You are on page 1of 2

Unit#1 BOILERHOT FLUSHING LIGHT UP POST OVERHAULING: Time Period-16 Hrs

FINAL LIGHT UP, STEAM DUMPING, SOAKING & SYNCHRONISATION Time- 10 Hrs.

Schedule

Box Up, Interlock Protection checks. SLC Loop Check, DC Back Up Checks on 23 rd Sept to 24th
Sept Up to 4 PM.

1. Slow Firing Start up: 24th Sept : 04 to 07 PM


2. Final Light up: 11 am to 12 PM.
3. Steam Dumping, Rolling, Soaking & Synchronization: 9 pm to 10 PM

SL. No. Activities Start Total


Start Date End Date End Time Emission Level (Stack)
Time Duration Remarks
HOT ALKALI
FLUSHING OF 6~8 10 AM~ Visible 06 Hrs in Coordination
1 24.09.23 25.09.23 16 Hrs
BOILER (Slow Oil PM 12 PM Range Day Time with EHS
Firing)
BOILER LIGHT UP
FINAL ( Rapid Oil 11~12 Till Synch. 06 Hrs in Coordination
2 25.09.23 25.09.24 08 Hrs High
Firing ) PM & ESP ON Day Time with EHS

STEAM DUMPING,
TURBINE ROLLING, 20:00 Coordination
3 25.09.23 25.09.25 11 PM 03 Hrs. High Night Time
SOAKING & SYNC PM with EHS
(Oil & Coal firing)
00:00 During Coordination
4 SABILIZATION 26.09.23 26.09.23 03:00 Hrs 02 Hrs. High with EHS
Hrs Night

OBJECTIVE OF HOT FLUSHING:-

To remove oil, grease and other welding impurities adhering to the interior evaporative
surface of pressure parts of theBoilerIt will be carried out at drum pressures of 10-20 kg/cm2.

COMPLETION CRITERIA:

Hot flushing would be considered complete when MS parameters will be SiO2 < 30 ppb and Fe
< 50 ppb.

ACTIVITY DESCRIPTION:

The system will be flushed continuouslyby filling and draining DM water. Ammonia will be added
in the drum to maintain pH. CBD and MS sample will be tested on hourly basis till the
Parameters meet the value for turbine rolling criteria (mentioned above).After achieving the MS
criteria, clearance for turbine rolling will be given.

Consumption of Chemical, Water, and Expected Criteria to be achieved during Unit-1 hot
flushing (As per reference to Unit # 2 hot flushing last year):-

Detail of Chemicals required


Ammonia: 23 liters
Hydrazine: 30 liters
Water: 1000 cubic meters approx.
Time required for completing the process 16.00 hours.

CRITERIA TO BE ACHIEVED THROUGH HOT FLUSHING:-

Chemical Criteria (Achieved in Unit 2 last Year)


Sample Parameter Rolling Criteria Actual (attained)
Main Steam SiO2 < 30 ppb < 28 ppb
Fe < 50 ppb < 39 ppb

Target of Chemical Criteria to be achieved in Unit 1


Sample Parameter Rolling Criteria Actual
Main Steam SiO2 < 30 ppb < ppb
Fe < 50 ppb < ppb