STANDARISASI HARGA BAHAN BANGUNAN DAN JASA PERALATAN

HARGA SATUAN
NO JENIS DAN NAMA BARANG SATUAN
DASAR (Rp)
1 2 3 4
1 Pekerja OH 120,000.00
2 Tukang OH 135,000.00
3 Kepala Tukang OH 140,000.00
4 Mandor OH 155,000.00

HARGA SATUAN
NO JENIS DAN NAMA BARANG SATUAN
DASAR (Rp)
1 2 3 4
A. BAHAN PENGISI
1 Batu Pecah 1-2 cm M3 550,000.00
2 Batu Belah M3 200,000.00
3 Pasir Kasar M3 200,000.00
4 Pasir Halus M3 200,000.00
5 Semen PC @50 Kg Zak 90,000.00
6 Semen PC @1 Kg Kg 1,800.00
7 Tanah Timbunan M3 75,000.00
8 Batako 20 x 40 x 7 cm Bh 3,300.00
9 Keramik 25 x 25 cm (Polish-Biasa) M2 70,000.00
10 Keramik 25 x 52 cm (UnPolish-Biasa) M2 68,000.00
11 Keramik 40 x 40 cm (Polish-Biasa) M2 63,000.00
12 Keramik 40 x 40 cm (UnPolish-Biasa) M2 73,000.00
13 Keramik Dinding 25 x 40 cm (Polish-Biasa) dus 70,000.00
14 Bahan Plastik Cor M2 5,000.00
B. BAHAN KAYU
1 Ky. Klas I Bengkirai Uk. 5/10 - 4 m (Ketam/Untuk Kusen) M3 5,000,000.00
2 Kayu Belian tidak Ketam Uk.8/8 M3 10,000,000.00
3 Kayu Belian tidak Ketam Uk.4/8 M3 9,000,000.00
4 Ky. Klas III Uk. 4/6 - 4 m (tidak ketam) M3 1,800,000.00
5 Papan Kayu Klas I ketam M3 5,000,000.00
6 Papan Mall Klas III M3 1,800,000.00
7 Kayu Simpiran M3 500,000.00
8 Renglat Kayu Klas II Uk. 1/8 cm Btg 10,000.00
9 Kayu Cerucuk/Dolken ø6-8 - pj. 4m Btg 8,000.00
10 Kayu Cerucuk/Dolken ø8-10 - pj. 4m Btg 12,000.00
11 Kayu Cerucuk/Dolken pj. 6m Btg 40,000.00
C. BAHAN CAT
1 Amplas Lbr 5,000.00
2 Cat Kilat Kg 55,000.00
3 Plamur Tembok/Kayu Kg 20,000.00
4 Cat Dasar Kg 50,000.00
5 Cat Tembok Interior Kg 50,000.00
6 Cat Tembok Exterior Kg 100,000.00
7 Cat Waterproofing Kg 175,000.00
8 Thinner / Pengencer Ltr 15,000.00
9 Menie Kayu Kg 55,000.00
10 Oker Kg 18,000.00
11 Lem Kayu Kg 12,000.00
12 Sealant Tube 45,000.00
13 Kuas 4" Bh 10,000.00
D. BAHAN BESI DAN ALUMINIUM
1 Besi Tulangan Beton Polos/Ulir Kg 13,800.00
2 Besi Wiremesh M5 Kg 15,000.00
3 Kawat Baja/Bendrat Kg 30,000.00
4 Kusen aluminium 3" Silver M 120,000.00
5 Main trus C-75-75 Btg 105,000.00
6 Rangka Metal hollow 40.40.2 mm(metal furing) m 6,500.00
7 Suncreen alumunium m2 120,000.00
8 Plat Bondex 0.75 mm M2 150,000.00
9 Profil Kaca M 60,000.00
10 Kawat Las Kg 50,000.00
11 Frame Alumunium 1 1/2"x3" M 120,000.00
12 Besi Profil Kg 15,000.00
E. BAHAN PENGGANTUNG
1 Kusen & Pintu PVC Toilet Unit 500,000.00
2 Kait Angin Bh 30,000.00
3 Handle Jendela Bh 15,000.00
4 Handle Pintu Bh 100,000.00
5 Engsel Jendela Bh 35,000.00
6 Engsel Pintu Bh 55,000.00
7 Slot Pintu Bh 40,000.00
8 Slot Jendela Bh 30,000.00
9 Kunci Tanam Biasa Bh 120,000.00
10 Paku Campuran 1"-12" Kg 22,000.00
11 Paku Beton Kg 30,000.00
12 Paku Atap Seng Kg 35,000.00
13 Paku GRC Kg 35,000.00
14 Sekrup Gypsum Kg 40,000.00
15 Sekrup Atap Kg 45,000.00
16 Sekrup Atap Bh 800.00
17 Sekrup Fixer Bh 500.00
F. BAHAN ATAP
1 Atap Zincalume 0.30 mm Lbr 77,000.00
2 Nok genteng metal 100 cm Bh 25,000.00
3 Seng Plat Bjls 20 Lbr 40,000.00
4 Seng Plat Bjls 30 bh 25,000.00
5 List Plank (Wood Plank uk. 4,05 x 0,3 x 0,08 m) M 16,000.00
G. BAHAN KACA
1 Kaca Polos, t = 5 mm M2 175,000.00
2 Kaca Polos, t = 8 mm M2 250,000.00
3 Kaca Rayben, t = 5 mm M2 175,000.00
4 Kaca Cermin, t = 3 mm M2 200,000.00
5 Kaca Rayben, t = 8 mm M2 250,000.00
6 Glass Block Bh 30,000.00
H. BAHAN TRIPLEK (PENUTUP)
1 Triplek t = 3 mm Lbr 50,000.00
2 Triplek t = 6 mm Lbr 80,000.00
3 Triplek t = 9 mm Lbr 160,000.00
4 Triplek t = 12 mm Lbr 220,000.00
5 Panel GRC 120 x 240 x 40 Lbr 80,000.00
6 Gypsum Board t = 9 mm Lbr 80,000.00
7 List Profil 8 cm Gypsum M 30,000.00
I. BAHAN SANITASI
1 Kloset Duduk/Monoblok Bh 1,800,000.00
2 Bak Air Fiberglass Bh 500,000.00
3 Wastafel Bh 500,000.00
4 Kran Air Wastafel Unit 35,000.00
5 Kloset Jongkok Standar Bh 200,000.00
6 Kran Air 1/2" Plastik Bh 20,000.00
7 Jet washer Bh 200,000.00
8 PIPA PVC dia 3/4" Type A/W Btg 35,000.00
9 PIPA PVC dia 1" Type A/W Btg 48,000.00
10 PIPA PVC dia 2" Type A/W Btg 100,000.00
11 PIPA PVC dia 2,5" Type A/W Btg 120,000.00
12 PIPA PVC dia 3" Type A/W Btg 250,000.00
13 PIPA PVC dia 4" Type A/W Btg 400,000.00
14 Floor Drain Plastik Bh 25,000.00
15 Seal tape Pipa Bh 5,000.00
16 Tangki Air Fiberglass (FRP) Kap. 2000 liter Bh 2,500,000.00
REKAPITULASI
RENCANA ANGGARAN BIAYA
PEKERJAAN : PEMELIHARAAN DAN PENINGKATAN GEDUNG DAN STADION BANING
LOKASI : KABUPATEN SINTANG, KALIMANTAN BARAT
SUMBER DANA : ANGGARAN PENDAPATAN DAN BELANJA DAERAH (APBD) KABUPATEN SINTANG TAHUN ANGGARAN 2023

JUMLAH TOTAL JUMLAH


NO. URAIAN PEKERJAAN HARGA HARGA
(Rp.) (Rp.)

A. GEDUNG UTAMA 397,201,910.48

B. PEKERJAAN TOWER AIR 75,996,287.72

TOTAL 473,198,198.20
PPN 11 % 52,051,801.80
JUMLAH TOTAL + PPN 11 % 525,250,000.00

TERBILANG : Lima Ratus Dua Puluh Lima Juta Dua Ratus Lima Puluh Ribu Rupiah

Dibuat Oleh,
Kubu Raya, 15 September 2023
CV. TRISUNG JAYA MAKMUR

SUJITO
Direktur
RENCANA ANGGARAN BIAYA
PEKERJAAN : PEMELIHARAAN DAN PENINGKATAN GEDUNG DAN STADION BANING
LOKASI : KABUPATEN SINTANG, KALIMANTAN BARAT
TAHUN ANGGARAN : ANGGARAN PENDAPATAN DAN BELANJA DAERAH (APBD) KABUPATEN SINTANG TAHUN ANGGARAN 2023

VOLUME HARGA SATUAN SUB TOTAL JUMLAH TOTAL


NO URAIAN PEKERJAAN SAT KODE ANALISA
TOTAL
(Rp.) (Rp.) (Rp.)
1 2 3 4 5 6 7 8
A. GEDUNG UTAMA
I. PEKERJAAN PENDAHULUAN
a. Pekerjaan Persiapan
1 Pembongkaran Dan Pembersihan lokasi 1.000 Pkt - 5,000,000.00 5,000,000.00
2 Dokumentasi Dan Papan Nama Proyek 1.000 Pkt - 263,175.42 263,175.42

b. Penyelenggaraan SMKK Bangunan Gedung


A. PERLENGKAPAN K3
1 Penyiapan RKK
Pembuatan Prosedur dan Instruksi Kerja 1.000 Ls - 200,000.00 200,000.00
2 Sosialisasi & Promosi K3
Spanduk (Banner) 1.000 Lmbr - 100,000.00 100,000.00
Papan Informasi K3 1.000 Bh - 50,000.00 50,000.00
3 Alat Pelindung Diri
Topi Pelindung (Safety Helmet) 10.000 Bh - 50,000.00 500,000.00
Pelindung Pernapasan dan Mulut (Masker) 5.000 Kotak - 30,000.00 150,000.00
Sarung Tangan (Safety Gloves) 10.000 Psng - 20,000.00 200,000.00
Rompi Keselamatan (Safety Vest) 10.000 Bh - 25,000.00 250,000.00
Sepatu Karet Keselamatan 10.000 Psng - 120,000.00 1,200,000.00
Handsatizer 500 ML 8.000 Botol - 30,000.00 240,000.00
Pelindung Jatuh 5.000 Bh - 250,000.00 1,250,000.00
4 Asuransi
Asuransi Kecelakaan Kerja Risiko Sangat Rendah
Mandor 1.000 OB - 125,000.00 125,000.00
Kepala Tukang 1.000 OB - 125,000.00 125,000.00
Tukang 6.000 OB - 125,000.00 750,000.00
Pekerja 3.000 OB - 125,000.00 375,000.00
5 Personel K3 Konstruksi
Ahli K3 3.000 OB - 2,000,000.00 6,000,000.00
6 Fasilitas Sarana & Prasarana Kesehatan
Peralatan P3K (Kotak K3, Obat Luka, Obat Umum, Perban) 1.000 Ls - 200,000.00 200,000.00
7 Rambu-Rambu
Rambu Petunjuk 1.000 Bh - 50,000.00 50,000.00
Rambu Larangan 1.000 Bh - 50,000.00 50,000.00
Rambu Peringatan 1.000 Bh - 50,000.00 50,000.00
8 Pengendalian Risiko Keselamatan Konstruksi
Bendera K3 1.000 Ls - 50,000.00 50,000.00
9 BPJS Tenaga Kerja 1.000 Ls - 500,000.00 500,000.00
17,678,175.42
II. PEKERJAAN PENUTUP DINDING DAN STRUKTUR FASAT
1 Pekerjaan Penutup ACP Lisplank 11.200 M - 600,000.00 6,720,000.00
2 Pekerjaan Rangka ACP Fasad Pintu Utama 25.120 M - 330,000.00 8,289,600.00
3 Pekerjaan Penutup ACP Fasad Pintu Utama 25.120 M - 600,000.00 15,072,000.00
4 Pekerjaan Rangka ACP kolom Utama 24.000 M - 330,000.00 7,920,000.00
5 Pekerjaan Penutup ACP kolom Utama 24.000 M - 600,000.00 14,400,000.00
6 Rangka Holow Dinding Depan ACP Costume Cutting 70.000 M - 330,000.00 23,100,000.00
7 Pemasangan Penutup Dinding Depan ACP Costume Cutting 70.000 M - 1,000,000.00 70,000,000.00
145,501,600.00
III. PEKERJAAN PLAFOND
1 Plafon Triplek t = 3 mm 398.390 M A.4.5.1.7 48,616.25 19,368,227.84
19,368,227.84
IV. PEKERJAAN PENGECATAN
1 Pengecatan Dinding Tembok Lama 1,829.880 M 3.3.10.(c) 52,039.80 95,226,589.22
2 Pengecatan Plafon 410.000 M 3.3.10.(c) 52,039.80 21,336,318.00
116,562,907.22
V. PEKERJAAN MEKANIKAL ELEKTRIKAL
1 Jaringan Instalasi Listrik (Kabel NYY Uk. 3 x 2,5 mm) 400.000 M - 25,000.00 10,000,000.00
2 Lampu Led Inbow 18 watt 96.000 Bh - 120,000.00 11,520,000.00
3 Lampu Sorot 600 Watt IP66 LED COB 8.000 Bh - 3,500,000.00 28,000,000.00
4 Lampu Sorot Spotlight 20 Watt 6.000 Bh - 200,000.00 1,200,000.00
5 Kotak MCB Box Panel 4.000 Bh - 250,000.00 1,000,000.00
6 Led Strip 50.000 M - 50,000.00 2,500,000.00
54,220,000.00
VOLUME HARGA SATUAN SUB TOTAL JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT KODE ANALISA
TOTAL
(Rp.) (Rp.) (Rp.)
1 2 3 4 5 6 7 8
VI. PEKERJAAN PINTU
1 Pintu Volding Gate 200x220cm 8.800 M - 1,000,000.00 8,800,000.00
2 Pintu Utama (Rangka Besi Hollow + Plat) + Rell 20.000 M - 850,000.00 17,000,000.00
3 Rangka Holow ACP Costume Cutting 8.700 M - 330,000.00 2,871,000.00
4 Pemasangan ACP Costume Cutting 8.700 M - 1,000,000.00 8,700,000.00
37,371,000.00
VII. PEKERJAAN PELENGKAP BANGUNAN
1 Pengadaan Kursi bench Pemain 2.000 Unit - 500,000.00 1,000,000.00
2 Tulisan Skor ACP 1.000 Unit - 3,000,000.00 3,000,000.00
3 Tulisan Nama Stadion Baning 1.000 Huruf - 2,500,000.00 2,500,000.00
6,500,000.00
TOTAL PEKERJAAN A. 397,201,910.48
B. PEKERJAAN TOWER AIR
I. PEKERJAAN PONDASI
a. Pekerjaan Tapak Pondasi
1 Pengukuran dan Pemasangan Bowplank 20.000 M 1.1.d.(c) 60,622.25 1,212,445.00
2 Galian Tanah Pondasi 5.410 M 1.7.1.a.(c) 107,956.25 584,043.31
3 Pengadaan Cerucuk 4 m diameter 12 cm 48.000 M - 15,000.00 720,000.00
4 Pemancangan 48.000 M - 10,000.00 480,000.00
5 Penghamparan pasir alas 0.340 M 1.7.2.d.(c) 319,182.50 108,522.05
6 Cor Beton Tumbuk Lantai Kerja, mutu K.100 0.340 M 2.2.1.1.a.(a) 1,291,737.80 439,190.85
7 Pekerjaan Pembesian Tulangan 120.000 Kg 2.2.6.1.b.(c) 19,417.75 2,330,130.00
8 Pekerjaan Bakesting 2.660 M A.4.1.1.18 211,335.50 562,152.43
9 Pekerjaan Cor Beton, mutu K.225 0.780 M 2.2.1.2.f.(a) 1,562,930.32 1,219,085.65
10 Urugan Kembali Tanah Galian Pondasi 4.200 M 1.7.2.a.(c) 77,912.50 327,232.50
b. Pekerjaan Padestal
1 Pekerjaan Pembesian tulangan 20.870 Kg 2.2.6.1.b.(c) 19,417.75 405,248.44
2 Pekerjaan Bakesting 0.760 M A.4.1.1.20 221,685.50 168,480.98
3 Pekerjaan Cor Beton, mutu K.225 0.040 M 2.2.1.2.f.(a) 1,562,930.32 62,517.21
8,619,048.43
II. PEKERJAAN KOLOM
1 Pekerjaan Pembesian tulangan 78.120 Kg 2.2.6.1.b.(c) 19,417.75 1,516,914.63
2 Pekerjaan Bakesting 13.610 M A.4.1.1.20 221,685.50 3,017,139.66
3 Pekerjaan Cor Beton, mutu K.225 0.730 M 2.2.1.2.f.(a) 1,562,930.32 1,140,939.13
4 Plesteran Kolom 50.160 M 3.2.1.(c) 91,162.57 4,572,714.51
5 Pengecatan 50.160 M 3.3.10.(c) 52,039.80 2,610,316.37
12,858,024.30
III. PEKERJAAN BALOK
a. Pekerjaan Balok Lantai 1
1 Pekerjaan Pembesian tulangan 134.820 Kg 2.2.6.1.b.(c) 19,417.75 2,617,901.05
2 Pekerjaan Bakesting 6.300 M A.4.1.1.21 232,857.75 1,467,003.83
3 Pekerjaan Cor Beton, mutu K.225 0.540 M 2.2.1.2.f.(a) 1,562,930.32 843,982.37
b. Pekerjaan Balok Lantai 2
1 Pekerjaan Pembesian tulangan 134.150 Kg 2.2.6.1.b.(c) 19,417.75 2,604,891.16
2 Pekerjaan Bakesting 6.300 M A.4.1.1.21 232,857.75 1,467,003.83
3 Pekerjaan Cor Beton, mutu K.225 0.540 M 2.2.1.2.f.(a) 1,562,930.32 843,982.37
9,844,764.61
IV. PEKERJAAN LANTAI
a. Pekerjaan Lanti 1
1 Pekerjaan Pembesian Tulangan (wire mesh) 104.930 Kg 2.2.7.a.(a) 18,585.44 1,950,169.96
2 Pekerjaan Bakesting 6.300 M A.4.1.1.22 244,127.75 1,538,004.83
3 Pekerjaan Cor Beton, mutu K.225 0.900 M 2.2.1.2.f.(a) 1,562,930.32 1,406,637.29
b. Pekerjaan Lantai 2
1 Pekerjaan Pembesian Tulangan (wire mesh) 104.930 Kg 2.2.7.a.(a) 18,585.44 1,950,169.96
2 Pekerjaan Bakesting 6.300 M A.4.1.1.22 244,127.75 1,538,004.83
3 Pekerjaan Cor Beton, mutu K.225 0.900 M 2.2.1.2.f.(a) 1,562,930.32 1,406,637.29
9,789,624.14
V. PEKERJAAN SANITASI
a. Instalasi air bersih
1 Pengadaan sumur bor
Pengeboran tanah 60.000 M - 200,000.00 12,000,000.00
Pipa PVC 4 (type AW) 60.000 M A.5.1.1.32 213,353.75 12,801,225.00
Pipa PVC 1 (type AW) 60.000 M A.5.1.1.27 36,995.50 2,219,730.00
Pipa PVC 3\/4 80.000 M A.5.1.1.26 28,183.63 2,254,690.00
Mesin air \/ jetpump 1.000 Unit - 1,000,000.00 1,000,000.00
2 Tangki Air 1000 Liter 2.000 Bh - 1,500,000.00 3,000,000.00
3 Pipa PVC 3\/4 (type AW) 50.000 M A.5.1.1.26 28,183.63 1,409,181.25
4 Keran Air 3\/4 4.000 Bh - 50,000.00 200,000.00
34,884,826.25
TOTAL PEKERJAAN B. 75,996,287.72
JUMLAH TOTAL 473,198,198.20
PPN 11% 52,051,801.80
JUMLAH TOTAL + PPN 11 % 525,250,000.00
A.2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN

1.1.d.(c) PENGUKURAN DAN PEMASANGAN 1 M BOUWPLANK


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.100 120,000.00 12,000.00
Tukang L.02 OH 0.100 135,000.00 13,500.00
Kepala Tukang L.03 OH 0.010 140,000.00 1,400.00
Mandor L.04 OH 0.005 155,000.00 775.00
JUMLAH TENAGA KERJA 27,675.00
B BAHAN
Kayu Cerucuk/dolken 8-10 pj.4 m Btg 1.000 12,000.00 12,000.00
Paku Biasa 2-5" Kg 0.020 22,000.00 440.00
Papan Mall Klas III M3 0.007 1,800,000.00 12,600.00
JUMLAH HARGA BAHAN 25,040.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 52,715.00
E Overhead & Provit 15% x D 7,907.25
F Harga Satuan Pekerjaan ( D + E ) 60,622.25
A.2.3.1 HARGA SATUAN PEKERJAAN TANAH

1.7.1.a.(c) PENGGALIAN 1 M3 TANAH BIASA SEDALAM 1 M


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.750 120,000.00 90,000.00
Mandor L.04 OH 0.025 155,000.00 3,875.00
JUMLAH TENAGA KERJA 93,875.00
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 93,875.00
E Overhead & Provit 15% x D 14,081.25
F Harga Satuan Pekerjaan ( D + E ) 107,956.25

1.7.2.a.(c) PENGURUGAN KEMBALI 1 M3 GALIAN TANAH


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.500 120,000.00 60,000.00
Mandor L.04 OH 0.050 155,000.00 7,750.00
JUMLAH TENAGA KERJA 67,750.00
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 67,750.00
E Overhead & Provit 15% x D 10,162.50
F Harga Satuan Pekerjaan ( D + E ) 77,912.50

1.7.2.d.(c) PENGURUGAN 1 M3 DENGAN PASIR URUG


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.300 120,000.00 36,000.00
Mandor L.04 OH 0.010 155,000.00 1,550.00
JUMLAH TENAGA KERJA 37,550.00
B BAHAN
Pasir urug 1.200 200,000.00 240,000.00
JUMLAH HARGA BAHAN 240,000.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 277,550.00
E Overhead & Provit 15% x D 41,632.50
F Harga Satuan Pekerjaan ( D + E ) 319,182.50
1.7.2.a.(d) PENGURUGAN 1 M3 DENGAN TANAH DATANG
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.300 120,000.00 36,000.00
Mandor L.04 OH 0.010 155,000.00 1,550.00
JUMLAH TENAGA KERJA 37,550.00
B BAHAN
Tanah Datang 1.200 75,000.00 90,000.00
JUMLAH HARGA BAHAN 90,000.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 127,550.00
E Overhead & Provit 15% x D 19,132.50
F Harga Satuan Pekerjaan ( D + E ) 146,682.50
A.3.2.1 Harga Satuan Pekerjaan Pondasi

A.3.2.1.1 PEMASANGAN 1 M3 PONDASI BATU BELAH CAMPURAN 1 SP: 3PP


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.500 120,000.00 180,000.00
Tukang batu L.02 OH 0.750 135,000.00 101,250.00
Kepala tukang L.03 OH 0.075 140,000.00 10,500.00
Mandor L.04 OH 0.075 155,000.00 11,625.00
JUMLAH TENAGA KERJA 303,375.00
B BAHAN
Batu belah (10-15 cm) m3 1.200 200,000.00 240,000.00
Semen Portland Kg 202.000 1,800.00 363,600.00
Pasir pasang m3 0.485 200,000.00 97,000.00
JUMLAH HARGA BAHAN 700,600.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 1,003,975.00
E Overhead & Provit 15% x D 150,596.25
F Harga Satuan Pekerjaan ( D + E ) 1,154,571.25

ABK.SNI.P.K.09.a 1 M' MELANCIP TIANG/BATANG


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.250 120,000.00 30,000.00
Tukang Kayu L.02 OH 0.025 135,000.00 3,375.00
Kepala tukang L.03 OH 0.100 140,000.00 14,000.00
Mandor L.04 OH 0.005 155,000.00 775.00
JUMLAH TENAGA KERJA 48,150.00
B BAHAN
-
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 48,150.00
E Overhead & Provit 15% x D 7,222.50
F Harga Satuan Pekerjaan ( D + E ) 55,372.50

ABK.SNI.P.K.10.a MEMBUAT PUTING DAN LOBANG/PASANG


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Tukang Kayu L.02 OH 0.600 135,000.00 81,000.00
Kepala tukang L.03 OH 0.060 140,000.00 8,400.00
JUMLAH TENAGA KERJA 89,400.00
B BAHAN
-
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 89,400.00
E Overhead & Provit 15% x D 13,410.00
F Harga Satuan Pekerjaan ( D + E ) 102,810.00

ABK.SNI.P.K.11 1 M MEMANCANG TIANG PONDASI KEDALAM TANAH


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.180 120,000.00 21,600.00
Tukang Kayu L.02 OH 0.040 135,000.00 5,400.00
Kepala tukang L.03 OH 0.004 140,000.00 560.00
Mandor L.04 OH 0.043 155,000.00 6,665.00
JUMLAH TENAGA KERJA 34,225.00
B BAHAN
-
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 34,225.00
E Overhead & Provit 15% x D 5,133.75
F Harga Satuan Pekerjaan ( D + E ) 39,358.75
2.2.1.(a) HARGA SATUAN PEKERJAAN BETON SECARA MANUAL DAN SEMI MEKANIS

2.2.1.1.a.(a) 1 M3 BETON UNTUK LANTAI KERJA (BEDDING) BETON FC' = 7,4 S.D 9,8 Mpa (K-100 S.D. K-125)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.200 120,000.00 144,000.00
Tukang batu L.02 OH 0.200 135,000.00 27,000.00
Kepala tukang L.03 OH 0.020 140,000.00 2,800.00
Mandor L.04 OH 0.060 155,000.00 9,300.00
JUMLAH TENAGA KERJA 183,100.00
B BAHAN
Semen Portland Kg 227.000 1,800.00 408,600.00
Pasir beton Kg 869.000 142.86 124,142.86
Kerikil (maks 30 mm) Kg 1000.000 407.41 407,407.41
Air Liter 215.000
JUMLAH HARGA BAHAN 940,150.26
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 1,123,250.26
E Overhead & Provit 15% x D 168,487.54
F Harga Satuan Pekerjaan ( D + E ) 1,291,737.80

2.2.1.2.f.(a) 1 M3 BETON MUTU F'C=19,3 MPa(K225)


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.000 120,000.00 120,000.00
Tukang batu L.02 OH 0.250 135,000.00 33,750.00
Kepala tukang L.03 OH 0.025 140,000.00 3,500.00
Mandor L.04 OH 0.050 155,000.00 7,750.00
JUMLAH TENAGA KERJA 165,000.00
B BAHAN
Semen Portland Kg 371.000 1800.00 667,800.00
Pasir beton Kg 698.000 142.86 99,714.29
Kerikil (maks 30 mm) Kg 1047.000 407.41 426,555.56
Air Liter 215.000
JUMLAH HARGA BAHAN 1,194,069.84
C PERALATAN
Molen Kap.0,35 m3 Hari 0.238 - -
JUMLAH HARGA ALAT
D Jumlah (A + B + C) 1,359,069.84
E Overhead & Provit 15% x D 203,860.48
F Harga Satuan Pekerjaan ( D + E ) 1,562,930.32

2.2.6.1.b.(c) PENULANGAN 100 KG DENGAN BESI BETON POLOS ATAU BESI STRIP
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.700 120,000.00 84,000.00
Tukang besi L.02 OH 0.700 135,000.00 94,500.00
Kepala tukang L.03 OH 0.070 140,000.00 9,800.00
Mandor L.04 OH 0.040 155,000.00 6,200.00
JUMLAH TENAGA KERJA 194,500.00
B BAHAN
Besi beton Polos Kg 105.000 13,800.00 1,449,000.00
Kawat beton Kg 1.500 30,000.00 45,000.00
JUMLAH HARGA BAHAN 1,494,000.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 1,688,500.00
E Overhead & Provit 15% x D 253,275.00
F Harga Satuan Pekerjaan ( D + E ) Per 100 Kg 1,941,775.00
G Harga Satuan Pekerjaan per 1Kg besi 19,417.75

2.2.7.a.(a) PEMBESIAN 100 KG JARING KAWAT (WIREMESH M6) UNTUK PLAT


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.2500 120,000.00 30,000.00
Tukang besi L.02 OH 0.2500 135,000.00 33,750.00
Kepala tukang L.03 OH 0.0250 140,000.00 3,500.00
Mandor L.04 OH 0.0250 155,000.00 3,875.00
JUMLAH TENAGA KERJA 71,125.00
B BAHAN
Besi beton Polos Kg 102.000 15,000.00 1,530,000.00
Kawat beton Kg 0.500 30,000.00 15,000.00
JUMLAH HARGA BAHAN 1,545,000.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 1,616,125.00
E Overhead & Provit 15% x D 242,418.75
F Harga Satuan Pekerjaan ( D + E ) Per 100 Kg 1,858,543.75
G Harga Satuan Pekerjaan ( D + E ) Per 1 Kg 18,585.44

A.4.1.1.18 PEMASANGAN 1 M2 BEKISTING UNTUK PONDASI


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.520 120,000.00 62,400.00
Tukang kayu L.02 OH 0.260 135,000.00 35,100.00
Kepala tukang L.03 OH 0.026 140,000.00 3,640.00
Mandor L.04 OH 0.026 155,000.00 4,030.00
JUMLAH TENAGA KERJA 105,170.00
B BAHAN
Papan mall Kelas III m3 0.040 1,800,000.00 72,000.00
Paku 5 - 10 cm Kg 0.300 22,000.00 6,600.00
Minyak Bekisting Ltr 0.100 - -
JUMLAH HARGA BAHAN 78,600.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 183,770.00
E Overhead & Provit 15% x D 27,565.50
F Harga Satuan Pekerjaan ( D + E ) 211,335.50
A.4.1.1.19 PEMASANGAN 1 M2 BEKISTING UNTUK SLOOF(PEMAKAIAN BERULANG)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.520 120,000.00 62,400.00
Tukang kayu L.02 OH 0.260 135,000.00 35,100.00
Kepala tukang L.03 OH 0.026 140,000.00 3,640.00
Mandor L.04 OH 0.026 155,000.00 4,030.00
JUMLAH TENAGA KERJA 105,170.00
B BAHAN
Kayu Kelas III m3 0.045 1,800,000.00 81,000.00
Paku 5 - 10 cm Kg 0.300 22,000.00 6,600.00
Minyak Bekisting Liter 0.100 - -
JUMLAH HARGA BAHAN 87,600.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 192,770.00
E Overhead & Provit 15% x D 28,915.50
F Harga Satuan Pekerjaan ( D + E ) 221,685.50

A.4.1.1.20 PEMASANGAN 1 M2 BEKISTING UNTUK KOLOM(DENGAN PAPAN MAL PEMAKAIAN BERULANG)


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.660 120,000.00 79,200.00
Tukang kayu L.02 OH 0.330 135,000.00 44,550.00
Kepala tukang L.03 OH 0.033 140,000.00 4,620.00
Mandor L.04 OH 0.033 155,000.00 5,115.00
JUMLAH TENAGA KERJA 133,485.00
B BAHAN
Kayu kelas III m3 0.020 1,800,000.00 36,000.00
Paku 5 - 12 cm Kg 0.400 22,000.00 8,800.00
Minyak Bekisting Ltr 0.200 - -
Papan Mall m3 0.008 1,800,000.00 14,400.00
Dolken kayu ɸ8-10cm - panj 4 m Batang 1.000 8,000.00 8,000.00
JUMLAH HARGA BAHAN 67,200.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 200,685.00
E Overhead & Provit 15% x D 30,102.75
F Harga Satuan Pekerjaan ( D + E ) 230,787.75

A.4.1.1.21 PEMASANGAN 1 M2 BEKISTING UNTUK BALOK (MENGGUNAKAN PAPAN MALL)


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.660 120,000.00 79,200.00
Tukang kayu L.02 OH 0.330 135,000.00 44,550.00
Kepala tukang L.03 OH 0.033 140,000.00 4,620.00
Mandor L.04 OH 0.033 155,000.00 5,115.00
JUMLAH TENAGA KERJA 133,485.00
B BAHAN
Kayu kelas III m3 0.0200 1,800,000.00 36,000.00
Paku 5 - 12 cm Kg 0.4000 22,000.00 8,800.00
Minyak Bekisting Ltr 0.2000 - -
Papan Mall m3 0.0090 1,800,000.00 16,200.00
Dolken kayu ɸ8-10cm - panj 4 m Batang 1.0000 8,000.00 8,000.00
JUMLAH HARGA BAHAN 69,000.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 202,485.00
E Overhead & Provit 15% x D 30,372.75
F Harga Satuan Pekerjaan ( D + E ) 232,857.75
A.4.1.1.22 PEMASANGAN 1 M2 BEKISTING UNTUK LANTAI(DENGAN PAPAN MAL PEMAKAIAN BERULANG
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.660 120,000.00 79,200.00
Tukang kayu L.02 OH 0.330 135,000.00 44,550.00
Kepala tukang L.03 OH 0.033 140,000.00 4,620.00
Mandor L.04 OH 0.033 155,000.00 5,115.00
JUMLAH TENAGA KERJA 133,485.00
B BAHAN
Kayu kelas III m3 0.0220 1,800,000.00 39,600.00
Paku 5 - 12 cm Kg 0.4000 22,000.00 8,800.00
Minyak Bekisting Ltr 0.2000 - -
Papan Mall m3 0.0080 1,800,000.00 14,400.00
Dolken kayu galam, ɸ(8-10)cm 4 m Batang 2.0000 8,000.00 16,000.00
JUMLAH HARGA BAHAN 78,800.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 212,285.00
E Overhead & Provit 15% x D 31,842.75
F Harga Satuan Pekerjaan ( D + E ) 244,127.75
A.4.4.1 HARGA SATUAN PEKERJAAN DINDING

A.4.4.1.20.b PEMASANGAN 1 M2 DINDING BATAKO 20 X 40 X 7 CM


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.300 120,000.00 36,000.00
Tukang batu L.02 OH 0.100 135,000.00 13,500.00
Kepala tukang L.03 OH 0.010 140,000.00 1,400.00
Mandor L.04 OH 0.015 155,000.00 2,325.00
JUMLAH TENAGA KERJA 53,225.00
B BAHAN
batako Bh 12.500 3,300.00 41,250.00
Semen Portland Kg 11.000 1,800.00 19,800.00
Pasir pasang m³ 0.035 200,000.00 7,000.00
JUMLAH HARGA BAHAN 68,050.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 121,275.00
E Overhead & Provit 15% x D 18,191.25
F Harga Satuan Pekerjaan ( D + E ) 139,466.25
3.2 HARGA SATUAN PEKERJAAN PLESTERAN

3.2.1.(c) PEMASANGAN 1 M2 PLESTERAN 1 SP:4PP TEBAL 15 MM


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.300 120,000.00 36,000.00
Tukang batu L.03 OH 0.150 135,000.00 20,250.00
Kepala tukang L.03 OH 0.015 140,000.00 2,100.00
Mandor L.04 OH 0.015 155,000.00 2,325.00
JUMLAH TENAGA KERJA 60,675.00
B BAHAN
Semen Portland Kg 7.776 1,800.00 13,996.80
Pasir Pasang m3 0.023 200,000.00 4,600.00
JUMLAH HARGA BAHAN 18,596.80
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 79,271.80
E Overhead & Provit 15% x D 11,890.77
F Harga Satuan Pekerjaan ( D + E ) 91,162.57

3.2.2.(d) PEK. ACIAN


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.200 120,000.00 24,000.00
Tukang batu L.03 OH 0.100 135,000.00 13,500.00
Kepala tukang L.03 OH 0.010 140,000.00 1,400.00
Mandor L.04 OH 0.010 155,000.00 1,550.00
JUMLAH TENAGA KERJA 40,450.00
B BAHAN
Semen Portland Kg 3.250 1,800.00 5,850.00
Pasir Pasang m3 0.024 -
JUMLAH HARGA BAHAN 5,850.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 46,300.00
E Overhead & Provit 15% x D 6,945.00
F Harga Satuan Pekerjaan ( D + E ) 53,245.00
A.4.2.1 HARGA SATUAN PEK. BESI & ALUMINIUM

A.4.2.1.1 PEMASANGAN 1 KG BESI PROFIL


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.060 120,000.00 7,200.00
Tukang Las Konstruksi L.02 OH 0.060 135,000.00 8,100.00
Kepala tukang L.03 OH 0.0060 140,000.00 840.00
Mandor L.04 OH 0.0030 155,000.00 465.00
JUMLAH TENAGA KERJA 16,605.00
B BAHAN
Baja Profil Kg 1.150 15,000.00 17,250.00
Kawat Las -
JUMLAH HARGA BAHAN 17,250.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 33,855.00
E Overhead & Provit 15% x D 5,078.25
F Harga Satuan Pekerjaan ( D + E ) 38,933.25

A.4.2.1.22 1 M2 RANGKA ATAP BAJA RINGAN (BAHAN DAN ONGKOS PASANG) DENGAN JURAI (TYPE 1)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.734 120,000.00 88,080.00
Tukang Khusus Aluminium L.02 OH 0.734 135,000.00 99,090.00
Kepala tukang L.03 OH 0.0730 140,000.00 10,220.00
Mandor L.04 OH 0.0370 155,000.00 5,735.00
JUMLAH TENAGA KERJA 203,125.00
B BAHAN
Main Trus C-75-75 Btg 0.873 105,000.00 91,665.00
-
JUMLAH HARGA BAHAN 91,665.00
C PERALATAN
Aksesories (% bahan) 10 1,050.00 10,500.00
JUMLAH HARGA ALAT 10,500.00
D Jumlah (A + B + C) 305,290.00
E Overhead & Provit 15% x D 45,793.50
F Harga Satuan Pekerjaan ( D + E ) 351,083.50

A.4.2.1.24 PEMASANGAN 1 M KUSEN ALUMINIUM


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.043 120,000.00 5,160.00
Tukang Khusus Aluminium L.02 OH 0.043 135,000.00 5,805.00
Kepala tukang L.03 OH 0.0043 140,000.00 602.00
Mandor L.04 OH 0.0021 155,000.00 325.50
JUMLAH TENAGA KERJA 11,892.50
B BAHAN
Kusen Aluminium 3" Silver M 1.100 120,000.00 132,000.00
Skrup Fixer Bh 2.000 500.00 1,000.00
Sealant tube 0.060 45,000.00 2,700.00
JUMLAH HARGA BAHAN 135,700.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 147,592.50
E Overhead & Provit 15% x D 22,138.88
F Harga Satuan Pekerjaan ( D + E ) 169,731.38

A.4.2.1.21.a PEMASANGAN 1 M2 RANGKA BESI HOLLOW ZINCALUME 40.40 MM, MODUL 60X120 CM, UNTUK PLAFON
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.350 120,000.00 42,000.00
Tukang L.02 OH 0.350 135,000.00 47,250.00
Kepala tukang L.03 OH 0.0350 140,000.00 4,900.00
Mandor L.04 OH 0.0180 155,000.00 2,790.00
JUMLAH TENAGA KERJA 96,940.00
B BAHAN
Rangka Metal hollow 40.40.2 M 3.500 6,500.00 22,750.00
mm(metal furing)
aksesories Ls 100% x rangka 6,500.00 6,500.00
JUMLAH HARGA BAHAN 29,250.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 126,190.00
E Overhead & Provit 15% x D 18,928.50
F Harga Satuan Pekerjaan ( D + E ) 145,118.50

A.4.2.1.9 PEMASANGAN 1 M2 SUNSCREEN ALUMUNIUM (JALUSI ALUMINIUM)


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.080 120,000.00 9,600.00
Tukang L.02 OH 0.800 135,000.00 108,000.00
Kepala tukang L.03 OH 0.080 140,000.00 11,200.00
Mandor L.04 OH 0.004 155,000.00 620.00
JUMLAH TENAGA KERJA 129,420.00
B BAHAN
Sunscreen Aluminium M2 1.000 120,000.00 120,000.00
JUMLAH HARGA BAHAN 120,000.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 249,420.00
E Overhead & Provit 15% x D 37,413.00
F Harga Satuan Pekerjaan ( D + E ) 286,833.00
AT.4.2.1.24.a PEMASANGAN 1 M2 JENDELA CASEMENT FRAME ALUMUNIUM + KACA
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.734 120,000.00 88,080.00
Tukang L.02 OH 0.734 135,000.00 99,090.00
Kepala tukang L.03 OH 0.0734 140,000.00 10,276.00
Mandor L.04 OH 0.037 155,000.00 5,735.00
JUMLAH TENAGA KERJA 203,181.00
B BAHAN

M 4.000 120,000.00 480,000.00


Frame Aluminium 1 1/2"x3"
Skrup fixer Bh 4.000 500.00 2,000.00
Kaca t.5 M2 1.050 175,000.00 183,750.00
JUMLAH HARGA BAHAN 665,750.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 868,931.00
E Overhead & Provit 15% x D 130,339.65
F Harga Satuan Pekerjaan ( D + E ) 999,270.65
A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING

A.4.4.3.36.a PEMASANGAN 1 M2 LANTAI KERAMIK UK. 40X40 CM POLISHED


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.700 120,000.00 84,000.00
Tukang batu L.02 OH 0.350 135,000.00 47,250.00
Kepala tukang L.03 OH 0.035 140,000.00 4,900.00
Mandor L.04 OH 0.035 155,000.00 5,425.00
JUMLAH TENAGA KERJA 141,575.00
B BAHAN
Keramik 40x40 cm (polish/Biasa) Bh 1.050 63,000.00 66,150.00
Semen portland Kg 10.000 1,800.00 18,000.00
Pasir Pasang m3 0.045 200,000.00 9,000.00
Semen Warna Kg 0.050 18,000.00 900.00
JUMLAH HARGA BAHAN 94,050.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 235,625.00
E Overhead & Provit 15% x D 35,343.75
F Harga Satuan Pekerjaan ( D + E ) 270,968.75

A.4.4.3.36.b PEMASANGAN 1 M2 LANTAI KERAMIK UKURAN 40 X 40 CM (UNPOLISH/BIASA)


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.700 120,000.00 84,000.00
Tukang batu L.02 OH 0.350 135,000.00 47,250.00
Kepala tukang L.03 OH 0.035 140,000.00 4,900.00
Mandor L.04 OH 0.035 155,000.00 5,425.00
JUMLAH TENAGA KERJA 141,575.00
B BAHAN
Keramik 40x40 cm (Unpolish/Biasa) kotak 1.050 73,000.00 76,650.00
Semen portland Kg 10.000 1,800.00 18,000.00
Pasir Pasang M3 0.045 200,000.00 9,000.00
Semen Warna Kg 0.050 18,000.00 900.00
JUMLAH HARGA BAHAN 104,550.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 246,125.00
E Overhead & Provit 15% x D 36,918.75
F Harga Satuan Pekerjaan ( D + E ) 283,043.75

A.4.4.3.53.a PEMASANGAN 1 M2 DINDING KERAMIK 25 X 40 CM (POLISH/BIASA)


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.900 120,000.00 108,000.00
Tukang batu L.02 OH 0.450 135,000.00 60,750.00
Kepala tukang L.03 OH 0.045 140,000.00 6,300.00
Mandor L.04 OH 0.045 155,000.00 6,975.00
JUMLAH TENAGA KERJA 182,025.00
B BAHAN
Keramik 25x40 cm (polish biasa) dus 1.050 70,000.00 73,500.00
Semen portland Kg 9.300 1,800.00 16,740.00
Pasir Pasang m3 0.018 200,000.00 3,600.00
Semen Warna Kg 1.940 18,000.00 34,920.00
JUMLAH HARGA BAHAN 128,760.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 310,785.00
E Overhead & Provit 15% x D 46,617.75
F Harga Satuan Pekerjaan ( D + E ) 357,402.75

A.4.4.3.53.b PEMASANGAN 1 M2 LANTAI KERAMIK 25 X 25 CM (UNPOLISH/BIASA)


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.700 120,000.00 84,000.00
Tukang batu L.02 OH 0.350 135,000.00 47,250.00
Kepala tukang L.03 OH 0.035 140,000.00 4,900.00
Mandor L.04 OH 0.035 155,000.00 5,425.00
JUMLAH TENAGA KERJA 141,575.00
B BAHAN
Keramik 25x25 cm Unpolish dus 1.050 68,000.00 71,400.00
Semen portland Kg 10.000 1,800.00 18,000.00
Pasir Pasang m3 0.045 200,000.00 9,000.00
Semen Warna Kg 0.050 18,000.00 900.00
JUMLAH HARGA BAHAN 99,300.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 240,875.00
E Overhead & Provit 15% x D 36,131.25
F Harga Satuan Pekerjaan ( D + E ) 277,006.25
A.4.5.1 HARGA SATUAN PEKERJAAN LANGIT-LANGIT (PLAFOND)

A.4.5.1.7 PEMASANGAN 1 M2 LANGIT-LANGIT TRIPLEK


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.100 120,000.00 12,000.00
Tukang kayu L.02 OH 0.050 135,000.00 6,750.00
Kepala tukang L.03 OH 0.005 140,000.00 700.00
Mandor L.04 OH 0.005 155,000.00 775.00
JUMLAH TENAGA KERJA 20,225.00
B BAHAN
Triplek t = 3 mm Lembar 0.364 50,000.00 18,200.00
Paku GRC Kg 0.110 35,000.00 3,850.00
JUMLAH HARGA BAHAN 22,050.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 42,275.00
E Overhead & Provit 15% x D 6,341.25
F Harga Satuan Pekerjaan ( D + E ) 48,616.25

A.4.5.1.7.a PEMASANGAN 1 M2 LANGIT-LANGIT GRC UKURAN 120 x 240 MM TEBAL 4 MM


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.100 120,000.00 12,000.00
Tukang kayu L.02 OH 0.050 135,000.00 6,750.00
Kepala tukang L.03 OH 0.005 140,000.00 700.00
Mandor L.04 OH 0.005 155,000.00 775.00
JUMLAH TENAGA KERJA 20,225.00
B BAHAN
GRC tebal 4 mm Lembar 0.364 80,000.00 29,120.00
sekrup grc Kg 0.110 35,000.00 3,850.00
JUMLAH HARGA BAHAN 32,970.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 53,195.00
E Overhead & Provit 15% x D 7,979.25
F Harga Satuan Pekerjaan ( D + E ) 61,174.25
A.4.5.2 HARGA SATUAN PEKERJAAN PENUTUP ATAP

A.4.5.2.32.a PEMASANGAN 1 M2 ATAP ZINCALUME


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.200 120,000.00 24,000.00
Tukang L.02 OH 0.100 135,000.00 13,500.00
Kepala tukang L.03 OH 0.010 140,000.00 1,400.00
Mandor L.04 OH 0.001 155,000.00 155.00
JUMLAH TENAGA KERJA 39,055.00
B BAHAN
Atap Zincalume 0.30 mm lbr 1.316 77,000.00 101,332.00
Sekrup Atap Kg 0.200 45,000.00 9,000.00
JUMLAH HARGA BAHAN 110,332.00
C PERALATAN
Aksesories (% bahan) 10 - -
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 149,387.00
E Overhead & Provit 15% x D 22,408.05
F Harga Satuan Pekerjaan ( D + E ) 171,795.05

A.4.5.2.38 PEMASANGAN 1 M NOK


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.250 120,000.00 30,000.00
Tukang L.02 OH 0.150 135,000.00 20,250.00
Kepala tukang L.03 OH 0.015 140,000.00 2,100.00
Mandor L.04 OH 0.013 155,000.00 2,015.00
JUMLAH TENAGA KERJA 54,365.00
B BAHAN
Nok plat seng bh 1.100 25,000.00 27,500.00
Sekrup Atap Kg 0.050 45,000.00 2,250.00
JUMLAH HARGA BAHAN 29,750.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 84,115.00
E Overhead & Provit 15% x D 12,617.25
F Harga Satuan Pekerjaan ( D + E ) 96,732.25
A.4.6.1 HARGA SATUAN PEKERJAAN KAYU

A.4.6.1.1 PEMBUATAN DAN PEMASANGAN 1 M3 KUSEN PINTU DAN KUSEN JENDELA, KAYU KELAS I
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 7.000 120,000.00 840,000.00
Tukang Kayu L.02 OH 21.000 135,000.00 2,835,000.00
Kepala Tukang L.03 OH 2.100 140,000.00 294,000.00
Mandor L.04 OH 0.350 155,000.00 54,250.00
JUMLAH TENAGA KERJA 4,023,250.00
B BAHAN
Balok Kayu m3 1.100 5,000,000.00 5,500,000.00
Paku 10cm kg 1.250 22,000.00 27,500.00
Lem kayu kg 1.000 12,000.00 12,000.00
JUMLAH HARGA BAHAN 5,539,500.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 9,562,750.00
E Overhead & Provit 15% x D 1,434,412.50
F Harga Satuan Pekerjaan ( D + E ) 10,997,162.50

A.4.6.1.5 PEMBUATAN DAN PEMASANGAN 1 M2 DAUN PINTU PANEL, KAYU KELAS I ATAU II
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.000 120,000.00 120,000.00
Tukang Kayu L.02 OH 3.000 135,000.00 405,000.00
Kepala Tukang L.03 OH 0.300 140,000.00 42,000.00
Mandor L.04 OH 0.050 155,000.00 7,750.00
JUMLAH TENAGA KERJA 574,750.00
B BAHAN
Papan Kayu Kelas I m3 0.040 5,000,000.00 200,000.00
Lem kayu kg 0.500 12,000.00 6,000.00
JUMLAH HARGA BAHAN 206,000.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 780,750.00
E Overhead & Provit 15% x D 117,112.50
F Harga Satuan Pekerjaan ( D + E ) 897,862.50

A.4.6.1.6 PEMBUATAN & PEMASANGAN 1 M2 PINTU DAN JENDELA KACA, KAYU KELAS I ATAU II
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.800 120,000.00 96,000.00
Tukang Kayu L.02 OH 2.400 135,000.00 324,000.00
Kepala Tukang L.03 OH 0.240 140,000.00 33,600.00
Mandor L.04 OH 0.040 155,000.00 6,200.00
JUMLAH TENAGA KERJA 459,800.00
B BAHAN
Papan Kayu Kelas I m3 0.024 5,000,000.00 120,000.00
Lem kayu kg 0.300 12,000.00 3,600.00
JUMLAH HARGA BAHAN 123,600.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A + B + C) 583,400.00
E Overhead & Provit 15% x D 87,510.00
F Harga Satuan Pekerjaan ( D + E ) 670,910.00

A.4.6.1.7 PEMBUATAN 1 M2 PINTU DAN JENDELA JALUSI, KAYU KELAS I ATAU II


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.000 120,000.00 120,000.00
Tukang Kayu L.02 OH 3.000 135,000.00 405,000.00
Kepala Tukang L.03 OH 0.300 140,000.00 42,000.00
Mandor L.04 OH 0.050 155,000.00 7,750.00
JUMLAH TENAGA KERJA 574,750.00
B BAHAN
Papan Kayu Kelas I m3 0.064 5,000,000.00 320,000.00
Lem Kayu kg 0.500 12,000.00 6,000.00
JUMLAH HARGA BAHAN 326,000.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 900,750.00
E Overhead & Provit 15% x D 135,112.50
F Harga Satuan Pekerjaan ( D + E ) 1,035,862.50

A.4.6.1.8.1 PEMBUATAN 1 M2 DAUN PINTU MULTIPLEKS RANGKAP, RANGKA KAYU KELAS II TERTUTUP (LEBAR SAMPAI 90CM)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.700 120,000.00 84,000.00
Tukang Kayu L.02 OH 2.100 135,000.00 283,500.00
Kepala Tukang L.03 OH 0.210 140,000.00 29,400.00
Mandor L.04 OH 0.035 155,000.00 5,425.00
JUMLAH TENAGA KERJA 402,325.00
B BAHAN
Papan Kayu m3 0.025 5,000,000.00 125,000.00
Paku kg 0.030 22,000.00 660.00
Lem Kayu kg 0.500 12,000.00 6,000.00
Multiplek 9 mm Lbr 1.000 160,000.00 160,000.00
JUMLAH HARGA BAHAN 291,660.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 693,985.00
E Overhead & Provit 15% x D 104,097.75
F Harga Satuan Pekerjaan ( D + E ) 798,082.75

A.4.6.1.21.a PEMASANGAN 1 M LISPLANK UKURAN (3X20) CM, WOODPLANK


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.100 120,000.00 12,000.00
Tukang Kayu L.02 OH 0.200 135,000.00 27,000.00
Kepala Tukang L.03 OH 0.020 140,000.00 2,800.00
Mandor L.04 OH 0.005 155,000.00 775.00
JUMLAH TENAGA KERJA 42,575.00
B BAHAN
Papan Lisplank M 1.100 16,000.00 17,600.00
Sekrup kg 0.100 45,000.00 4,500.00
JUMLAH HARGA BAHAN 22,100.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 64,675.00
E Overhead & Provit 15% x D 9,701.25
F Harga Satuan Pekerjaan ( D + E ) 74,376.25

A.4.6.1.13 PEMASANGAN 1M3 KONSTRUKSI KUDA-KUDA KONVENSIONAL


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 4.000 120,000.00 480,000.00
Tukang Kayu L.02 OH 12.000 135,000.00 1,620,000.00
Kepala Tukang L.03 OH 1.200 140,000.00 168,000.00
Mandor L.04 OH 0.200 155,000.00 31,000.00
JUMLAH TENAGA KERJA 2,299,000.00
B BAHAN
Balok Kayu M3 1.100 4,000,000.00 4,400,000.00
Besi Strip kg 15.000 20,000.00 300,000.00
Paku kg 5.600 22,000.00 123,200.00
JUMLAH HARGA BAHAN 4,823,200.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 7,122,200.00
E Overhead & Provit 15% x D 1,068,330.00
F Harga Satuan Pekerjaan ( D + E ) 8,190,530.00

A.4.6.1.15 PEMASANGAN 1 M3 KONSTRUKSI GORDENG


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 6.700 120,000.00 804,000.00
Tukang Kayu L.02 OH 20.100 135,000.00 2,713,500.00
Kepala Tukang L.03 OH 2.010 140,000.00 281,400.00
Mandor L.04 OH 0.335 155,000.00 51,925.00
JUMLAH TENAGA KERJA 3,850,825.00
B BAHAN
Balok Kayu M3 1.100 4,000,000.00 4,400,000.00
Besi Strip kg 15.000 20,000.00 300,000.00
Paku kg 3.000 22,000.00 66,000.00
JUMLAH HARGA BAHAN 4,766,000.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 8,616,825.00
E Overhead & Provit 15% x D 1,292,523.75
F Harga Satuan Pekerjaan ( D + E ) 9,909,348.75
A.4.6.2 HARGA SATUAN PEKERJAAN KUNCI DAN KACA

A.4.6.2.2.a PEMASANGAN 1 BUAH KUNCI TANAM 2 SLAG


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.010 120,000.00 1,200.00
Tukang Kayu L.02 OH 0.500 135,000.00 67,500.00
Kepala Tukang L.03 OH 0.050 140,000.00 7,000.00
Mandor L.04 OH 0.005 155,000.00 775.00
JUMLAH TENAGA KERJA 76,475.00
B BAHAN
Kunci Tanam 2 slag Bh 1.000 120,000.00 120,000.00
JUMLAH HARGA BAHAN 120,000.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 196,475.00
E Overhead & Provit 15% x D 29,471.25
F Harga Satuan Pekerjaan ( D + E ) 225,946.25

A.4.6.2.5 PEMASANGAN 1 BUAH ENGSEL PINTU


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.015 120,000.00 1,800.00
Tukang Kayu L.02 OH 0.150 135,000.00 20,250.00
Kepala Tukang L.03 OH 0.015 140,000.00 2,100.00
Mandor L.04 OH 0.0008 155,000.00 124.00
JUMLAH TENAGA KERJA 24,274.00
B BAHAN
Engsel Pintu bh 1.000 55,000.00 55,000.00
JUMLAH HARGA BAHAN 55,000.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 79,274.00
E Overhead & Provit 15% x D 11,891.10
F Harga Satuan Pekerjaan ( D + E ) 91,165.10

A.4.6.2.6 PEMASANGAN 1 BUAH ENGSEL KUPU-KUPU


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.010 120,000.00 1,200.00
Tukang Kayu L.02 OH 0.100 135,000.00 13,500.00
Kepala Tukang L.03 OH 0.010 140,000.00 1,400.00
Mandor L.04 OH 0.0050 155,000.00 775.00
JUMLAH TENAGA KERJA 16,875.00
B BAHAN
Engsel kupu-kupu bh 1.000 35,000.00 35,000.00
JUMLAH HARGA BAHAN 35,000.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 51,875.00
E Overhead & Provit 15% x D 7,781.25
F Harga Satuan Pekerjaan ( D + E ) 59,656.25

A.4.6.2.9 PEMASANGAN 1 BUAH KAIT ANGIN


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.015 120,000.00 1,800.00
Tukang Kayu L.02 OH 0.150 135,000.00 20,250.00
Kepala Tukang L.03 OH 0.015 140,000.00 2,100.00
Mandor L.04 OH 0.0008 155,000.00 124.00
JUMLAH TENAGA KERJA 24,274.00
B BAHAN
Kait Angin bh 1.000 30,000.00 30,000.00
JUMLAH HARGA BAHAN 30,000.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 54,274.00
E Overhead & Provit 15% x D 8,141.10
F Harga Satuan Pekerjaan ( D + E ) 62,415.10

A.4.6.2.6.a PEMASANGAN 1 BUAH HANDLE JENDELA


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.010 120,000.00 1,200.00
Tukang Kayu L.02 OH 0.100 135,000.00 13,500.00
Kepala Tukang L.03 OH 0.010 140,000.00 1,400.00
Mandor L.04 OH 0.0005 155,000.00 77.50
JUMLAH TENAGA KERJA 16,177.50
B BAHAN
handle Jendela bh 1.000 15,000.00 15,000.00
JUMLAH HARGA BAHAN 15,000.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 31,177.50
E Overhead & Provit 15% x D 4,676.63
F Harga Satuan Pekerjaan ( D + E ) 35,854.13

A.4.6.2.11.a PEMASANGAN 1 BUAH KUNCI SLOT UNTUK PINTU


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.020 120,000.00 2,400.00
Tukang Kayu L.02 OH 0.200 135,000.00 27,000.00
Kepala Tukang L.03 OH 0.020 140,000.00 2,800.00
Mandor L.04 OH 0.0010 155,000.00 155.00
JUMLAH TENAGA KERJA 32,355.00
B BAHAN
Kunci Slot bh 1.000 30,000.00 30,000.00
JUMLAH HARGA BAHAN 30,000.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 62,355.00
E Overhead & Provit 15% x D 9,353.25
F Harga Satuan Pekerjaan ( D + E ) 71,708.25

A.4.6.2.17 PEMASANGAN 1 M2 KACA POLOS TEBAL 5 MM


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.015 120,000.00 1,800.00
Tukang Kayu L.02 OH 0.150 135,000.00 20,250.00
Kepala Tukang L.03 OH 0.015 140,000.00 2,100.00
Mandor L.04 OH 0.0008 155,000.00 124.00
JUMLAH TENAGA KERJA 24,274.00
B BAHAN
Kaca tebal 5 mm M2 1.100 175,000.00 192,500.00
Sealant Kg 0.050 45,000.00 2,250.00
JUMLAH HARGA BAHAN 194,750.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 219,024.00
E Overhead & Provit 15% x D 32,853.60
F Harga Satuan Pekerjaan ( D + E ) 251,877.60
3.3. HARGA SATUAN PEKERJAAN PENGECATAN

A.4.7.1.4 1 M2 PENGECATAN BIDANG KAYU BARU (1 LAPIS PLAMUR,1 LAPIS CAT DASAR,2 LAPIS CAT PENUTUP)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.070 120,000.00 8,400.00
Tukang cat L.02 OH 0.009 135,000.00 1,215.00
Kepala tukang L.03 OH 0.0060 140,000.00 840.00
Mandor L.04 OH 0.003 155,000.00 465.00
JUMLAH TENAGA KERJA 10,920.00
B BAHAN
Cat Menie Kg 0.200 55,000.00 11,000.00
Plamuur Kg 0.150 20,000.00 3,000.00
Cat dasar Kg 0.170 50,000.00 8,500.00
Cat penutup Kg 0.260 55,000.00 14,300.00
Kuas Bh 0.010 10,000.00 100.00
Pengencer Kg 0.030 15,000.00 450.00
Amplas Lbr 0.200 5,000.00 1,000.00
JUMLAH HARGA BAHAN 38,350.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 49,270.00
E Overhead & Provit 15% x D 7,390.50
F Harga Satuan Pekerjaan ( D + E ) 56,660.50

3.3.10.(c) PENGECATAN 1 M2 TEMBOK BARU (1 LAPIS PLAMUR,1 LAPIS CAT DASAR,2 LAPIS CAT PENUTUP)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.020 120,000.00 2,400.00
Tukang cat L.02 OH 0.063 135,000.00 8,505.00
Kepala tukang L.03 OH 0.0063 140,000.00 882.00
Mandor L.04 OH 0.003 155,000.00 465.00
JUMLAH TENAGA KERJA 12,252.00
B BAHAN
Plamuur Kg 0.100 20,000.00 2,000.00
Cat dasar Kg 0.100 50,000.00 5,000.00
Cat penutup Weathershield Kg 0.260 100,000.00 26,000.00
JUMLAH HARGA BAHAN 33,000.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 45,252.00
E Overhead & Provit 15% x D 6,787.80
F Harga Satuan Pekerjaan ( D + E ) 52,039.80

A.4.7.1.10.b 1 M2 PENGECATAN PLAFOND (1 LAPIS PLAMUR, 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.020 120,000.00 2,400.00
Tukang cat L.02 OH 0.063 135,000.00 8,505.00
Kepala tukang L.03 OH 0.0063 140,000.00 882.00
Mandor L.04 OH 0.003 155,000.00 465.00
JUMLAH TENAGA KERJA 12,252.00
B BAHAN
Plamuur Kg 0.100 20,000.00 2,000.00
Cat dasar Kg 0.100 50,000.00 5,000.00
Cat penutup Weathershield Kg 0.260 50,000.00 13,000.00
JUMLAH HARGA BAHAN 20,000.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 32,252.00
E Overhead & Provit 15% x D 4,837.80
F Harga Satuan Pekerjaan ( D + E ) 37,089.80
A.5.1.1 HARGA SATUAN PEKERJAAN SANITASI

A.5.1.1.1 PEMASANGAN 1 BUAH CLOSET DUDUK TOTO


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 3.300 120,000.00 396,000.00
Tukang L.02 OH 1.100 135,000.00 148,500.00
Kepala tukang L.03 OH 0.0100 140,000.00 1,400.00
Mandor L.04 OH 0.160 155,000.00 24,800.00
JUMLAH TENAGA KERJA 570,700.00
B BAHAN
Closet Duduk Unit 1.000 1,800,000.00 1,800,000.00
Perlengkapan Ls 0.060 1,800,000.00 108,000.00
JUMLAH HARGA BAHAN 1,908,000.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 2,478,700.00
E Overhead & Provit 15% x D 371,805.00
F Harga Satuan Pekerjaan ( D + E ) 2,850,505.00

A.5.1.1.2 PEMASANGAN 1 BUAH CLOSET JONGKOK PORSELEN


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.000 120,000.00 120,000.00
Tukang L.02 OH 1.500 135,000.00 202,500.00
Kepala tukang L.03 OH 0.1500 140,000.00 21,000.00
Mandor L.04 OH 0.160 155,000.00 24,800.00
JUMLAH TENAGA KERJA 368,300.00
B BAHAN
Closet Jongkok(setaraf toto) Unit 1.000 200,000.00 200,000.00
Semen Portland Kg 6.000 1,800.00 10,800.00
Pasir Pasang M3 0.010 200,000.00 2,000.00
JUMLAH HARGA BAHAN 212,800.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 581,100.00
E Overhead & Provit 15% x D 87,165.00
F Harga Satuan Pekerjaan ( D + E ) 668,265.00

A.5.1.1.5.F PEMASANGAN 1 BUAH KRAN AIR PENDEK


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.010 120,000.00 1,200.00
Tukang L.02 OH 0.200 135,000.00 27,000.00
Kepala tukang L.03 OH 0.0400 140,000.00 5,600.00
Mandor L.04 OH 0.005 155,000.00 775.00
JUMLAH TENAGA KERJA 34,575.00
B BAHAN
Kran air Unit 1.000 35,000.00 35,000.00
Perlengkapan % 0.025 350.00 8.75
JUMLAH HARGA BAHAN 35,008.75
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 69,583.75
E Overhead & Provit 15% x D 10,437.56
F Harga Satuan Pekerjaan ( D + E ) 80,021.31

A.5.1.1.5 PEMASANGAN 1 BUAH WASTAFEL


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.200 120,000.00 144,000.00
Mandor L.04 OH 0.060 155,000.00 9,300.00
JUMLAH TENAGA KERJA 153,300.00
B BAHAN
Wastafel Unit 1.000 500,000.00 500,000.00
Perlengkapan % 0.120 500,000.00 60,000.00
JUMLAH HARGA BAHAN 560,000.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 713,300.00
E Overhead & Provit 15% x D 106,995.00
F Harga Satuan Pekerjaan ( D + E ) 820,295.00

A.5.1.1.10 PEMASANGAN 1 BUAH BAK FIBERGLASS VOL 1 M3


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.300 120,000.00 36,000.00
Tukang L.02 OH 0.450 135,000.00 60,750.00
Kepala tukang L.03 OH 0.4500 140,000.00 63,000.00
Mandor L.04 OH 0.015 155,000.00 2,325.00
JUMLAH TENAGA KERJA 162,075.00
B BAHAN
Bak Air Fiberglass Unit 1.000 500,000.00 500,000.00
Perlengkapan % 0.120 500,000.00 60,000.00
JUMLAH HARGA BAHAN 560,000.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 722,075.00
E Overhead & Provit 15% x D 108,311.25
F Harga Satuan Pekerjaan ( D + E ) 830,386.25

A.5.1.1.14 PEMASANGAN 1 BUAH FLOOR DRAIN


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.010 120,000.00 1,200.00
Tukang L.02 OH 0.100 135,000.00 13,500.00
Kepala tukang L.03 OH 0.0100 140,000.00 1,400.00
Mandor L.04 OH 0.005 155,000.00 775.00
JUMLAH TENAGA KERJA 16,875.00
B BAHAN
Floor Drain m 1.000 25,000.00 25,000.00

JUMLAH HARGA BAHAN 25,000.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 41,875.00
E Overhead & Provit 15% x D 6,281.25
F Harga Satuan Pekerjaan ( D + E ) 48,156.25

A.5.1.1.14.a PEMASANGAN 1 BUAH JETWASHER


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.010 120,000.00 1,200.00
Tukang L.02 OH 0.100 135,000.00 13,500.00
Kepala tukang L.03 OH 0.0100 140,000.00 1,400.00
Mandor L.04 OH 0.005 155,000.00 775.00
JUMLAH TENAGA KERJA 16,875.00
B BAHAN
Jetwasher Bh 1.000 200,000.00 200,000.00
Sealtape Bh 1.000 5,000.00 5,000.00
JUMLAH HARGA BAHAN 205,000.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 221,875.00
E Overhead & Provit 15% x D 33,281.25
F Harga Satuan Pekerjaan ( D + E ) 255,156.25

A.5.1.1.26 PEMASANGAN 1 M PIPA PVC TIPE AW DIAMETER 3/4"


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.036 120,000.00 4,320.00
Tukang L.02 OH 0.060 135,000.00 8,100.00
Kepala tukang L.03 OH 0.0060 140,000.00 840.00
Mandor L.04 OH 0.002 155,000.00 310.00
JUMLAH TENAGA KERJA 13,570.00
B BAHAN
Pipa PVC 3/4" M 1.200 8,750.00 10,500.00
Perlengkapan % 0.050 8,750.00 437.50
JUMLAH HARGA BAHAN 10,937.50
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 24,507.50
E Overhead & Provit 15% x D 3,676.13
F Harga Satuan Pekerjaan ( D + E ) 28,183.63

A.5.1.1.27 PEMASANGAN 1 M PIPA PVC TIPE AW DIAMETER 1"


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.036 120,000.00 4,320.00
Tukang L.02 OH 0.060 135,000.00 8,100.00
Kepala tukang L.03 OH 0.0060 140,000.00 840.00
Mandor L.04 OH 0.002 155,000.00 310.00
JUMLAH TENAGA KERJA 13,570.00
B BAHAN
Pipa PVC 1" M 1.200 12,000.00 14,400.00
Perlengkapan % 0.350 12,000.00 4,200.00
JUMLAH HARGA BAHAN 18,600.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 32,170.00
E Overhead & Provit 15% x D 4,825.50
F Harga Satuan Pekerjaan ( D + E ) 36,995.50

A.5.1.1.29 PEMASANGAN 1 M PIPA PVC TIPE AW DIAMETER 2"


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.054 120,000.00 6,480.00
Tukang L.02 OH 0.090 135,000.00 12,150.00
Kepala tukang L.03 OH 0.0090 140,000.00 1,260.00
Mandor L.04 OH 0.003 155,000.00 465.00
JUMLAH TENAGA KERJA 20,355.00
B BAHAN
Pipa PVC 2" M 1.200 25,000.00 30,000.00
Perlengkapan % 0.350 25,000.00 8,750.00
JUMLAH HARGA BAHAN 38,750.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 59,105.00
E Overhead & Provit 15% x D 8,865.75
F Harga Satuan Pekerjaan ( D + E ) 67,970.75

A.5.1.1.30 PEMASANGAN 1 M PIPA PVC TIPE AW DIAMETER 2.5"


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.054 120,000.00 6,480.00
Tukang L.02 OH 0.090 135,000.00 12,150.00
Kepala tukang L.03 OH 0.0090 140,000.00 1,260.00
Mandor L.04 OH 0.003 155,000.00 465.00
JUMLAH TENAGA KERJA 20,355.00
B BAHAN
Pipa PVC 2,5" M 1.200 30,000.00 36,000.00
Perlengkapan % 0.350 30,000.00 10,500.00
JUMLAH HARGA BAHAN 46,500.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 66,855.00
E Overhead & Provit 15% x D 10,028.25
F Harga Satuan Pekerjaan ( D + E ) 76,883.25

A.5.1.1.31 PEMASANGAN 1 M PIPA PVC TIPE AW DIAMETER 3"


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.081 120,000.00 9,720.00
Tukang L.02 OH 0.135 135,000.00 18,225.00
Kepala tukang L.03 OH 0.0135 140,000.00 1,890.00
Mandor L.04 OH 0.004 155,000.00 620.00
JUMLAH TENAGA KERJA 30,455.00
B BAHAN
Pipa PVC 2" M 1.200 62,500.00 75,000.00
Perlengkapan % 0.050 62,500.00 3,125.00
JUMLAH HARGA BAHAN 78,125.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 108,580.00
E Overhead & Provit 15% x D 16,287.00
F Harga Satuan Pekerjaan ( D + E ) 124,867.00

A.5.1.1.32 PEMASANGAN 1 M PIPA PVC TIPE AW DIAMETER 4"


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.081 120,000.00 9,720.00
Tukang L.02 OH 0.135 135,000.00 18,225.00
Kepala tukang L.03 OH 0.0140 140,000.00 1,960.00
Mandor L.04 OH 0.004 155,000.00 620.00
JUMLAH TENAGA KERJA 30,525.00
B BAHAN
Pipa PVC 4" M 1.200 100,000.00 120,000.00
Perlengkapan % 0.350 100,000.00 35,000.00
JUMLAH HARGA BAHAN 155,000.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 185,525.00
E Overhead & Provit 15% x D 27,828.75
F Harga Satuan Pekerjaan ( D + E ) 213,353.75
PEKERJAAN : PEMELIHARAAN DAN PENINGKATAN GEDUNG DAN STADION
LOKASI : KABUPATEN SINTANG, KALIMANTAN BARAT
TAHUN ANGGARAN : ANGGARAN PENDAPATAN DAN BELANJA DAERAH (APBD) KAB

VOLUME
NO URAIAN PEKERJAAN
TOTAL

A. GEDUNG UTAMA
I. PEKERJAAN PENDAHULUAN
a. Pekerjaan Persiapan
1 Pembongkaran Dan Pembersihan lokasi 1.000
2 Dokumentasi Dan Papan Nama Proyek 1.000

b. Penyelenggaraan SMKK Bangunan Gedung


A. PERLENGKAPAN K3
1 Penyiapan RKK
Pembuatan Prosedur dan Instruksi Kerja 1.000
2 Sosialisasi & Promosi K3
Spanduk (Banner) 1.000
Papan Informasi K3 1.000
3 Alat Pelindung Diri
Topi Pelindung (Safety Helmet) 10.000
Pelindung Pernapasan dan Mulut (Masker) 5.000
Sarung Tangan (Safety Gloves) 10.000
Rompi Keselamatan (Safety Vest) 10.000
Sepatu Karet Keselamatan 10.000
Handsatizer 500 ML 8.000
Pelindung Jatuh 5.000
4 Asuransi
Asuransi Kecelakaan Kerja Risiko Sangat Rendah
Mandor 1.000
Kepala Tukang 1.000
Tukang 6.000
Pekerja 3.000
5 Personel K3 Konstruksi
Ahli K3 3.000
6 Fasilitas Sarana & Prasarana Kesehatan
Peralatan P3K (Kotak K3, Obat Luka, Obat Umum, Perban) 1.000
7 Rambu-Rambu
Rambu Petunjuk 1.000
Rambu Larangan 1.000
Rambu Peringatan 1.000
8 Pengendalian Risiko Keselamatan Konstruksi
Bendera K3 1.000
9 BPJS Tenaga Kerja 1.000

II. PEKERJAAN PENUTUP DINDING DAN STRUKTUR FASAT


1 Pekerjaan Penutup ACP Lisplank 11.200
2 Pekerjaan Rangka ACP Fasad Pintu Utama 25.120
3 Pekerjaan Penutup ACP Fasad Pintu Utama 25.120
4 Pekerjaan Rangka ACP kolom Utama 24.000
5 Pekerjaan Penutup ACP kolom Utama 24.000
6 Rangka Holow Dinding Depan ACP Costume Cutting 70.000
7 Pemasangan Penutup Dinding Depan ACP Costume Cutting 70.000

III. PEKERJAAN PLAFOND


1 Plafon Triplek t = 3 mm 398.390

IV. PEKERJAAN PENGECATAN


1 Pengecatan Dinding Tembok Lama 1,829.880
2 Pengecatan Plafon 410.000

V. PEKERJAAN MEKANIKAL ELEKTRIKAL


1 Jaringan Instalasi Listrik (Kabel NYY Uk. 3 x 2,5 mm) 400.000
2 Lampu Led Inbow 18 watt 96.000
3 Lampu Sorot 600 Watt IP66 LED COB 8.000
4 Lampu Sorot Spotlight 20 Watt 6.000
5 Kotak MCB Box Panel 4.000
6 Led Strip 50.000

VI. PEKERJAAN PINTU


1 Pintu Volding Gate 200x220cm 8.800
2 Pintu Utama (Rangka Besi Hollow + Plat) + Rell 20.000
3 Rangka Holow ACP Costume Cutting 8.700
4 Pemasangan ACP Costume Cutting 8.700

VII. PEKERJAAN PELENGKAP BANGUNAN


1 Pengadaan Kursi bench Pemain 2.000
2 Tulisan Skor ACP 1.000
3 Tulisan Nama Stadion Baning 1.000

TOTAL PEKERJAAN A.
B. PEKERJAAN TOWER AIR
I. PEKERJAAN PONDASI
a. Pekerjaan Tapak Pondasi
1 Pengukuran dan Pemasangan Bowplank 20.000
2 Galian Tanah Pondasi 5.410
3 Pengadaan Cerucuk 4 m diameter 12 cm 48.000
4 Pemancangan 48.000
5 Penghamparan pasir alas 0.340
6 Cor Beton Tumbuk Lantai Kerja, mutu K.100 0.340
7 Pekerjaan Pembesian Tulangan 120.000
8 Pekerjaan Bakesting 2.660
9 Pekerjaan Cor Beton, mutu K.225 0.780
10 Urugan Kembali Tanah Galian Pondasi 4.200
b. Pekerjaan Padestal
1 Pekerjaan Pembesian tulangan 20.870
2 Pekerjaan Bakesting 0.760
3 Pekerjaan Cor Beton, mutu K.225 0.040

II. PEKERJAAN KOLOM


1 Pekerjaan Pembesian tulangan 78.120
2 Pekerjaan Bakesting 13.610
3 Pekerjaan Cor Beton, mutu K.225 0.730
4 Plesteran Kolom 50.160
5 Pengecatan 50.160

III. PEKERJAAN BALOK


a. Pekerjaan Balok Lantai 1
1 Pekerjaan Pembesian tulangan 134.820
2 Pekerjaan Bakesting 6.300
3 Pekerjaan Cor Beton, mutu K.225 0.540
b. Pekerjaan Balok Lantai 2
1 Pekerjaan Pembesian tulangan 134.150
2 Pekerjaan Bakesting 6.300
3 Pekerjaan Cor Beton, mutu K.225 0.540

IV. PEKERJAAN LANTAI


a. Pekerjaan Lanti 1
1 Pekerjaan Pembesian Tulangan (wire mesh) 104.930
2 Pekerjaan Bakesting 6.300
3 Pekerjaan Cor Beton, mutu K.225 0.900
b. Pekerjaan Lantai 2
1 Pekerjaan Pembesian Tulangan (wire mesh) 104.930
2 Pekerjaan Bakesting 6.300
3 Pekerjaan Cor Beton, mutu K.225 0.900

V. PEKERJAAN SANITASI
a. Instalasi air bersih
1 Pengadaan sumur bor
Pengeboran tanah 60.000
Pipa PVC 4 (type AW) 60.000
Pipa PVC 1 (type AW) 60.000
Pipa PVC 3\/4 80.000
Mesin air \/ jetpump 1.000
2 Tangki Air 1000 Liter 2.000
3 Pipa PVC 3\/4 (type AW) 50.000
4 Keran Air 3\/4 4.000

TOTAL PEKERJAAN B.
JUMLAH TOTAL
JUMLAH KOMULATIF
RENCANA KOMULATIF
TIME SCHEDU
UNG DAN STADION BANING
AT
AERAH (APBD) KABUPATEN SINTANG TAHUN ANGGARAN 2023

HARGA KONTRAK

SAT KODE ANALISA BOBOT


HARGA SATUAN SUB TOTAL

Pkt - 5,000,000.00 5,000,000.00 1.06


Pkt - 263,175.42 263,175.42 0.06

Ls - 200,000.00 200,000.00 0.04


Lmbr - 100,000.00 100,000.00 0.02
Bh - 50,000.00 50,000.00 0.01

Bh - 50,000.00 500,000.00 0.11


Kotak - 30,000.00 150,000.00 0.03
Psng - 20,000.00 200,000.00 0.04
Bh - 25,000.00 250,000.00 0.05
Psng - 120,000.00 1,200,000.00 0.25
Botol - 30,000.00 240,000.00 0.05
Bh - 250,000.00 1,250,000.00 0.26

OB - 125,000.00 125,000.00 0.03


OB - 125,000.00 125,000.00 0.03
OB - 125,000.00 750,000.00 0.16
OB - 125,000.00 375,000.00 0.08

OB - 2,000,000.00 6,000,000.00 1.27

Ls - 200,000.00 200,000.00 0.04

Bh - 50,000.00 50,000.00 0.01


Bh - 50,000.00 50,000.00 0.01
Bh - 50,000.00 50,000.00 0.01

Ls - 50,000.00 50,000.00 0.01


Ls - 500,000.00 500,000.00 0.11
17,678,175.42

M - 600,000.00 6,720,000.00 1.42


M - 330,000.00 8,289,600.00 1.75
M - 600,000.00 15,072,000.00 3.19
M - 330,000.00 7,920,000.00 1.67
M - 600,000.00 14,400,000.00 3.04
M - 330,000.00 23,100,000.00 4.88
M - 1,000,000.00 70,000,000.00 14.79
145,501,600.00
M A.4.5.1.7 48,616.25 19,368,227.84 4.09
19,368,227.84

M 3.3.10.(c) 52,039.80 95,226,589.22 20.12


M 3.3.10.(c) 52,039.80 21,336,318.00 4.51
116,562,907.22

M - 25,000.00 10,000,000.00 2.11


Bh - 120,000.00 11,520,000.00 2.43
Bh - 3,500,000.00 28,000,000.00 5.92
Bh - 200,000.00 1,200,000.00 0.25
Bh - 250,000.00 1,000,000.00 0.21
M - 50,000.00 2,500,000.00 0.53
54,220,000.00

M - 1,000,000.00 8,800,000.00 1.86


M - 850,000.00 17,000,000.00 3.59
M - 330,000.00 2,871,000.00 0.61
M - 1,000,000.00 8,700,000.00 1.84
37,371,000.00

Unit - 500,000.00 1,000,000.00 0.21


Unit - 3,000,000.00 3,000,000.00 0.63
Huruf - 2,500,000.00 2,500,000.00 0.53
6,500,000.00
Rp 397,201,910.48

M 1.1.d.(c) 60,622.25 1,212,445.00 0.26


M 1.7.1.a.(c) 107,956.25 584,043.31 0.12
M - 15,000.00 720,000.00 0.15
M - 10,000.00 480,000.00 0.10
M 1.7.2.d.(c) 319,182.50 108,522.05 0.02
M 2.2.1.1.a.(a) 1,291,737.80 439,190.85 0.09
Kg 2.2.6.1.b.(c) 19,417.75 2,330,130.00 0.49
M A.4.1.1.18 211,335.50 562,152.43 0.12
M 2.2.1.2.f.(a) 1,562,930.32 1,219,085.65 0.26
M 1.7.2.a.(c) 77,912.50 327,232.50 0.07

Kg 2.2.6.1.b.(c) 19,417.75 405,248.44 0.09


M A.4.1.1.20 221,685.50 168,480.98 0.04
M 2.2.1.2.f.(a) 1,562,930.32 62,517.21 0.01
8,619,048.43

Kg 2.2.6.1.b.(c) 19,417.75 1,516,914.63 0.32


M A.4.1.1.20 221,685.50 3,017,139.66 0.64
M 2.2.1.2.f.(a) 1,562,930.32 1,140,939.13 0.24
M 3.2.1.(c) 91,162.57 4,572,714.51 0.97
M 3.3.10.(c) 52,039.80 2,610,316.37 0.55
12,858,024.30

Kg 2.2.6.1.b.(c) 19,417.75 2,617,901.05 0.55


M A.4.1.1.21 232,857.75 1,467,003.83 0.31
M 2.2.1.2.f.(a) 1,562,930.32 843,982.37 0.18

Kg 2.2.6.1.b.(c) 19,417.75 2,604,891.16 0.55


M A.4.1.1.21 232,857.75 1,467,003.83 0.31
M 2.2.1.2.f.(a) 1,562,930.32 843,982.37 0.18
9,844,764.61

Kg 2.2.7.a.(a) 18,585.44 1,950,169.96 0.41


M A.4.1.1.22 244,127.75 1,538,004.83 0.33
M 2.2.1.2.f.(a) 1,562,930.32 1,406,637.29 0.30

Kg 2.2.7.a.(a) 18,585.44 1,950,169.96 0.41


M A.4.1.1.22 244,127.75 1,538,004.83 0.33
M 2.2.1.2.f.(a) 1,562,930.32 1,406,637.29 0.30
9,789,624.14

M - 200,000.00 12,000,000.00 2.54


M A.5.1.1.32 213,353.75 12,801,225.00 2.71
M A.5.1.1.27 36,995.50 2,219,730.00 0.47
M A.5.1.1.26 28,183.63 2,254,690.00 0.48
Unit - 1,000,000.00 1,000,000.00 0.21
Bh - 1,500,000.00 3,000,000.00 0.63
M A.5.1.1.26 28,183.63 1,409,181.25 0.30
Bh - 50,000.00 200,000.00 0.04
34,884,826.25
Rp 75,996,287.72
473,198,198.20 100.00
TIME SCHEDULE

JADWAL PELAKSANAAN

MINGGU 1 MINGGU 2 MINGGU 3 MINGGU 4 MINGGU 5

1.06
0.06

0.04
0.02
0.01

0.11
0.03
0.04
0.05
0.25
0.05
0.26

0.002 0.002 0.002 0.002 0.002


0.002 0.002 0.002 0.002 0.002
0.014 0.014 0.014 0.014 0.014
0.007 0.007 0.007 0.007 0.007

0.42 0.42

0.04

0.01
0.01
0.01

0.01
0.11

0.71 0.71
0.88
2.05 2.05

3.35
4.51

2.11
2.43
1.97 1.97 1.97
0.25
0.21
0.53

0.26
0.12
0.15
0.10
0.02
0.09
0.49
0.12
0.26
0.07

0.09
0.04
0.01

0.32
0.64
0.24
0.97
0.55
2.63 2.07 8.97 9.12 10.61
2.63 4.70 13.67 22.80 33.40
JADWAL PELAKSANAAN

MINGGU 6 MINGGU 7 MINGGU 8 MINGGU 9 MINGGU 10


0.002 0.002 0.002 0.002 0.002
0.002 0.002 0.002 0.002 0.002
0.014 0.014 0.014 0.014 0.014
0.007 0.007 0.007 0.007 0.007

0.42

0.88
1.06 1.06 1.06
1.67
3.04
2.44 2.44
4.93 4.93 4.93
3.35 3.35 3.35 3.35 3.35

1.86
3.59
0.61
1.84

0.63
0.53
0.55
0.31
0.18

0.55
0.31
0.18

0.41
0.33
0.30

0.41
0.33
0.30

2.54
2.71
0.47
0.48
0.21

9.84 15.56 16.62 19.25 4.12


43.24 58.80 75.42 94.67 98.79
KET.
MINGGU 11
0.002
0.002
0.014
0.007
0.21
0.63
0.30
0.04

1.21
100.00