ADDITIONAL 3RD-RF DECK CONSTRUCTION COST SUMMARY

DESCRIPTION MATERIAL COST TOTAL MATERIAL


GENERAL REQUIREMENTS & LABOR

3RD FLOOR ADDITIONAL


STEEL WORKS 172,850.00 259,275.00
CONCRETE 134,300.00 201,450.00
FORMWORKS 100,854.25 151,281.38
MASONRY 237,491.67 356,237.50
FENESTRATION 75,000.00 112,500.00
STEEL RAILING/ STEEL LADDER 60,000.00 90,000.00
PLUMBING 45,000.00 67,500.00
ELECTRICAL 60,000.00 90,000.00
PAINTING 80,000.00 120,000.00
1,448,243.88
ROOF DECK DECK ADDITIONAL
STEEL WORKS 189,870.00 284,805.00
CONCRETE 151,700.00 227,550.00
ROOF FRAMING 240,000.00 360,000.00
MASONRY 41,250.00 61,875.00
FENESTRATION 70,000.00 90,625.00
STEEL RAILING/ STEEL LADDER 50,000.00 75,000.00
PLUMBING 60,000.00 90,000.00
ELECTRICAL 75,000.00 112,500.00
PAINTING 80,000.00 120,000.00
1,422,355.00
# CHANNEL CCTV
AIRCON
SUBTOTAL DIRECT COST 1,923,315.92 1,422,355.00
OVERHEAD CONTINGENCY MISCELLANEOUS 192,331.59
CONTRACTORS PROFIT 711,177.50
PROFESSIONAL FEE 142,235.50

GRAND TOTAL 2,468,099.59


NOTES:
ITEMS NOT INCLUDED:
*ALL GOVERNMENT PERMITS AND FEES
*BONDS AND INSURANCES
*WATER AND ELECTRICAL CONSUMPTION
*BUILDING PERMIT APPLICATION
*TEMPORARY SERVICE LINE (WATER & ELECTRIC)
*SITE DEVELOPMENT (LANSCAPE, SOFTSCAPE, HARDSCAPE)