DATE : NOVEMBER 24, 2022

PROJECT : PROPOSED 3 STOREY COMMERCIAL APARTMENT BUILDING


LOCATION : FAUSTINO ST., PUNTURIN, VALENZUELA CITY
OWNER : MRS. ERLEYNDA GO NOSCAL
SUBJECT : WORK SCHEDULE & CASH FLOW
30 DAYS 30 DAYS 30 DAYS 30 DAYS 30 DAYS 30 DAYS 30 DAYS 30 DAYS 30 DAYS 30 DAYS
NO. OF DAYS
5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100 105 110 115 120 125 130 135 140 145 150 155 160 165 170 175 180 185 190 195 200 205 210 215 220 225 230 235 240 245 250 255 260 265 270 275 280 285 290 295 300

I GENERAL REQUIREMENTS
-MOBILIZATION, TEMPORARY FACILITIES, WARNING & SIGNAGES
SAFETY CATCH WQITH NET, TEMPORARY FENCE, BOND & INSURANCE,
TOOLS AND EQUIPMENT, DEMOBILIZATION.

II DEMOLITION / DISPOSAL
-DEMOLITION OF FIREWALL, DISPOSAL OF DEBRIS

III SITE WORK


-LAY-OUT AND STAKING, BATTER BOARD

IV CIVIL WORKS
-EARTHWORK, GRAVEL BEDDING, BACKFILLING,DAMP PROOFING
CONCRETING, REINFORCING STEEL BARS, FORMWORKS,
SCAFFOLDING AND STRUCTURAL STEEL

V MASONRY WORK
-CHB LAYING, PLASTERING, LINTEL BEAM, STIFFENER COLUMN,
BOND BEAM AND WALL FOOTING

VI ARCHITECTURAL WORK
-DOOR & DOOR JAMBS, GLASS AND GLAZING, CEILING, TILE WORK,
CONCRETING TOPPING, HARDWARE & LOCKSET, STEEL DOOR &
GENSET DOOR, STAIR HANDRAIL AND RAILING, WINDOW GRILLS,
WATERPROOFING, CABINET AND PAINTING WORKS

VII ELECTRICAL WORK


-ROUGHING-INS, LIGHTING FIXTURES, SWITCHES, OUTLETS
& EXHAUST FAN

VIII PLUMBING WORK


-ROUGHING-IN, FIXTURES, OVERHEAD WATER TANK,
FLOAT SWITCH, PUMPS AND CONTROL PANEL

IX FIRE PROTECTION
-AUTOMATIC FIRE SPRINKLER & PUMPS & MOTORS

X COMISSIONING AND TESTING

XI GENERAL CLEANING

CASH FLOW

Prepared By:

ARCH. RODERICK M. CANUEL


AIC Engineer-Contractor