: June 25, 2018
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Jun-18
Page 29 of 38 SP-2065: Document Management in Engineering Projects and Operations Printed: June 25, 2018
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Jun-18
For clarification, a sheet is a separate electronic file. Multiple pages could exist within a
single file (such as a line list) and should be noted as pages, not sheets. For the purpose
of project execution activities, dispensation may be applied for the use of document
grouping to facilitate effective document review and approval. However during final
submission, these grouped documents shall be split back to single sheet before delivery
to PDO.
3.2. Issue and Status Code
Review and approval of a project document is a very important aspect of delivering an
engineering project to the right quality. Typically an engineering project document will go
through several reviews and changes by multiple parties until it attains final approval status.
As such, a transparent and systematic method that indicates the status of the content of the
document at any point in time during the document flow is essential.
“Issue” codes (transmittal code) are those codes that are used to identify the purpose for
which a document is issued while “status” codes are used to identify the current state of the
document in the development chain. The following table illustrates how “status” codes are to
be applied in engineering projects:
sequence number, which shall be the ORIGINAL sequence number prefaced by 9, the new
number shall be formed by using the taxonomy in this specification. The Originator code is
“000000” and it is constant for all re-numbered document.
HWL-1-4503-008-A
Page 32 of 38 SP-2065: Document Management in Engineering Projects and Operations Printed: June 25, 2018
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Jun-18
4. DOCUMENT EXCHANGE
The following sections defines requirement that ensures that all Engineering Project
documentation sent to PDO is received and returned via formal exchange channels and to
standard and formats that have been agreed between the Project and its contracting
partners. Failure to agree upon a standard approach for the receipt and return of deliverable
will lead to unnecessary delay and possible financial loss among all parties working on the
Project.
4.1. Collaboration Media
PDO maintain a sharing and collaboration area on Livelink extranet site for the purposes of
sending and receiving formally transmitted documentation with external parties. All
documents sent to the project team should be forwarded via this medium. A detailed folder
structure will be set up and agreed with each external party with required access permissions
in place.
Documents sent by the first party should be removed and stored in an appropriate location
once received by the other party. Documentation sent via any other communication medium
will not be accepted unless prior approval has been sought and granted by the project team.
4.2. Exchange of Documents
During the project, all exchange of documentation between PDO and external partner shall
be through the DCC. Internal documents issued within project team shall be under the cover
of an ASSAI internal transmittal. Internal document distribution shall be according to the
distribution matrix. Originator or responsible engineer shall issue an email to DCC requesting
a document to be issued. External documents issued to or from the project team for the
purposes of review, approval or information should be placed on the FTP or Livelink extranet
site under the cover of a transmittal. An E-mail notification should be sent to relevant DCC
personnel notifying them about the placement.
4.2.1. Document Transmittal
Both internal and external transmittals shall contain the following information as a minimum:
Unique Transmittal Number
Purpose for Issue
Transmittal Date
Expected due date for (return of comments)
Project Document Number
Document Title
Revision Code
Revision Date
Document Status Code
Sender: Address, telephone, fax and e-mail details
Name of Sender
Purchase Order or Contract Number (For Vendor or Contractor)
Page 33 of 38 SP-2065: Document Management in Engineering Projects and Operations Printed: June 25, 2018
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Jun-18
CSV Template.xls
Page 34 of 38 SP-2065: Document Management in Engineering Projects and Operations Printed: June 25, 2018
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Jun-18
Page 35 of 38 SP-2065: Document Management in Engineering Projects and Operations Printed: June 25, 2018
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Jun-18
Advise distribution list for each document and closeout date for
document review cycle if different from standard.
Collates, clarify and incorporates review comments. This
includes resolving conflicting opinions and feedback between
reviewers.
Provides confidentiality requirements (Unclassified, Restricted,
Confidential, Most Confidential) to DCC
Ensuring that documents are approved to the correct level of
discipline TA prior to issue to the project DCC for distribution.
Document Owner He/She owns document content, responsible for the completion and
(ATA) execution of the document, and ultimately responsible for the
document quality in terms of business relevance and audit ability.
Document Custodian Accountable person in the business area where the document is
applied. In project this role is the PM (or delegate).
Approver or Technical Relevant person identified on the distribution matrix or PCAP to
Authority(TA) approve a document.
In line with section 2.3.1, authorize discipline document that are not
impacted by project scope.
Responsible Engineer Discipline focal person assigned to provide review input or
support the delivery of discipline scope of the project, package
and equipment.
He/she reviews DDR, and document schedule from external
parties, and validate the documents that must be submitted “for
discipline review and approval” or “for information”.
Provides discipline input as part of DDM development
Ensures that document received for comments are processed
and returned to contractor/vendor within a specified timeframe,
and ultimately delivers the document or work package.
Delegation of this role shall be officially communicated.
Project Engineer Ensure that existing documents impacted by project scope are
(Construction Site evaluated for impact in line with section 2.3.1
Representative) Ensure that information deliverables are duly generated and
delivered in time to support PSUA, commissioning and start-up.
Ensure that all changes made during the construction phase are
MoC controlled, and that mark-up on the related documents are
returned to Document Originator for As-Building.
Page 36 of 38 SP-2065: Document Management in Engineering Projects and Operations Printed: June 25, 2018
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Jun-18
Asset Information UOI2 team where Master Information: As-Built drawings, EDS
Center (AIC) System files and other CFD documents are centrally located and
managed. Other functions of AIC shall include, but not be limited to:
Receive final handover IM deliverables (design and vendor)
electronically from project as part of structured and scheduled
handover, sign PCC and load in the IM system.
Issue publish notification to all stakeholders requesting them to
“Replace” any copy in their custody
Ensure that users have adequate access to view latest
Information in IM Portal
Issue support information as requested on the IM Kickoff Form:
Master Information required for any Brownfield modification or
asset expansion, Tag number allocation, etc.
Ensure that current status and true position of information is
clearly indicated in IM systems
Manage this Information throughout Asset Operations Lifecycle
Sustainability IM Team Receive the publish notification from AIC and follow-up with OI
Field Coordinator to supersede controlled hardcopy in the
station.
Process Controlled Hardcopy of Tier 1 Critical Documents and
deliver to the field
Monitor field IM performance and report compliance against
agreed KPIs
Project IM Delivery Ensure adequate compliance to the requirement of this
Lead specification
Ensures that Information to be delivered to AIC is in compliance
with approved IM standard for quality
Manage the Document Control Center and the Document
Controller
Archive Management Maintains the Projects Documentations in the archive for the
specified retention life of the document
Reviewers Reviews documents and provide comments to the originator or
responsible engineer within the review window.
Document Templates Appendix 9 for document templates for use by the Contractors.
Page 37 of 38 SP-2065: Document Management in Engineering Projects and Operations Printed: June 25, 2018
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Jun-18
6. APPENDIXES
6.1. Appendix 1 – User Feedback Form
6.2. Appendix 2 – IM Kickoff Form
6.3. Appendix 3 – Blank VDRL and Equipment List and Customized VDRL
6.4. Appendix 4 – Information Requirement scope for MR/PO
6.5. Appendix 5 - Document Status Code Descriptions
6.6. Appendix 6 – Vendor MRB Document Cover Sheet
6.7. Appendix 7 - Vendor Document Schedule (VDS) Blank template
6.8. Appendix 8 - Vendor Document Requirement Catalogue (VDRC)
6.9. Appendix 9 – Document Templates: Excel, Word and Drawing
6.10. Appendix 10 – Comment Resolution Sheet (CRS)
6.11. Appendix 11 – Vendor Document Requirement Matrix (VDDM)
6.12. Appendix 12 – Document Distribution Matrix
6.13. Appendix 13 – Document Deliverables Register
6.14. Appendix 14 – Master Document/Drawing Revision Conversion
6.15. Appendix 15 - Equipment List and Vendor MRB Delivery
Page 38 of 38 SP-2065: Document Management in Engineering Projects and Operations Printed: June 25, 2018
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.