RENCANA ANGGARAN BIAYA (RAB)

1 titik
HARGA SATUAN JUMLAH
NAMA / JENIS BARANG VOLUME SATUAN
NO ( RP ) ( RP )
1 2 3 4 5
I Belanja Bahan
1 Kabel TIC 2 X 10 mm 25 Meter 14,000 350,000
2 Kabel NYM 3 x 2,5 mm 5 Meter 14,000 70,000
3 Wade Clam 2 Set 15,000 30,000
4 Stainless Stell Strip 10 Meter 11,000 110,000
5 Stopink Buckle 4 Buah 10,000 40,000
6 Link 4 Buah 5,000 20,000
7 MCB 6 1 Buah 150,000 150,000
8 Box Pengaman MCB 1 Buah 12,000 12,000
9 Stang PJU Galvanis 1 Buah 200,000 200,000
10 Klem PJU 1 Set 150,000 150,000
11 Solasiban 1 Buah 12,000 12,000
12 Box KWH 1 Buah 255,000 255,000
13 Lampu LED 100 Watt 1 Unit 1,750,000 1,750,000
14 Foto Cell 6 A 1 Buah 135,000 135,000
15 Paralon PVC 1 inc 1 Batang 50,000 50,000
16 Paralon PVC 5/8 inc 1 Batang 40,500 40,500
17 Fleksibel 1" 1 Meter 15,000 15,000
18 Besi Arde 1 Batang 20,000 20,000
19 Terminal Nol 1 Buah 22,000 22,000
20 Kawat Arde/BC 3 Meter 12,000 36,000
JUMLAH 3,467,500
II Upah Kerja
1 Pemasangan Hantaran Udara Jaringan PJU 25 Meter 2,000 50,000
2 Perakitan instalasi PJU dan Pemasangannya berikut Gambar 1 Lokasi 100,000 100,000
3 Perakitan Instalasi APP 1 Lokasi 120,000 120,000
4 Ongkos Angkut 1 Rit 100,000 100,000
JUMLAH 370,000

JUMLAH TOTAL 3,837,500

KABID PRASARANA DAN PERPARKIRAN KEPALA SEKSI PRASARANA


DINAS PERHUBUNGAN KABUPATEN KUNINGAN DINAS PERHUBUNGAN KABUPATEN KUNINGAN

SOLIKIN, SE,MM DIDIN ARDIANSAH, ST


Pembina Penata Tk.I
Nip. 19650510 198903 1 020 Nip. 19770702 200901 1 003

You might also like