Professional Documents
Culture Documents
Technical Details
Technical Details
JOHKASOU
Dear Sir,
DAIKI AXIS
Clean water is necessary for our life, but in many developing
ENVIRONMENT (PVT)
countries, access to wastewater treatment facilities is limited,
LTD and untreated wastewater is released to rivers, lakes, and the
ocean. Contamination of the source of drinking water causes
water-borne diseases. DAIKI AXIS. has advanced technology for
treating wastewater. DAIKI AXIS’s products are called Johkasou,
which means “water purifying tank” in Japanese. Johkasou look
like conventional septic tanks that are used in many Asian
+94 112 894 423
countries, Africa, and Middle East. but their functions are
+94 765 380 380 completely different from those of a standard septic tank.
Traditionally, septic tanks have been made from concrete, a
225, GALAVILAWATHA, material that tends to break down over time and that requires a
HOMAGAMA considerable amount of maintenance. Although the company
started out using concrete – DAIKI AXIS 's headquarters are in
japan that is famous for its pottery, so it was natural that they
began with the clay-like material – the firm developed materials
that would allow them to make better products. DAIKI AXIS
now makes their tanks out of fiberglass-reinforced polymer
(FRP) and polypropylene (PP), substances that stand up
particularly well against the elements, and they need far less
maintenance in the long run, making them very cost effective.
DAIKI AXIS has been awarded an Eco-Mark certification for its
XE models.
Sincerely,
DAIKI Axis Environment (PVT) LTD
Version 2.00 (Issued in Apr 2020)
Installation Procedures
△! Caution Prior to installation of the Johkasou, carefully read the warnings and
cautions in this document to fully understand them.
・・・・・・・・・・ 4
2. Standard Installation
2-1 Prior On-Site Survey ・・・・・・・・ 5
2-2 Temporary Work ・・・・・・・・ 7
2-3 Excavation ・・・・・・・・ 7
2-4 Foundation Work ・・・・・・・・ 8
2-4-1 Leveling the base with rubble stones ・・・・・・・・ 8
2-4-2 Leveling concrete casting ・・・・・・・・ 8
2-4-3 Temporary base formwork ・・・・・・・・ 8
2-4-4 Bar arrangement for base ・・・・・・・・ 8
2-4-5 Base concrete casting ・・・・・・・・ 8
2-5 Installation (of FRP Main Unit) ・・・・・・・・ 9
2-6 Filling Water ・・・・・・・・ 9
2-7 Backfill ・・・・・・・・ 10
2-8 Piping ・・・・・・・・ 10
2-9 Electrical Work ・・・・・・・・ 11
2-10 Installation of Incidental Equipment ・・・・・・・・ 11
2-11 Upper Concrete Work ・・・・・・・・ 11
2-12 Trial Operation ・・・・・・・・ 12
2-13 Cleaning after Work, Completion Inspection and Delivery ・・・・・・・・ 12
3. Special Installation ・・・・・・・・・・ 13
・・・・・・・・・・ 17
4. After-Sales Services
1
1.Precautions before Work
● Explanation of Indication
! Caution …1) Prevention of fall from manhole or inspection hole and injury
(i) During the work, be sure to keep the manhole and the inspection hole closed with covers except when
they need to be open.
(ii)If the manhole and the inspection hole is found to have any crack or damage, immediately replace it.
Failure to observe this could result in a fall or injury.
Place scaffold planks or equivalents while filling water and attaching anti-floatation fittings.
Failure to observe this could result in a fall.
Set up a protection fence around the hole dug for the burial work to keep anyone other than personnel
concerned outside of the fence.
Failure to observe this could result in a fall (and an injury).
(i) Be sure to ground the blower, the pump, the control panel and other electrical equipment as required.
(ii) If the blower is powered by an outlet, use a rainproof power outlet.
(iii) Ask a specialist with qualifications for electrical work to carry out the work for the blower, pump, control
panel and other electrical equipment.
Failure to observe this could result in an electric shock or ignition.
2
・ Pay attention to the following to maintain safety during the work.
Attention
Attention (i) Check the documents to be submitted to governmental offices, such as notification of STP
installation. Documents vary depending on the country where Johkasou is installed.
Attention (ii) Firmly comply with the Work Implementation Procedures, the Installation Procedures, the
Technical Standards for STP Installation and other laws and ordinances when carrying out
the installation.
Incorrect installation could result in damage to the tank that leads to the leakage of
wastewater and deterioration of discharged water.
Attention (iii) Pay attention to air blower, moisture prevention and noise at the site where the blower is
installed.
Check that the foundation is made of concrete to prevent vibrations and that it is designed
to withstand the weight and vibrations of the blower.
Make sure that the concrete foundation for the installation is not directly connected to any
building and that it is at least 12 cm above ground (GL) and 5 cm larger than the exterior
dimensions of the blower platform.
Attention (iv) Carry out the work in compliance with the Technical Standards for STP Installation.
Particularly, foundation work, backfill work and upper slab installation work, among others
must be carried out properly in accordance with the Installation Procedures.
In the event where Johkasou is installed at a parking space or a garage or near a busy
road, on soft ground or in a region with heavy snowfall or where the load of a nearby
building affects the whole system, special work is required. Carry out reinforcement work
in a way that does not affect the whole system.
Especially in the event where Johkasou is installed in a place where an indefinite number
of vehicles are parked in connection with an office or a store, pay attention to carrying out
reinforcement work for making Johkasou resistant to the presumable maximum load in
consideration of the scale of the store or other establishment and the size of the parking
space.
Attention (v) Pay attention to the following during backfill work in order not to damage Johkasou.
1) Fill water before starting the backfill work.
2) Fill sandy soil without stones for backfill purposes.
3) Do not bring the bucket or other part of the heavy machine into contact with Johkasou
or drop backfill soil from a high place during backfill work.
Attention (vi) Do not open the package of the disinfectant to be put into Johkasou until Johkasou is put
into use.
Failure to observe this notice could resulting in the generation of chlorine gas from the
disinfectant, a reaction of the gas with moisture in the air to generate hydrochloric acid,
which erodes metal.
Attention
(vii) Perform a check with the use of the Installation Checklist while proceeding with the
installation work.
Attention (viii) Advise the user to conclude a maintenance and management agreement with a STP
maintenance and inspection operator.
Attention (ix) When handing the warranty certificate to the owner, be sure to receive a letter of receipt
and to store it.
Attention (x) Contact our personnel for any questions about system installation.
3
2. Standard Installation
● Work Process Flow
1 Prior on-site survey
↓
2 Temporary Work
↓
3 Excavation
↓
4 Foundation work: leveling the base with rubble stones
↓
: Leveling concrete casting
↓
: Temporary base formwork
↓
: Bar arrangement for base
↓ Production
: Base concrete casting completed in factory
↓
5 Installation (of FRP Main Unit)
↓
6 Filling Water
↓
7 Backfill
↓
8 Piping
↓
9 Electrical Work
↓
10 Installation of Incidental Equipment
↓
11 Upper Concrete Work
↓
12 Trial Operation
↓
13 Cleaning, Completion Inspection and Delivery
4
2-1 Prior On-Site Survey
In preparation for the work, carry out an on-site survey to check the conditions specified below for work
implementation.
Check if the space has the size required as in the installation drawings.
(i) Installation space Refer to the work drawings. Normally, there shall be a distance of
approximately 300 mm between tanks.
(ii) Installation conditions Bury Johkasou underground in accordance with the conditions in Table 1.
In the event where the space above Johkasou is used for parking, where
Johkasou is installed near a busy road or where Johkasou is next to any
(iii) Necessity of special work
cliff or building, special work is needed. Refer to the section titled Cases
where Special Work is Needed.
Install an exhaust pipe if necessary because Johkasou may general foul
odors. The exhaust pipe shall be extended to the designated position with
the use of a horizontal pipe and an upright pipe shall be erected to a height
(iv) Exhaust pipe position that is around three meter above the ground level to prevent any problems
with foul odors.
Install an exhaust fan if necessary. In that case, capacity of the exhaust fan
has to be below.
Check if maintenance, inspection and cleaning work can be easily
(v) Ease of maintenance work
accomplished.
Install the blower and machine room in places where they will cause no
trouble relating to sound and vibrations to neighboring residences and other
buildings, which are at least 15 meters away. Especially if a roots blower is
(vi) Equipment Installation place used, take necessary measures to prevent sound and vibration.
Install the blower (and machine room) within an approximate distance of 10
meters from Johkasou if possible. Provide a power outlet and water faucet
for inspection near Johkasou.
(vii) Existing pipe position Check if the gas pipe or water service pipe are not being laid in the ground
(gas & water) in the planned place of installation.
(viii) Status of the pipeline Check if there is any obstacle in the pipeline of Johkasou.
Check if there is any obstacle to carry Johkasou-related machinery and
(ix) Status of carry-in (out)
materials to the place of installation.
Check if there is any storage space for materials and any space where
(x) Status of the area around trucks and surplus soil can be temporarily placed, if crane and truck
the place of installation operations can be ensured, whether Johkasou adopts natural discharge or
pumped discharge.
(xi) Soil quality Check the soil quality. Refer to Table 1.
Check if there is any spring water.
(xii) Spring water conditions
Check if any sheet pile or equivalent is needed.
(xiii) Electric power and water Check if electric power and water for work can be procured on site.
5
Table 1: Installation Conditions (Burial)
Standard value
Bearing capacity of soil 50 kN/m2
Live load 1.8 kN/m2
Ground water level Up to the ground level
Special load Must not be imposed.
6
2-2 Temporary Work
(i) Before starting the work, enclose the installation place with a
rope to confirm the space and check it against the design
drawing.
(ii) Drive wooden piles and concrete piles at places where they
do not hinder the work in preparation for centering and the
height check.
(iii) Perform a prior check on the designated ground as a benchmark.
(iv) Install a temporary fence if necessary to ensure safety.
(v) Check if Johkasou has any damage or cracks while it is carried in
and place it in a location where it will not be damaged.
Fig.1
2-3 Excavation
W2
(i) Determine the method of disposing of excavated soil
Prior to the work, determine how to dispose of the excavated soil.
(ii) Minimum excavation dimensions W1 W1
Provide the same margin for in front, behind, left and right edge of
W2
the main unit dimensions as portrayed in Fig. 2.
Normally, both W1 and W2 shall not be any smaller than 0.5
meters, respectively.
(iii) Space where excavated soil is placed Fig.2
For the purpose of preventing collapse, put excavated soil in a
place as distant to the excavation plane as possible.
(iv) Protection of natural ground
In the excavation work, ensure the specified form and dimensions.
Excessive excavation could cause damage to the natural ground to
make the foundation unstable and make Johkasou not level. Check
the excavation depth during the work.
(v) Work at a place with a spring
Provide a water-collecting sump basin for the pump as portrayed in
Fig. 3 to discharge underground water with the sump pump. Fig.3
(vi) Cases where retaining walls are needed
As portrayed in Fig. 4, the minimum excavation dimension W2 shall
be 0.5 meters or more.
For retailing walls, use sheet piles and H-shaped steel sheet piles.
Retaining walls are required in the cases described below.
- The place of excavation is next to any building or road.
- Excavation slope is not secured enough.
- Soft ground is excavated.
- There is high volume of spring water.
Fig.4
Fig.4
7
2-4 Foundation Work
2-4-1 Leveling the base with rubble stones
(i) The soil must have a bearing capacity that is equivalent or superior to the level specified as part
of the installation conditions in Table 1 (See 2-1 Prior On-Site Survey.) Drive support posts into the
ground with a bearing capacity below this specified level.
(ii) Pay attention to achieve a sufficient leveling precision when preparing the ground.
(iii) For rubble stones and crusher-run stones, use uniformly-sized hard stones. After placing them, scatter
the gap-filling sand. Then stamp them sufficiently with a rammer or other device. Generally, the base
should be completed with the thickness of 150 mm.
8
W
φ2170
Fig.5
Fig.6
9
2-7 Backfill
(i) Before starting the backfill work, check if the water is filled throughout Johkasou. Never carry out the
backfill work if Johkasou is empty.
(ii) For the backfill work, use soil of high quality, such as mountain sand and river sand. Make sure that
it does not contain any large stones, stone chips, wood chips or equivalent.
(iii) Properly add covers to the manhole cover, the feed pipe, the discharge pipe and others to prevent
any sand or earth from entering Johkasou.
(iv) Carry out the backfill and water binding work in three steps. First, evenly carry out backfill and water
binding up to one third of the full height. Then compact the area with a rammer or a vibration plate.
Carry out the second step in the same way. During the third step, do not compact the area above
Johkasou with a rammer or other apparatus.
(v) For water binding, wait until the water goes down before adding water for the next time. Pay attention
not add water for binding beyond the level of water filling. Failure to observe this will result in the
floating of Johkasou.
(vi) During the backfill work, securely fix the connection piping to prevent damage.
2-8 Piping
Piping work
(i) The piping inside Johkasou has been produced in a factory at the best possible quality. On-site piping is
mainly for connections between tanks and piping from the blower to the main unit.
(ii) Install piping for connecting tanks via an MC Union joint or a basin. Make sure the piping has a grade of
1 in 80 to 1 in 100 and that it has no counter-gradient or leakage at the joint.
(iii) For the air piping from the blower to the main unit of Johkasou, use a polyvinyl chloride pipe (or a VP pile
according to JIS), which is unlikely to corrode. In the event of using a steel pipe for the purpose of
addressing the problem with heat from the blower, apply anti-corrosion treatment to it.
(iv) Make sure that the cover soil for the outdoor piping has a depth of at least 20 cm and that the piping is
not exposed. In the case of making it exposed for unavoidable reasons, provide a safety fence as
necessary.
(v) Support the piping with the use of columns and support plates as necessary. To prevent accidents
resulting from subsidence, carry out sufficient rolling compaction before piping.
(vi) During backfill work, perform sufficient compaction around the piping while paying attention not to cause
damage to it and backfill to the specified height.
(vii) For details about piping, follow the On-Site Piping Work Drawings.
Exhaust pipe
(i) This system may generate foul odor. Install an exhaust pipe if necessary.
(ii) Install an exhaust pipe fan if necessary.
(iii) Set the upright position of the exhaust pipe in a well-ventilated place and make the horizontal pipe as
short as possible, sloped downward towards Johkasou.
(iv) The exhaust pipe position shall be decided in consideration for the neighboring environmental conditions.
10
2-9 Electrical Work
(i) Make sure that electrical work will be carried out by qualified specialists.
(ii) Be sure to conduct grounding work.
(iii) Gas that corrodes metal is generated in Johkasou. Be sure to tightly seal the part that comes into contact
with the control panel.
(iv) Make sure that electrical work will be conducted in accordance with the electrical and wiring drawings. For
the places where float switches are to be installed, refer to page 16.
Installing a pump
(i) Normally use a rigid polyvinyl chloride pipe for pump piping.
(ii) Make sure the pump can be easily detached and reattached so that remedial action can be taken in the
event that the pump becomes clogged.
(iii) Set the discharge pipe in a position that is higher than the highest water level of the discharge destination.
(iv) Install float switches for the start and stop positions where the walls of Johkasou do not induce them to
malfunction.
11
2-12 Trial Operation
(i) During the trial operation, use the Operation Checklist provided on a separate sheet.
(ii) The installation will be complete if it is confirmed that the individual equipment functions properly and that
the functions of the control panel operate without a problem.
12
3. Special Installation
(1) Manhole neck extension by more than 300 mm Reinforced Checkered
concrete pit plate
support the load and to prevent Johkasou from being directly subject
to it (See Fig. 8).
In the event of installing Johkasou where large vehicles pass by, construct Fig.8
a retaining wall to prevent the wheel pressure and load from being applied
to Johkasou. Replace the manhole with a pressure-resistant one.
13
concrete wall
Fig.10
Fig.9
車の交通に
Separate to the position
影響のない
Where the traffic of the car
does not have the influence
位置まで離す
Fig.11
14
(4) In the case where Johkasou cannot be installed away from the foundation of a building
Install a reinforced concrete retaining wall.
Determine the reinforced concrete’s thickness, reinforcing bar’s diameter and intervals in accordance with the
soil pressure that applies to the retaining wall (See Fig. 13).
Foundation
of building
Reinforced
concrete wall
Fig.13
(5) Installing Johkasou in a cold region
(i) Thermal insulation
If there is a risk of freezing inside Johkasou, install it at a depth that ensures that the water surface is below
the freezing line in the region.
When installing at a depth, use the same method as in the case of extending the manhole neck by more
than 300 mm.
(ii) Installing Johkasou in a region with heavy snowfall
Provide a roof enclosure or the equivalent above Johkasou to prevent the snow load from directly applying
to Johkasou, although the conditions may vary slightly depending on the region. If the base is raised in any
region where snowfalls are not so heavy, install it in consideration of the soil pressure arising from the
raised height and the snow load (See Fig. 14).
Fig. 14
(6) In the case in which pumping is needed
If the drainage channel to which the water is discharged is high, pumping is required. Choose a pump with
a diameter of at least 40 mm. Check the water level in the drainage channel to secure a lifting height with a
sufficient margin.
Be sure to install two discharge pumps and configure them to automatically operate alternately and to
simultaneously operate when the water is at a high level (See Fig. 15).
15
Drainage
Channel
Inlet pipe
Submersible pump
Float switch
Discharge diameter≧40mm
Sand pit
Fig.15
The diagram below is a rough guide to the cord length setting and the operating range of a float switch.
Alarm
Double pump
operation
Set the LWL and the HWL at the positions specified in the diagram. Set the LWL at the position where the
independently operating float is powered off, the LWL at the position where the simultaneously operating
float is powered on, and the AWL at the position where it will become active at the level that is 10 cm above
that of the HWL.
16
4. After-Sales Services
● Warranty Period and Coverage
1) After-sales services
Should any abnormality occur while Johkasou is in use, contact our sales office.
2) Warranty
The warranty period is three years from the date of shipment for the main unit and one year from the
same date for the drive unit and internal components. We will repair problems as mentioned in the
warranty certificate. For details, please refer to the warranty certificate. Enter your name, the dealer
and the date of installation and store it carefully in a safe place.
For any repair after the expiration of the warranty period, please feel free to contact us.
The warranty guarantees that we will offer free repair to Johkasou that has a problem during the
warranty period under the normal conditions of use in accordance with the precautions in the operation
manual. However, it is meant to guarantee the functions of Johkasou and not its performance
17
MEMO
18
Daiki Axis Johkasou (BA/BAE/BJ/BJE/AI/AIJ)
Process Description
DOMESTIC WASTE WATER (2) Waste water then flows into anaerobic media contact chamber from
sedimentation and separation chamber. It contains organic material
which is decomposed by anaerobic microorganism.
On the other hand, nitrite and nitrate contained in the circulated water
(1) SEDIMENTATION &
are converted into N2 gas by denitrification microorganisms.
SEPARATION CHAMBER
Anaerobic reaction shown as follow :
Organic Material ------------> CH4 + NH3 + smaller materials + H2O
NO2 + NO3 ------------> N2 + H2O
(2) ANAEROBIC CONTACT
Anaerobic Microorganism
MEDIA CHAMBER
(3) Anaerobic process treatment water flows into moving bed chamber.
CIRCULATION
B
Illustration
Separation Box
Inflow Outflow
Sedimentation
Separation
Function Separating solid waste and liquid waste based on their gravity. Solid waste which has bigger
density than water will be settled in the bottom of sedimentation chamber. On the other hand,
lower density materials float and stay here.
Components
Inlet / Influent
Pipe
Circulation Pipe
Illustration
Transfer Baffle
Inflow Outflow
Anaerobic Media
Function (1) Anaerobic media inside of anaerobic contact media chamber is the place where
microorganism is growing up to decompose organic material contained in domestic wastewater
resulting more simple organic content.
(2) To store excess sludge at the bottom and scum at surface of the water.
(3) Small SS is caught and stored by anaerobic media to reduce a load of moving bed chamber.
(4) Almost of NO2 and NO3 are reduced to N2 gas by denitrification microorganisms which
settled in anaerobic media.
Components
Anaerobic Media
1. Anaerobic Media
- The Place where anaerobic microorganism is growing up.
- Anaerobic media catches SS and stores it inside.
2. Transfer Baffle
- As waste water channnel
- Desludging channel of anaerobic chamber
Illustration
Moving Bed Media B Aeration Blower
Inflow Outflow
Function Moving bed chamber consist of contact media called " Moving Bed Media", and aerobic
microorganism is growing up inside of it. Moving bed chamber filled by moving bed media with
30 - 50% of the volume. Aerobic microorganism will decompose organic material from anaerobic
chamber.
This aerobic microorganism consumption oxygen supplied by blower distributed through pipe
line and diffuser located in the bottom of moving bed chamber. By generating oxygen in this
chamber, moving bed media circulate in this chamber. Organic material is contacted to
microorganism inside of moving bed media due to this circulation. In this process, organic
material decomposition process will occur, and majority of the BOD, COD and other parameters
are removed.
NH3 is oxidated to NO2 and NO3.
Components
1. Moving Bed Media
The Place where aerobic microorganism is growing up.
2. Diffuser
- Air diffuser is a device that is designed to provide uniform air flow throughout a room.
- It works to increase the efficiency of air conditioning
3. Media Screen/Trap
To prevent the media from transffering to the next chamber.
4. Blower
It provides air to the moving bed chamber.
It works for 24 hr.
Illustration
B Aeration
Inflow Outflow
Measuring Box
Circulation Pipe
Function Sedimentation chamber is the place to settle sludge generated by aeration process, and treated
water flowed into disinfection chamber. Sludge accumulated in the bottom will be transferred to
sedimentation and separation chamber, which is called circulation because besides returning
sludge into the sedimentation separation chamber, it also helps the denitrification process.
Components
1. Measuring Box
- Circulation flow control
*Circulated water quantity is controlled by adjustment of air quantity for air lift pump,
and it can be checked at V-notch weir.
Measuring
Box
※ View of Sedimentation
Chamber
Circulation Pipe V notch
Illustration
B Aeration
Influent Effluent
Device
Function Microoranisms consisting in the treated water are disinfected by chlorine in the device before
discharged into the environment.
Components
Disinfection tank
Disinfection stage
V notch
1. Disinfection Device
Disinfection device consists of V notch, disinfection stage and disinfection tank
(1) Treated water comes into the disinfection stage over a V notch.
(2) Chlorine tablet which is in the chlorine tube is dissolved with the treated water.
(3) The treated water containing dissolved chlorine drops into the disinfection tank.
(4) In the disinfection tank, microorganisms are disinfected by chlorine.
Project Name
Johkasou Type
Handover Date
This is that certify that the above product was handed over to the owner and this Maintenance and
Inspection Procedures was explained by Daiki Axis or official dealer. Please note that the Johkasou will not
exhibit its intended performance without prior maintenance and inspection, and the warranty guarantees
under the normal conditions of use in accordance with the precautions in this procedures.
△! Caution Prior to installation of the Johkasou, carefully read the warnings and
cautions in this document to fully understand them.
1
1. Safety Precautions
・ Prior to working, carefully read these safety precautions to perform the appropriate
maintenance and inspection. After reading, carefully store this document.
・ Explanation of Indication
△
! Warning
Indicates presumable human death or serious injury resulting
from ignorance of the indication and mishandling.
! Warning
The maintenance and inspection personnel may be held responsible and liable for any accident
arising from failure to observe the following.
! Warning
… 1) Prevention of ignition, explosion and hazardous gas accidents
(i) The disinfectant is a strong oxidant.
Disinfectants are divided into two types: chlorinated organic and chlorinated inorganic.
Do not put these two types of disinfectants into the agent container together.
(ii) In the event of handling the disinfectant, be sure to wear rubber gloves, a dust mask, protection goggles and
other protective equipment for protecting your eyes, nose and skin
! Warning
… 3) Prevention of electric shock, ignition and entanglement
(i) Keep anything at least 50 cm away from the blower or the control panel.
(iii) After inspection of the blower, be sure to reattach the cover that was detached.
Failure to observe this could result in entanglement.
! Warning
… 4) Prevention of fall from manhole and inspection hole and injury
(i) After finishing the work, be sure to close the manhole and the inspection hole with their respective covers.
If they have a lock mechanism, be sure to lock them.
(ii) If any crack, damage or other abnormality is found on the manhole cover or the inspection hole cover,
immediately replace it.
Failure to observe these could result in a fall or an injury.
2
During inspection, pay attention to the following for the purpose of maintaining Johkasou functions
Attention
Attention (i) Carry out the following to prevent ignition and fire at a power outlet.
Check if the power plug is free from dust and securely insert it into the base of the blades in a
way that prevents it from rattling.
Attachment of dust and incomplete connection could result in an electric shock or fire.
Attention (iii) If the frame and the cover of the manhole and the inspection hole are made of casting or steel,
remove the rust and apply a coating on a regular basis.
Attention (iv) Carry out maintenance and inspection in firm compliance with the Technical Standards for
Maintenance and Inspection, the Technical Standards for Cleaning and other laws and
ordinances as well as with the manufacturer’s Maintenance and Inspection Procedures.
Attention (v) Do not open the package of the disinfectant until Johkasou is put into use.
Failure to observe this notice could result in the generation of chlorine gas from the
disinfectant, a reaction of the gas with moisture in the air to generate hydrochloric
acid, which erodes metal.
3
2. System Management
1) Manager’s obligations
Implement maintenance and inspection in accordance with the laws in the region.
Johkasou will not exhibit its intended performance without prior maintenance and inspection.
If the manager is unable to conduct maintenance, inspection and cleaning alone, ask a maintenance
and inspection specialist to do so.
Notes:
○ Depending on the region, it may be stipulated that the maintenance and inspection must be
conducted more frequently than specified in the table above for the stability of the treatment function.
○ The inspection of operations of the drive unit and the pump unit and filling of disinfectant shall be
conducted when it is necessary irrespective of Table 1-1.
4
5) Frequency of Sludge Removal
Carry out cleaning at a frequency equivalent to or higher than that specified in Table 1-2.
Table 1-2
Item Frequency
Once every half a year or more
Sludge
Sludge Removal shall be conducted as necessary depending on the maintenance
removal
and inspection results and the state of sludge recipients in the region.
* The sludge removal work removes a large amount of sludge at a time. Prior to installation of the product,
coordinate particularly with the sludge recipients.
7) Statutory Inspection
If the region has a law that requires Johkasou to undergo water quality inspection, make sure that the
inspection is done in accordance with the law.
5
3. Composition and Function
Treatment Capacity: Discharge BOD of 20 mg or less per liter
Airlift
6
4. Maintenance and Inspection
4-1 Main inspection items
Table 1 shows the apparatuses and equipment necessary for inspection.
Table 2 shows the main inspection items.
- Removal of scum
Ladle ・Each chambers
- Check on properties of sludge
・Sedimentation chamber
Siphon Pump - Sampling of treated water
・Disinfection chamber
Measuring cup
・Moving bed chamber - Check on moving bed quantity
(two liters)
7
Table 2: Main inspection items and frequency
Check item Descriptions Frequency
・ Remove the sludge according to the state of sludge sedimentation Once every six months
8
4-2 Pre-Use Inspection and Check and Adjustment
Before regular maintenance and inspection, checking on the construction and work on Johkasou and
functions of the internal operation units just before use is very important to normal Johkasou operation and
to the prevention of problems during the inspection and cleaning processes.
Note
At the start of operation, moving beds are floating in the moving bed chamber, but it
is not abnormal. The moving beds will no longer float after operation for some period
of time (normally two to three weeks).
Note
At the start of operation, please fill chlorine tablets in the chlorine dispenser.
9
4-3 Key Points of Maintenance and Inspection
Daiki Domestic Wastewater Treatment Systems BA Type & BJ Type both adopt the moving bed system.
The following describes key points to be noted when performing maintenance and inspection.
Like the separation and sedimentation chamber, this chamber retains sludge. As soon as it becomes
full, the water in the subsequent moving bed chamber will deteriorate. Make sure that too much sludge
is not retained or it does not flow out of the transfer outlet. Note that this chamber is filled with anaerobic
media. If it is clogged with sludge and foreign matter, that will disrupt the water flow.
Check if there is any difference in the water level from the outlet to the moving bed chamber.
Check if moving beds are floating and moving without staying in one place.
Check if biofilms are attached to moving beds.
Check that there is no large volume of suspended substances in the chamber.
Check if moving bed volume is appropriate level.
If these conditions are fulfilled, biological treatment will be effective.
4) Sedimentation chamber
Check if there is any floating scum. If there is, use the ladle to move it from this chamber to the
separation and sedimentation chamber. The existence of floating scum means that the flow rate of
the airlift is insufficient. Adjust the flow rate.
5) Airlift
Clean the airlift, measuring box and circulation pipe line after each inspection.
① Fully close the airlift valve and count 5 seconds.
② Fully open the valve and see high concentrated SS is lifted up in the measuring box.
③ When concentration of SS becomes low, return to ①, and repeat ① to ③ until the high
concentrated SS is not lifted up.
④ Clean the measuring box and circulation pipe line with tap water.
⑤ Adjust the settings of the airlift valve.
10
4-4 Checking and Adjusting Individual Units
11
Table 3: Wastewater Volume and Circulation Water Volume to be Set (for the BA(E) Type)
Daily average
wastewater
volume
10 20 30 40 50 60 70 80 90 100
[m3/day]
Circulation
water volume 20 40 60 80 100 60×2※ 70×2※ 80×2※ 90×2※ 70×3※
[m3/day]
※:[appropriate water volume at each measuring box] × [number of measuring box in sedimentation chamber]
Table 4: Wastewater Volume and Circulation Water Volume to be Set (for the BJ(E) Type)
Daily average
wastewater
volume
10 20 30 40 50 60 70 75
[m3/day]
Circulation
water volume 40 80 60×2※ 80×2※ 100×2※ 80×3※ 95×3※ 100×3※
[m3/day]
※:[appropriate water volume at each measuring box] × [no. of measuring box in the sedimentation chamber]
12
Table 5 Thickness limits of scum and settled sludge in sedimentation and separation chamber
BA(E) 1 2 3 4 5 6 8,10 12,15 ≥ 20
Water amount [m3/D]
BJ(E) - 1 2 3 4 5 6 8,10,12 ≥ 15
Over surface 100 100 150
Scum
Under surface 300 350 400
Settled sludge Bottom 400 450 650 900 1000 1200
13
3) Moving bed chamber
Inspection
Inspection Item State of Abnormality Maintenance Work
Method
14
4) Sedimentation chamber
③ Ammonia nitrogen ・ Check if DO level and pH level are normal and, if any
(to be measured) Ammonia ・ More than 10 mg per are abnormal, take the appropriate measures.
measurement kit liter ・ Check if a sufficient number of microorganisms are
*(for BJ Type) attached. If it is insufficient, carry out seeding.
・ There is no
difference between ・ Check if the accumulated sludge on the bottom is
the concentration of hardened with the use of a long stick.
⑤ Circulation water Visual test
SS in the moving bed ・ Lower the flow rate for sludge removal (circulation
chamber and the volume).
circulation water.
15
5) Disinfection chamber
Inspection
Inspection Item State of Abnormality Maintenance Work
Method
* If the amount of water is small, some of the treated water may move to the Disinfection chamber without passing the
overflow weir. This poses no problem.
16
6) Blower
③ Sounds and ・ Abnormal sounds or vibrations ・ Check how the blower is installed
vibrations are generated. ・ Check if the diaphragm is damaged.
● Replace the diaphragm valve, clean or replace the air filter on a regular basis and carry out other maintenance work in
accordance with the operation manual of the blower.
7) Pump
● Replace lubricant (around once a year) and carry out an overhaul (around once every two years) and other maintenance work
in accordance with the operation manuals of the pump and the float.
17
8) Terminal Box / Control Panel
Pump / Blower
9) Common
All Chamber ・ Scums are adhered to partition plate and the wall. ・ Clean dirty part with a brush.
18
4-6 Action in the Event of Abnormality
There are a variety of possible measures to address odor issues, such as:
(1) Sealing the manhole with packings, as a temporary measure.
(2) A reverse flow of odor to the building may occur when the trap is not properly in place in in the piping for the Johkasou. Review
the piping route to check if the trap is appropriately installed.
(3) Properly install a ventilation pipe and a ventilation fan. Make sure that the ventilation pipe is taller than the eves of neighboring
buildings and erect it with full consideration of wind directions and other factors.
(4) Add a seeding agent and deodorant to the anaerobic contact media chamber and the moving bed chamber.
* For seeding, use a commercially available seeding agent, digested sludge in a STP, a night soil disposal plant or sludge in the
aeration tank. If sludge is added, adjust the added amount to ensure that the sludge concentration will be roughly within the range
of 200 mg to 300 mg per liter in the anaerobic contact media chamber and roughly within the range of 100 mg to 200 mg per liter in
the moving bed chamber.
19
5. Sludge Removal
5-1 Rough Guide to Timing of Sludge Removal
It is stipulated that sludge removal shall be carried out at least once every half a year in a normal state of use.
As a rough guide, it is time to carry it out in any of the states described below.
1) There is a considerable amount of scum sediment in the sedimentation and separation chamber or in the
anaerobic contact media chamber, or a considerable amount of sludge sediment at the bottom of the
chamber.
2) A dramatic rise in water level in the tank or any trace thereof is observed.
3) SS are generated in large quantities in the moving bed chamber that do not decrease even after the
circulation process.
Note
Sludge removal from the moving bed chamber or the sedimentation chamber is normally not required.
If it is necessary, do not directly remove sludge from the center of these chambers. Failure to observe
this instruction will result in the removal of moving beds together with the sludge. In the event of
removal, carry out the work in accordance with the following.
○ Sedimentation chamber
Set the end of a hose inside the tank to carry out the removal. In this event, pay attention to avoid
damage to the airlift.
1) Preparation work
Prior to the cleaning of individual units, take the following steps.
① Turn off the breaker of the blower to stop its operation.
② Remove accretions on the feed pipe (and the baffle) and the discharge pipe (and the baffle).
③ For removing suspended substances from the moving bed chamber or sludge from the sedimentation
chamber, take the steps mentioned in the previous paragraph.
20
2) Sedimentation and separation chamber
Positions for insertion of the cleaning hose
Lateral surface of the separation box and the manhole installation position (Refer to Fig. 3)
① From the position shown in the diagram, remove scum through a suction hose while breaking it up with
a stick or equivalent.
② Insert a suction hose to the bottom of the chamber and remove all of the sludge.
SEPARATION BOX
SEDIMENTATION
Fig. 3: Positions on the sedimentation and separation chamber for insertion of a sludge removal hose
Note Be sure to remove scum before removing sludge. Removing the sludge at the
bottom of the chamber could lower the water level to possibly allow sludge on
the anaerobic media roof net to enter the anaerobic media and cause occlusion.
ANAEROBIC
CONTACT MEDIA Positions for insertion MOVING BED
CHAMBER of a sludge removal hose CHAMBER
Transfer baffle
Return pipe
Fig. 4: Positions on the anaerobic contact media chamber for insertion of a sludge removal hose
21
4) Work after removal
After finishing the sludge removal, fill the chamber with water to the specified level (at which the water overflows).
Then turn the breaker of the blower on to put the blower into operation.
Note Do not remove a large portion of water in the chamber at a time or leave the tank empty
for a long time. Failure to observe the instruction above could result in application of a
significant buoyant force or load onto the tank and cause damage to the tank.
22
6. After-Sales Services
6-1 Period and Scope of Warranty
1) After-sales services
Should any abnormality occur while Johkasou is in use, contact us or your maintenance and inspection
service operator.
2) Warranty
The warranty period is three years from the date of shipment for the main unit and one year from the same
date for the drive unit and the internal components. We will repair problems as mentioned in the warranty
certificate.
For repairs after the expiration of the warranty period, please feel free to contact us.
The warranty guarantees that we will offer free repair for system failure during the warranty period under the
normal conditions of use in accordance with the precautions in the maintenance and inspection procedures.
It is meant to guarantee the functions of Johkasou and not its performance.
4) In the event of loss or damage of the operation manual for Johkasou, please
contact us and we will immediately send you another copy.
23
MEMO
Version 2.00 (Revised in Apr 2020)
☆:Instruction manual
※:5402 is spare for electrode of DO.
Pictures
1st-Oct. 2020
Daiki Axis Co., Ltd.
KAZUO SAEKI
NOTE
・Maintenance work shall be done after the water sampling.
・Maintenance and Inspection Report shall be filled out.
Procedures
① To conduct an interview with an analysis institution and be sure whether to be able or not to
check the above items.
② To confirm required sample water volume for submitting to the analysis institution to analyze.
If you do not get that information, you shall follow the example below.
*Example : Raw Water is 1L、Treated Water is 2L
③ To prepare the instruments and vessels for collecting water.
Bucket, Sample bottle (Like a PET bottle.), Cooler, Ice, Measuring Cup and Ladle
④ To specify the sampling point (Please refer Appendix-1_Priority of sampling point)
⑤ To rinse the inside of collecting bottle by sampling water.
⑥ Throwing away the rinsed water, and pouring collected sample water as much as you can make it
full to decrease the air space in the collecting bottle.
⑦ To confirm that the cap shall be closed perfectly in order not to leak the sample.
⑧ After collecting water, keep it inside of cooler contained with ice as fast as you possibly can.
(please refer Appendix – 2_Container samples)
⑨ The collected water shall be submitted to the analysis institution within two days.
Appendix 1 - Priority of sampling point
- Raw Water:
(Ⅰ)Equalization Tank>(Ⅱ)Raw Water Tank>(Ⅲ)1st room of Separation Box in Johkasou
*In case of (Ⅰ) or (Ⅱ): you can collect water directly
or collect it from inflow pipe with operating pump.
*About (Ⅲ): refer the video “Raw water sampling from Johkasou”.
- Treated water:
(Ⅳ)Discharge Pump Tank(ZP Tank)>(Ⅴ)Disinfection Chamber>(Ⅵ)Sedimentation Chamber
*In case of (V): there is a negative possibility that Biofilm attached on wall of chamber would peel
off and contaminate when you collect the water. Therefore, you are required to
collect water calmly and quietly.
If it’s difficult to do it, you can collect water in 30 minutes after the removement
of biofilm by brush or stick.
*In case of (Ⅵ): it should be avoided as possible because disinfection has not been done yet.
*In case of (V) (Ⅵ): It becomes easier to do sampling when you use a siphon pump.
Appendix 2 – Container samples
Ladder