FINAL LIGHT UP, STEAM DUMPING, SOAKING & SYNCHRONISATION Time- 10 Hrs.
Schedule
Box Up, Interlock Protection checks. SLC Loop Check, DC Back Up Checks on 23 rd Sept to 24th
Sept Up to 4 PM.
STEAM DUMPING,
TURBINE ROLLING, 20:00 Coordination
3 25.09.23 25.09.25 11 PM 03 Hrs. High Night Time
SOAKING & SYNC PM with EHS
(Oil & Coal firing)
00:00 During Coordination
4 SABILIZATION 26.09.23 26.09.23 03:00 Hrs 02 Hrs. High with EHS
Hrs Night
To remove oil, grease and other welding impurities adhering to the interior evaporative
surface of pressure parts of theBoilerIt will be carried out at drum pressures of 10-20 kg/cm2.
COMPLETION CRITERIA:
Hot flushing would be considered complete when MS parameters will be SiO2 < 30 ppb and Fe
< 50 ppb.
ACTIVITY DESCRIPTION:
The system will be flushed continuouslyby filling and draining DM water. Ammonia will be added
in the drum to maintain pH. CBD and MS sample will be tested on hourly basis till the
Parameters meet the value for turbine rolling criteria (mentioned above).After achieving the MS
criteria, clearance for turbine rolling will be given.
Consumption of Chemical, Water, and Expected Criteria to be achieved during Unit-1 hot
flushing (As per reference to Unit # 2 hot flushing last year):-