Professional Documents
Culture Documents
CO2 capture in natural gas combined cycle with SEWGS. Part B: Economic
assessment
Giampaolo Manzolini ∗ , Ennio Macchi, Matteo Gazzani
Politecnico di Milano, Dipartimento di Energia, Via Lambruschini 4, 20156 Milano, Italy
a r t i c l e i n f o a b s t r a c t
Article history: This two part-paper investigates the adoption of an innovative CO2 capture concept named SEWGS (sorp-
Received 3 January 2012 tion enhanced water gas shift) in natural gas combined cycle. In Part A, SEWGS working conditions were
Received in revised form 25 June 2012 optimized in terms of carbon capture ratio as well as CO2 purity and two different sorbent performances
Accepted 29 June 2012
were analyzed. Part B presents the economic assessment of investigated SEWGS cases together with
Available online 28 July 2012
three reference cases selected for electricity production: without carbon capture, with post-combustion
carbon capture by MEA and with pre-combustion carbon capture by MDEA. Results shows that with ref-
Keywords:
erence sorbent performances the calculated cost of CO2 avoided is about 58 D/tCO2 , which is lower than
CAESAR
SEWGS
reference MDEA (64 D/tCO2 ) but higher than MEA (48.5 D/tCO2 ). The adoption of a sorbent with improved
MDEA performances brings down the cost of CO2 avoided down to 49 D/tCO2 , which is comparable to post com-
Pre-combustion capture bustion technology. This is a consequence of reforming sections costs which penalizes pre-combustion
Natural gas combined cycles technologies: specific investment costs for SEWGS cases are 15% higher than MEA. Finally, as far as SEWGS
Cost of electricity working conditions are concerned, the optimal CO2 capture rate depends on the sorbent cyclic capacity
Cost of CO2 avoided ranging from 90% to 95%, while the selected CO2 purity is 99%. This activity was carried out under the
FP7 project CAESAR financed by the EU community.
© 2012 Elsevier Ltd. All rights reserved.
1750-5836/$ – see front matter © 2012 Elsevier Ltd. All rights reserved.
http://dx.doi.org/10.1016/j.ijggc.2012.06.021
G. Manzolini et al. / International Journal of Greenhouse Gas Control 12 (2013) 502–509 503
Table 1
Total plant costs assessment methodology.
only difference is related to the generator power output. For this GT, eight trains are necessary for the Sorbent Alfa, while it can be
reason, a relatively low scale factor of 0.3 is assumed. Costs related reduced to six for Sorbent Beta (a detailed description of these sor-
to combustor modifications required by syngas compositions are bents and explanation on the number of vessel are given in Part A
neglected. of this work).
Most of the other data used for power section total investment For the air compressor, a conservative specific cost of an axial
cost calculation are derived from results presented by DOE (2007), air compressor was assumed even if, considering the low pressure
recently updated adopting a cost index variation and are consis- ratio and volumetric flow, it would probably be a radial type, and
tent with EBTF public report on economic assessment (Franco et al., consequently less expensive.
2011). The equipment costs database is summarized in Table 3. The expander specific cost was set equal to the steam turbine,
Estimated cost of a SEWGS train, which is composed of 9 ves- because of the similar working conditions in terms of pressure and
sels, is 8.7 MD based on previous studies carried out in CCP (Project, temperature.
Carbon Capture, 2010). For the adopted configuration with two
3.1. GHR–ATR cost assessment
Table 2
O&M and consumable costs.
For the GHR–ATR cost, in open literature the few references are
also scattered (see Table 4).
Natural gas costs D/GJLHV 6.5 In addition to wide variability, it was difficult to understand
O&M
Labor costs, no capture case MD 6
what cost included (e.g. installation or indirect cost). For this rea-
Labor costs, capture case MD 9 son, it was decided to calculate the GHR–ATR cost as the sum of
Maintenance costs % of total plant cost 2.5 the two separate components: ATR and GHR. For the ATR, costs are
Insurance % of total plant cost 2 taken from the CACHET project, while GHR is determined starting
Consumables
from a conventional external fired reformer and scaling down for
Evaporative tower blow-off % of evaporated water 100
Cooling water make-up costs D/m3 0.35 the reaction heat duty. It must be outlined that this is a conser-
HRSG water blow-off % of steam produced 1 vative assumption, because a conventional fired tubular reformer
Process water costs D/m3 2 works with hot gases at significantly higher temperature than this
MEA make-up (Franco et al., 2011) kgMEA /tCO2 1.5 case (i.e. 1250 ◦ C vs. 950 ◦ C). The maximum size of the GHR–ATR,
MEA make-up costs (Franco et al., 2011) D/tMEA 1042
Catalyst and sorbent replacement
according to references is 1500 MWth (INC, Fluor Daniel, 2000),
Reforming catalyst lifetime Years 5 thus it can be assumed that one reactor will feed two gas turbines.
Reforming catalyst cost kD/m3 50 Resulting costs are summarized in Table 5 (cases considered refer
Water gas shift lifetime Years 5 to Part A of this work and performances are summarized in the cost
Water gas shift cost kD/m3 14
of electricity section).
G. Manzolini et al. / International Journal of Greenhouse Gas Control 12 (2013) 502–509 505
Table 3
Equipment costs for main components.
Plant component Scaling parameter Reference erected Reference size, S0 Scale factor, f N
cost, C0 (MD)
Gas turbine, generator and auxiliaries GTNet power [MW] 49.4 272.12 0.3 2
(DOE-NETL, 2007; Gas Turbine World
Handbook, 2010)
HRSG, ducting and stack (DOE-NETL, 2007; Gas U * S [MW/K] 32.6 12.9 0.67 2
Turbine World Handbook, 2010)
Steam turbine, generator and auxiliaries STGross power [MW] 33.7 200.0 0.67 1
(DOE-NETL, 2007; Gas Turbine World
Handbook, 2010)
Cooling water system and BOP (DOE-NETL, Q rejected [MW] 49.6 470.0 0.67 1
2007)
MEA CO2 separation system (Project Carbon CO2 captured [kg/s] 29.0 38.4 0.8a 2
Capture, 2010)
MDEA CO2 separation system CO2 captured [kg/s] 68.2 46.14 0.8 2
CO2 compressor and condenser (Project Compressor power [MW] 9.9 13.0 0.67 1
Carbon Capture, 2010)
Desulfurization process Thermal input LHV [MW] 0.66 413.82 0.67 4
Gas heated reformer–auto thermal reformer Thermal input LHV [MW] See below
(GHR–ATR)
Waste heat boiler Heat transferred [MW] 1.8 57.2 0.9 2
High temperature shift + low temperature shift Thermal power input LHV [MW] 3.71 815.2 0.67 2
(HTS + LTS)
High temperature shift (HTS) Thermal power input LHV [MW] 3.33 827.6 0.67 2
Sorption enhanced water gas shift (SEWGS) No. of trains 8.74 1 1 -
Air blower (DOE-NETL, 2007; Gas Turbine Compressor power [MW] 14.77 47.61 0.67 1
World Handbook, 2010)
Expander (DOE-NETL, 2007) Expander power [MW] 33.7 200 0.67 2
a
The adoption of two GT and two HRSG requires two separated carbon capture system, one for each HRSG.
Table 4
Installed cost database for reforming sections.
Type Source Year Scaling parameter Size Cost 2008 [MD] f Update specific cost
2008 [D/kW]
The resulting total capital requirement and specific cost is sum- In SEWGS cases, TEC increases about 80% compared to NGCC,
marized in Table 6. Component size presented in Part A of the paper half of which depends on SEWGS process costs. This assessment
is summarized in the next section. shows that SEWGS equipment cost in NG applications looks as
Specific investment costs for capture plant are significantly expensive as amine scrubbing, thus reducing advantages of this
higher than reference NGCC without capture. In particular, they technology from an investment point of view.
range from 54% of MEA and 100% of MDEA; SEWGS cases are Finally, the adoption of CO2 -steam expansion accounts for
between these two figures. Higher investment costs of MEA than 20 MD plus 5 MD for a larger CO2 compressor. Cost of Electricity
NGCC are mainly due to CO2 capture island (80%) and to CO2 com- will indicate if these additional costs are more than balanced by
pressor (20%). It must be outlined that assumed cost for MEA, taken the higher efficiency and consequently fuel cost savings.
from EBTF work, seems to be on the optimistic side compared to
other references (e.g. another EU project named DEMOYS indicated
a specific investment cost of 1100 D/kW compared to 979 D/kW 4. Cost of electricity and CO2 avoided calculation
given here). Most of the MDEA reference case additional costs are
due to the capture section which accounts for 28% of the total plant As anticipated, the aim of the economic assessment is to make
cost. an estimation of the final cost of electricity (COE).
The time required for power plant construction, also for carbon
capture cases, is assumed to be 3 years (with payment distributed
Table 5 40% in the first year, and the remaining evenly distributed in the
GHR–ATR costs assumed for the considered cases. second and third years).
Plant component MDEA capture SEWGS Case 2 The main economic assumptions are reported in Table 7.
(Manzolini et al., 2011) The assumed operating hours per annum are typical of early
GHR size [reaction duty, MWth] 72.3 61.7
2000, where large scale fossil fuel power plant worked predom-
ATR size [thermal input, MWth] 1506.4 1428.5 inantly at base load, with hydro-power and small scale plants
GHR cost [MD] 10.0 8.9 as peak-load. Recently, because of the increasing penetration of
ATR cost [MD] 29.0 27.9 non-dispatchable renewable energy generation, this value has sig-
Overall GHR–ATR cost [MD] 39.1 36.9
nificantly decreased. However, it is difficult to predict what the
506 G. Manzolini et al. / International Journal of Greenhouse Gas Control 12 (2013) 502–509
Table 6
Total capital requirement (MD) calculation.
NGCC reference NGCC MEA NGCC MDEA SEWGS Case 1 SEWGS Case 2 SEWGS Case 3 SEWGS Case 4 SEWGS Case 5
Cost [MD]
Desulfurizer – 2.4 2.6 2.5 2.5 2.5 2.5 2.5
GHR–ATR/ATR – – 29.3 27.7 27.7 27.7 27.7 27.7
WGS HTS + LTS – – 11.2 – – – – –
HTS – – – 6.4 6.4 6.4 6.4 6.4
MEA – 56.7 – – – – – –
MDEA – – 132.2 – – – – –
SEWGS – – – 69.6 69.6 69.6 69.6 69.6
Gas turbine 98.8 98.8 101.2 99.3 99.1 99.0 99.4 99.2
HRSG 45.7 44.8 59.7 51.4 51.6 52.8 51.5 52.1
Steam turbine 43.2 35.1 44.2 39.9 38.2 36.0 39.5 37.8
Heat rejection 49.4 54.9 55.1 54.8 52.8 55.4 54.8 55.1
CO2 compressor – 14.4 17.0 22.1 22.8 23.3 22.0 22.8
Air blower – – 7.9 6.2 6.2 6.2 6.2 6.2
CO2 + steam exp. – – – 16.7 19.4 22.5 17.0 19.7
Heat exchangers 0.3 0.3 6.0 5.6 5.8 5.7 5.9 5.9
BOP 0.1 0.1 4.5 1.7 1.7 1.7 1.8 1.8
TEC [MD] 237.5 307.4 468.3 404.1 406.3 409.0 404.6 407.0
TIC [MD] 161.5 217.8 342.5 292.9 294.9 297.1 293.3 295.3
TDPC [MD] 399.0 525.2 810.7 697.0 701.2 706.2 697.8 702.3
Indirect cost [MD] 55.9 73.5 113.5 97.6 98.1 98.9 97.7 98.3
EPC [MD] 454.9 598.7 924.2 794.6 799.4 805.0 795.5 800.6
C&OC [MD] 68.2 89.8 138.6 119.2 119.9 120.8 119.3 120.1
Total plant cost [MD] 523.1 688.5 1062.9 913.8 919.3 925.8 914.9 920.7
Net power output [MW] 829.9 709.92 830.0 795.41 786.99 779.20 795.47 786.9
Specific costs [D/kW] 630.4 969.9 1280.6 1148.7 1168.1 1188.1 1150.1 1170.1
Table 7 CO2 avoided is achieved for Case 2 and Case 5 which have a CO2
Main economic assumptions (Franco et al., 2011).
avoidance of about 90% (95% CCR of SEWGS). The reason is that
Discount rate, % 8 Case 3, which has a higher CO2 avoidance, is penalized by system
First year operating hours, h 5700 efficiency (a higher energy is required to regenerate the sorbent)
Rest of lifetime operating hours, h 7500
which is not balance by the lower emissions. While Case 1 and Case
Operating lifetime, years 25
Construction time, years 3
4 have a lower CO2 avoidance which is penalized by investment
costs: the SEWGS system cost is not influenced by CCR, so its specific
costs for CO2 captured is higher. Since the difference in terms of CO2
future will be and if power plant with CO2 capture will be assimi- avoided between Case 2 and Case 5 is negligible (0.2 D/tCO2 ), Case
lated to green-energy sources or not.1 5 that has the CO2 purity of 99% is the preferred option reducing
The estimated COE and cost of CO2 avoided for investigated transport and storage costs.
cases is summarized in Table 8 where cost of CO2 avoided is defined Compared to NGCC with MDEA, SEWGS cases have a lower
as: investment, fixed operating and fuel cost thanks to the higher
efficiency; only consumables costs, which are mainly related to
(COE)CO2 cap − (COE)Ref
Cost of CO2 avoided = sorbent replacement, are higher than MDEA. The resulting cost
(CO2 kWh−1 )Ref − (CO2 kWh−1 )CO2 cap of CO2 avoided is about 59 D/tCO2 , which is about 7% lower than
MDEA. Compared to MEA, SEWGS higher efficiency cannot balance
where Ref is the power plant without carbon capture and CO2 cap
the penalties arising from higher investment costs rising the CO2
is the plant with carbon capture. Calculated cost of electricity for
avoidance costs by12 D/tCO2 .
SEWGS and reference cases are summarized in Table 8.
One of the optimization parameters investigated in Part A was
The resulting levelized cost of electricity for NGCC without CO2
the CO2 -steam expander outlet pressure. This analysis is here pro-
capture is 54.10 D/MWh. As shown in Table 8, most of LCOE depends
posed in terms of COE and cost of CO2 avoided (see Fig. 1) showing
on fuel costs (as typical of NG based power plants), while the sum
that the optimal condition occurs for 0.15 bara which coincides
of fixed and variable costs accounts for less than 10%. In CO2 cap-
with the thermodynamic assessment. Additional investment costs
ture case, LCOE increases by 15–20 D/MWh as a consequence of the
are balanced by the higher efficiency and consequently lower fuel
higher investment costs and lower efficiency which leads to higher
costs.
specific fuel consumption. The calculated cost of CO2 avoided for
To summarize, the assessment of SEWGS in NGCC showed that
MEA and MDEA cases are 48.5 D/tCO2 and 63.8 D/tCO2 respectively.
Sorbent Alfa performances has a lower cost of CO2 avoided than
The cost of CO2 avoided for the MEA case is lower than similar stud-
MDEA which belongs to the same capture route. However, Sorbent
ies in the literature (GCCSI, 2011; Finkenrath, 2011; Valenti et al.,
Alfa performances are not competitive with the amine scrubbing
in press), however it can represent amine scrubbing with advanced
technology; higher efficiency of SEWGS configuration is not enough
solution.
to balance 20% additional investment costs.
Among all investigated SEWGS cases, COE is almost constant
For this reason, SEWGS economic assessment was also per-
and higher than reference NGCC of about 33%. The lowest cost of
formed assuming Sorbent Beta which has an improved capacity of
62% more than Sorbent Alfa (at 2.7 bara CO2 partial pressure). First,
the same cases as Sorbent Alfa will be presented to evaluate the
1
Plants with CO2 capture have limited emissions and reduced impact on the impact of thermodynamic advantages on COE (number of vessels
environment; for this reason, they are closer to renewable energy rather than con-
equal to 72 and CO2 purity 99%). Considering the higher capac-
ventional fossil fuel power stations. However, at present time, no plant has ever
been built and there is no directive and/or law on this subject. ity, the overall steam usage is reduced by about 80%, thus optimal
G. Manzolini et al. / International Journal of Greenhouse Gas Control 12 (2013) 502–509 507
Table 8
Cost of electricity and cost of CO2 avoided for SEWGS and reference cases.
Plant component NGCC reference NGCC MEA NGCC MDEA SEWGS SEWGS SEWGS SEWGS SEWGS
Case 1 Case 2 Case 3 Case 4 Case 5
Table 9
Comparison between different SEWGS numbers with Sorbent Beta in terms of cost of electricity and cost of CO2 avoided.
No. of vessels 72 54
expander outlet pressure increases from 0.15 bara to 0.3 bara. The A lower number of SEWGS trains (6 vs. 8) was also investigated
calculated results, summarized in Fig. 2 and Table 9, show that the to determine investment cost reduction on COE. The adoption of
improved capacity of the sorbent can reduce COE and the cost of a higher capacity allows investigating fewer number of vessels, 6
CO2 avoided by 1 D/MWh and 5 D/tCO2 , respectively. These costs are trains instead of 8, which means 54 vessels vs. 72 with advantages
determined keeping the same SEWGS vessel number of Sorbent Alfa both in terms of efficiency (see Part A), and investment costs.
case, and consequently equipment costs, hence they are only due Results, summarized in Table 9, show that a reduced number of
to the higher efficiency (about 1% points). vessels allows to achieve a CO2 avoidance costs of 49 D/tCO2 with
Lower specific investment costs result mainly from higher 95% CCR; this result is very similar to MEA case. Main advantages
efficiency, but also on lower cost of the CO2 compressor and CO2 - of 54 vessels compare to 72 vessels case are in terms of investment
expander as a consequence of the reduced steam flow-rate and and consumables cost; these two costs only depend on the SEWGS
higher pressure at expander outlet and consequently at compressor volume. Another consideration is that the optimum CCR is not 98%
inlet. as in cases with 72 vessels, but occurs at 95%. This is because the
Focusing on the cost of CO2 avoided, Sorbent Beta shows the number of vessel reduction requires an exponential increase of
lowest value for 98% CCR in SEWGS; for Sorbent Alfa, the optimum the steam to regenerate the sorbent causing higher efficiency
occurred at 95%.
Fig. 1. Cost of electricity and cost of CO2 avoided as a function of expander outlet Fig. 2. Comparison between Sorbent Alfa and Sorbent Beta in terms of cost of elec-
pressure for Sorbent Alfa with CCR 95% and CO2 purity 99%. tricity and cost of CO2 avoided (CO2 purity 99%) with 72 vessels.
508 G. Manzolini et al. / International Journal of Greenhouse Gas Control 12 (2013) 502–509
reformer with permeate side combustion. In: Proceedings of ASME Turbo Expo, Tijmensen, M.J.A., et al., 2002. Exploration of the possibilities for production of Fis-
May 2006, Barcelona (Spain). cher Tropsch liquids and power via biomass gasification. Biomass and Bioenergy
Manzolini, G., Macchi, E., Binotti, M., Gazzani, M., 2011. Integration of SEWGS for 23, 129–152.
carbon capture in natural gas combined cycle. Part B: reference case comparison. Valenti, G., Bonalumi, D., Macchi, E. A parametric investigation of the
International Journal of Greenhouse Gas Control 5 (2), 214–225. Chilled Ammonia Process from energy and economic perspective. Fuel,
Project, Carbon Capture, 2010. http://www.co2captureproject.org/ccp2 capture.html http://dx.doi.org/10.1016/j.fuel.2011.06.035, in press.
(cited: January 7 (Online)). van Vliet, O.P.R., Faaij, A.P.C., Turkenburg, C., 2009. Fischer–Tropsch diesel produc-
Thermoflow Inc., 2011. http://www.thermoflow.com. Thermoflow website. Visited tion in a well-to-wheel perspective: a carbon, energy flow and cost analysis.
June (Online). Energy Conversion and Management 50, 855–876 (Elsevier).