Professional Documents
Culture Documents
BT4 - Final - Technical Specifications - Compilation
BT4 - Final - Technical Specifications - Compilation
TECHNICAL SPECIFICATIONS
OF A PROPOSED TWO STOREY
RESIDENTIAL UNIT
BLANCA , CLARISSE M.
BS ARCHITECTURE 2020-47005
BUILDING TECHNOLOGY 04
CONTENTS:
Division 3: Concrete
Division 4: Masonry
Division 5: Metals
Division 9: Finishes
Bill of materials
Cost estimates
TECHNICAL SPECIFICATIONS
The proposed two-story residence would be built on a 121 SQM lot as an entire unit in Eastcove
Village Subdivision, Sto. Domingo Cainta, Rizal with a total gross floor area of 192.5 SQM. The
construction of the project will cost the amount of _________. The said proposed two-storey residential
unit was owned by Mr. And Mrs. Romnick and Zaida Malabiga.
I. GENERAL CONDITION
In compliance with the Architects Code of Ethics, the National Building Code, and the Civil Code of
the Philippines, all permanent laws must be applied before, during construction, and upon turnover of
the project.
II. AGREEMENT
The contractor shall verify that he or she will have enough resources available for the duration of the
project to carry out and finish the work in line with the project schedule of "Proposed two-storey
residence unit's".
I. Contract Documents define by this reference:
Scope of Work (Drawings and specifications)
Preliminary schedule of values (preliminary estimate of cash flow needs for the owner)
Form of waivers
Project schedule
Contractor rates as of the date agreement
Form of subcontractor’s express warranties
II. Contractor’s fee shall cover all of the Contractor's expenses that are not covered by the Cost of the
Work.
III. The Cost of the Work shall not exceed the actual expenses that the Contractor faces in performing
the job, excluding any components supplied by the Owner. On the date of the agreement, the
contractor's tools, labor, and supervision shall be billed in compliance with the contractor's current rate
schedules.
IV. Financing agreements required for this agreement by the owner
V. Payment that owner shall make monthly progress payments and a final payment equal to the
Contract Price to the Contractor.
V. UTILITIES
Shall include a requirements for temporary utility, control, facility, and construction aid installation,
maintenance, and disposal during construction.
A. Temporary Utilities
Temporary Electricity
Temporary Fire Protection
Temporary Fuel-oil
Temporary Heating, Cooling, and Ventilating
Temporary Lighting
Temporary Natural gas
Temporary Telecommunications
Temporary Water
B. Construction Facilities
Field Offices and sheds
First Aid Facilities
Sanitary Facilities
C. Temporary Construction
Temporary Bridges
Temporary Decking
Temporary Overpasses
Temporary Ramps
Temporary Runarounds
VI. BONDS
Contractual agreement shall be applied between the three parties. The contractor, surety bond company
and the project owner which was MR. And MRS. Romnick and Zaida Malabiga. All of these ensure
that contractors will complete projects in accordance with the terms of the contract and legal
requirements. They serve as a form of financial security, protecting the public, other contractors, and
project owners.
III. EARTHWORKS
The earthwork in this section is "rough and finish grading necessary to grades and design for proper
site,lawns, shrubs, and ground cover beds, and other landscape materials. There are standards for
building and site storms in this section as well. Retention of water is required, and it must be contained
on-site in retention areas, ponds, or dry wells. Conceptual grade elevations must be taken into account,
indicated on the site plan schematic, and used for the soil fill material and should adhere to these
requirements:
GW, GP, GM, SM, SW, and other soil classification groups described in ASTM D 2487
must be followed while creating soil material SP;
Crushed gravel combinations that have been graded naturally or artificially must be stated
as the sub-base material,sand, stone, or slag;
Crushed gravel combinations that have been graded naturally or artificially must be
designated as base course material, or according to MAG standard 702, Type B, stone;
Backfill and fill materials must be described as soil that is devoid of rock, gravel, or clay
that is larger than 4 inches "the waste trash or other harmful substances;
Top soil must be described as being natural, friable, loamy, producing heavy vegetative
growth, and free of contaminants.
bigger stones, hard clay, weeds, sods, and subsurface than 3/4 "total soluble salts in
saturation, soil pH not greater than 8.0 nor lower than 6.5 of 2,000 parts per million or
more;
Any compaction need must follow the MAG specifications that are in force.
B. TERMITE PROOFING
All new construction and renovation projects that involve wood structures must use termite control
structure's touch with the earth. A licensed professional must certify the application of Records of
Treatment, including the date, time, and place of treatment (particular area / facility), must be
submitted weather the product being used, and the plan section. Prior to approving any payment for
services shall submitted and approved documents, including warranty
Although dead end driveways are strongly discouraged, if site constraints demand this
design strategy, the length of the pull must be at least 20 feet, and its width must be
equivalent to the driveway.
DIVISION 03 - CONCRETE
I. CONCRETE
Every concrete work must adhere to ACI and Section 01 41 00 of the code and
Specifications for Structural Concrete Standard 301 and Standard 318 (Building Code Requirements
for Structural Concrete). Any
Work that wouldn't be suitable must be taken down and replaced at the contractor's expense.
C. Reinforced concrete
Protection of reinforcement in concrete must be negligible.
footings and foundations for walls 50mm
suspension of beams and slabs 20mm
stubbed on grade 40mm
Columns 40mm
all other buildings 20mm
* All bar laps must have a minimum DIA of 20 bars and be spaced apart if possible. except
where otherwise stated, or 300mm.
V. STRUCTURAL CONCRETE
Each and every piece of structural concrete must adhere to the MAG Uniform Standard for portland
cement concrete, see Public Works Construction (MAG 2010). (PCC). PCC shall be made up of
cementitious ingredients, fine and coarse aggregates, and water, as well as specific chemical
admixtures and additions, if permitted, respect for MAG 2010 Section 725.
I. GENERAL
Any masonry construction built on a site must, at the very least, adhere to the
specifications outlined in this document. generally when the outside temperature is below
40 degrees F.
Masonry work cannot be built without heat, heated materials, or safety measures.
All pieces must be solid and without cracks or other flaws that could affect the
construction's strength or permanency if the item is not placed properly.
Mortar: Portland cement, standard-Type 11, low alkali, ASTM C150. Hydrated lime: Type
S of ASTM C 207. Sand that adheres to ASTM C144. Alkali-free or low-alkali cement
(no more than 0.1 percent) shall be used in the formulation of mortar mixes to lessen the
chance of evaporation.
MATERIALS
EXECUTION
1. Masonry should not be installed in cold weather unless enough heating is available.
Supplies, shield the area being worked on from cold and ice, and ensure that the mortar will set
up
without becoming icy.
2. When work is not being done, it is imperative to prevent staining of the face material and to
keep the tops of the walls covered with non-staining waterproof coverings.
INSTALLATION
1. Both the inside and exterior masonry face must be stain-resistant. When no work is being
done, the tops of the walls during construction must be covered with waterproof, non-staining
materials. During the erection of walls, no water may enter.
2. To get the best possible bond with the new work, wipe the visible surface of the set masonry
and lightly damp it. Take out any loose mortar and masonry.
3. Provide secure, suitable scaffolding, centering, and other tools required for the correct
performance of masonry work.
4. The following is the required bond and coursing, with joint reinforcement for the bond as
hereby stated.The mortar between each brick joint must be fully filled.
5. Walls and partitions made of concrete masonry units must be built using the
Unless otherwise specified on the drawings, strength units, bonding and anchoring
METAL DECKS
GENERAL : STEEL ROOF
PRODUCTS:
GALVANIZED SHEET PLATE
STANDARD : ISO,JIS,ASTM,AS EN
ZINC COATED : 40-300g/m2
HARDNESS:Softy , half hard and hard quality
THICKNESS : 0.12-5.0mm
WIDTH: 90-1500mm
INSTALLATION
A. Provide a minimum 2 inch bearing on steel support members.
B. Install the deck across at least three spans and weld it with 5/8-inch diameter concrete.
C. Install the deck over at least three spans, then weld it using 5/8-inch-diameter weldments at
six-foot intervals with two welds in each rib in the corner area, inches in each corner and
around the perimeter of the design layout.
D. Provide a minimum level bearing of [4] [6] inches at each masonry support.
E. Utilizing a carborundum blade, make field cuts.
F. Install concrete unless otherwise indicated:
METAL FABRICATION
Sheet metal fabrication- process of forming flat metal sheets into different steel or aluminum
metal structures. This procedure can cut, punch, fold, and assemble sheet metal into any shape by
using a variety of production techniques.
Fabrication of Steel Ladders - these steel ladders are offered in a variety of shapes and sizes.
They are also utilized in emergency escapes.
MATERIALS:
A. Steel Sections: ASTM A36.
B. B. Sheet Steel: 12 gauge minimum, hot rolled, ASTM A569.
C. C. Steel Tubing: Cold Formed, ASTM A500B and A513.
D. D. Steel Pipe: ASTM A53, type and grade selected by manufacturer as required for design
loading.
E. E. Wall Mounted Handrail Assemblies: Match stair mounted assemblies. F. Threaded End
Hanger Rods: 16 mm (5/8 inch) diameter minimum, ASTM A36. G. Pipe Columns (If
Required): 50 mm (2 inch) nominal minimum.
F. H. Plates, Angles, and Other Accessories: ASTM A36.
G. I. Reinforcing for Concrete Fill: No. 5 bars, grade 40, 356 mm (14 inches) OC maximum.
H. J. Welding Material: AWS D1.1; type required for materials being welded. K. Bolts, Nuts,
Washers, and Other Fasteners: ASTM A307.
I. L. Paint Primer for Steel: Manufacturer's standard.
FINISH :
Before priming, remove all rust, scale, grease, and foreign debris from the surface.
EXAMINATION :
A. Check that field measurements are suitable for the tolerances of the stair assembly.
B. Make sure the supports and anchors are placed properly.
C. Accepting the state of circumstances before installation can begin
PROTECTION:
During welding activities, provide sufficient fire protection.
WASTE REMOVAL :
Waste materials resulting from or produced by the work of this section should be removed
from the area and properly disposed of.
I. All items must be protected from moisture and inclement weather before, during, and after delivery
to the site. Materials must be delivered in insufficient quantities to avoid work delays prior to their
actual use. It must be stacked neatly and at least 150 mm above the ground in a protected area where it
won't disrupt the work in any way.
All dimensions, nailer/metal frame alignment, material specifications, and the full installation of
sanitary/plumbing are in compliance prior to the enclosure of the ceiling and securely attached to the
carrying metal channel/wood runner.
The ceiling board that will be utilized must be in precise line and level with the framing and be free of
any damages.
II. Interior ceiling
All toilets have metal framing with cement board that is 4 mm thick, Hardilite, or equivalent.
V. Finish Carpentry
Interior trims must be made of local stock wood that is maple select's color, grain, and quality
equivalent.
Waterproofing:
6 mL of polyethylene placed above the gravel bed but below the rebars forms the sub-floor vapor
barrier. Ensure that there are spaces between the rebars and the polyethylene sheets.
Toilets: Cemvathene 3, pre-formed single 1.5 mm thick elastic self-sealing bituminous membrane
bonded to 0.15 mm thick polyethylene sheet.
Roof: Guage #24 pre-painted roofing sheets are required. When fixing, it must be in great condition
and free of any sort of zinc coating.
I. SCOPE OF WORK
The best commercial standard must be followed by all materials. Doors must be treated
with a wood preservative, treated for insects, and kiln dried.
1.1 Doors and door frames must adhere to the specifications for doors listed in the plan section titled
Doors and Windows, including their sizes, designs, and types of materials.
1. Doors leading in and out:
Swinging door with a single leaf and a transom window
2.Bathroom doors:
PVC door hinge with a door closer and a 2" x 5" door frame.
BRAND : P.TECH
SERIES : PVC DOORS
DESCRIPTION : PVC MOULDED DOOR
MODEL: P16-B
SIZE: 2100X900X40 MM
3.Room door:
A panel door with a light carving hinge is attached to a door closer and 2" x 5" door
frame.
BRAND : SIKA PHILIPPINES INC.
SERIES : PANEL DOOR
DESCRIPTION: MAHOGANY, TANGUILE
1.2 WINDOWS
The dimensions and styles of the sliding glass windows and full accessories to be utilized in this
project must match those in the detail drawings and window schedule, or as specified in the bill of
materials.
DIVISION 09 - FINISHES
I.SCOPE OF WORK
For the location, see the architectural plans. Verify any other finishes not mentioned or excluded in
this document. A sample of each material must be provided to the procuring entity for review and
approval with regard to color and level of workmanship.
1.Living/dining: painted aluminum framing with cement board that is 2.5 mm thick.
1. Vinyl tiles: 2 mm thick, 250 mm × 250 mm homogenous vinyl tiles are supplied and installed.
2. Color: 64 Odessa. Samples from the contractor must be approved by the procuring entity. Vinyl tiles
must be well cleaned, free of any cement, dirt, or other materials, and then given two coats of water
emulsion wax, with each layer being polished to provide a well-polished sheen.
3. Interior Wall: Semi-gloss latex painted plain smooth cement finish on 6 mm fiber cement boards
with acoustic wool insulation.
1.4 PAINTING
All painting supplies must be brought to the project location intact in their original tins or drums,
mixed exactly as directed by the manufacturer, and applied with the engineer's approval. Applying
latex and enamel paints requires the use of a brush.The Environmental Protection Agency (EPA) must
certify and authorize all painting supplies.For information on the brand and painting supplies to be
used, see the Detailed Unit Price Analysis (DUPA) and Bill of Materials.
1.5 GROUT
Tiles must be damp and joints must be completely grouted with plastic mix of pure cement using
a trowel, brush, or finger. Before grouting the joints, the tiles must have been in place for at least 24
hours. All extra grout must be removed from the tile after grouting with damp sponges and cloths.
DIVISION 10 - SPECIALITIES
Accessories are shown on the drawings and in the processes described above. All toilet accessories
that are stated or indicated on the plans must be provided and installed by the contractor.
1.1 Delivery, storage, and handling of the product: Delivery of the supplies must be planned to
allow for immediate installation. Both during transit and on the construction site, products must
be secured and kept covered. Be careful when handling products to avoid damage.
1.2 Model: Eco-Cassandra water closet with matching seat cover; Sabina wall-hung toilet;
Victoria bidet; Sabina soap holder; Acrylic Cassandra bathtub; Sannix or American Standard
faucet; Sannix or American Standard shower head and valve.
This group includes all household appliances, including those used in the kitchen, laundry, and air
handling and exhaust systems. Residential kitchen appliances include microwaves, refrigerators, ovens,
toaster ovens, and dishwashers.
1. GENERAL CONDITIONS
Provide the tools, materials, and manpower necessary to construct any free-standing, moveable
furnishings, such as chairs, desks, cabinets, sofas, and other pieces of furniture.
A. Framing - Cut square on bearings, firmly fitted, precisely leveled, and securely fastened in position
B. Trim- Free from tool marks that will show through the finish, conform to the design, and follow the
details.
As the name indicates, special construction is distinctive and necessitates evaluation due to its degree
of uniqueness, as well as the particular requirements and properties of the materials used. Inspection of
special constructions frequently consists of a composite of the special construction's components. In
other instances, it is important to carefully follow the manufacturer's or designer's instructions. A
specific field erection representative is frequently offered by the contractor or the employees to provide
instruction and quality control.
1. GENERAL CONDITIONS
Drawings and general contract provisions, Standard General of Division 1 Specification, as well as
Supplementary General Conditions and the Related Sections listed below, and other related
Specification Sections is apply to this Section.
A. TROLLEY HOISTS
Provide hand-operated, army-style trolley hoists. A trolley with gears and a hoist that
provide chains and hooks to units of both ends of the rail having cushioned stop fittings
for the conclusion of transit.
B. BRIDGE CRANE END TRUCKS
Give manual and modular versions of the underhung girder bridge crane and motorized
end trucks and connections (push-pull). Prepare units with both ends of the runway beams
have cushioned stop fittings at the end of transport
C. SCAFFOLDINGS AND PLATFORMS
Each platform must be fully decked and planked, with no more than an inch separating the
platform from the uprights. The area cannot be larger than 9 when side brackets are
inches.
There is a bigger gap between the platform and the upright in constructions that are irregularly
formed.
Each end of platform 10 feet or less in length shall not extend over its support more than
12 inches, and when more than 10 inches it shall not extend over its support of more than
18 inches
Every scaffold must be well-built, made of sturdy materials, and strong enough to serve
the intended purpose.
All scaffold components and materials must be kept in good condition and kept apart from
other materials that are inappropriate for scaffolds while not in use or intended for reuse.
All manufactured scaffolds and their attachments must comply to the design and
standards of the manufacturer. For manufactured scaffolds higher than 6 meters, a
structural engineer's design must be approved by the authority.
1. PLUMBING WORKS
The Philippine Plumbing Code, the National Building Code, and the laws and regulations
of the city or municipality where the project will be developed must all be followed while
carrying out any plumbing work that is covered in this document.
Coordinate the drawing with other important drawings and specifications; any differences
must be reported right once to the engineer.
All pipes must be installed according to the designs, and any changes needed for other
trades to be completed correctly must have the architect's or engineer's prior clearance.
For details about where to find an area drain, catch basin, floor drain, and clean out, see
architectural plans.
The manufacturer's recommendations must be followed regarding the size of the water
supply pipes to fixtures.
Unless otherwise stated, the contractor must check all on-site utilities and coordinate the
work with the line service connecting point.
All pipe diameters and measurements are given in millimeters unless otherwise specified.
Unless the structural engineer specifically approves differently, no hangers may be
anchored at purlins.
I. SCOPE OF WORKS
The work provided by this section of the specification entails providing all labor, tools, materials,
and supplies as well as carrying out all operations required for the installation of a full interior wiring
system. The electrical installation shall be carried out in accordance with the approved plans under
the direct supervision and control of a Professional Electrical Engineer or Registered Electrical
Engineer. The installation shall be complying with the the applicable rules of the latest edition of the
Philippine National Electrical Code wherever otherwise noted on the drawings.
II. WIRING
Installation of the outlet shall take place in the area depicted in the drawing. In order for their work
to be compatible with the other tasks required by these specifications, the contractors must study the
building plans in relation to the areas surrounding each outlet. The electrical wiring must be installed
using PVC electrical conduit, fittings, and accessories that adhere to the ISO dimensions.
IV. TESTS
A test shall be conducted in the presence of the Architect-in- Charge after the installation of all
electrical system reported inwiring by the contractor to be studied for acceptance to estimate whether
it is In accordance with the requirements of this specifications or fail to do the contract.
V. LIGHTING FIXTURES
The owner shall borne for out all lighting fixtures, requirements to P.D. Fire code of the Philippines ,
Section 1185.
1. All wooden parts, including the roof framing and other wooden material's, Should be treated with a
fire-retardant applicator.
2. Set up of fire-resistant application
3. Fire exit construction.
4. According to the Philippines Electrical Code, electrical wiring must be of standard size.
5.. Every position for a split knob and every change in direction needs to have a circular loom.
6. Light outlets must all be 2.0 square. 1.5 mm THW wire and 2.0 sq. For each outlet, use mm THW
wire.
7. Every branch connection requires a junction box
BILL OF MATERIALS
The proposed two-story residence would be built on a 121 SQM lot as an entire unit in Eastcove
Village Subdivision, Sto. Domingo Cainta, Rizal with a total gross floor area of 192.5 SQM. The
construction of the project will cost the amount of ₱1,689,625 . The said proposed two-storey
residential unit was owned by Mr. And Mrs. Romnick and Zaida Malabiga.
IV. LUMBER
PLYWOOD
1/2” 4’ X 8’ 24 pcs 600
LUMBER
2” X 3” x 10” 24 Bd.ft 120
V. ROOFING MATERIALS
RIB TYPE ROOF 11 pcs 683
PURLINS 36 pcs 485
GUTTER 19 pcs 392
BLIND RIVETS 361 pcs 137
SEALANT 7 pcs 164
RIDGE FLASHING 5 pcs 306
RIDGE CAP 6 pcs 332
VI. IRONWORKS
PURLINS
C-PURLINS Z” X 3” 36 pcs 485
The proposed two-story residence would be built on a 121 SQM lot as an entire unit in Eastcove
Village Subdivision, Sto. Domingo Cainta, Rizal with a total gross floor area of 192.5 SQM. The
construction of the project will cost the amount of ₱1,689,625 . The said proposed two-storey
residential unit was owned by Mr. And Mrs. Romnick and Zaida Malabiga.
2. TILEWORKS
0.80 X 0.80m ROSSIO PIL 214 pcs 113848 45539 159387
CYPRESS
GREY TILES
0.40 X 0.40 MARIWASA 58 pcs 4118 1647 5765
DIGITILE PRIMEA GREY
FLOOR TILES
0.40 x 0.40 MARIWASA 254 pcs 18034 7213 25247
DIGITILE CABIN OCHRE
WALL TILES
TILE ADHESIVE 6 pcs 1800 720 2520
TILE GROUT 4 pcs 320 128 448
1. FOOTING
EXCAVATION 19 Cu.m. 11400 4560 15960
CEMENT 40KG. 135 bags 32130 12852 44982
SAND 8 Cu.m. 9600 3840 13440
GRAVEL 3/4 16 Cu.m. 14080 5632 19712
16MM dia. DEF. BARS 22 pcs 8624 3450 12073
G.I. TIE WIRE #16 4 Kg 244 98 342
SUB-TOTAL 106,509
2. COLUMN
CEMENT 40KG. 185 bags 44030 17612 58212
SAND 11 Cu.m. 13200 5280 18480
GRAVEL 3/4 21 Cu.m. 18480 7392 25872
16MM dia. DEF. BARS 18 pcs 7056 2822 9878
10MM dia. DEF. BARS 142 pcs 22152 8860 31012
GI.TIE WIRE #16 15 kg 915 366 1281
1/2” THK x4’ x8’ plywood 12 pcs 9480 3792 13272
board
2” x 3” x 10” COCO 12 pcs 3240 1296 4536
LUMBER
CONCRETE NAIL 1” 5 kg 865 346 1211
CONCRETE NAIL 3” 5 kg 840 336 1176
COMMON WIRE NAIL 4 kg 560 224 784
2”
COMMON WIRE NAIL 4 kg 528 212 740
3”
SUB-TOTAL 166,454
4. SLAB ON GROUND
CEMENT 40KG. 130 bags 30940 12376 43316
SAND 10 Cu.m. 12000 4800 16800
GRAVEL 3/4 15 Cu.m. 13200 5280 18480
10MM dia. DEF.BARS 272 pcs 42432 16927 21170
G.I. TIE WIRE #16 26 kg 1586 635 2221
CONCRETE NAIL 1” 5 kg 865 346 1211
CONCRETE NAIL 3” 5 kg 840 336 1176
SUB-TOTAL 105,384
5. ROOFING
2X4 TUBULAR RAFTER 10 pcs 4440 1776 6216
2X3 C-PURLINS 36 pcs 17460 6984 24444
12MM dia. DEF.BARS 9 pcs 3213 1285 4498
(Sag Rods)
WELDING ROD 6013 7 kg 11550 4620 16170
REFLECTIVE FOIL 168 Sq.m. 369600 147840 517440
INSULATION
GA #24 G.I. RIB TYPE 154 Sq.m. 23100 9240 13860
PANEL
1/2” X 1’ X 8’ HARDIE 17 pcs 8449 3379 11828
SENEPA
G.I. GUTTER 19 In.m. 7448 2979 10427
G.I. CAPPING 6 In.m. 1992 796 2788
G.I. FLASHING 5 In.m 1530 612 2142
TEK SCREW 101 pcs 9090 3636 12726
SILICON SEALANT 7 tubes 1148 459 1607
EPOXY PRIMER 4 cans 1140 456 1596
NIPPON PAINT 6 cans 1722 688 2410
SUB -TOTAL 628,152
1. SANITARY LINE
4” DIA. PVC PIPE 18 pcs 14400 5760 20160
3” DIA. PVC PIPE 18 pcs 10818 4327 15145
2” DIA. PVC PIPE 20 pcs 5380 2152 7532
PVC FITTNGS lot 259 103 362
FLOOR DRAIN 4”X4” 4 pcs 1124 450 1573
C.I. STAINER 500X500 4 Pcs 10128 4051 14179
MM
3. PLUMBING FIXTURES
WATER CLOSET (by 2 pcs 15300 6120 21420
contractor)
LAVATORY ( by 2 pcs 3598 1439 5037
contractor)
4. CONSUMABLES 4000
SUB- TOTAL 99,555
TOTAL AMOUNT 1,689,625