16A2093-L0006 - S6 - Revb SURFACE TREATMENT AND PAINTING - META
16A2093-L0006 - S6 - Revb SURFACE TREATMENT AND PAINTING - META
P.O.Box 4 (Jaakonkatu 3)
FI-01621 Vantaa
Finland
Domicile Vantaa, Finland
Technical project instruction Business ID. 1071411-1
Tel. +358 9 894 71
Fax +358 9 878 1818
Contents 1 General
2 Surface Preparation
3 Painting systems and coat thicknesses
4 Painting method and work
5 Hot Dip Galvanising and Painting of Galvanised Surfaces
6 Patching-up
7 Colour shades
8 Quality control, inspections and work acceptance
9 Guarantee
Distribution MB
JPH: JMR MIT SL RY LRH Files
1 GENERAL
This instruction presents standards and principles to be used for painting of steel
constructions, tanks, piping and equipment.
This instruction shall be followed if not otherwise agreed in the purchase contract or
its technical part.
2 SURFACE PREPARATION
Part of the structures has to be painted on site. In this case special attention shall be
paid to provide suitable conditions and to selection of painting system. At least pre-
treatment and pre-painting with shop primer should be done in a paint shop.
It shall always be made sure of surface cleanness prior to further treatment. This can
be assisted by keeping the time interval to the original painting short and by protecting
the products during transport and storing.
2.1 Precleaning
Remove solid and water-soluble impurities and greases.
Solid impurities, such as concrete - and paint residues, shall be removed by beating,
scraping or by brushing. The use of rotating brush is not recommended.
Water-soluble, such as salts, shall be removed by washing and brushing with water, by
high pressure water or by steam.
Special attention shall be paid to blast cleaning of weld seams and smoothness of
welding seams.
With approval from the Purchaser the thin plates can be treated by water blast-
cleaning with immediate drying.
Priming shall be made immediately after blasting in accordance with the standard EN
ISO 12944-5, Annex B.
Selection of the prefabrication primer shall be made considering suitability for the
painting system to be applied over it, properties required for the prefabrication primer
(see EN ISO 12944-5, Annex B) and loading during the protection time.
Before final painting prefabrication primed surfaces shall be cleaned from dirt and
grease. Surface to be painted shall be pre treated mechanically and cleaned in
accordance with standard EN ISO 12944-4.
If the prefabrication primer does not match with painting system it must be removed
thoroughly before final painting and the surface treated to the required grade.
Priming and top coat markings shall follow EN ISO 12944-5 painting standard.
Different paint layers shall be painted with different colours to make supervision
easier.
Priming coats:
1)
3. Structures Sa 2 ½ EP80/1 EP 420/1 EPEP 500/2 -
under water
-
1)
4. Structures Sa 2 ½ EP 80/1 EP 420/1 EPEP 500/2 -
buried in soil
1) With separate agreement EH400/4, where EH= resin modified epoxy paint
The dry film thickness requirement is fulfilled when in the film thickness
measurement at maximum 5 % of the measurement areas go under the nominal dry
film thickness. The individual measurement area may go under the nominal dry film
thickness at maximum 20 %. The maximum dry film thickness must not exceed the
value given by the paint manufacturer; however at maximum double the nominal dry
film thickness can be accepted.
Individual dry film thicknesses which go under the nominal dry film thickness more
than 20 % are not accepted.
The standard ISO 2808 and the measurement instrument manufacturer’s instructions
shall be considered in the film thickness measurement.
When doing the measurement special attention shall be paid on sharp edges, welding
seams and other similar places
Special attention shall be paid on careful painting work, painting conditions (relative
humidity and temperature) and on correct film thicknesses.
The Purchaser has right to make supervision at scope after his own judgement.
The Vendor shall keep site diary for the painting work which shall be used at the same
time as a supervision diary of the Purchaser.
16A2093-L0006
To control the film thickness the Vendor shall make the thickness measurement using
meter with printer.
6 PATCHING-UP
Patching-up belongs to the Vendor until the handing over.
The surface defects and sharp edges in the surface under repair shall be grinded and
weld splatters removed. The surface to be painted shall be prepared to the surface
preparation grade of the painting system.
16A2093-L0006
The area between prepared surface and the uniform painted surface shall be bevelled.
Corroded points shall be prepared to the required surface preparation grade on so wide
area that the primer at the edge of the patching-up area is well attached to the surface.
The patching-up area shall be marked off if necessary and the painted surfaces outside
the area shall be protected.
Patching-up shall be done with the original painting system up to the full film
thickness following the boundaries of different paint layers.
When painting edges, it is important to consider the film thickness and if necessary
add an additional layer.
7 COLOUR SHADES
Colour shades shall be selected according to standard KY620 and architect design.
The Purchaser and the paint manufacturer will survey the work during the surface
treatment of steel structures. The painting work shall be finally accepted during the
handover of the purchase.
The Vendor is responsible for the quality of the painting and shall make the quality
control. The Purchaser can do the inspections that he considers necessary.
A report shall be made of the handover, with among other things following matters:
− documents and control report
− guarantee starting day and specified surface quality requirement after guarantee
period and things which the guarantee does not concern
− delay penalties
10
9 GUARANTEE
Guarantee provisions in SFS 4426 shall be followed.
At the end of the guarantee period the derusting grade of the painted surface shall be
at maximum Ri 1 according to classification in ISO 4628-3 standard.
JAAKKO PÖYRY OY
Ref. No 16A2093-L0006
Appendix I Page 1 (2)
Botnia S.A.
Page 1 ( )
Painting object, structure/equipment, Cost place Work Number. Project Number.
drawing Number
Purchaser / contact person Vendor / contact person Order Number Painting system