You are on page 1of 15

Journal of Building Engineering 41 (2021) 102705

Contents lists available at ScienceDirect

Journal of Building Engineering


journal homepage: www.elsevier.com/locate/jobe

Prefabricated versus conventional construction: Comparing life-cycle


impacts of alternative structural materials
V. Tavares a, *, N. Soares a, N. Raposo b, P. Marques a, F. Freire a
a
University of Coimbra, ADAI, Department of Mechanical Engineering, Portugal
b
Department of Civil Engineering, Polytechnic Institute of Viseu, Viseu, Portugal

A R T I C L E I N F O A B S T R A C T

Keywords: Prefabrication can have advantages in terms of materials and time efficiency, but the overall environmental and
Life cycle assessment (LCA) cost trade-offs between the two construction methods are unclear and influenced by the choice of the structural
Life cycle costing (LCC) material. A life cycle assessment was carried out to compare two constructive systems (prefabrication and
Light steel framing (LSF)
conventional) and different structural materials for a single-family house. Impacts, waste, costs, and production
Wood framing (WF)
Reinforced concrete (RC)
time were assessed for two prefabricated construction systems – lightweight steel frame (LSF) and wooden frame
Construction and demolition waste (CDW) (WF) – and two conventional construction systems – reinforced concrete (RC1) with a single layer concrete block
or with a double-layer brick external wall (RC2). Results showed that WF has the lowest impacts followed by LSF,
and that embodied impacts can represent more than half of total impacts. Prefabricated houses have up to 65%
less embodied impacts, and end-of-life impacts of prefabricated LSF are lower due to recycling; thus, unveiling
the importance of embodied and end-of-life phases. Prefabrication can decrease impacts, materials consumption,
and waste generation, pushing forward circularity within the construction sector.

different uses with minimal waste production. At the end-of-life (EoL),


buildings can be entirely disassembled, enabling the separation of ma­
1. Introduction terials that can be reused or recycled [9], the reuse of modules or
components [10], or even the relocation of a whole building [11].
In Europe, buildings are responsible for about one-third of CO2 However, prefabrication may also pose some challenges such as more
emissions and waste generated, 40% of energy consumption, and half of complex logistics and transport constraints, package- and
materials extraction [1]. The reduction of residential building impacts is transport-related burdens, and higher implementation cost. The reduc­
one of the key targets identified by the European Union (EU) to meet the tion of impacts and costs of buildings through prefabrication adoption
Paris agreement targets and progress towards a circular economy. A must be assessed to support environmentally sustainable policy-making
more holistic approach using life cycle assessment has been proposed to towards energy-efficient and low carbon buildings. Costs and environ­
assess buildings considering not only energy efficiency but also mental tradeoffs between prefabricated and conventional construction
embodied impacts and resources conservation [2]. methods had not been comprehensively quantified and balanced in
Buildings prefabrication is an industrialized process based on the off- previous cradle-to-grave LC assessment, which is the main research gap
site production and pre-assembly of components that afterward will be this article intends to fulfill.
transported to the site to be fully assembled [3]. Prefabrication can be The research questions we intend to answer are: “Can prefabrication
used as an alternative to conventional construction for residential reduce house impacts and costs? Which structural materials should be used
buildings, but its adoption is not consistent and relies on several con­ and under what conditions?” The main goal of this paper is to assess the
ditions [4]. The key benefits of prefabrication are materials use and life cycle environmental impacts, costs, waste, and production time of
waste reduction, shorten construction cost and time, increase in safety two constructive systems (prefabrication and conventional) and
and product quality, growth of productivity, and improved buildings different structural materials for a single-family house. Two pre­
performance [5–8]. By being a dry construction system, prefabricated fabricated construction systems with lightweight steel frame (LSF) and
buildings can be partially disassembled during use-phase, allowing wooden frame (WF) were compared with two conventional construction
maintenance works or the reconfiguration of the inner space, enabling

* Corresponding author.
E-mail address: vanessa.tavares@dem.uc.pt (V. Tavares).

https://doi.org/10.1016/j.jobe.2021.102705
Received 27 October 2020; Received in revised form 18 March 2021; Accepted 8 May 2021
Available online 24 May 2021
2352-7102/© 2021 Elsevier Ltd. All rights reserved.
V. Tavares et al. Journal of Building Engineering 41 (2021) 102705

buildings with steel structure followed by wood, with prefabricated


Abbreviations concrete buildings being the least frequent. The majority of the case
studies are single-family houses at a specific location, though educa­
AC - Acidification tional, industrial, and commercial buildings can also be found. Some
AD - Abiotic depletion studies consider only materials and activities that differ from conven­
ADFF - Abiotic depletion (fossil fuels) tional ones [17] or that are used during the transformation of a
CED - Cumulative energy demand ship-container into a house (excluding the container itself) [18,19];
CDW - Construction and demolition waste while others have a more comprehensive approach.
EoL - End-of-life Differences in case studies, boundaries, and assumptions have led to
GW - Global warming a wide range of results. The sensitivity of results to transportation dis­
LCA - Life cycle assessment tance, level of prefabrication, and materials has already been analyzed
LCC - Life cycle costing [20]. For prefabricated buildings, embodied carbon range between 193
LSF - Light steel framing and 852 kgCO2eq/m2; operational carbon 10.8–20.5 kgCO2eq/m2 per
NRE - Non-renewable energy year, and end-of-life carbon -228– (-0.17) kgCO2eq/m2; embodied en­
WF - Wood framing ergy range 1.74–10.38 GJ/m2, operational energy 0.38–1.37 GJ/m2 per
RC - Reinforced concrete year, and end-of-life energy -1.7–0.14 GJ/m2. In the few studies
OD - Ozone layer depletion comparing prefabricated with conventional buildings, results show that
PO - Photochemical oxidation prefabrication reduces 5–40% of impacts, being this reduction more
EU - Eutrophication relevant in the embodied phase. Compared with conventional, pre­
fabricated buildings reduce GHG emissions [17,21], energy use,
resource depletion, and health and ecosystem damage [22]. While
reducing embodied and operational carbon [21,23], prefabrication can
systems: reinforced concrete with a single layer concrete block (RC1) cost roughly 30% less than conventional construction [24]. Pre­
and reinforced concrete with a double-layer brick external wall (RC2). fabricated concrete and wood schools have less CO2 emissions than
This paper presents a comprehensive LC and cost assessment of the two conventional schools; and prefabricated steel schools slightly more (due
most frequently used prefabrication construction system (LSF and WF) to transport-related impacts, the remote factory, and the transport of
and draws a comparison with conventional construction, in a multi- finished modules) [25]. In a study comparing LSF construction with
disciplinary research intersecting environmental impacts, construc­ reinforced concrete [26], LSF showed a reduction in respiratory in­
tion, buildings design and production, waste reduction and organics, global warming, and non-renewable energy. At the end-of-life,
management. prefabricated steel and wood buildings present higher recyclability rates
than prefabricated concrete and non-prefabricated buildings [25].
The LCA literature of buildings has shown that prefabrication can
1.1. Background
reduce costs and impacts. However, most papers present incomplete
assessments (e.g., excluding EoL), mainly focusing on reducing use
Life Cycle Assessment (LCA) quantifies environmental impacts and
phase impacts [27] even though prefabrication presents an opportunity
identifies improvement opportunities during the life-cycle of products:
to further reduce buildings burdens by reducing embodied and
from the early beginning (the cradle) all through the end-of-life (the
end-of-life impacts [28]. Moreover, previous works fail to capture the
grave) [12]. LCA has been applied since the 1970s [13], although the
differences between prefabrication and conventional construction in
first papers focusing on buildings were published only in the 1990s [14],
terms of production time, materials used, and waste generated.
with two of them focusing on prefabricated buildings [15,16]. Since
This works responds to the following research gaps: 1) comprehen­
then, some studies focused on prefabricated buildings, but few made a
sive assessments and the comparison between prefabrication and con­
comparison with conventional buildings, with limitations, as detailed in
ventional construction are scarce and fail to capture the differences
the next paragraphs.
between both approaches (not only in the environmental impacts but
Table 1 presents an overview of LCA studies for prefabricated
also in costs, production time, materials used, and waste generated); 2)
buildings with different structural materials, showing energy and carbon
most LCA exclude end-of-life, referring to it as an insignificant phase and
impacts (divided into embodied, operational, and end-of-life). The few
missing the opportunity (or the challenge) in waste management; 3)
studies with a comparison with conventional buildings are also
most studies focus solely on environmental impacts or costs ignoring
included. Most of the studies have been performed for prefabricated

Fig. 1. System boundary of prefabricated and conventional construction.

2
V. Tavares et al. Journal of Building Engineering 41 (2021) 102705

Table 1
Prefabricated and conventional buildings:(a) embodied, (b) operational, and (c) end-of-life energy and carbon emissions.
Prefabricated Conventional

Ref. Location Typology Energy Carbon Energy Carbon

a) Embodied energy and carbon emissions GJ/m2 kgCO2eq/m2 GJ/m2 kgCO2eq/m2

STEEL
[25] Spain Educational – 852 – –
[29] Australia Residential 14.4 864 – –
[30] Italy Industrial 3.5–6.8 246–459 – –
[24] Turkey Residential 3.2–4.1 – – –
[31] Australia Residential 3–3.3 212–217 – –
[18] Iran Containers 2.4–4.2 – – –
[26] Italy Containers 1.0a 63a – –
[32] Various Residential 7.5–10.4 454–647 – –
[33] Canada Containers 3.1–3.8 222–286 – –
[34] Italy Residential 5.5a 371a – –
WOOD
[16] Sweden Residential 2.9–3.7 – – –
[25] Spain Educational – 526 – –
[35] UK Residential 5.7–7.7 405–535 – –
[17] USA Residential – 62–89b – 65–156b
[29] Australia Residential 10.5 630 – –
[36] Germany Residential 2.1 207 – –
[33] Canada Residential 3.0–3.6 185–248 – –
[37] Slovenia Residential 5.5–8.4 26–162 – –
[38] USA Residential 3.4 327–333 – –
CONCRETE
[25] Spain Educational – 692 – 752
[29] Australia Residential 9.6 578 – –
[39] China Residential – 337 – 348
[22] China Residential – 193 – 215
[18] Iran Containers 1.8–3.0 – – –
[26] Italy Containers – – 0.76 47
[40] China Residential – 418–480 – –
[20] China Commercial – 406–448 – 447–489
[38] USA Residential 3.7 450 – –

b) Operational energy and carbon emissions (in Southern Europe) GJ/m2ay kgCO2eq/m2ay GJ/m2ay kgCO2eq/m2ay

STEEL
[25] Spain Educational – 12.2 – –
[41] Portugal Residential – – 0.03–0.04
[24] Turkey Residential 1–1.4 – – –
[26] Italy Containers 0.4 20.5 – –
WOOD
[42] France Residential – – 0.12 –
[25] Spain Educational – 11.6 – –
[43] France Residential – – 0.1–0.58 –
[37] Slovenia Residential 0.88–0.91 43.2–45.8 – –
CONCRETE
[25] Spain Educational – 10.8 – 12.2
[26] Italy Residential – – 0.43 23.07

c) End-of-life energy and carbon emissions GJ/m2 kgCO2eq/m2 GJ/m2 kgCO2eq/m2

STEEL
[29] Australia Residential -11.70 – –
[30] Italy Industrial -0.02− (-0.017) -0.26− (-0.17) – –
[31] Australia Residential -0.07− (-0.14) -52.90− (-25.61) – –
[26] Italy Containers -1.65a -227.69a -1.72 -193.08
[33] Canada Containers 0.13–0.20 8.4–12.6
[34] Italy Residential -0.85a -114.6a – –
WOOD
[16] Sweden Residential 0.10–0.14 – – –
[29] Australia Residential -7.20 – – –
[36] Germany Residential -0.02 -1.30 – –
[33] Canada Residential 0.13–0.20 2.97–3.60 – –
[37] Slovenia Residential 0.20–0.45 51.1–105.4 – –
CONCRETE
[29] Australia Residential -3.10 – – –
a
Light steel frame.
b
Only considered the building materials whose amounts differed between construction methods.

3
V. Tavares et al. Journal of Building Engineering 41 (2021) 102705

Fig. 2. Picture, 3D views, floor plan, and elevations of the single-story house.

that, to be fully implemented, both costs and impacts have to be mini­ materials extraction and transformation, use phase, and end-of-life
mized. This paper presents a comprehensive life cycle and cost assess­ waste treatment, mainly based on market data and the Ecoinvent 3.
ment that unveils the environmental impacts and costs trade-offs by The use phase is part of the background, with similar energy con­
performing a complete life cycle (LC) comparing conventional and sumption assumed for the construction alternatives. An appropriate
prefabrication, an innovative production approach, using less materials, design of the alternatives (thermal transmittance, users’ profile, and
and producing less waste. HVAC system) was performed to assure a similar use performance, not
dependent on the construction method.
2. Material and methods Bill of materials, time, waste rates, and production costs were
directly collected from the company producing prefabricated houses and
The research framework implemented for this article is based on the designers to construct the inventory. Current costs were considered to
LCA ISO 14040 standards [44] which is organized into four phases: Goal assess the end-of-life stage. Further information on costs can be found in
and Scope Definition, Inventory Analysis, Impact Assessment and Appendix B, Table B.2 Two Life Cycle Impact Assessment (LCIA)
Interpretation, extended to address costs and production time to respond methods, CML and Cumulative Energy Demand (CED), have been used
to the research questions (summarized in Figure A.1 Research frame­ to calculate the following impacts: Abiotic depletion (AD), Abiotic
work, Appendix A). depletion (fossil fuels) (ADFF), Global warming (GW), Ozone layer
depletion (OD), Photochemical oxidation (PO), Acidification (AC),
2.1. Goal and scope Eutrophication (EU) (from CML 2001 baseline), and Non-renewable
energy (NRE) (from CED). These categories were commonly used in
A life cycle model and inventory were developed and implemented previous studies and are used in the environmental product declaration
for alternative construction systems of a single-family house. The main (EPD) of building materials. The environmental impacts calculations
goal is to assess the embodied and end-of-life phases of the two con­ were performed using the SimaPro V8.0 software and Ecoinvent data­
struction methods (prefabricated and conventional) with different base version 3. The system model approach considered was Allocation at
structural materials (steel, wood, and concrete). the Point of Substitution (APOS), “the attributional approach in which
Fig. 1 shows the system boundary. The foreground includes prefab­ burdens are attributed proportionally to specific processes, including the
rication and construction, and disassembly and demolition. Primary treatment of waste allocated by aggregated activity” [45].
data was collected directly from building companies or experts (further Fig. 2 presents the house, a one-story house built in Portugal (warm-
information on Appendix B, Table B.1). The background includes raw summer Mediterranean climate) with 125 m2 living area (3.2 m story

4
V. Tavares et al. Journal of Building Engineering 41 (2021) 102705

Fig. 3. The single-family house building process with the LSF construction.

Fig. 4. Cross-section of the roof and the external wall of the prefabricated (LSF and WF) and conventional (RC1 and RC2) construction (not to scale).

5
V. Tavares et al. Journal of Building Engineering 41 (2021) 102705

Table 2
Life cycle inventory for the prefabricated (LSF and WF) and conventional (RC1 and RC2) alternatives.
Life cycle phase LSF WF RC1/RC2 Life cycle phase LSF WF RC1/RC2

1. MATERIALS 51231 46602 260575a 2. OFFSITE PREFABRICATION


(kg) /260247b
Foundations Transport
(kg)
Concrete 12480 12480 17885 Materials (tkm) 40287 26008 -
Reinforcing steel 385 385 577 Workers (pkm) 2800 2800 -
Formwork wood 244 244 412 Waste (tkm) 13 14 -
Polyethylene 9 9 9 Prefabrication
Floor (kg) Labor (h) 672 672 -
Cold-formed 308 – – Electricity (kWh) 240 240 -
Steel
Structural wood – 435 – Water (l) 65 65 -
Concrete – – 4570 Production waste (kg) 265 289 -
Reinforcing steel – – 343
Oriented strand 364 364 – 3. ONSITE ASSEMBLY/CONSTRUCTION
board
Formwork wood – – 429 Transport
Concrete vaults – – 2138 Modules to site (tkm) 825 664 –
Concrete beams – – 6942 Materials (tkm) 3893 3822 240655a/240639b
Aluminum – 48 – Workers to site (pkm) 8067 12833 20167
Internal wall Waste (tkm) 65 67 482a/406b
(kg)
Cold-formed 1129 – – Assemblage/construction
steel
Structural wood – 205 – Labor (h) 2112 2816 7040
Concrete – – 2990 Electricity (kWh) 3000 3000 6000
Reinforcing steel – – 312 Water (l) 150 150 300
Formwork wood – – 411 Construction waste (kg) 2590 2697 18496a/17893b
Gypsum board 1920 1920 –
Ceramic bricks – – 22500 4. USE PHASE (50 years)
Plaster – – 3900 Electricity (MWh) 340–680 340–680 340–680
Steel connectors – 49 – Water (ton) 10950 10950 10950
Roof (kg)
Cold-formed 4058 – – 5. DISASSEMBLY/DEMOLITION
steel
Structural wood – 4450 – Transport
Concrete – – 33528 Workers (pkm) 133 133 67
Reinforcing steel – – 2231 Deconstruction/demolition
Formwork wood – – 2157 Labor (h) 1232 1232 616
Concrete vaults – – 16980 Electricity (kWh) 1000 1000 500
Concrete beams – – 53716 Water (l) 50 50 50
Oriented strand 3120 3120 – Demolition waste (kg)
board
Ceramic tiles 4000 4000 4000 Insulation materials 3454 2115 2287a/2071b
Polyester 30 30 30 Mixture concrete & bricks – – 97942a/41386b
Polyethylene 30 30 – Bricks – – 20925a/82073b
foam
Mineral wool 1800 960 1200 Concrete 11856 11856 72079
Gypsum board 4000 4000 4000 Tiles & ceramics 3800 3800 3800
Aluminum – 97 – Wood 7794 13390 1148
External wall Aluminum – 145 –
(kg)
Thermal – – 61850a Iron and steel 9725 588 53893
concrete block
Bricks – – 61750b Gypsum-based 7357 7357 9852
Gypsum board 1824 1824 – Mixed CDW 4655 4655 4655
Granite 4900 4900 4900
Plaster – – 2470 6. WASTE TREATMENT
Mineral wool 1710 1140 1140a/912b Transport (tkm)
Cold-formed 4056 – – Demolition waste 1216 1098 5422a/5531b
steel
Structural wood – 863 – Waste treatment (kg)
Concrete – – 6101 Recycled 17348 13142 74572a/103286b
Reinforcing steel – – 636 Landfilled 23499 23899 165485a/136844b
Oriented strand 3458 3458 – Incinerated 7794 6865 1148
board
Formwork wood – – 839
Wooden slaters 1350 1350 1350
Polyester 29 29 29
Polyethylene 29 29 –
foam
Steel connectors – 185 –

a
Referring to RC1.
b
Referring to RC2.

6
V. Tavares et al. Journal of Building Engineering 41 (2021) 102705

height). It includes three bedrooms, two bathrooms, a kitchen, a dining and very suitable for dry prefabricated construction being commonly
and a living room, a pantry, a corridor, and an entry. The 11 m2 storage used in prefabrication; RC is a heavyweight structure used in the vast
area includes the laundry and a storeroom. The gross floor area is 249 m2 majority of conventional Southern European construction. LSF con­
(including porches, storage, utility spaces, and carports), and 50 years struction was designed by Balthazar Aroso Arquitectos Lda. www.
lifespan was considered. balthazar-aroso.com[46] manufactured and assembled in the North of
Portugal using the prefabricated LSF System B(A)a www.urbimagem.
com [47]as presented in Fig. 3. Further details about the LSF System B
2.2. Life cycle inventory: four construction systems (A)a can be found in refs [48,49]. A detailed execution project for the
other three construction systems was developed by designers, including
Four construction systems were modeled: prefabricated light steel the activities and bill of quantities that allowed to construct the in­
framing (LSF) and wooden frame (WF); and conventional reinforced ventory (detailed in Appendix B, Table B1).
concrete with a single layer concrete block (RC1) and with a double- Materials and activities inherent to each construction alternative
layer brick external wall (RC2). The LSF and WF structures are lighter

Fig. 5. Embodied (materials, off-site prefabrication, onsite assemblage, and construction) and end-of-life energy and environmental impacts for the prefabricated
(LSF and WF) and conventional (RC1 and RC2) construction.

7
V. Tavares et al. Journal of Building Engineering 41 (2021) 102705

were included in the assessment, and the common ones were considered equal to the previous values. The thermal resistance of the vapor
out of the scope (e.g., windows, doors, HVAC system, water, and permeable and water control layers was neglected in the calculation of
wastewater collection systems, lighting, electricity, home automation the U-values. In the LSF, a simplified method was used to account for the
systems, furniture, landscaping activities and finishes, etc.). The build­ effect of thermal bridging caused by steel framing components in the
ing envelopes associated with each construction system have similar calculation of the U-value of the hybrid-framed LSF walls [50,51] and
thermal transmittance (U-value) to guarantee similar heating and was used (p = 0.5). The method is similar to the one presented in ISO
cooling energy demand. Different insulation layer thicknesses were 6946 [52]and was used in previous studies [48,53].
considered at the external walls and roofs of the four alternative sce­ Fig. 4 shows the cross-section and the U-value of the building en­
narios to achieve the same U-value. The effect of thermal mass was velope (external wall and roof) of each alternative. The LSF system uses
neglected. a single cold-formed shape profile (C100 × 45 × 1.2 mm), and for the
The following assumptions were considered for all the alternatives: walls were considered: stud and nogging spacing of 625 mm, flange
internal surface resistances of 0.13 m2K/W (horizontal heat flux) and width of 45 mm, and studs of 100 mm deep made of 1.2 mm thick steel.
0.10 m2K/W (heat flow upwards); for the ventilated air gaps, the ther­ The wood-framed structural system is composed of Glulam GL24H
mal resistance of the air equals zero, and the surface resistances are beams and columns, secured by aluminum alloy connectors, and the

Fig. 6. Life cycle impacts of materials, per building element, for the prefabricated (LSF and WF). and conventional (RC1 and RC2) construction.

8
V. Tavares et al. Journal of Building Engineering 41 (2021) 102705

bracing against horizontal loads consists of steel tie rods connecting reduction (less 7–19%) for PO and AC, compared with conventional
adjacent columns. The RC structural system consists of a space frame construction. Regarding the two prefabricated construction, LSF has
made with C30/37 concrete and A500 reinforcing bars, and the roof is significantly more impacts than WF (more 17–78%), while for conven­
made of prestressed T beams and infills hollow concrete blocks. tional construction methods, RC1 has more impacts than RC2 for GW,
Table 2 presents the inventory of the four construction alternatives PO, AC, and EU (more 18–42%).
per life cycle phases: (1) materials divided by element: foundation and Embodied impacts vary 7–54% of total life cycle impacts (presented
ground floor, floor, external wall, internal wall, and roof; (2) off-site in appendix C, figure C1) and are mainly influenced by materials that
prefabrication includes transport (to and from the plant), labor, elec­ represent ca. 60–90% of embodied impacts (further detailed in section
tricity, water, and production waste; (3) onsite assembly and construc­ 3.2). For prefabricated construction, the second most important phase is
tion includes transport (to and from the construction site), labor, the off-site prefabrication (5–22%), while for the conventional is the
electricity, water, and construction waste; (4) use phase includes space construction phase (13–27%). Fig. 6 shows an important reduction in
heating and cooling, energy, and water use; (5) disassembly and de­ the total impacts of the LSF structure due to the recycling of the steel at
molition includes (transport to and from demolition site), labor, elec­ the end-of-life (less 15–35% in NRE, EU, PO, GW, and ADFF). Embodied,
tricity, water, and demolition waste; (6) waste treatment includes operational, and end-of-life impacts per m2 are further detailed in
transport (to waste treatment facilities) and waste recycling, landfilling Appendix C, Table C.1.
and incinerating activities. The inventory includes the gross amount of Fig. 6 shows the life cycle impacts associated with materials, per
materials required and waste from production, construction, and de­ building element (foundations, floor, external walls, internal walls, and
molition. For the use phase, 40–80 kWh/m2 of electricity consumption roof). The external wall and the roof are the most critical elements
per year was considered for heating and cooling needs, and no electricity summing up 75–95% of materials, followed by foundations and internal
consumption for other appliances was considered. For the LSF structure, wall. The roof has an important contribution to all impacts (30–95%)
it is assumed that 85% of the steel will be sent for recycling at the EoL, except for OD (representing 10–20%). The external wall represents
while in the RC structure will be 43%. 30–80% of impacts (except for AD, representing 10–25%). However,
impacts by building elements are deeply influenced by architectural
3. Results design as another layout (e.g., a different external wall to gross floor
area ratio) would change the relative weight of elements in the global
This section presents LC results divided into embodied and end-of- impacts.
life impacts, costs, production time, and waste. Total LC impacts,
including the use phase, are presented in appendix C, Figure C.1. Use
phase impacts vary between 45 and 90% of total impacts (depending on 3.2. Costs
the construction system and impact category) and are identical for the
four construction systems. Fig. 7 shows the embodied and end-of-life costs for prefabricated and
conventional construction methods. Use phase costs have not been
included because they are similar for all four alternatives and are highly

Fig. 7. Embodied and end-of-life costs for the prefabricated (LSF and WF)and conventional (RC1 and RC2) construction.

3.1. Embodied and end-of-life impacts dependent on the users’ profile. LSF has the lowest total cost, mainly due
to low onsite assemblage costs, and WF has the highest cost due to
Fig. 5 presents the life cycle impacts, excluding the use phase. The materials and onsite assemblage. However, the variation in the total cost
impacts are divided into (i) embodied impacts, including materials of the four alternatives is lower than 20%.
extraction and transformation, transport to plant, off-site prefabrication,
transport to site, onsite assembly and construction; and (ii) end-of-life
impacts, including disassembly or demolition, transport to waste facil­ 3.3. Production time
ities, and waste treatment.
Prefabricated construction has significantly fewer impacts than Fig. 8 presents the time associated with prefabrication, onsite as­
conventional construction for most impact categories (less 20–63% for sembly or construction, and end-of-life disassembly or demolition of the
ADFF, GW, OD, AC, and NRE). WF has the lowest impacts in all cate­ four alternatives, considering the sequential performance of works (8.a)
gories, having half the impacts of RC1 and RC2 (except for AD and OD) or that the off-site prefabrication is done simultaneously to site works (8.
and 10–50% less than LSF (except for AD). Results show that pre­ b). In comparison with conventional, prefabricated construction takes
fabricated LSF presents an increase in AD (more 26–32%) and smaller around 2/3 of the time to build or almost half of the time if the pre­
fabricated stage is simultaneously done with site works.

9
V. Tavares et al. Journal of Building Engineering 41 (2021) 102705

Fig. 8. Time for prefabrication and disassembly (LSF and WF) and construction and demolition (RC1 and RC2) considering sequential (a) or simultaneous works (b).

Fig. 9. a) Construction and b) demolition waste for the prefabricated (LSF and WF) and conventional (RC1 and RC2) construction.

3.4. Waste (weighting roughly ¼ of conventional construction) and produce less


waste (with a higher recycling rate).
Fig. 9 shows construction (9a) and demolition waste (9b) for the four The total cost variation between prefabricated and conventional
construction systems. The total waste associated with prefabricated construction is bellow 20%, and materials are responsible for more than
construction (LSF and WF) is around 20% of the RC1 and RC2. In 50% of the total cost. Even though prefabricated construction weights
addition, prefabricated construction has a lower rate of landfill waste five times less than conventional, costs are roughly similar because the
(43% for LSF and 49% for WF) compared to RC (62–76%), with half of cost of conventional materials (concrete and bricks) is much lower than
the waste being recycled or incinerated. Waste recycling is higher in prefabricated materials (steel or wood). Moreover, some prefabricated-
prefabricated buildings not only because of the type of materials used related costs reductions might be underestimated, as cost reduction due
but also because it is a dry assembly system enabling the complete to large scale production is envisaged but has not been accounted for.
separation of materials. Finally, shorten production time should be viewed as an added value,
but as it is highly dependent on market fluctuation, it has been
4. Discussion disregarded.
Within both prefabricated houses, the light steel house (LSF) has up
Embodied impacts can represent more than half of total life cycle to 50% more burdens than the prefabricated wood house (WF), showing
impacts, demonstrating the importance of the embodied phase. In the influence of the structural material. Within both conventional, single
comparison with conventional construction, prefabricated houses have layer concrete block wall house (RC1) has up to 40% more burdens than
up to 65% less embodied impacts. Prefabricated houses fit the low edge a double layer brick wall house (RC2), showing the influence of external
of the values presented in Table 1 for previous studies. The embodied wall composition. Besides all these variations, we can affirm that pre­
impacts of the prefabricated LSF house are c.a. 167 kg CO2eq/m2 and fabricated buildings have lower environmental impacts and cost the
2.2 GJ/m2 (in literature, the values are typically in the 63–864 CO2eq/ same (or even less) than conventional buildings while having a similar
m2 and 1.0–14.4 GJ/m2 ranges for steel structure houses); while for the performance, using less materials, and producing less waste.
WF house these values are about 145 CO2eq/m2 and 2.2 GJ/m2 (in Some of the simplifications and assumptions of this article led to
literature, these values are about 26–630 CO2eq/m2 and 2.1–10.5 GJ/ limitations and potential uncertainties. The LC model adopted for
m2 for WF houses). The embodied costs are about 436 €/m2for LSF, 516 background processes average European data for materials, similarly for
€/m2 for WF, 497 €/m2 for RC1 and 482 €/m2 for RC2, In literature, the all alternatives and system boundaries. Background data homogenously
embodied costs typically range from 400 €/m2 to 1400 €/m2 [24,33]. represents the group of suppliers. Use phase impacts were statistically
Therefore, the results are in accordance with the values provided in the calculated considering a ±33% variation; however, results are expected
literature. In addition, steel recycling contributes to reducing impacts at to hold as the four houses have similar energy performances. End-of-life
the end-of-life (EoL). The prefabricated LSF house has -61 kg CO2eq/m2 is expected to be different 50 years from now with higher recycling rates
and -0.5 GJ/m2 of EoL impacts, fitting the literature range (-227.7– and material recycled contents, but changes are difficult to forecast. This
(-0.17) CO2eq/m2 and -11.7–(+0.20) GJ/m2). Moreover, considering a study has focused on a specific house and location, and results may not
circular economy perspective, prefabricated buildings use less materials represent different building sizes. This was previously discussed in

10
V. Tavares et al. Journal of Building Engineering 41 (2021) 102705

Tavares et al., 2019 [32], concluding that impacts per m2 are similar prefabricated with conventional construction, balancing embodied,
among different size prefabricated houses. operational, and end-of-life impacts and costs, unveiling the importance
of embodied and end-of-life phases. Hotspots and improvement oppor­
5. Conclusions tunities have been identified for a single-family house. Prefabrication
can reduce impacts, material use, waste and production time for a
This study presents a life cycle assessment (LCA) comparing two similar operational performance, leading the way towards a more cir­
constructive systems (prefabrication and conventional) and different cular construction sector.
structural materials (steel, wood, and concrete) for a single-family
house, considering impacts, waste, costs, and production time. In com­
parison with conventional construction, prefabricated construction has Declaration of competing interest
lower environmental impacts (with the exception of abiotic depletion
for LSF), uses less materials, and produces a small fraction of waste, The authors declare that they have no known competing financial
taking half the time to build. WF has the lowest environmental impacts interests or personal relationships that could have appeared to influence
for all the categories, but slightly higher cost. LSF has the lowest life the work reported in this paper.
cycle cost. Differences exist within the same building process: for pre­
fabricated alternatives, WF has fewer impacts and lower costs than LSF; Acknowledgments
and for conventional, RC2 has fewer impacts (except for OD) and a
similar cost than RC1. Including the end-of-life presents a more holistic This work was carried out in the framework of the Sustainable En­
insight over buildings’ assessment showing that prefabrication can ergy Systems focus area of the MIT-Portugal Program, and it was
present an opportunity to decrease buildings’ impacts, not only during partially supported by the Portuguese Foundation for Science and
production but also at the end-of-life. Technology (FCT) under the Ph.D. scholarship PD/BD/128067/2016.
The difference in the total cost of the four alternatives is lower than The support from FCT projects: CENTRO-01-0145-FEDER-030570 (SET-
20% of the total cost. Construction costs are variable and highly sensi­ LCA) and M-ERA-NET2/0017/2016 (CTB BASICS) is also acknowl­
tive to local costs (e.g., labor and materials), so the ability to relocate edged. The authors are grateful to Ar. Baltazar Aroso for providing in­
part of the building process might present a significant economic formation on the LSF System B(A)a and for authorizing the use of the
advantage for prefabricated buildings, reducing prefabrication (and information presented in Figs. 2 and 3. The authors also thank Ar.
buildings) costs, although transport cost ought to be considered. Andreia Campos for the authorship of the architecture project of the case
This article presents a comprehensive assessment comparing study building.

Appendix A. Framework

Fig. A.1. Research framework (based on ISO 14040).

Appendix B. Inventory
Table B.1
Data and assumptions for the life cycle inventory

LSF WF RC

1. TIME Off-site fabrication Steel 13 – –


(days) OSB 15 15 –
Wood – 13 –
Onsite assembly and Foundations 22 22 22
construction (days) Assembly/construction 22 22 66
Finishes 22 22 22
(continued on next page)

11
V. Tavares et al. Journal of Building Engineering 41 (2021) 102705

Table B.1 (continued )


LSF WF RC

Use phase (years) Lifespan 50 50 50


Demolition (days) Demolition/disassembly 22 22 11
2. NUMBER OF Off-site fabrication (nr) Steel 2 2 –
WORKERS OSB 2 2 –
Wood 2 2 –
Onsite assembly and Foundations 4 4 4
construction (nr) Assembly/construction 4 8 8
Finishes 4 4 4
Demolition (nr) Demolition/disassembly 8 8 4
3. ELECTRICITY Production Electricity (kWh) 448 448 –
& WATER Water (l) 110 110 –
CONSUMPTION Assembly/ Electricity (kWh) 3000 3000 6000
construction Water (l) 150 150 300
Use phase Electricity (kWh/m2 year) 40–80 40–80 40–80
Water (l/person day) 200 200 200
Demolition Electricity (kWh) 1000 1000 500
Water (l) 50 50 25
4. DISTANCE To/from plant (km) From home 25 25 –
From OSB distributor 300 300 –
From steel distributor 4000 – –
From wood distributor – 4000 –
To waste facilities 50 50 –
To/from site (km) From home 50 50 50
From plant 50 50 –
From reinforcing steel distributor 4000 4000 4000
From concrete and formwork distributor 100 100 100
From other distributors 50 50 50
To waste facilities 50 50 50
5. WASTE Production (%) OSB 2 2 –
GENERATION Steel 0 – –
Wood – 2 –
Construction (%) Concrete 2 2 5
Steel 2 2 5
Wood 6 6 15
Block/brick 2 2 7
Others 5 5 5
Demolition (%) Concrete 98 98 95
Steel 98 98 95
Wood 94 92 85
Block/brick 98 98 93
Others 95 95 95

Table B.2
Costs of materials and main activities

Main materials Concrete (€/m3) 80.00 €


Formwork wood (€/m2) 18.00 €
Reinforcing Steel (€/kg) 0.90 €
OSB (€/m2) 13.40 €
Galvanized Steel (€/kg) 1.20 €
Gypsum board (€/m2) 19.80 €
Ceramic roofing (€/m2) 83.40 €
Wood slates (€/m2) 74.30 €
Granite (€/m2) 134.60 €
Polyethylene (€/m2) 0.40 €
Polyester (€/m2) 10.00 €
Rockwool (€/m2) 5.40 €
Ceramic bricks (€/m2) 6.90 €
Concrete block (€/m2) 31.90 €
Transport Transport of workers (€/km) 0.28 €
Transport of materials (€/tkm) 0.15 €
Transport of waste (€/tkm) 0.15 €
Labor Specialized (€/h) 8.00 €
Non-specialized (€/h) 6.00 €
Consumption Electricity (€/kWh) 0.14 €
Water (€/m3) 1.73 €
Waste management Landfill tax (€/ton) 20.00 €
Recycled steel (€/ton) - 105.00 €
Recycled aluminum (€/ton) - 105.00 €
Recycled CDW (€/ton) - 4.80 €

12
V. Tavares et al. Journal of Building Engineering 41 (2021) 102705

Appendix C. Results

Fig. C.1. Embodied (materials, off-site prefabrication, onsite construction, and construction), operational (use phase) and end-of-life energy and environmental
impacts for the prefabricated (LSF and WF) and conventional (RC1 and RC2) construction, considering electricity consumption of 40–80 kWh/m2 per year, water
consumption of 200 l/day per person, and a life span of 50 years.

Table C.1
Environmental impacts (AD, ADFF, GW, OD, PO, AC, EU, and NRE), costs and waste per m2 for the four alternative structural materials

AD ADFF GW OD PO AC EU NRE COSTS WASTE LANDFILL


2
Units g Sbeq GJ kg CO2eq g RCC-11eq g C2H4 eq/m kg SO2eq kg PO4eq GJ € kg kg
/m2 /m2 /m2 /m2 /m2 /m2 /m2 /m2 /m2 /m2

LSF (total) 3.35 17.4 1322 0.118 434 10.52 2.76 18.9 828 370 100
Embodied 1.81 2.0 167 0.033 75 0.98 0.39 2.2 436 175 6
(continued on next page)

13
V. Tavares et al. Journal of Building Engineering 41 (2021) 102705

Table C.1 (continued )


AD ADFF GW OD PO AC EU NRE COSTS WASTE LANDFILL

Units g Sbeq GJ kg CO2eq g RCC-11eq g C2H4 eq/m2 kg SO2eq kg PO4eq GJ € kg kg


/m2 /m2 /m2 /m2 /m2 /m2 /m2 /m2 /m2 /m2

Operational (per year) 0.03 0.3 24 0.002 8 0.19 0.05 0.3 7 – –


End-of-life -0.01 -0.4 -61 -0.002 -31 -0.07 -0.06 -0.5 29 195 94
WF (total) 2.87 17.9 1355 0.125 440 10.46 2.69 19.4 912 700 101
Embodied 1.31 2.0 145 0.037 49 0.78 0.26 2.2 516 524 5
Operational (per year) 0.03 0.3 24 0.002 8 0.19 0.05 0.3 7 – –
End-of-life 0.00 0.0 -7 0.000 1 0.07 0.01 0.0 33 176 96
RC1 (total) 3.35 20.4 1649 0.143 517 11.92 3.00 22.0 882 1046 707
Embodied 1.78 4.4 436 0.054 126 2.10 0.57 4.7 497 77 43
Operational (per year) 0.03 0.3 24 0.002 8 0.19 0.05 0.3 7€ – –
End-of-life 0.02 0.1 -3 0.002 1 0.20 0.01 0.1 23 969 665
RC2 (total) 3.28 20.0 1586 0.143 494 11.32 2.92 21.5 865 1045 582
Embodied 1.71 3.9 368 0.053 101 1.48 0.48 4.2 482 76 32
Operational (per year) 0.03 0.3 24 0.002 8 0.19 0.05 0.3 7 – –
End-of-life 0.02 0.1 1 0.002 3 0.22 0.02 0.2 20 969 550
NB: Total impacts = embodied + (operational per year x 50 years) + end-of-life.

References [19] P. Vitale, N. Arena, F. Di Gregorio, U. Arena, F. Di, U. Arena, Life cycle assessment
of the end-of-life phase of a residential building, Waste Manag. 60 (2017) 311–321,
https://doi.org/10.1016/j.wasman.2016.10.002.
[1] K. Dosch, Resource Efficiency in the Building Sector, 2018, pp. 297–303, https://
[20] M. Sandanayake, W. Luo, G. Zhang, Direct and indirect impact assessment in off-
doi.org/10.1007/978-3-319-50079-9_19.
site construction—a case study in China, Sustain. Cities Soc. 48 (2019) 101520,
[2] Climate Action Tracker, CAT, Scaling up Climate Action: Key Opportunities for
https://doi.org/10.1016/j.scs.2019.101520.
Transitioning to a Zero Emissions, society - European Union, 2018.
[21] Z. Ding, S. Liu, L. Luo, L. Liao, A building information modeling-based carbon
[3] Y.H. Chiang, E. Hon-Wan Chan, L. Ka-Leung Lok, Prefabrication and barriers to
emission measurement system for prefabricated residential buildings during the
entry-a case study of public housing and institutional buildings in Hong Kong,
materialization phase, J. Clean. Prod. 264 (2020) 121728, https://doi.org/
Habitat Int. 30 (2006) 482–499, https://doi.org/10.1016/j.
10.1016/j.jclepro.2020.121728.
habitatint.2004.12.004.
[22] X. Cao, X. Li, Y. Zhu, Z. Zhang, A comparative study of environmental performance
[4] D.A. Steinhardt, K. Manley, Adoption of prefabricated housing – the role of country
between prefabricated and traditional residential buildings in China, J. Clean.
context, Sustain. Cities Soc. 22 (2016) 126–135, https://doi.org/10.1016/j.
Prod. (2014), https://doi.org/10.1016/j.jclepro.2015.04.120.
scs.2016.02.008.
[23] Y. Teng, K. Li, W. Pan, T. Ng, Reducing building life cycle carbon emissions
[5] Y. Chen, G.E. Okudan, D.R. Riley, Decision support for construction method
through prefabrication: evidence from and gaps in empirical studies, Build.
selection in concrete buildings: prefabrication adoption and optimization, Autom.
Environ. 132 (2018) 125–136, https://doi.org/10.1016/j.buildenv.2018.01.026.
ConStruct. 19 (2010) 665–675, https://doi.org/10.1016/j.autcon.2010.02.011.
[24] A. Atmaca, N. Atmaca, Comparative life cycle energy and cost analysis of post-
[6] M. Kamali, K. Hewage, Life cycle performance of modular buildings: a critical
disaster temporary housings, Appl. Energy 171 (2016) 429–443, https://doi.org/
review, Renew. Sustain. Energy Rev. 62 (2016) 1171–1183, https://doi.org/
10.1016/j.apenergy.2016.03.058.
10.1016/j.rser.2016.05.031.
[25] O. Pons, G. Wadel, Environmental impacts of prefabricated school buildings in
[7] Y. Wang, J.P. Duarte, Automatic generation and fabrication of designs, Autom.
Catalonia, Habitat Int. 35 (2011) 553–563, https://doi.org/10.1016/j.
ConStruct. 11 (2001) 291–302, https://doi.org/10.1016/S0926-5805(00)00112-6.
habitatint.2011.03.005.
[8] M. Shahpari, F.M. Saradj, M.S. Pishvaee, S. Piri, Assessing the productivity of
[26] A.U. Vitale Pierluca, Spagnuolo Antonio, Lubritto Carmine, Environmental
prefabricated and in-situ construction systems using hybrid multi-criteria decision
performances of residential buildings with a structure in cold formed steel or
making method, J. Build. Eng. 27 (2020) 100979, https://doi.org/10.1016/j.
reinforced concrete, J. Clean. Prod. 189 (2018) 839–852, https://doi.org/10.1016/
jobe.2019.100979.
j.jclepro.2018.04.088.
[9] L.C. Malabi Eberhardt, J. Rønholt, M. Birkved, H. Birgisdottir, Circular Economy
[27] A.Z.Z. Szalay, What is missing from the concept of the new European Building
potential within the building stock - mapping the embodied greenhouse gas
Directive? Build. Environ. 42 (2007) 1761–1769, https://doi.org/10.1016/j.
emissions of four Danish examples, J. Build. Eng. 33 (2020) 101845, https://doi.
buildenv.2005.12.003.
org/10.1016/j.jobe.2020.101845.
[28] Z. Li, G. Qiping, X. Xue, Critical review of the research on the management of
[10] J. Navarro-Rubio, P. Pineda, A. García-Martínez, Sustainability, prefabrication and
prefabricated construction 43 (2014) 240–249.
building optimization under different durability and re-using scenarios: potential
[29] L. Aye, T. Ngo, R.H. Crawford, R. Gammampila, P. Mendis, Life cycle greenhouse
of dry precast structural connections, Sustain. Cities Soc. 44 (2019) 614–628,
gas emissions and energy analysis of prefabricated reusable building modules,
https://doi.org/10.1016/j.scs.2018.10.045.
Energy Build. 47 (2012) 159–168, https://doi.org/10.1016/j.
[11] D. Lopez, T.M. Froese, Analysis of costs and benefits of panelized and modular
enbuild.2011.11.049.
prefabricated homes, Procedia Eng 145 (2016) 1291–1297, https://doi.org/
[30] E. Bonamente, F. Cotana, Carbon and energy footprints of prefabricated industrial
10.1016/j.proeng.2016.04.166.
buildings: a systematic life cycle assessment analysis, Energies 8 (2015)
[12] I.S.O. ISO, 2006 Environmental Management — Life Cycle Assessment —
12685–12701, https://doi.org/10.3390/en81112333.
Principles and Framework, International Organization for Standardization, 2006.
[31] H. Islam, G. Zhang, S. Setunge, M.A. Bhuiyan, Life cycle assessment of shipping
[13] G. Rebitzer, T. Ekvall, R. Frischknecht, D. Hunkeler, G. Norris, T. Rydberg, W.
container home: a sustainable construction, Energy Build. 128 (2016) 673–685,
P. Schmidt, S. Suh, B.P. Weidema, D.W. Pennington, Life cycle assessment Part 1:
https://doi.org/10.1016/j.enbuild.2016.07.002.
framework, goal and scope definition, inventory analysis, and applications,
[32] V. Tavares, N. Lacerda, F. Freire, Embodied energy and greenhouse gas emissions
Environ. Int. 30 (2004) 701–720, https://doi.org/10.1016/j.envint.2003.11.005.
analysis of a prefabricated modular house: the “Moby” case study, J. Clean. Prod.
[14] M.M. Khasreen, P.F.G.G. Banfill, G.F. Menzies, Life-cycle assessment and the
212 (2019) 1044–1053.
environmental impact of buildings: a review, Sustainability 1 (2009) 674–701,
[33] C. Dara, C. Hachem-Vermette, G. Assefa, Life cycle assessment and life cycle
https://doi.org/10.3390/su1030674.
costing of container-based single-family housing in Canada: a case study, Build.
[15] K. Adalberth, Energy use during the life cycle of buildings: a method, Build.
Environ. 163 (2019) 106332, https://doi.org/10.1016/j.buildenv.2019.106332.
Environ. 32 (1997) 317–320, https://doi.org/10.1016/S0360-1323(96)00068-6.
[34] O. Iuorio, L. Napolano, L. Fiorino, R. Landolfo, The environmental impacts of an
[16] K. Adalberth, Energy use during the life cycle of single-unit dwellings: examples,
innovative modular lightweight steel system: the Elissa case, J. Clean. Prod. 238
Build, Environ 32 (1997) 321–329, https://doi.org/10.1016/S0360-1323(96)
(2019) 117905, https://doi.org/10.1016/j.jclepro.2019.117905.
00069-8.
[35] J. Monahan, J.C. Powell, An embodied carbon and energy analysis of modern
[17] J. Quale, M.J. Eckelman, K.W. Williams, G. Sloditskie, J.B. Zimmerman,
methods of construction in housing: a case study using a lifecycle assessment
Construction matters: comparing environmental impacts of building modular and
framework, Energy Build. 43 (2011) 179–188, https://doi.org/10.1016/j.
conventional homes in the United States, J. Ind. Ecol. 16 (2012) 243–253, https://
enbuild.2010.09.005.
doi.org/10.1111/j.1530-9290.2011.00424.x.
[36] H. Achenbach, J.L. Wenker, S. Rüter, Life cycle assessment of product- and
[18] G. Heravi, T. Nafisi, R. Mousavi, Evaluation of energy consumption during
construction stage of prefabricated timber houses: a sector representative approach
production and construction of concrete and steel frames of residential buildings,
for Germany according to EN 15804, EN 15978 and EN 16485, Eur. J. Wood Wood
Energy Build. 130 (2016) 244–252, https://doi.org/10.1016/j.
Prod. 76 (2018) 711–729, https://doi.org/10.1007/s00107-017-1236-1.
enbuild.2016.08.067.
[37] V.Ž. Leskovar, M. Žigart, M. Premrov, R.K. Lukman, Comparative assessment of
shape related cross-laminated timber building typologies focusing on

14
V. Tavares et al. Journal of Building Engineering 41 (2021) 102705

environmental performance, J. Clean. Prod. 216 (2019) 482–494, https://doi.org/ Assess. (2021) 1218–1230. http://link.springer.com/10.1007/s11367-016-1087
10.1016/j.jclepro.2018.12.140. -8/.
[38] F. Pierobon, M. Huang, K. Simonen, I. Ganguly, Environmental benefits of using [46] Website “Balthazar Aroso Arquitectos Lda (n.d.), www.balthazar-aroso.com.
hybrid CLT structure in midrise non-residential construction: an LCA based [47] Website “URBIMAGEM” (n.d.), www.urbimagem.com.
comparative case study in the U.S. Pacific Northwest, J. Build. Eng. 26 (2019), [48] E. Rodrigues, N. Soares, M.S. Fernandes, A.R. Gaspar, Á. Gomes, J.J. Costa, An
https://doi.org/10.1016/j.jobe.2019.100862. integrated energy performance-driven generative design methodology to foster
[39] C. Mao, Q. Shen, L. Shen, L. Tang, Comparative study of greenhouse gas emissions modular lightweight steel framed dwellings in hot climates, Energy Sustain. Dev.
between off-site prefabrication and conventional construction methods: two case 44 (2018) 21–36, https://doi.org/10.1016/j.esd.2018.02.006.
studies of residential projects, Energy Build. 66 (2013) 165–176, https://doi.org/ [49] N. Soares, P. Santos, H. Gervásio, J.J. Costa, L. Simões da Silva, Energy efficiency
10.1016/j.enbuild.2013.07.033. and thermal performance of lightweight steel-framed (LSF) construction: a review,
[40] Y. Teng, W. Pan, Systematic embodied carbon assessment and reduction of Renew. Sustain. Energy Rev. 78 (2017) 194–209, https://doi.org/10.1016/j.
prefabricated high-rise public residential buildings in Hong Kong, J. Clean. Prod. rser.2017.04.066.
238 (2019) 117791, https://doi.org/10.1016/j.jclepro.2019.117791. [50] S. Doran, M. Gorgolewski, U-values for Light Steel-Frame Construction - BRE Digest
[41] H. Gervásio, P. Santos, R. Martins, L.S. Silva, A macro-component approach for the 465, Building Research Establishment, 2002.
assessment of building sustainability in early stages of design, Build. Environ. 73 [51] M. Gorgolewski, Developing a simplified method of calculating U-values in light
(2014) 256–270, https://doi.org/10.1016/j.buildenv.2013.12.015. steel framing, Build, Environ 42 (2007) 230–236, https://doi.org/10.1016/j.
[42] B.L.P. Peuportier, Life cycle assessment applied to the comparative evaluation of buildenv.2006.07.001.
single family houses in the French context, Energy Build. 33 (2001) 443–450, [52] I.S.O. ISO, Building Components and Building Elements - Thermal Resistance and
https://doi.org/10.1016/S0378-7788(00)00101-8. Thermal Transmittance - Calculation Method, International Organization for
[43] B. Peuportier, S. Thiers, A. Guiavarch, Eco-design of buildings using thermal Standardization, 2007.
simulation and life cycle assessment, J. Clean. Prod. 39 (2013) 73–78, https://doi. [53] N. Soares, A.R. Gaspar, P. Santos, J.J. Costa, Multi-dimensional optimization of the
org/10.1016/j.jclepro.2012.08.041. incorporation of PCM-drywalls in lightweight steel-framed residential buildings in
[44] ISO, Environmental Management–Life Cycle Assessment—Principles and different climates, Energy Build. 70 (2014) 411–421, https://doi.org/10.1016/j.
Framework, 2006. enbuild.2013.11.072.
[45] G. Wernet, C. Bauer, B. Steubing, J. Reinhard, E. Moreno-Ruiz, B. Weidema, The
ecoinvent database version 3 (part I): overview and methodology, Int. J. Life Cycle

15

You might also like