Professional Documents
Culture Documents
This paper was prepared for presentation at the SPE Nigeria Annual International Conference and Exhibition held in Lagos, Nigeria, 05– 07 August 2014.
This paper was selected for presentation by an SPE program committee following review of information contained in an abstract submitted by the author(s). Contents
of the paper have not been reviewed by the Society of Petroleum Engineers and are subject to correction by the author(s). The material does not necessarily reflect
any position of the Society of Petroleum Engineers, its officers, or members. Electronic reproduction, distribution, or storage of any part of this paper without the written
consent of the Society of Petroleum Engineers is prohibited. Permission to reproduce in print is restricted to an abstract of not more than 300 words; illustrations may
not be copied. The abstract must contain conspicuous acknowledgment of SPE copyright.
Abstract
Efficient gas lift optimization and sustained steady state production performance in dual-completion gas
lifted wells has remained an industry challenge as a result of the inherent legacy well configuration in
which two strings of a dual completion well share a common gas injection annulus. Common well
symptoms include, but are not limited to, surging, instability as a result of fluctuations in casing and tubing
pressure, gas deprivation to one arm of the dual completion, low productivity, and, in extreme cases,
inability to concurrently produce both arms of the dual completion.
A deep investigation into the identified problems of instability, gas sharing, and gas deprivation
revealed that optimal gas allocation to the respective arms of the dual completion was influenced by the
surface injection pressures, fluctuations in tubing pressure, and inability to attain critical flow using the
traditional square-edge orifice valve installed in most of the wells under review.
The existing conventional square-edge orifice valve typically would require approximately 56%
pressure1 differential between upstream and downstream to attain critical flow; this contrasts with the
NOVA venturi orifice valve, which requires barely 10% pressure differential. This pressure differential is
rarely achieved in the traditional square-edge orifice valve. Consequently, slugging, suboptimal gas
injection, unstable production, and sometimes total loss of production are evident.
Whilst industry research is on-going to identify optimal management of this class of wells, the NOVA
venturi orifice valves deployed in some carefully screened candidate wells using established criteria have
addressed, to a large extent, some of the challenges inherent with the current well configuration.
The NOVA venturi valve uses a venturi-type mechanism and overcomes the limitation of the
square-edge orifice valve to achieve critical flow and stabilize the gas injection rate through the orifice by
minimizing the pressure drop across the valve to as low as 10%.
A pilot trial of the NOVA venturi orifice valves in the restoration and stabilization of five candidate
wells in two brownfields located in the Niger Delta resulted in recommendations for optimal use of the
NOVA venturi orifice valves.
2 SPE-172451-MS
Introduction
Over 70% of producing strings in two brownfields
(A and B) located in the Niger Delta produce with
continuous gas lift assistance. These conduits have
dual completions and share a common gas injection
annulus. The inherent design problem is the chal- Figure 1—Square-orifice valve.
lenge of optimally allocating gas to each arm of the
dual completion without excessive allocation to one
arm and consequent deprivation of gas to the other arm. Optimization of production in dual completions
is difficult to achieve when flow is unstable (tubing or casing heading). Incorrect port sizing and
suboptimal gas injection volume and rates are the main causes of instability.
The existing conventional square-edge orifice valve (Figure 1) typically would require approximately
56% pressure differential between upstream and downstream to attain critical flow; this contrasts with the
venturi orifice valve (Figure 2), which requires barely 10% pressure differential. This pressure differential
is rarely achieved in the traditional square-edge orifice valve. Consequently, slugging, suboptimal gas
injection, unstable production, and sometimes total loss of production are evident.
Prior to the trial of venturi valves in selected conduits, all gas lift valves installed in fields A and B were
square-edge orifice valves with inherent suboptimal lift due to the high pressure differential required to
attain critical flow across the valves. Consequences of suboptimal lift are well slugs, low production, and,
in extreme cases, total loss of well production.
Field Overview
Fields A and B currently produce at a combined rate of approximately 80,000 BOPD with gas lift
contributing over 50% of the total production. The major drive mechanisms range from moderate to weak
aquifer support. In most reservoirs, a combination of two or more drive mechanisms provides the system’s
energy requirement. Some of the reservoir blocks were originally undersaturated, while others are
saturated as a result of depletion. The reservoirs are generally shoreface and channel deposits with average
porosity of 18 to 33%, permeability range of 100 to 3000 md, fluid API of 18 to 37 °API, and oil viscosity
of 0.3 to 13 cp. A key well production challenge in these fields is early water breakthrough with high water
production which necessitates continuous gas lift assistance. Also, suboptimal gas allocation in dual
completions poses a major challenge in management and efficient gas lift optimisation.
Technology Overview
The venturi valve series replaces conventional square-edge orifice valves, whose injection rates are
inherently unstable because of the effect of tubing pressure. Even slight variations in the tubing flow
regime can lead to wide fluctuations in the tubing pressure and result in unsteady injection rates,
instability, and slugging.
The venturi orifice valves have an exclusive computer-generated flow profile to promote a constant-
flow gas-injection rate. This profile produces maximum gas passage with minimal differential across the
valve. The venturi valve flow regime virtually eliminates any effect of tubing pressure on the gas-injection
rate and stabilizes the gas-injection pressure. Stable injection rates can result in more stable tubing
pressure, increased production, and reduced operating expenses.
Mode of Operation
The venturi valve design uses an orifice venturi and a check valve for continuous flow operations.
Injection fluid or gas enters through the entry port and then flows through the orifice venturi. Injection
pressure moves the check valve off the seat allowing gas to enter the tubing.
Reverse flow pushes the check valve closed to prevent tubing fluids and pressure from flowing back
into the casing. For injection of gas from the tubing to the casing annulus, the valve is installed in a
SPE-172451-MS 3
mandrel with a type EC pocket, which has tubing ports between the sealbores in the mandrel pocket.
Injection gas flows out the bottom of the valve through the mandrel pocket into the casing or tubing
annulus.
Venturi Orifice Valve Applications
The venturi orifice valve overcomes the limitation of the square-edge orifice valve to achieve critical flow
regime for the flow of injection gas through the orifice by minimizing the pressure drop requirement
across the valve to as low as 10%. To achieve the critical flow, the conventional, square-edge orifice valve
would require a pressure differential between the upstream and downstream pressure of over 56%.
With the venturi valve (blue line in Figure 3), the critical flow regime is achieved at a much higher
downstream pressure of approximately 1100 psia (the point at which the curve starts to form a straight
line), or a tubing pressure (Pt) to casing pressure (Pc) ratio2 of 0.90. With the square-edge orifice valve
(green line), to reach the critical flow conditions given the same upstream pressure, the downstream
(production) pressure must be lowered to 670 psia (Pt/Pc ⫽ 0.56). The critical flow of lift gas through the
orifice valve in the practical sense implies that any fluctuations in the downstream pressure (production/
tubing pressure) will not affect the stability of the injection gas flow through the orifice valve. This, in
turn, can have a positive effect on helping create production pressure stability in the tubing.
Well Instability
In a slugging gas lifted well, slugging conditions could be due to multitude of reasons, including problems
related to the surface flowline, suboptimal completion design, downhole gas lift system, and inflow.
4 SPE-172451-MS
Project Methodology
Candidate Screening
Gas lift instability can be detected from the historical well performance data. Fluctuation in total liquid
production, lift gas injection rate, tubing heading pressure, and casing heading pressure not related to
choke modifications or adjustments to the gas lift system are typical indicators.
A chart showing the procedure for selecting candidates for the pilot trial is as shown in Figure 8. The
candidate wells were highlighted in the daily operations report as being difficult to operate concurrently
because of a suspected gas sharing issue. These wells were then reviewed by an integrated team of surface
and subsurface engineers using available production data (production rates and pressure data). Following
the review, monitoring campaign for tubing head pressure (THP) and casing head pressure (CHP) was
undertaken for each well to validate and provide recent data that would form the basis for the trial. The
data acquired were then analyzed to assess the need for trial of the venturi valves.
Data Gathering/Gaps
The key data required for the gas lift well performance analysis and subsequent design are tubing and
casing pressure data, gas injection rates, and well test production parameters. These data were mostly
available in the appropriate databases, but a few gaps were identified. Furthermore, the wells are in
brownfields with aging production facilities, and getting data from the existing metering devices was a
challenge. Consequently, digital pressure recorders were deployed to acquire casing and tubing pressure
data and a clamp-on gas meter was used to measure lift gas injection rates.
Gas Lift Well Design Before and After
Prior to field execution, preliminary optimised designs of the selected candidate wells were carried out
using a software application for design, analysis, and surveillance of gas lifted wells.
SPE-172451-MS 7
Table 1—WELL A1 MANDREL DEPTHS, LONG STRING Table 3—WELL A2 MANDREL DEPTHS, LONG STRING
Depth (ft) Retrieved Installed Depth (ft) Retrieved Installed
Table 2—Well A1 MANDREL DEPTHS, SHORT STRING Table 4 —WELL A2 MANDREL DEPTHS, SHORT STRING
Depth (ft) Retrieved Installed Depth (WL ft) Retrieved Installed
Most recent bottomhole and production data were acquired for each well prior to implementation and
used to evaluate the existing well performance, identify multipointing scenarios and injection depths, and
optimise the preliminary designs. The key driver was the need to increase the precision of the designs and
optimisation of the valve and orifice depths.
A typical schematic for the wells is shown in (Figure 4). The basic completion design is 2-3/8 in.
tubing for both the long and short strings equipped with gas lift mandrels for continuous gas lift.
Well A1 In Well A1, the mandrel depth for the orifice was changed from 3,285 feet along-hole (ftah) to
2,865 ftah on the long string (Table 1) and 4,107 ftah to 3,597 ftah on the short string (Table 2). The
performance of Well A1 after installation of the venturi orifice did not significantly improve in terms of
oil production as it maintained the production rate prior to use of the venturi orifice valve. It is worth
noting, however, that the orifice depth was optimised and moved shallower on both arms of the well while
still achieving the same production performance. Both arms of the well were subsequently produced
concurrently after installation of the venturi orifice valves, pointing to the effectiveness of the venturi
valves in improving stability of the well.
Well A2 In Well A2, the mandrel depth for the orifice was changed from 4,582 ftah to 3,631 ftah on the
long string and from 4,107 ftah to 3,597 ftah on the short string. The performance of the long string of
the well was not significantly improved as it maintained a liquid production rate of approximately 330
BPD. The well maintained the same performance after installation of the venturi orifice valve eventhough
the orifice depth was moved two mandrels shallower.
There was an increase in liquid production rate of 420 BPD with an oil gain of 190 BOPD from the
short string after venturi orifice installation. This was achieved despite moving the orifice depth shallower.
Both arms of the well could be produced concurrently after installation of the venturi orifice valve
pointing to the effectiveness of the venturi valves in improving stability of the well as was also observed
in Well A1.
Results Discussion
The post-installation test results indicate that the venturi valve was successful in eliminating the gas
injection volume fluctuation and ensured that both arms of the dual completion produced together, thus
reducing deferments. Table 5 shows test results obtained from Well A1, and Table 6 shows the test results
from Well A2.
8 SPE-172451-MS
SHORT STRING
29-Jan-12 136 64 499 52 239 1.5 980 Post Nova
15-Dec-11 135 64 505 51 246 1.6 980
21-Oct-11 135 64 500 45 277 1.6 1090
10-Aug-11 136 64 516 41 306 1.5 750
2-Jul-11 135 64 526 41 312 1.8 520
5-Jun-11 130 64 541 39 331 1.8 370 Prior Nova
5-M ay-11 135 64 530 39 322 2.0 350
4-Apr-11 135 64 533 40 324 1.7 590
Long String
13-Jan-12 165 48 625 35 407 1.4 860 Post Nova
29-Sep-11 165 48 658 34 435 1.4 950
6-Aug-11 165 48 689 34 456 1.7 920
9-J ul-11 164 48 697 34 462 1.6 896
2-Jun-11 164 48 652 40 392 2.0 1280 Prior Nova
4-May-11 165 48 724 35 470 2.0 924
4-Apr-11 164 48 729 37 454 1.5 2550
SHORT STRING
9-Jan-12 220 52 685 54 310 1.7 737 Post Nova
26-Dec-11 221 52 683 52 322 1.7 605
25-Dec-11 221 52 666 52 315 1.7 531
12-Dec-11 121 52 259 52 122 1.4 920 Prior Nova
4-Nov-11 120 52 256 52 121 1.5 78
12-Oct-11 118 52 256 52 121 1.8 579
Long String
2-Jan-12 108 60 330 32 229 1.2 375 Post Nova
28-Dec-11 108 60 342 32 231 1.9 295
5-Nov-11 108 60 343 28 244 1.7 338 Prior Nova
22-Oct-11 108 60 347 37 217 1.7 491
23-Aug-11 108 60 352 44 196 1.7 710
● CHP and THP profiles of the candidate well should be recorded for reasonable length of time
especially after venturi installation as stability in tubing and casing pressure can only be evident
once critical flow is established.
● Suboptimal lift gas injection and low injection pressures can cause instability and nonproduction
of gas lift conduits.
● Venturi orifice valve can stabilize production from previously unstable wells by attaining critical
flow much earlier than with conventional orifice.
● Choke size of the venturi orifice needs to be carefully designed and sized to enable passage of
optimal amount of lift gas.
Recommendations
● Eliminate other possible causes of suboptimal or nonproductivity before proposing the venturi
solution.
● Proper measurement of injection gas is required to help model actual performance of the gas lift
system with the venturi valve deployed.
● Use venturi orifice valves where a clear case of gas sharing issues has been established.
● Venturi orifice valve should be installed in both arms of the dual gas lift wells with production
challenge.
● The orifice should be carefully designed and optimum choke size selected to ensure required
amount of lift gas is injected and not more.
● More field trials should be done to further confirm the benefits of venturi orifice valves over
conventional orifice valves.
Future Outlook
● In the future, venturi orifice valves should be deployed as a standard in dual gas lift
wells based on the favorable critical flow characteristics.
● Venturi orifice is the preferred orifice for surging wells ether single- or dual-string
producers.
Conclusions
Venturi orifice valve installation results carried out in the carefully selected candidate wells yielded
positive results. Key benefits were the regulation of injected gas volumes, restoration of deferred conduits,
and enabling of concurrent production from all the candidate dual-completion gas lifted wells. A total of
520 BOPD was restored and is currently being sustained even 1 year after venturi orifice valve
installation. Estimated revenue of USD 15.18 million has been realised in the last 1 year (based on
producing 520 BOPD for 365 days at USD 80 per barrel).
Acknowledgements
The authors wish to thank the Production Technology Discipline Lead, Arjen Kooijman; Regional
Completions & Well Interventions Manager, Chris Ayanruoh; Asset Development Manager Land East,
Howard Mackay; Development Manager Subsurface Studies, Esben Johnsen; Production Services and
Support Manager, Obi Akosa; and the Schlumberger Artificial Lift Team for their support all through the
various phases of the project.
SPE-172451-MS 11
References
1. Tokar, T., Schmidt, Z., and Tuckness, C. 1996. New Gaslift Valve Design Stabilises Injection
Rates: Case Studies. Paper SPE 36597 presented at the1996 SPE Annual Technical Conference
and Exhibition, Denver. Colorado, USA, 6 –9 October.
2. Faustinelli, J., Bermúdez, G., and Cuauro, A. 199. A Solution to Instability Problems in
Continuous Gas-lift Wells Offshore Lake Maracaibo. Paper SPE 53959 presented at the SPE Latin
American and Caribbean Petroleum Engineering Conference, Caracas, Venezuela, 21–23 April.