ANNEXURE- I
BAS SOFTWARE SITE ACCEPTANCE TEST
PROTOCOL - ADMINBAS SOFTWARE SITE
ACCEPTANCE TEST PROTOCOL - ADMIN
Bayer Oy, Laaketehdas BT02, Artukaistentie 10, Turku, Finland
Document Number: TUK-02-XX-ITP-BA-3611-A1
Panel Number: AK-T810.3.36
Revision: A.01
TABLE OF CONTENTS
1 REVIEW STRATEGY..........................................................................................................................
1.1 SUPPLIED TEST SCRIPTS................................................................................................................
1.2 PROVIDED TEST FORMS.................................................................................................................
1.3 REFERENCE DOCUMENTS...............................................................................................................
2 SIGNATURES.....................................................................................................................................
3 SECTION 1 – PRE-REQUISITES VERIFICATION..............................................................................
4 SECTION 2 - PRE-TEST DOCUMENTATION VERIFICATION..........................................................
5 SECTION 3 – PRE-TEST CPO CONTROLLER SOFTWARE............................................................
6 SECTION 4 – FRONT END SOFTWARE VERSION VERIFICATION................................................
7 SECTION 5 – FACILITY CODE VERIFICATION................................................................................
8 SECTION 6 - GLOBAL POINTS VERIFICATION.............................................................................
9 SECTION 7 – POINTS AND ALARMS VERIFICATION...................................................................
10 SECTION 8 – CUSTOM GRAPHICS VERIFICATION......................................................................
11 SECTION 9 – SEQUENCE OF OPERATION VERIFICATION..........................................................
12 SECTION 10 – LOOP TUNING RECORD.........................................................................................
13 EVIDENCE/ATTACHMENTS............................................................................................................
14 COMMON COMMENTS....................................................................................................................
15 REVISION HISTORY.........................................................................................................................
1 REVIEW STRATEGY
1.1 Supplied Test Scripts
The appendices of this protocol contain SAT test forms, which are being used as testing for
this SAT protocol.
Test Sheets for each controller identified for Software Site Acceptance Test will be provided
as attachments to this document.
Note: The BAS Software SAT report (TUK-02-XX-REP-BA-3616) will be generated upon
completion of the SAT protocol test with exceptions and comments listed.
2 SIGNATURES
The following table identifies all the individuals who collected data, performed tests, verified
test results, and/or witnessed test results in the execution of this protocol.
Name Initials
Title Organization
Name Initials
Title Organization
Name Initials
Title Organization
Name Initials
Title Organization
Name Initials
Title Organization
Name Initials
Title Organization
Name Initials
Title Organization
Exceptions / Comments
A copy of the approved BAS - Master I/O and Instrument List AK-T810.3.36 is available and will be used
3. Pass / Fail / NA
during the test and attached to this test protocol.
A copy of the approved BAS - Detailed Description of Operation AK-T810.3.36 is available and will be used
4. Pass / Fail / NA
during the test and attached to this test protocol.
Exceptions / Comments
SW-SATF-003 Physical Installation of the Panel Verification Form Run Number ___
Exceptions / Comments
Exceptions / Comments
Exceptions / Comments
1. Modbus RTU points are configured and reading correctly. Pass / Fail / N/A
2. BACnet MS/TP points are configured and reading correctly. Pass / Fail / N/A
3. Global points are configured and reading correctly as per the testing sheets. Pass / Fail / N/A
1. Field instruments ranges (characteristics) have been verified against Master I/O document Pass / Fail / N/A
2. Polarity for DI point is configured correctly as per design documentation Pass / Fail / N/A
3. Alarms are enabled and configured according to APL (Alarm Parameter List) Pass / Fail / N/A
Graphical representation
place verification
engineering unit
Sr Initials/Date Test Result
Graphics points
Area Graphic File Name
No (DD/MMM/YYDDMMMYY) (Pass / Fail / NA)
verification
1 ADMIN BT02_KOF34_1_1.htm Yes / No Yes / No Yes / No Yes / No Pass / Fail / NA
2 ADMIN BT02_KOF34_1_1_A_1_31.htm Yes / No Yes / No Yes / No Yes / No Pass / Fail / NA
3 ADMIN BT02_TK32.htm Yes / No Yes / No Yes / No Yes / No Pass / Fail / NA
4 ADMIN BT02_TK32_A_1_01.htm Yes / No Yes / No Yes / No Yes / No Pass / Fail / NA
5 ADMIN BT02_TK32_A_1_18.htm Yes / No Yes / No Yes / No Yes / No Pass / Fail / NA
6 ADMIN BT02_TK32_A_1_23.htm Yes / No Yes / No Yes / No Yes / No Pass / Fail / NA
7 ADMIN BT02_TK32_A_1_24.htm Yes / No Yes / No Yes / No Yes / No Pass / Fail / NA
8 ADMIN BT02_TK32_A_1_25.htm Yes / No Yes / No Yes / No Yes / No Pass / Fail / NA
9 ADMIN BT02_TK32_A_1_28.htm Yes / No Yes / No Yes / No Yes / No Pass / Fail / NA
10 ADMIN BT02_TK32_A_1_29.htm Yes / No Yes / No Yes / No Yes / No Pass / Fail / NA
11 ADMIN BT02_TK32_A_1_31.htm Yes / No Yes / No Yes / No Yes / No Pass / Fail / NA
12 ADMIN BT02_TK32_A_1_61.htm Yes / No Yes / No Yes / No Yes / No Pass / Fail / NA
13 ADMIN BT02_TK32_A_1_62.htm Yes / No Yes / No Yes / No Yes / No Pass / Fail / NA
14 ADMIN BT02_TK32_A_1_63.htm Yes / No Yes / No Yes / No Yes / No Pass / Fail / NA
15 ADMIN BT02_TK32_A_1_64.htm Yes / No Yes / No Yes / No Yes / No Pass / Fail / NA
Graphical representation
place verification
engineering unit
Sr Initials/Date Test Result
Graphics points
Area Graphic File Name
No (DD/MMM/YYDDMMMYY) (Pass / Fail / NA)
verification
16 ADMIN BT02_TK35.htm Yes / No Yes / No Yes / No Yes / No Pass / Fail / NA
17 ADMIN BT02_TK35_A_1_07.htm Yes / No Yes / No Yes / No Yes / No Pass / Fail / NA
18 ADMIN BT02_TK35_A_1_08.htm Yes / No Yes / No Yes / No Yes / No Pass / Fail / NA
19 ADMIN BT02_TK35_A_1_09.htm Yes / No Yes / No Yes / No Yes / No Pass / Fail / NA
20 ADMIN BT02_TK35_A_1_10.htm Yes / No Yes / No Yes / No Yes / No Pass / Fail / NA
21 ADMIN BT02_TK35_A_1_15.htm Yes / No Yes / No Yes / No Yes / No Pass / Fail / NA
22 ADMIN BT02_TK35_A_1_16.htm Yes / No Yes / No Yes / No Yes / No Pass / Fail / NA
23 ADMIN BT02_TK35_A_1_60.htm Yes / No Yes / No Yes / No Yes / No Pass / Fail / NA
24 ADMIN BT02_TK7_1.htm Yes / No Yes / No Yes / No Yes / No Pass / Fail / NA
25 ADMIN BT02_TK7_1_A_1_02.htm Yes / No Yes / No Yes / No Yes / No Pass / Fail / NA
26 ADMIN BT02_TK7_1_A_1_03.htm Yes / No Yes / No Yes / No Yes / No Pass / Fail / NA
27 ADMIN BT02_TK7_1_A_1_04.htm Yes / No Yes / No Yes / No Yes / No Pass / Fail / NA
28 ADMIN BT02_TK7_1_A_1_05.htm Yes / No Yes / No Yes / No Yes / No Pass / Fail / NA
Exceptions / Comments
2.
IV-32 | Temperature Control Re-heat unit LP-32.1.1
3.
IV-32 | Temperature Control Re-heat unit LP-32.1.2
4.
IV-34 | Supply Air Temperature Control
5.
13 EVIDENCE/ATTACHMENTS
Evidence Attachment List
No of
Section
Item Attachment Pages
Reference
Attached
Exceptions/Comments
14 COMMON COMMENTS
Section
Number Comment Description
Reference
15 REVISION HISTORY
End of Document