Dallas Bike Plan 2023

City Council Briefing


November 1, 2023

Ghassan “Gus” Khankarli, Ph.D. P.E., PMP, CLTD


Director
Department of Transportation

Kathryn Rush
Chief Planner
Department of Transportation
Presentation Overview
• Purpose
• Plan Objectives and Scope
• Public and Stakeholder Engagement
• Advisory Committees Overview
• Final Draft Plan Review
• Next Steps
• Discussions

2
Purpose
• Provide an overview of the Bike Plan Update approach.
• Summarize public and stakeholder engagement and
comments received.
• Provide updates to the Final Draft Bike Plan.

3
Plan Objectives and Scope
Existing Bike Network

1. Update the Bike Network Map


• Inventory the entire bike network, including
changes since the 2011 Bike Plan.
• Coordinate with bike plans and projects from
partnering agencies and neighboring cities.
• Ensure the updated bike network:
a) Connects existing network gaps
b) Provides greater safety and comfort
c) Improves system connectivity, including
connections to trails and transit

4
Plan Objectives and Scope (cont.)
2. Develop new or updates to bike facility design standards

3. Develop a list of prioritized projects and provide more detailed


implementation guidance on the top 15 projects

4. Educate residents about this mobility option and ensure equity

Design guidance from


NACTO, FHWA,
AASHTO

5
Plan Objectives and Scope
1. EXISTING CONDITIONS ANALYSIS 2. UPDATE BIKE NETWORK,
• Demand POLICIES & DESIGN STANDARDS
• Level of Traffic Stress • Network Alternatives Evaluation
• Safety • Feasibility Evaluation
• Public Health • Standards, Guidelines, Specifications
• Equity Review & Recommendations
• Network Gaps • Initial, Draft, and Final Recommendations
• Plans & Policies

3. PROJECT PRIORITIZATION & 4. PLAN DEVELOPMENT


FUNDING • Draft Plan
• Project Prioritization Framework • Revised Draft Plan
• Prioritize Identified Projects • Final Plan
• Project Plan Sheets
• Funding Analysis
• Project Cost Estimates (Top 15 prioritized
projects)

6
Public and Stakeholder Engagement
Public Involvement Plan
INITIAL OUTREACH: Spread
Awareness of the Project
• When: Spring 2022
• How: Flyer distribution at events, social media
outreach

PHASE 1: Input on Existing Issues,


Opportunities, Vision
• When: Summer 2022
• How: Online/paper surveys and interactive
comment map

7
Public and Stakeholder Engagement cont.
Public Involvement Plan
PHASE 2: Input on the Draft Bike
Network
• When: Fall 2022
• How: 7 in-person events, 3 in-person pop-up
events, & online input via interactive webmap

PHASE 3: Input on Priority Projects


and the Draft Plan
• When: Summer 2023
• How: 1 virtual meeting, scavenger hunt, online
surveys

8
Phase 1 Public Engagement
PHASE 1
VIRTUAL • 3,182 participated in the survey (online + paper)
ENGAGEMENT • 1,823 provided comments on the interactive
Jul 2022 existing bike network webmap

PHASE 2
OPEN HOUSES

Oct-Nov 2022
more than of survey respondents mentioned
conflicts with cars, fears for safety,
PHASE 3 and lack of access to bike facilities
as barriers to biking in Dallas
VIRTUAL
ENGAGEMENT
Jun-Jul 2023

9
Phase 2 Public Engagement
PHASE 1
VIRTUAL
ENGAGEMENT
Jul 2022

PHASE 2
OPEN HOUSES

Oct-Nov 2022

PHASE 3
VIRTUAL
ENGAGEMENT
Jun-Jul 2023

10
Phase 2 Public Engagement
PHASE 1
VIRTUAL
ENGAGEMENT
Jul 2022

PHASE 2
OPEN HOUSES

Oct-Nov 2022

PHASE 3
VIRTUAL
ENGAGEMENT
Jun-Jul 2023

11
Phase 3 Public Engagement
PHASE 1
VIRTUAL
ENGAGEMENT
• 464 comments on proposed • 88 survey comments on
Jul 2022
bike network map the Draft Bike Plan
document
PHASE 2 • Feedback themes:
OPEN HOUSES Preference for • Feedback themes:
separated bike facilities General support of
Oct-Nov 2022 Bike Plan Update
Safe crossings at
PHASE 3 intersections General support of
VIRTUAL updated bike network
ENGAGEMENT Connections to parks,
trails, and transit
Jun-Jul 2023
Traffic calming

12
Advisory Committees
2 Committees Guided the Plan Update:
• Bicycle Advisory Committee (17 members):
o Representatives nominated by Mayor and each Councilmember.
o 2 additional representatives nominated by DDOT
o 5 meetings throughout the plan update
o 1 additional joint meeting with Technical Advisory Committee
• Technical Advisory Committee (34 members):
o City of Dallas staff from several departments
o Regional Transportation Partners (DART, NCTCOG, Dallas County, TxDOT)
o 8 meetings throughout the plan update

13
Final Draft Plan Review- Overview

Report Sections
• Executive Summary
• Introduction
• Methodology for Updating Bike Network
• Design Standards
• Policies
• Implementation

14
Final Draft Plan Review– Sections
Methodology for Updating the Bike Network
Network
Development Process
• Existing Conditions Analysis: • Map and spatially
assess existing
o Existing Facilities Inventory conditions.
• Evaluate gaps and
o Bike Demand Assessment opportunities in
existing road and bike
o Level of Stress Assessment •
network.
Leverage major street
connections to
o Safety Assessment emphasize directness.
• Use local network for
o Equity & Public Health Assessment neighborhood
connections.
• Evaluate routes to
• Network Development Process. determine preferred
spacing.
• Include trail
connections as part of
the network.

15
Final Draft Plan Review– Sections
Recommended Design Standards Updates

Bike Boulevard Traffic Calming

“Floating” Bus
Platform
16
Final Draft Plan Review– Sections
Recommended Design Standards Updates Bike Facility Classifications

(cont.) Physically Separated Bike Lanes

Bike Boulevards

• Updated Bike Facility Classifications:


o Bike Boulevards
o Visually Separated Bike Lanes
o Physically Separated Bike Lanes
o Shared Use Paths (paved trails)
• DART Bus Stops.
• Treatments for Intersections and Signalization.

Shared Use Paths (paved trails)


Visually Separated Bike Lanes
17
Final Draft Plan Review– Sections
Implementation & Next Steps
• Funding Opportunities.
• Phasing:
o Top 15 Priority Projects
o Long-Term Project Phasing
• Inclusion of Bike Facilities in Capital
Reconstruction Projects.
• Interdepartmental, Interagency, and Community
Bike Plan Working Groups.
• Bike Plan Implementation Progress Reporting.
18
Final Draft Plan Review– Policy Recommendations

Any road reconfiguration The bike facility type The facility selection chart The City shall utilize a
project on a street with a identified in the Bike Plan shall be used to guide the standardized methodology
bike improvement project shall be the recommended determination of the bike for identifying, prioritizing,
identified in the Bike Plan facility type to be facility type on roads that and implementing bike facility
shall include that bike implemented. are not specifically identified improvements consistent
project in the design plans. in the Bike Plan as having a with the process used for the
bike improvement project. Bike Plan.

If a project that reconfigures roadway lanes does not


The target design user for A Bicycle Route or Bike
include a bicycle facility when one is recommended in
future bike facilities in the Boulevard facility shall not be
the Bike Master Plan, or it is determined by the DDOT
City of Dallas shall be implemented on any road
Director that the desirable Low Stress bicycle facility is
someone that is “Interested with speeds greater than 25
not feasible on that roadway, an alternate parallel route
but Concerned.” mph or volume greater than
that can provide a Low Stress facility shall be identified,
3,000 vehicles per day.
and the bicycle facility implemented on that route is to
be part of that original roadway project

19
Final Draft Plan Review– Policy Recommendations

11
Bike facility design Bike facilities shall be Implement when possible The City shall use the 3-1-
standards shall include maintained on a low-cost/fast 1 System to allow the
the use of green schedule similar to or implementation design or reporting of bike facility
pavement markings and more frequently than operational modifications problems or concerns.
related high visibility the adjacent vehicle that would immediately
design elements… travel lanes. improve the safe
operation of bike riders.

12 13 14 15 16
The City shall require The City shall prohibit The City’s Thoroughfare The City shall develop Street lighting along
that bike facility and vehicle parking that Plan shall be updated dedicated funding facilities with constructed
safety issue shall be partially or wholly with the information strategies for bike bike facilities should be
considered in all roadway obstructs any bike from the Bike Plan to projects to leverage the evaluated to improve the
or development design facility. identify constructed and funding apportioned from safety and visibility of
plans review. proposed facilities. the General Fund. bike riders.

20
Final Draft Plan Review-Future Amendment Process

• The Bicycle Network needs to be able to respond to future


development, changing land use/facilities conditions, and
feasibility challenges.
• A process to review and approve the Bike Network will be
proposed in the Bike Plan.

21
Final Draft Plan Review-BAC Functions

• Refine the Bicycle Advisory Committee (BAC) functions to


provide guidance and input to proposed projects.
• The details of the refined functions will be provided in the
Bike Plan.

22
Next Steps

• City Council adoption of the Bike Plan Update by Early


2024.
• Recommendations to update the Street Design Manual and
revisions to the City’s standard design details.
• Development of the framework for the consolidation of the
BAC functions.
• Continue the development of bike projects.
• Continue the identification of potential funding sources for
projects implementation.

23
Discussion

• General questions/comments/feedback.

24
Dallas Bike Plan 2023
City Council Briefing
November 1, 2023

Ghassan “Gus” Khankarli, Ph.D. P.E., PMP, CLTD


Director
Department of Transportation

Kathryn Rush
Chief Planner
Department of Transportation
Final Draft Plan Review– Policy Recommendations

• Any reconfiguration • The bike facility type • The facility selection • The City shall utilize a
project on a street identified in the Bike chart shall be used to standardized process for
identified in the bike Plan shall be the guide the determination identifying, prioritizing,
plan to have a bike recommended facility of the bike facility type and implementing bike
improvement project type to be implemented. on roads not specifically facility improvements
will include that project identified in the Bike consistent with the
in design plans. Plan. process used for the Bike
Plan.

• If a reconfiguration project does not include a bicycle


• The target design user • A Bicycle Route or Bike
facility when one is recommended in the Bike Master
for future bike facilities Boulevard facility shall not
Plan, or the DDOT Director determines that the
in the City of Dallas is a be implemented on any
desirable Low Stress bicycle facility is not feasible on
user who is “Interested road with speeds greater
that roadway, an alternate parallel route that can
but Concerned.” than 25mph or volume
provide a Low Stress facility shall be identified. The
greater than 3,000
bicycle facility implemented on that route is to be
vehicles per day.
part of that original roadway project.

26
Final Draft Plan Review– Policy Recommendations
cont.
11
• Bike facility design • Bike facilities shall • Implement when • The City shall use the
standards shall be maintained on a possible low-cost/fast 3-1-1 System to allow
include the use of schedule similar or implementation the reporting of bike
high visibility design more frequently design or operational facility problems or
elements, including than the adjacent modifications that concerns.
green pavement vehicle travel lanes. would immediately
markings. improve the safety of
bike riders.

12 13 14 15 16
• The City shall require • The City shall continue • The City’s • The City shall develop • Street lighting along
that bike facility and to prohibit vehicle Thoroughfare Plan dedicated funding facilities with
safety issues shall be parking that partially shall be updated to strategies for bike constructed bike
considered in all or wholly obstructs reflect proposed and projects to leverage facilities should be
roadway and/or any bike facility. existing bike facilities the funding evaluated to improve
development design from the Bike Plan apportioned from the the safety and visibility
plan reviews. General Fund. of bike riders.

27
Discussion/Feedback
Central Planning Area Network Recommendations

28
Discussion/Feedback
North Central Planning Area Network Recommendations

29
Discussion/Feedback
Northeast Planning Area Network Recommendations

30
Discussion/Feedback
Northwest Planning Area Network Recommendations

31
Discussion/Feedback
South Central Planning Area Network Recommendations

32
Discussion/Feedback
Southeast Planning Area Network Recommendations

33
Discussion/Feedback
Southwest Planning Area Network Recommendations

34