Professional Documents
Culture Documents
2023 2024
1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7
NO DESCRIPTION P/A REMARKS
-1 -2 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
P - - - 5 5 5 9 22 33 33 26 7 6 4 - - - - -
a. EQUIPMENT
A - - - 6 21 29 35 - - - - - - - - - - - -
P 1 1 1 1 2 3 3 2 1 1 1 - - - - -
1 Foreman
A 1 3 3
P 2 2 2 4 9 14 14 11 3 3 2 - - - - -
2 Skilled Worker
A 4 13 14 17
P 1 1 1 1 4 5 5 4 1 1 1 - - - - -
3 Welder Support
A 1 1
P 1 1 1 3 7 11 11 9 2 1 - - - - - -
4 Unskilled Worker
A 2 7 11 14
P - - - 2 4 4 4 4 4 4 - - - - - -
d. FO TERMINATION
A
P - - - 2 4 4 4 4 4 4 - - - - - - Include at Sub Con
1 Skill FO Termination
A
P - - - - - - - - - - - - - - - - By KINDEN
e. ASSIST. COMMISSIONING
A
P
1 Assist. Commissioning
A
P - - - 10 10 17 17 17 17 17 17 18 17 17 15 13 13 - -
f. SUPPORTING MANPOWER
A - - - 11 19 31 36 - - - - - - - - - - - -
P 2 2 2 2 2 2 2 2 2 2 2 2 2 2
1 Rigger, Signalman
A 5 5 6 7
P 2 2 2 2 2 2 2 2 3 2 2 2 2 2
2 Matecon /Mat. Handling
A 2 2 2 3
P 1 1 2 2 2 2 2 2 2 2 2 2 2 2
3 F/M Maintenance & F/M Mat. Handling
A 1 2 2 2
P 1 1 2 2 2 2 2 2 2 2 2 2 2 2
4 Maintenance Helper
A 1 5 7 termasuk skill 2 mp
P 1 1 1 1 1 1 1 1 1 1 1 1 1 1
5 Tools & Consumable Keeper Helper
A 2 3 3 4
P 3 3 8 8 8 8 8 8 8 8 8 6 4 4
6 Cleaning/Time Keeper/Ptw/others
A 1 6 13 13
P - - 1 29 30 31 34 36 39 42 42 42 38 36 33 31 26 7 -
II INDIRECT MANPOWER
A - - 13 27 34 36 39 - - - - - - - - - - - -
P 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 Site Manager
A 1 1 1 1 1
P 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
2 Planning Engineer
A 1 1 1 2 2
P 1 1 1 1 1 1 1 1 1 1 1 1 1 1
3 Progress & Planning Staff
A 1 2 2 2 2
P 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
4 Electrical Site Engineer
A 1 1 1 1 1
P 1 2 3 3 3 3 3 3 3 3 3 3 3 1
5 Electrical Site Engineer Staff
A 1 1 1 1 YOYON
P 1 1 1 1 1 1 1 1 1 1 1 1 1 1
6 Chief Supervisor
A 1 1 1 1 1
P - 1 1 1 2 3 4 6 6 6 5 4 3 2 2 -
7 Construction Supervisor
A 1 2 5 6 7
P 1 1 1 1 1 1 1 1 1 1 1 1 1 1
8 PTW Supervisor
A 1 1 1 1 1
P 1 1 1 1 1 1 1 1 1 1 1 1 1 1
9 PTW Staff
A 1 1 1 1
P 1 1 1 1 1 1
10 Surveyor Supervisor
A 1 1 1 1
P 1 1 1 1 1 1
11 Surveyor Staff
A 1 1 1
P 1 1 1 2 2 3 4 4 4 3 3 2 2 1
12 First Aider
A 1 1 1 2
P 2 2 2 2 2 2 2 2 2 2 2 2 2 2 For CAMP
13 Security
A
P 1 1 1 1 1 1 1 1 1 1 1 1 1 1
14 QC Engineer/Coordinator
A 1 1 1 1
P 2 2 2 2 2 2 2 2 2 2 2 2 2 1
15 QC Admin
A 2 2 2 1
1 of 12
PT. WASA MITRA ENGINEERING
MSP C,D,E KINDEN LECTRICAL PROJECT ### 290
2023 2024
1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7
NO DESCRIPTION P/A REMARKS
-1 -2 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
P 1 1 1 1 1 1 1 1 1 - - -
16 Welding Inspector
A 1 1 1 1
P 1 1 1 2 3 4 6 6 6 5 4 3 2 2 1
17 QC Inspector
A 2
P 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
18 Document Control/Cable Record
A 1 2 2 3 2 CABLE RECORD/1 DOCUMENT
P 1 1 1 1 1 1 1 1 1 1 1 1 1 1
19 Material Control Staff
A 1 1 1
P 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
20 Finance & Administration Supervisor
A 1 1 1 1 1
P 1 1 1 1 1 1 1 1 1 1 1 1 1 1
21 Finance & Administration Staff
A 1 1 1 1
P 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
22 HRD
A 1 1 1 1
P 1 1 1 1 1 1 1 1 1 1 1 1 1 1
23 HRD Staff (Time Keeper)
A 1 2 2 2 2
P 1 1 1 1 1 1 1 1 1 1 1 1 1 1
24 Material Control & Handling Supervisor
A 1 1 1 1 1
P 1 1 1 1 1 1 1 1 1 1 1 1 1 1
25 Logistic
A 1 2 2 2 2 STAFF DAN LOGISTIK
P 1 1 1 1 1 1 1 1 1 1 1 1 1
26 Procurement
A 1 1 1
P 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
27 Office Boy / Girl
A 1 1 1 1 1
P
III ACCOMODATION
A
P 2 1 1
1 Rental House For Indirect Manpower
A 2 1 -
P 4 6 6 6 6 8 8 8 8 8 6 6 6 6 4 -
2 Maid Mess
A 2 4 6 6 6
P
IV TRANSPORTATION
A
P - 46,474 46,474 46,474 46,474 46,474 46,474 46,474 46,474 46,474 23,237 23,237 23,237 23,237 23,237 23,237 -
1 Vehicle For Indirect Manpower
A
P 2 2 2 2 2 2 2 2 2 1 1 1 1 1 1 -
1.1 Minibus
A 3 3 3 4 3 termasuk elf 1
P - 2 2 2 2 2 2 2 2 2 1 1 1 1 1 1 -
- Driver For Above
A 2 3 3 3 3
- 55,774 55,774 55,774 55,774 55,774 55,774 55,774 55,774 55,774 55,774 55,774 55,774 55,774 55,774 27,887 -
P 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 -
1.2 Microbus (Elf)
A 1 1 1 1
P - 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 -
- Driver For Above
A 1 1 1 1
P 1 1 1 2 2 3 4 4 4 3 3 2 2 1 -
2.1 Bus Cap. 56 Psn
A 1 3 4
P 1 1 1 2 2 3 4 4 4 3 3 2 2 1 - -
- Driver For Above
A 1 3 4
2 of 12
PT. BUMIMITRA ADIPERSADA
Head Office S-CURVE MSP ELECTRICAL WORK AREA C, D & E
Owner : PT Freeport Indonesia Location : Gresik, Jawa Timur Scope Of Work : Electrical Installation Work Area CDE SOP No. : SOP - C1.2
Main Contractor : PT. Chiyoda International Indonesia Quotation. No. : 013/BMAP/EXT/Q-S/IX/2022/Rev.8 Duration : 14 Months Document No. : F-C1.2-02
Subcontractor : PT. KINDEN Indonesia Estimated Start : February 2023 Revision : 01
Client : PT. Wasa Mitra Engineering Estimated Finish : March 2024 Date Effective : 01 October 2022
Total Rencana Progress P - 0.24% 0.29% 1.09% 2.79% 4.21% 5.19% 8.72% 10.03% 18.56% 19.47% 14.89% 9.45% 3.18% 1.88%
A
Akumulasi Total Rencana Progress P - 0.24% 0.53% 1.62% 4.41% 8.63% 13.82% 22.54% 32.57% 51.13% 70.60% 85.50% 94.95% 98.12% 100.0%
A
President Planning & Finance & Resources HSSE & QA/QC Finance & Resources Planning & Construction
Commissioner President Director Marketing Manager
Commissioner Construction Director Director Manager Manager Manager
PT. BUMIMITRA ADIPERSADA
Head Office S-CURVE
Owner #REF! Quotation. No. #REF! SOP No. : SOP - C1.2
Main Contractor #REF! Scope Of Work #REF! Document No. : F-C1.2-02
Subcontractor #REF! Duration #REF! Revision : 01
Client #REF! Estimated Start #REF! Date Effective : 01 October 2022
Location #REF! Estimated Finish #REF!
Total Rencana Progress P 0.00% 0.24% 0.29% 1.09% 2.79% 4.21% 5.19% 8.72% 10.03% 18.56% 19.47% 14.89% 9.45% 3.18% 1.88%
Akumulasi Total Rencana Progress P 0.00% 0.24% 0.53% 1.62% 4.41% 8.63% 13.82% 22.54% 32.57% 51.13% 70.60% 85.50% 94.95% 98.12% 100.00%
A
PT. BUMIMITRA ADIPERSADA
Head Office SCHEDULE MSP ELECTRICAL WORK AREA C, D & E
Owner : PT Freeport Indonesia Location : Gresik, Jawa Timur Scope Of Work : Electrical Installation Work Area CDE SOP No. : SOP - C1.2
Main Contractor : PT. Chiyoda International Indonesia Quotation. No. : 013/BMAP/EXT/Q-S/IX/2022/Rev.8 Duration : 14 Months Document No. : F-C1.2-02
Subcontractor : PT. KINDEN Indonesia Estimated Start : February 2023 Revision : 01
Client : PT. Wasa Mitra Engineering Estimated Finish : March 2024 Date Effective : 01 October 2022
QUANTITY 2023 2024
DESCRIPTION
BQ UNIT 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5
AREA
EQUIPMENT INSTALLATION AREA C 415.00 Sets - 5 6 10 10 16 16 16 12 5 5 - - - - - -
3600 (Utility) 86.00 Sets - - 6 5 5 5 - - - - - - - - - - -
3610 / 3610(U) 4.00 Sets
371N / 360A 82.00 Sets 6 5 5 5
4200 (Acid Plant) 90.00 Sets - - - - - 6 6 6 3 5 5 - - - - - -
371I / 420C 78.00 Sets 6 6 6
4210 6.00 Sets 3 5
4200 / 4200(U) 6.00 Sets 5
4870 (WWT & ETP) 148.00 Sets - - - - - - 10 10 9 - - - - - - - -
371H / 487C 138.00 Sets 10 10 9
4870 / 4870(U) 10.00 Sets
STG 21.00 Sets - 5 - - - - - - - - - - - - - - -
4880 / 4880 (U) 21.00 Sets 5
Interconnection 70.00 Sets - - - 5 5 5 - - - - - - - - - - -
371J 70.00 Sets 5 5 5
EQUIPMENT INSTALLATION AREA D 230.00 Sets - - - 3 8 17 17 7 - - - - - - - - -
4850 (Slag Concentrator) 185.00 Sets - - - 3 8 12 12 7 - - - - - - - - -
485A 21.00 Sets 3
485B 2.00 Sets
371K / 485E 124.00 Sets 8 7 7 7
371M / 485F 38.00 Sets 5 5
5970 (Jetty & Wharf) 45.00 Sets - - - - - 5 5 - - - - - - - - - -
371P / 597E 27.00 Sets 5
597A 12.00 Sets 5
597C 4.00 Sets
597D 2.00 Sets
EQUIPMENT INSTALLATION AREA E 26.00 Sets - - - - - - - - 2 - - - - - - - -
4810 (Raw Material Handling) 26.00 Sets - - - - - - - - 2 - - - - - - - -
481A 10.00 Sets 2
481B 10.00 Sets
481C 6.00 Sets
CABLE PULLING AREA C 473,290.94 Meter - - - - - - 20 30 30 97 105 52 37 17 17 - -
3600 (Utility) 50,177.39 Meter - - - - - - - 30 30 - - - - - - - -
3610 / 3610(U) 27,255.00 Meter 10 10
371N / 360A 22,922.39 Meter 20 20
4200 (Acid Plant) 157,721.35 Meter - - - - - - - - - - 26 52 37 17 17 - -
371I / 420C 34,040.75 Meter 10 20 20
4210 21,044.62 Meter 15
4200 / 4200(U) 102,635.98 Meter 16 17 17 17 17
4870 (WWT & ETP) 212,194.64 Meter - - - - - - - - - 83 67 - - - - - -
371H / 487C 15,803.39 Meter 16
4870 / 4870(U) 196,391.25 Meter 67 67
STG 33,081.32 Meter - - - - - - - - - 14 12 - - - - - -
4880 / 4880 (U) 33,081.32 Meter 14 12
Interconnection 20,116.23 Meter - - - - - - 20 - - - - - - - - - -
371J 20,116.23 Meter 20
CABLE PULLING AREA D 482,086.00 Meter - - - 10 28 43 43 49 47 65 61 57 18 - - - -
3000 (Common/General) 35,829.22 Meter - - - - 13 13 - - - - - - - - - - -
3000 35,829.22 Meter 13 13
4850 (Slag Concentrator) 256,177.95 Meter - - - - - - 13 22 22 38 49 45 18 - - - -
485A / 485A(U) 186,945.83 Meter 22 22 22 22 18 18
485B / 485B(U) 22,025.59 Meter 13
371K / 485E 31,168.75 Meter 16 11 11
371M / 485F 16,037.77 Meter 16 16
4250 (Acid Storage / Load Out) 16,173.00 Meter - - - - - - - - - 12 - - - - - - -
4250 16,173.00 Meter 12
5970 (Jetty & Wharf) 173,905.83 Meter - - - 10 15 30 30 27 25 15 12 12 - - - - -
371P / 597E 13,200.00 Meter 10
597A / 597A(U) 26,401.41 Meter 10 9
597B / 597B(U) 87,670.68 Meter 15 15 12 12
597C 9,310.05 Meter 6
597D 37,323.70 Meter 30 30 27
CABLE PULLING AREA E 176,988.94 Meter - - - - - - - - 25 24 24 13 13 13 12 - -
4810 (Raw Material Handling) 176,988.94 Meter - - - - - - - - 25 24 24 13 13 13 12 - -
481A / 481A(U) 26,350.46 Meter 9 9
481B / 481B(U) 88,092.51 Meter 12 13 13 13 12
481C / 481C(U) 62,545.98 Meter 16 15 12
TERMINATION AREA C 28,355.00 Sets - - - - - - - 22 29 137 93 74 63 22 - - -
3600 (Utility) 2,757.00 Sets - - - - - - - - 29 29 5 5 - - - - -
371N / 360A 940.00 Sets 24 24
3610 / 3610(U) 1,817.00 Sets 5 5 5 5
4200 (Acid Plant) 7,700.00 Sets - - - - - - - - - - - 58 63 22 - - -
371I / 420C 1,189.00 Sets 33 33
4200 / 4200(U) 5,063.00 Sets 18 22 22
4210 1,448.00 Sets 7 8
4870 (WWT & ETP) 16,447.00 Sets - - - - - - - - - 108 77 - - - - - -
371H / 487C 1,132.00 Sets 31
4870 / 4870(U) 15,315.00 Sets 77 77
STG 662.00 Sets - - - - - - - - - - 11 11 - - - - -
4880 / 4880 (U) 662.00 Sets 11 11
Interconnection 789.00 Sets - - - - - - - 22 - - - - - - - - -
371J 789.00 Sets 22
TERMINATION AREA D 20,207.00 Sets - - - - 13 13 14 21 28 28 78 79 29 4 - - -
3000 (Common/General) 2,139.00 Sets - - - - - 9 7 7 5 - - - - - - - -
3000 2,139.00 Sets 9 7 7 5
4850 (Slag Concentrator) 12,522.00 Sets - - - - - - - 5 20 21 70 70 21 - - - -
485A / 485A(U) 9,570.00 Sets 16 21 21 21 21
485B / 485B(U) 852.00 Sets 5 4
371K / 485E 1,291.00 Sets 25 26
371M / 485F 809.00 Sets 24 23
4250 (Acid Storage / Load Out) 1,788.00 Sets - - - - - - - - - - 4 5 5 4 - - -
4250 1,788.00 Sets 4 5 5 4
5970 (Jetty & Wharf) 3,758.00 Sets - - - - 13 4 7 9 3 7 4 4 3 - - - -
371P / 597E 397.00 Sets 2 3 3
597A / 597A(U) 958.00 Sets 13
597B / 597B(U) 1,413.00 Sets 4 4 4 3
597C 433.00 Sets 4
597D 557.00 Sets 7 7
TERMINATION AREA E 6,239.00 Sets - - - - - - - - - 10 19 19 19 11 11 - -
4810 (Raw Material Handling) 6,239.00 Sets - - - - - - - - - 10 19 19 19 11 11 - -
481A / 481A(U) 1,398.00 Sets 5 5 5 5
481B / 481B(U) 3,387.00 Sets 9 9 9 11 11
481C / 481C(U) 1,454.00 Sets 5 5 5 5
TERMINATION FO AREA C 3,512.00 Core - - - - - - - 2 2 - - 3 3 - - - -
3600 (Utility) 744.00 Core - - - - - - - - 2 - - - - - - - -
371N / 360A 744.00 Core 2
4200 (Acid Plant) 1,184.00 Core - - - - - - - - - - - 3 3 - - - -
371I / 420C 768.00 Core 3 3
4210 200.00 Core
4200 / 4200(U) 216.00 Core
4870 (WWT & ETP) 896.00 Core - - - - - - - 2 - - - - - - - - -
371H / 487C 616.00 Core 2
4870 / 4870(U) 280.00 Core
STG 400.00 Core - - - - - - - - - - - - - - - - -
4880 / 4880 (U) 400.00 Core
Interconnection 288.00 Core - - - - - - - - - - - - - - - - -
371J 288.00 Core
Page 5 of 12
PT. BUMIMITRA ADIPERSADA
Head Office SCHEDULE MSP ELECTRICAL WORK AREA C, D & E
Owner : PT Freeport Indonesia Location : Gresik, Jawa Timur Scope Of Work : Electrical Installation Work Area CDE SOP No. : SOP - C1.2
Main Contractor : PT. Chiyoda International Indonesia Quotation. No. : 013/BMAP/EXT/Q-S/IX/2022/Rev.8 Duration : 14 Months Document No. : F-C1.2-02
Subcontractor : PT. KINDEN Indonesia Estimated Start : February 2023 Revision : 01
Client : PT. Wasa Mitra Engineering Estimated Finish : March 2024 Date Effective : 01 October 2022
QUANTITY 2023 2024
DESCRIPTION
BQ UNIT 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5
371J 288.00 Core
Page 6 of 12
PT. BUMIMITRA ADIPERSADA
Head Office SCHEDULE MSP ELECTRICAL WORK AREA C, D & E
Owner : PT Freeport Indonesia Location : Gresik, Jawa Timur Scope Of Work : Electrical Installation Work Area CDE SOP No. : SOP - C1.2
Main Contractor : PT. Chiyoda International Indonesia Quotation. No. : 013/BMAP/EXT/Q-S/IX/2022/Rev.8 Duration : 14 Months Document No. : F-C1.2-02
Subcontractor : PT. KINDEN Indonesia Estimated Start : February 2023 Revision : 01
Client : PT. Wasa Mitra Engineering Estimated Finish : March 2024 Date Effective : 01 October 2022
QUANTITY 2023 2024
DESCRIPTION
BQ UNIT 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5
TERMINATION FO AREA D 5,234.00 Core - - - - - - - 4 4 4 - - - - - - -
3000 (Common/General) 16.00 Core - - - - - - - - - - - - - - - - -
3000 16.00 Core
4850 (Slag Concentrator) 2,642.00 Core - - - - - - - 4 4 - - - - - - - -
485A / 485A(U) 1,658.00 Core 4
485B / 485B(U) 48.00 Core 4
371K / 485E 624.00 Core
371M / 485F 312.00 Core
5970 (Jetty & Wharf) 2,576.00 Core - - - - - - - - - 4 - - - - - - -
371P / 597E 360.00 Core
597A / 597A(U) 612.00 Core
597B / 597B(U) 1,452.00 Core 4
597C 64.00 Core
597D 88.00 Core
TERMINATION FO AREA E 1,746.00 Core - - - - - - - - - - 4 - - - - - -
4810 (Raw Material Handling) 1,746.00 Core - - - - - - - - - - 4 - - - - - -
481A / 481A(U) 20.00 Core
481B / 481B(U) 1,466.00 Core 4
481C / 481C(U) 260.00 Core
Page 7 of 12
SCHEDULE WORK
2022 2023 2024
ACTIVITY NAME
11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5
AREA Cal MDS Sum Mds
EQUIPMENT C 2,622.63 2,626.00 - - - 5 6 10 10 16 16 16 12 5 5 - - - - - -
3600 (Utility) 567.60 546.00 - - - - 6 5 5 5 - - - - - - - - - - -
3610 / 3610(U) 6.88 -
597D 4.00 -
EQUIPMENT E 39.63 52.00 - - - - - - - - - - 2 - - - - - - - -
4810 (Raw Material Handling) 39.63 52.00
Page 8 of 12
2022 2023 2024
ACTIVITY NAME
11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5
4810 (Raw Material Handling) 39.63 52.00 - - - - - - - - - - 2 - - - - - - - -
481A 15.50 52.00 2
481B 15.50 -
481C 8.63 -
CABLE PULLING C 10,530.65 10,530.00 - - - - - - - - 20 30 30 97 105 52 37 17 17 - -
3600 (Utility) 1,546.02 1,560.00 - - - - - - - - - 30 30 - - - - - - - -
3610 / 3610(U) 490.39 520.00 10 10
371N / 360A 1,055.63 1,040.00 20 20
4200 (Acid Plant) 3,874.54 3,874.00 - - - - - - - - - - - - 26 52 37 17 17 - -
371I / 420C 1,290.98 1,300.00 10 20 20
4210 392.13 390.00 15
4200 / 4200(U) 2,191.43 2,184.00 16 17 17 17 17
4870 (WWT & ETP) 3,903.29 3,900.00 - - - - - - - - - - - 83 67 - - - - - -
371H / 487C 417.35 416.00 16
4870 / 4870(U) 3,485.94 3,484.00 67 67
STG 689.99 676.00 - - - - - - - - - - - 14 12 - - - - - -
4880 / 4880 (U) 689.99 676.00 14 12
Interconnection 516.81 520.00 - - - - - - - - 20 - - - - - - - - - -
371J 516.81 520.00 20
CABLE PULLING D 10,952.58 10,946.00 - - - - - 10 28 43 43 49 47 65 61 57 18 - - - -
3000 (Common/General) 664.91 676.00 - - - - - - 13 13 - - - - - - - - - - -
3000 664.91 676.00 13 13
4850 (Slag Concentrator) 5,478.50 5,382.00 - - - - - - - - 13 22 22 38 49 45 18 - - - -
485A / 485A(U) 3,221.27 3,224.00 22 22 22 22 18 18
485B / 485B(U) 357.08 338.00 13
371K / 485E 1,048.49 988.00 16 11 11
STG 26.93 - - - - - - - - - - - - - - - - - - - -
4880 / 4880 (U) 26.93 -
Interconnection 19.30 - - - - - - - - - - - - - - - - - - - -
371J 19.30 -
TERMINATION FO D 327.13 312.00
Page 11 of 12
2022 2023 2024
ACTIVITY NAME
11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5
TERMINATION FO D 327.13 312.00 - - - - - - - - - 4 4 4 - - - - - - -
3000 (Common/General) 1.00 - - - - - - - - - - - - - - - - - - - -
3000 1.00 -
597D 5.50 -
TERMINATION FO E 109.13 104.00 - - - - - - - - - - - - 4 - - - - - -
4810 (Raw Material Handling) 109.13 104.00 - - - - - - - - - - - - 4 - - - - - -
481A / 481A(U) 1.25 -
Page 12 of 12