Professional Documents
Culture Documents
Budget Operation Desember 2020
Budget Operation Desember 2020
Working Schedule
Shift Start End Sub Rest Losses Grand Util
I 7:00 AM 7:00 PM 12 1 2.00 9.00
75.00%
II 7:00 PM 7:00 AM 12 1 2.00 9.00
24 2 4.00 18.00
DAILY ORDER
Date 1 2 3 4 5 6 7 8 9 10
Fuel Tank 5,000 5,000 5,000 5,000 5,000 25,000
Ballanced 3,713 2,426 6,138 4,851 8,564 7,277 10,989 9,702 8,415 12,128
Date 11 12 13 14 15 16 17 18 19 20
Fuel Tank 5,000 5,000 5,000 5,000 20,000
Ballanced 10,840 14,553 13,266 11,979 15,691 14,404 18,117 16,830 15,542 19,255
Date 21 22 23 24 25 26 27 28 29 30
Fuel Tank 5,000 5,000 5,000 5,000 20,000
Ballanced 17,968 21,681 20,393 24,106 22,819 21,532 25,245 23,957 27,670 26,383
65,000
Mine 65,000
RINCIAN GAJI KARYAWAN PPh 21
ANNUAL INCOME
STATUS PTKP
% K/0 Rp 4,320,000
5% Rp 25,000,000 K/1 Rp 5,760,000
10% Rp 50,000,000 K/2 Rp 7,200,000
Monthly Working Hours 25 15% Rp 100,000,000 K/3 Rp 8,640,000
Daily COLA 2.5% 25% Rp 200,000,000 TK/0 Rp 2,880,000
Monthly Overtime 125% 35% > Rp 200,000,000 TK/1 Rp 4,320,000
TK/2 Rp 5,760,000
TK/3 Rp 7,200,000
TAKE HOME PAY STAT PPh 21 TOTAL
DESCRIPTION REQ. BPJS K BASE TAX
BASIC TL O/T TJ TOTAL US LVL PENSION THP NETTO PTKP PKP DEBT THP BPJS K PPh 21 SUBTOTAL
MANAGER
General Manager 0 Rp 15,000,000 Rp 15,000,000 Rp 30,000,000 Rp 861,000 Rp 30,861,000 K/0 Rp - Rp 617,220 Rp 30,243,780 Rp 360,000 Rp 29,883,780 Rp 4,065,900 Rp - Rp - Rp - Rp -
HR/GA Manager 0 Rp 12,500,000 Rp 10,000,000 Rp 22,500,000 Rp 717,500 Rp 23,217,500 K/0 Rp - Rp 464,350 Rp 22,753,150 Rp 360,000 Rp 22,393,150 Rp 2,942,306 Rp - Rp - Rp - Rp -
Project Manager 1 Rp 10,000,000 Rp 5,000,000 Rp 15,000,000 Rp 574,000 Rp 15,574,000 K/0 Rp - Rp 311,480 Rp 15,262,520 Rp 360,000 Rp 14,902,520 Rp 1,818,711 Rp 15,000,000 Rp 574,000 Rp 1,818,711 Rp 17,392,711
PRODUCTION
Prod. Sec. Head 0 Rp 10,000,000 Rp 2,500,000 Rp 2,500,000 Rp 15,000,000 Rp 574,000 Rp 15,574,000 K/0 Rp - Rp 311,480 Rp 15,262,520 Rp 360,000 Rp 14,902,520 Rp 1,818,711 Rp - Rp - Rp - Rp -
Prod. Supervisor 1 Rp 5,000,000 Rp 3,000,000 Rp 8,000,000 Rp 287,000 Rp 8,287,000 K/0 Rp - Rp 165,740 Rp 8,121,260 Rp 360,000 Rp 7,761,260 Rp 747,522 Rp 8,000,000 Rp 287,000 Rp 747,522 Rp 9,034,522
Prod. Foreman/ML 4 Rp 3,500,000 Rp 1,500,000 Rp 5,000,000 Rp 200,900 Rp 5,200,900 K/0 Rp - Rp 104,018 Rp 5,096,882 Rp 360,000 Rp 4,736,882 Rp 293,866 Rp 20,000,000 Rp 803,600 Rp 1,175,463 Rp 21,979,063
Mekanik 2 Rp 1,750,000 Rp 2,187,500 Rp 3,937,500 Rp 100,450 Rp 4,037,950 K/0 Rp - Rp 80,759 Rp 3,957,191 Rp 360,000 Rp 3,597,191 Rp 255,552 Rp 7,875,000 Rp 200,900 Rp 511,105 Rp 8,587,005
Checker/Dumpman 4 Rp 1,000,000 Rp 1,250,000 Rp 2,250,000 Rp 57,400 Rp 2,307,400 K/0 Rp - Rp 46,148 Rp 2,261,252 Rp 360,000 Rp 1,901,252 Rp 95,063 Rp 9,000,000 Rp 229,600 Rp 380,250 Rp 9,609,850
ENGINEERING
Engineering Sec. Head 0 Rp 10,000,000 Rp 2,500,000 Rp 2,500,000 Rp 15,000,000 Rp 574,000 Rp 15,574,000 K/0 Rp - Rp 311,480 Rp 15,262,520 Rp 360,000 Rp 14,902,520 Rp 1,818,711 Rp - Rp - Rp - Rp -
Mine Plan Engineer 1 Rp 5,000,000 Rp 1,500,000 Rp 1,500,000 Rp 8,000,000 Rp 287,000 Rp 8,287,000 K/0 Rp - Rp 165,740 Rp 8,121,260 Rp 360,000 Rp 7,761,260 Rp 747,522 Rp 8,000,000 Rp 287,000 Rp 747,522 Rp 9,034,522
Surveyor 1 Rp 3,000,000 Rp 1,000,000 Rp 4,000,000 Rp 172,200 Rp 4,172,200 K/0 Rp - Rp 83,444 Rp 4,088,756 Rp 360,000 Rp 3,728,756 Rp 268,709 Rp 4,000,000 Rp 172,200 Rp 268,709 Rp 4,440,909
Survey Crew 2 Rp 1,500,000 Rp 1,875,000 Rp 3,375,000 Rp 86,100 Rp 3,461,100 K/0 Rp - Rp 69,222 Rp 3,391,878 Rp 360,000 Rp 3,031,878 Rp 199,021 Rp 6,750,000 Rp 172,200 Rp 398,042 Rp 7,320,242
HEALTH, SAFETY & ENVIRONMENT Rp -
HSE Officer 0 Rp 1,500,000 Rp 1,500,000 Rp 1,500,000 Rp 4,500,000 Rp 86,100 Rp 4,586,100 K/0 Rp - Rp 91,722 Rp 4,494,378 Rp 360,000 Rp 4,134,378 Rp 309,271 Rp - Rp - Rp - Rp -
LOGISTIC & WAREHOUSE
Logistic Supervisor 1 Rp 4,500,000 Rp 4,500,000 Rp 258,300 Rp 4,758,300 K/0 Rp - Rp 95,166 Rp 4,663,134 Rp 360,000 Rp 4,303,134 Rp 228,803 Rp 4,500,000 Rp 258,300 Rp 228,803 Rp 4,987,103
Fuelman 2 Rp 1,500,000 Rp 1,875,000 Rp 3,375,000 Rp 86,100 Rp 3,461,100 K/0 Rp - Rp 69,222 Rp 3,391,878 Rp 360,000 Rp 3,031,878 Rp 199,021 Rp 6,750,000 Rp 172,200 Rp 398,042 Rp 7,320,242
EQUIPMENT
Excavator PC-400 2 Rp 2,500,000 Rp 4,000,000 Rp 6,500,000 Rp 143,500 Rp 6,643,500 K/0 Rp - Rp 132,870 Rp 6,510,630 Rp - Rp 6,510,630 Rp 559,928 Rp 13,000,000 Rp 287,000 Rp 1,119,856 Rp 14,406,856
Exca DOOSAN-300 0 Rp 2,500,000 Rp 3,500,000 Rp 6,000,000 Rp 143,500 Rp 6,143,500 K/0 Rp - Rp 122,870 Rp 6,020,630 Rp - Rp 6,020,630 Rp 486,428 Rp - Rp - Rp - Rp -
Excavator PC-300 2 Rp 2,500,000 Rp 3,000,000 Rp 5,500,000 Rp 143,500 Rp - K/0 Rp - Rp - Rp - Rp - Rp - Rp - Rp 11,000,000 Rp 287,000 Rp - Rp 11,287,000
Dozer D-4 0 Rp 2,500,000 Rp 3,000,000 Rp 5,500,000 Rp 143,500 Rp 5,643,500 K/0 Rp - Rp 112,870 Rp 5,530,630 Rp - Rp 5,530,630 Rp 412,928 Rp - Rp - Rp - Rp -
Dozer D-65 Ess 4 Rp 2,500,000 Rp 3,500,000 Rp 6,000,000 Rp 143,500 Rp 6,143,500 K/0 Rp - Rp 122,870 Rp 6,020,630 Rp - Rp 6,020,630 Rp 486,428 Rp 24,000,000 Rp 574,000 Rp 1,945,711 Rp 26,519,711
Grader 0 Rp 2,500,000 Rp 4,000,000 Rp 6,500,000 Rp 143,500 Rp 6,643,500 K/0 Rp - Rp 132,870 Rp 6,510,630 Rp - Rp 6,510,630 Rp 559,928 Rp - Rp - Rp - Rp -
ADT 6 Rp 2,500,000 Rp 3,000,000 Rp 5,500,000 Rp 143,500 Rp 5,643,500 K/0 Rp - Rp 112,870 Rp 5,530,630 Rp - Rp 5,530,630 Rp 412,928 Rp 33,000,000 Rp 861,000 Rp 2,477,567 Rp 36,338,567
Hino 260 0 Rp 2,500,000 Rp 2,750,000 Rp 5,250,000 Rp 143,500 Rp 5,393,500 K/0 Rp - Rp 107,870 Rp 5,285,630 Rp - Rp 5,285,630 Rp 376,178 Rp - Rp - Rp - Rp -
Water Truck / FT 2 Rp 1,500,000 Rp 1,500,000 Rp 3,000,000 Rp 86,100 Rp - K/0 Rp - Rp - Rp - Rp - Rp - Rp - Rp 6,000,000 Rp 172,200 Rp - Rp 6,172,200
HR & GA
HR/GA Sec. Head 0 Rp 6,000,000 Rp 3,000,000 Rp 9,000,000 Rp 344,400 Rp 9,344,400 K/0 Rp - Rp 186,888 Rp 9,157,512 Rp 360,000 Rp 8,797,512 Rp 902,960 Rp - Rp - Rp - Rp -
HR staff/payroll 1 Rp 1,500,000 Rp 1,875,000 Rp 3,375,000 Rp 86,100 Rp 3,461,100 K/0 Rp - Rp 69,222 Rp 3,391,878 Rp 360,000 Rp 3,031,878 Rp 199,021 Rp 3,375,000 Rp 86,100 Rp 199,021 Rp 3,660,121
1
ADMIN. & FINANCE
Accounting 0 Rp 1,800,000 Rp 2,250,000 Rp 4,050,000 Rp 103,320 Rp 4,153,320 K/0 Rp - Rp 83,066 Rp 4,070,254 Rp 360,000 Rp 3,710,254 Rp 266,859 Rp - Rp - Rp - Rp -
Mine Stastician 2 Rp 1,500,000 Rp 1,875,000 Rp 3,375,000 Rp 86,100 Rp 3,461,100 K/0 Rp - Rp 69,222 Rp 3,391,878 Rp 360,000 Rp 3,031,878 Rp 199,021 Rp 6,750,000 Rp 172,200 Rp 398,042 Rp 7,320,242
Security 4 Rp 1,500,000 Rp 1,875,000 Rp 3,375,000 Rp 86,100 Rp 3,461,100 K/0 Rp - Rp 69,222 Rp 3,391,878 Rp 360,000 Rp 3,031,878 Rp 199,021 Rp 13,500,000 Rp 344,400 Rp 796,085 Rp 14,640,485
Office Boy 1 Rp 1,500,000 Rp 1,875,000 Rp 3,375,000 Rp 86,100 Rp 3,461,100 K/0 Rp - Rp 69,222 Rp 3,391,878 Rp 360,000 Rp 3,031,878 Rp 199,021 Rp 3,375,000 Rp 86,100 Rp 199,021 Rp 3,660,121
Pantry/Cooker 0 Rp 1,800,000 Rp 2,250,000 Rp 4,050,000 Rp 103,320 Rp 4,153,320 K/0 Rp - Rp 83,066 Rp 4,070,254 Rp 360,000 Rp 3,710,254 Rp 266,859 Rp - Rp - Rp - Rp -
Total Employees 44 Rp 203,875,000 Rp 6,027,000 Rp 13,809,474 Rp 223,711,474
SUMMARY
INCOME
Coal
Single Rate Rp 110,000 $ 7.63
Coal Hauling Rp (11,730) $ (0.81)
Projected Profit OB Removal Rp 1,736,797,428 $ 120,477.07