You are on page 1of 14

SPECIAL REPORT

An Overview of the PRESSS


Five-Story Precast Test Building
Suzanne Dow Nakaki, S.E. At the culmination of the PRESSS (Precast Seismic
Principal
Nakaki Eng ineering Structural Systems) research program , a 60
Santa Ana, California percent scale five-story precast/prestressed
concrete building will be tested under simulated
seismic lo ading. This paper describes the
prototype buildings used for design and the
structura l features of the test building. The
buildings were designed using the direct
displacement based approach, which is able to
take advantage of the unique properties of
John F. Stanton, Ph.D., P.E. precast/prestressed concrete using dry jointed
Professor construction. The test building incorporates four
Department of Civil Engineering different seismic frame systems in one direction,
University of Washington
Seattle, Washington and a jointed shear wall system in the orthogona l
direction. Pretopped double tees are used on three
floors, while the other two floors are constructed
using topped hollow-core slabs. A major objective
of the test program is to develop design guidelines
for precast/prestressed concrete seismic systems
that are appropriate for use in various seismic
S. (Sri) Sritharan, Ph.D. zones. These design guidelines can then be
Assistant Project Scientist incorporated into the appropriate building codes.
Department of Applied Mechanics
and Eng ineering Sciences
University of Ca liforn ia, San Diego
La joll a, California he Precast Seismic Structural Systems (PRESSS)

T program has been in progress for ten years, with the


final phase of the program well underway . PRESSS,
sponsored by the National Science Foundation (NSF),
Precast/Prestressed Concrete Institute (PCI) and
Precast/Prestressed Concrete Manufacturers Association of
California, Inc. (PCMAC), has coordinated the efforts of
over a dozen different research teams across the United
26 PCI JOURNAL
Fig. 1. Prototype building with pretopped double tees. Note: 1 ft = 0.3048 m.

8 in. hollow-
core slabs
(typ)

Fig. 2. Prototype building with topped hollow-core slabs. Note: 1 ft = 0.3048 m; 1 in.= 25.4 mm.

States to improve the seismic perfor- transportation structures are excluded. needed for a broader acceptance of
mance of precast/prestressed concrete Since the very beginning of the precast concrete construction in dif-
buildings. In the context of this paper, PRESSS program, all of the research ferent seismic zones.
"buildings" refer to low- and high-rise teams involved in the program have • To develop new materials, concepts,
buildings such as office buildings, focused their sights on two primary and techno logies for precast con-
parking structures, hotels, hospitals, objectives: crete construction in different seis-
multi-family housing , and other spe- • To develop comprehensive and ra- mic zones.
cial structures. However, bridges and tional design recommendations The first and second phases of the
March-April 1999 27
The size of the testing laboratory
limited the test building to 30 x 30 ft
PRECAST CONCRETE SEISMIC SYSTEMS (9. 14 x 9.14 m) in plan. Rather than
designing the test building to resist
just its own inertial loads, the inertial
loads of the prototype buildings were
Emulation of calculated and then scaled down to
Reliance on
Monolithic Behavior Unique Properties represent the scale of the test building.
(Jointed Construction) This gives a more accurate picture of
the demand that a practical building
configuration would be subjected to,
Fig. 3. Current code design choices for precast systems. without exceeding the space limita-
tions of the laboratory. The test build-
ing will be subjected to increasingly
PRESSS program have been described unless it also results in a lower cost. larger seismic demands that represent
by Priestley in the PCI JOURNAL. 1 Thus, the PRESSS Phase III research low service level earthquakes, moder-
The third phase consists of the seismic team, comprising researchers and in- ate (Zone 2 design level) earthquakes
design and analysis of a five-story pre- dustry advisory group members, has and design level earthquakes beyond
cast/prestressed concrete building kept in mind that in addition to improv- those required for Zone 4.
using dry jointed construction. A por- ing performance, cost effectiveness of The ultimate objective of the re-
tion of this building will be built at 60 the resulting systems is crucial. search, however, is not the test itself,
percent scale and tested. The purpose The PRESSS Phase III test program but the design recommendations that
of this paper is to present an overview is based on the design of two proto- will result from the testing program.
of the test building, describe the major type five-story precast office build- Because there are so many different
features of the structural systems in- ings, 100 x 200 ft (30.5 x 61 m) in combinations of systems included in
vestigated and offer some thoughts on plan, with 12ft 6 in. (3.81 m) story the test building, it does not represent
the practical implications of the test heights. Both buildings use frames to the most economical way to implement
results. resist lateral loads in the longitudinal these new structural systems. The final
direction and shear walls to resist lat- design recommendations are the key to
eral loads in the transverse direction. obtaining improved performance of the
PRESSS Ill PROGRAM The first building, shown in Fig. 1, proposed systems at a competetive cost
OBJECTIVES uses pretopped double tees to span be- in practical applications.
Academic research is often focused tween a central gridline and the
solely on improving the performance of perimeter of the building. The second
existing structural systems. While his- prototype building, shown in Fig. 2, is EXISTING DESIGN CODES
tory confmns that this is a worthy goal, based on a topped hollow-core slab During the life of the PRESSS pro-
the reality of the construction market- floor system. For simplicity, the same gram, there have been significant de-
place is that improved performance of a floor system was assumed at the roof velopments in the model codes 2•3 that
system will generally not be accepted as well as at each floor. provide some guidance to design engi-

Tab le 1. Detai ling requirements of Special Moment Res isting Frame and Intermed iate Moment Resisting Frame systems.
Detailing requirements Intermediate Moment Resisting Frame I Special Moment Resisting Frame

Column reinforcement to ensure Not required Often a few additional longitudinal


weak beam/strong column column bars are required

Column confinement reinforcement Tight tie spacing is required on top Same as Intermediate Moment Resisting Frame
and bottom of column except where axial overload is possible
(normall y at end bays of frames)

Column shear reinforcement Requ ired Required

Joint shear stress limitations No limit; however, joint shear Limi ted; this requires a larger column only
reinforcement is required where beams are heavily reinforced

Beam shear reinforcement Required Required

Positive moment resistance in beam Required Required

Design base shear 150 to 160 percent of that requi red fo r 60 to 65 percent of that required for Intermedi-
Special Moment Resisting Frame ate Moment Resisting Frame

28 PC l JOURNAL
neers wanting to implement precast
seismic systems in their buildings. As
shown in Fig. 3, current codes allow
15 ' - 0" 15'- 0"
precast seismic systems that either em-
ulate monolithic concrete or rely on Hybrid Frame
the unique properties of precast con-
crete (i.e., jointed, dry construction).
While jointed construction is allowed
by the code, the focus of the prescrip-
tive code provisions has been on emu- ~
lation of monolithic concrete, largely ~
because a consistent set of design rec-
ommendations for jointed precast sys- ""
!-

tems have not been developed. Jointed .."8


It
"
:;:;
:I ..
"8
It
systems can only be used if they are 0 8 0
justified by test data on a case-by-case
0
.
·;:: ~
c..
c..
·;::
cS
basis. The PRESSS program goes a
step further by focusing its efforts al-
l
most exclusively on systems that rely
on and take advantage of the unique "'.
~
properties of precast concrete. The in-
tention is then to develop a consistent
set of design recommendations for
jointed precast systems that can be used
to update existing code provisions. TCY Gap Frame

Force Based Design


Seismic design in current codes is Fig . 4. Test bui lding - Level 1 floor plan. N ote: 1 ft = 0.3048 m .
exclusively force based. That is , a de-
signer uses elastic properties to deter-
mine an elastic base shear, which is
then divided by a force-reduction fac-
tor R to obtain the design base shear.
The value of R depends largely on the 15 ' - 0" 15 ' - 0"

nominal ductility capacity of the sys-


PreTensioned Frame
tem chosen, which is somewhat arbi-
trary and varies between codes. While : : : : : ! I
!
maximum structural displacements
must satisfy certain limits, they are in Actuator Connection Panel I
most cases based on elastic structural
properties and are amplified by factors Topped Hollow Core
intended to approximate the post-elas- ------------------------- --------------- - -
tic response. This approach has some
significant drawbacks, as discussed by
Priestley,• especially for precast con-
] Actuator Connection Panel
crete. Despite these difficulties, it will
continue to be the legal design proce-
dure for at least the foreseeable future.
In Force Based Design, there are two -------- - ----------- ---- ---------------------- '
main ways that a designer can reduce Topped Hollow Core "'
the cost of a seismic system. Both - -- - - - - - - - - -- - -- - - - - - - - - - - - - I - - - - -- - - - - -- - - - -- - - - -- - -- - --

methods depend on reducing the de-


sign loads because for consistent de-
ActuatOr Connection Panel I
tailing, a lower force results in a lower lI
cost. In the first method, a larger R fac- I I I I I
TCY Frame
tor is used to reduce the design base
shear. For frames, the R value can be
maximized by detailing the structure as
a Special Moment-Resisting Frame Fig. 5 . Test bu ilding- Leve l 4 floor plan . Note: 1 ft = 0.3048 m.

March-April 1999 29
(UBC R = 8.5, NEHRP R = 8) rather
than an Intermediate Moment-Resist- 15 ' . o·· 15'- 0"
ing Frame (UBC R = 5.5, NEHRP R =
5). The seco nd method consists of
using a longer period to reduce the de- I I
sign base shear. This method forms the
basis of recommendations proposed by
the PCI Ad Hoc Committee Report on
Precast Walls.5
'
Frame Systems
II
Ordinary Moment-Resisting Frames
(OMRF) are not permitted in moderate
and high seismic zones (UBC Zones 2,
L n '

3, and 4) because of their fundamental


lack of ductile behavior. For seismic
design using frames in moderate seis- L J
mic zones, a designer has a choice be-
tween using an Intermediate Moment-
Resisting Frame (IMRF) or a Special
Moment-Resisting Frame (SMRF).
Table 1 compares the detailing require-
e ~
ments of the two frame types. In high
seismic zones, only SMRF frames are
permitted.
The appearance of a choice is de-
[ J I .I [ J
ceptive because the SMRF is almost
inv ar iably the mo st cost effective Fig. 6. Prestressed frame elevation. N ote: 1 ft = 0.3048 m; 1 in . = 25.4 mm .
frame solution. This is so because the
design loads on an SMRF are 35 to 40
percent lower, primarily due to th e
higher R factor. Also, the period of an 15 ' -0 " 15 '-0 "
SMRF system is slightly longer than
that of an IMRF system for the same -
building, due to the lower frame stiff-
6
·.:
ness. This, too, means that the SMRF
design load is lower. These benefits
easily outweigh the extra costs of the
I
u
G
...
slightly more stringent detailing re-
quirements for the SMRF. -
In summary , therefore , it is fro m
this perspective of the need for ductile -
performance and cost effective design
that only SMRF systems were chosen
for the PRESSS III te st buildin g .
These system s are appropriate, and
cost effective, in all seismic zones.

Wall System
Wall systems designed under cur-
rent codes are described as either load-
bearing or non-loadbearin g wall s. -
Since non-loadbearing walls are usu-
all y more ductil e than loadbearin g
walls, the UBC R factor for them is 18
percent more than that for loadbearing
[ J [ J [ J
walls. This results in an 18 percent de-
crease in the design base shear and a Fig. 7. Tension-Compress ion Yielding (TCY) fra me elevation. Note: 1 ft = 0 .3048 m;
concomitant reduction in the cost for 1 in.= 25.4 mm .

30 PCI JOURNAL
I'- 6 "

r r
COLUMN LONGITUDINAL REINFiORCING

o·- UNBONDED POST- TENSIONED


I
I

mff\
0.5 I
STR'ANDS IN PVC SLEEVE W/ NO
GR
~WRAP
I! !I 1/2" JOINT - FILL W/ FIBER GROUT
REBAR
1: iI PRIOR TO STRESSING

I
\ I _\
--
......
' I
I _l

-
\
I _l

ADD/TIONA L REINFORCING NOT


SLEEVES PER BEAM SECTIONS
J !
[\ ~EINFORCJNG TOP"" d
M IN METAL CORRUGATED
'£S SOLID GROUTED
1\

UNBONDED POST- TENSIONING


USING DYWIDAG THREADBARS y
l.<l\
I\_ o.so·-BONDED PRESTRESSING
STRANDS

Fig. 8. Hybrid frame interior jo int (transverse rei nfo rceme nt not shown fo r clari ty). Note: 1 ft = 0.3048 m; 1 in. = 25.4 mm.

non-loadbearing wall systems that are Wall direction (T11 = 0.48 seconds) prised of jointed wall panels. The de-
otherwise identical to their loadbear- Design base shear = 4889 kips (21746 kN) sign base shear for an equivalent cast-
ing wall counterparts. These values reflect the advantages in-place frame system would be iden-
It is fa irl y s tr a ig htfo r war d to of a ductile system (i.e. , R = 8.5 for tical, since the elastic stiffnesses of a
lengthen the building period in a pre- frames) and a lengthened period fo r precas t f ra m e a nd a cas t-in -pl ace
cast shear wall syste m by providing the shear wail building which is com- frame are similar. However, the elastic
vertical joints between the panels that
m a ke up a wa ll (see P CI A d Hoc
Committee Report on Precast Walls5 ). Fi g. 9.
T hu s, by p rov iding a j ointed shear Specimen O-P-Z4 Hybrid fra me
400 hysteres is loop
wall , the design forces are reduced, re- 90
(from Ref. 6).
sulting in a reduced building cost.
300 67

Results of Force Based Design 200 45


It should be noted that, although im- ---. 100
proving ductility and lengthening the z...__,
~
---.
~
...__,
system period reward buildings with 0 0 -o
-o
lower design loads, the magnitude of "'0 -100 -22
"'
0
....l
....l
the reduction reflects only poorly the
tr ue ad vantages tha t well-d esigned -200 -45
precas t sys tems offer. For exampl e,
the design base shear fo r the prototype ·300 -67
building using force based des ign in -90
-400
accordance with the 1997 UBC (Zone
4) is as follows: -7 -5 ·3 ·1 3 5 7
Frame direction (T11 = 0.67 seconds) Story Drift(%)
Design base shear = 2248 kips (10000 kN)
March-April 1999 31
1'- 6"

r r
COLUMN LONGITUDINAL REINFORCING
REBAR SPLICE .~ I !l UNBONDED POST- TENSIONING
USING DYWIDAG THREADBARS

I
PRESTRESSING STRANDS II II
I II
DED IN BEAMS) II
u
n
II
II
1i
I
I I
!I
I
II
u
n
II
II
ADDITIONAL 2-#4 EACH FACE OF
BEAM TERMINATING 1" CLEAR FROM
COLUMN FACE
II I I II

II I I I I
\ II
II
II
I I
I
I
I
I
I
I
I
I \ ;
I I I I

\ I
II 1 I I I
II I
I I I
:I I I I I

1:
1:
1111
u:1
II I
II I

I
'I ''i
II
'I Ill
II
'I Ill X
I
I
I
I
I
\I\
I lj II
11/l
II I I II

\ MAIN BEAM REINFORCING TOP


and BOTTOM W/ 9 O" HOOKS
1/2" JOINT -FILL W/ FIBER GROUT AT COLUMN FACES
PRIOR TO S TRESSING ..._
STEEL
IN CORRUGATED SL £EVES
SOLID GROUTED

1\ 0.50"¢ BONDED PR£STRESSING


STRANDS

Fig. 10. Pretensioned frame interior jo int (transverse reinforcement not shown for clarity). Note: 1 ft = 0.3048 m; 1 in. = 25.4 mm.

period for an equivalent, non-jointed, While the systems included in the systems. As will be discussed below, a
cast-in-place wall would be substan - test building are expected to be cost further reduction to design base shear
tially shorter than the jointed wall pe- effective even using force based de- is achieved, providing substantial cost
riod. Except in cases where the maxi- sign, the PRESSS III test building savings for precast buildings in all
mum base shear governs , a shorter adopts an alternative design procedure seismic zones.
period would result in a higher base that more efficiently incorporates the
shear. advantages of well-designed precast
DESIGN OF PRESSS Ill
TEST BUILD ING
The PRESSS Phase ill test building
150 is not intended to create new design
concepts, but rather to examine the
100 suitability of design concepts created
,.-.., in earlier phases of the PRESSS pro-
""c. 50 gram or other precast concrete re-
~ search . One criterion used in deter-
...
'-'
~ mining which systems would be
Cl) 0
..c: included in the test building was that
tZl
c
.s -50
the concept had to have been experi-
Cl:)
mentally validated through component
tests.
-1 00 The complete building test is impor-
tant because it addresses many ques-
-1 50 tions of design and constructability,
-6 -4 -2 0 2 4 6 which do not arise in component tests.
Story Drift(%) Also, the behavior of a complete, stati-
cally indeterminate system involves
Fig. 11. Pretensioned frame hysteres is loop (from Ref. 7) . many features, including verification
32 PCI JOURNAL
]'- 6"

r
~
~ COLUMN LONGITUDINAL REINFORCING

MILD REINFORCING AT TOP IN


METAL CORRUGATED SLEEVES
SOLID GROUTED IN BEAM and
COLUMN
\ WRAP REBAR-
IN SLEEVES
4
,~
, I! !I
li ll
ll ll
ll ll
L BACKER RODS AROUND P><O
SLEEVES AT JOINT TO KEEP
JOINT FREE OF GROUT

il!I
! li ll
li ll
ll ll
! JU!
I 'J 1/ llll
lll l
ADDITIONAL REINFORCING PER _ )
BEAM SECTIONS
lll l
1/ li ll \ _ I" JOINT - ALL BOrrDM 6" OF J OINT
W/ FIBER GROUT PRIOR TO STRESSING

UNBONDED POST- TENSIONING


USING DYWIDAG THREADBARS
j
ij 1\_

Fig. 12. TCY gap frame interior joint (transverse reinforcement not shown for clar ity). Note: 1 ft = 0.3048 m; 1 in .= 25.4 mm .

of seismic design methods that do not The building will be tested in both two independently controlled actuators
occur in statically determinate compo- the frame and wall directions indepen- at each floor level will prevent torsion.
nent tests. dently under simu lated seismic load s
The specific objectives of the test that represent earthquakes up to 50 Frame Connection Systems
are to: percent stronger than Zone 4 design Four different types of ductile connec-
• Validate a rational design procedure level earthquakes recognized in codes. tion systems are used in the PRESSS III
for precast seismic structural sys - During the loading in each direction, test building frames. They are:
tems.
• Provide acceptance of prestressing/
post-ten sioning of precast seismic
systems.
• Provide experimental proof of over-
all building performance under seis-
mic excitation.
• Establish a consistent set of design
recommendations for precast seis-
....
mic structural systems. ca
Q)
The PRESSS Ill test building con- .r:.
(/)
sists of frames in one direction and a
~
shear wall in the other, as shown in 0
Figs. 4 and 5. The floor system used in en
the first three levels is pretopped dou-
ble tees, and the top two levels consist
of topped hollow-core slabs. Tho se
choices were made in order to include -2 0 2 4 6
the two major structural framing sys- Drift (%)
tems commonly used in precast con-
struction today. Fig. 13. TCY gap frame hysteres is loop (from Ref. 7) .

March-April 1999 33
1,- 6"

r
~
MILD REINFORCING TOP AND COLUMN LONGITUDINAL REINFiORCING
BOTTOM IN METAL CORRUGAT[D
SLEEVE.S SOLID GROUTED

I!
I
1/2" JOINT- FILL W/ FIBER GROUT
3" WRAP REBAR II
IN SLEEVES TOP
AND BOTTOM -
~ II
II
l! ii / ADDITIONAL REINFiORCING
PER BEAM SECT70NS

\ liI ilI 1
....... I I
....... \ II
II
II
I
....... \
II
II
I
II
i I
\ II
II I
iii I
Iii
I
I
I
I
I
I
I
I
I
I
UNBONDED POST- TENSIONING I
USING DYWIDAG THREADBARS

~
Fig . 14. TCY frame interior joint (transverse reinforcement not shown for clarity). Note: 1 ft = 0.3048 m; 1 in . = 25.4 mm .

• Tension-Compression Yielding gle-bay beams, and are appropriate sioned connection are used in one
(TCY) gap connection for floor-by-floor construction. The seismic frame, referred to as the Pre-
• TCY connection pretensioned connection uses multi- Tensioned Frame, and the remaining
• Hybrid connection bay beams and single-story columns two connections are adopted in the
• Pretensioned connection and is appropriate for " up-and-out" other seismic frame , known as the
The first three types of connections construction. Tension-Compression Yielding Frame.
consist of multistory columns and sin- The hybrid connection and preten- These two frame elevations are shown
in Figs. 6 and 7 , respectively. The
amounts of energy dissipation and
residual displacement vary among the
200 four connections, allowing a designer
to control seismic behavior of the
150 structure with .an appropriate choice of
100 connection system.
en
c.
;g. 50 -- Hybrid Frame
iii The hybrid connection was devel-
Q)
.c: 0
en oped during the last phase of a multi-
-50 year project at the National Institute of
~
Standards and Technology (NIST). 6
tA -100 The hybrid frame interior joint is
-150
shown in Fig. 8. The beams are con-
nected to multistory columns by un-
-200 bonded post-tensioning strand s that
-8 -6 -4 -2 0 2 4 6 8 10 run through a duct in the center of the
Drift (%) beam and through the columns. Mild
steel reinforcement is placed in ducts
Fig. 15 . TCY frame hysteresis loop (from Ref. 7). at the top and bottom of the beam,
34 PCI JOURNAL
through the column, and is grouted. It tension and compression without frac- PRESSS ill test building, the connec-
yields alternately in tension and com- ture. Since the gap opens on one side tion has been included since it is con-
pression and provides energy dissipa- of the column as it closes on the other ceptually very similar to traditional
tion (see Fig. 9). The amount of mild side by an equal amount, the length of methods of construction. If vertical
steel reinforcement and post-tension- the frame does not change, even as the slip starts to occur at the ends of these
ing steel are balanced so that the frame connection yields. The TCY gap con- beams, steel corbels will be installed
re-centers after a major seismic event. nection tested in a PRESSS Phase II during the test so that slip does not ad-
The exterior joint of the Hybrid research program 7 used a coupler to versely affect the overall test results.
Frame uses a "stub" beam that con- splice the reinforcing steel through the
tains the multistrand anchor. This is column, rather than the sleeve through Fra me Columns
only required due to the scale of the the column shown in Fig. 12. The frame columns used for all sys-
test building. Research 8 indicates that The hysteresis loop obtained in tems contain both mild steel reinforce-
anchors located within the joint may PRESSS Phase II shows that this sys- ment and post-tensioning bars (see
actually improve joint performance. tem7 was performing as expected, and Figs. 8, 10, 12 and 14). The post-ten-
dissipated significant energy, until sioning bars are intended to represent
Prel e nsioned Fra me premature failure of the reinforcing the equivalent dead loads based on the
The PreTensioned frame, named so bar couplers at the top of the beam prototype structure, but their inclusion
as to differentiate it from just any failed the connection (see Fig. 13). in the test will also validate that this
frame constructed with pretensioned The possibility of a premature failure method of adding vertical load to a
members, is intended to be used for of this type is eliminated by the precast column is an effective way to
construction where the most economi- sleeved connection. influence system performance.
cal method consists of using one-story In addition, the columns in the pre-
columns with multi-span beams. TCY Fra me stressed concrete frame are preten-
Long, multi-span beams are cast in sioned up to the fourth level of the
The TCY frame connection at -
normal pretensioned casting beds, building. This bonded prestressing
tempts to model a traditional tension/
with specified lengths of the preten- economically adds strength to the
compression yielding connection,
sioning strand debonded. columns, which are prevented from
similar to what is used in cast-in-place
These beams are then set on one- yielding using capacity based design.
construction. However, rather than
story columns with the column rein- These details will validate the perfor-
distributed yielding over a finite plas-
forcing steel extending through mance of pretensioned frame columns.
tic hinge length, yielding is concen-
sleeves in the beams. Reinforcing bar
trated at the connection. To ensure
splices ensure the continuity of the Building Fra me Choices
that the beam reinforcement that pro-
column above the beam, as shown in
vides moment strength and energy While it was never intended that
Fig. 10. As the frame displaces later-
dissipation does not fracture prema- multiple connection types would be
ally, the de bonded strand remains
turely at this concentrated yielding lo- used on different floors or in different
elastic. While the system dissipates
cation, it is debonded over a short frames of the same building in practice,
relatively less energy than other sys-
length at the beam -to-column inter- the PRESSS research team and indus-
tems7·9·'0 (see Fig. 11), it re-centers the
face (see Fig. 14). try advisors felt strongly that several
structure after a major seismic event.
This type of connection was also different frame systems should be in-
tested in PRESSS Phase II research cluded in the test building. The objec-
TCY Ga p Frame
program,7·9·10 where it showed slightly tive was to provide designers with sev-
The TCY gap frame addresses the pinched hysteretic behavior due to eral alternatives using precast concrete;
problem of frame beam elongation in vertical slip at the beam-to-column in- not just different ways of building con-
an innovative way. The beams are terface (see Fig. 15). Although this ceptually similar systems (e.g. , struc-
erected between columns leaving a type of behavior may also occur in the tural steel in Table 2), but systems with
small gap between the end of the beam
and the face of the column. Only the
bottom portion of this gap is grouted Table 2. Frame system alternatives.
to provide contact between the beam Cast-in-place concrete Masonry Structural steel Precast concrete
and column (see Fig. 12). Centered on
Special Moment Resist- Frame per code Dog bone Hybrid
this bottom grout region, post-tension-
ing Frame
ing bars clamp the frame together. At per code
the top of the beam, mild steel rein-
- - Cover plates Pretensioned
forcement is grouted into sleeves that
extend the length of the beam and - - Meyers Nelson Tension/compression
Houghton connect ion yielding gap
through the column. - I--
- - Others Tension/compression
The reinforcing steel is carefully
yielding
debonded for a specified length at the -
gap so that it can yield alternately in - - - Others

March-April 1999 35
fundamentally different types of behav- cused on "tuning" jointed walls to testing laboratory, only one jointed
ior that might be appropriate for differ- lengthen the structural period and re- wall system is incorporated in the test
ent situations. This, as shown in Table duce the design base shear forces. The building. Instead of limiting the lateral
2, will provide versatility using precast focus was on evaluating elastic stiff- loads to those that could be resisted by
concrete that is not currently available ness, without explicit consideration of the inherent gravity loads in the sys-
using any other building material. ductility . Elastic forces were dis- tem , vertical unbonded post-tension-
In addition , by validating several tributed so that sufficient resistance to ing is used to resist overturning in this
different frame types, it is hoped that overturning was provided by the grav- wall system.
future innovations can fit into the ity loads on the system. U-shaped flexure plates (UFP) , as
framework developed by the PRESSS The PRESSS test building takes this tested in PRESSS Phase II,' ' are used
research program, through component concept one step further by consider- for vertical joint connection devices
testing rather than requiring additional ing the behavior of the jointed shear where damping is achieved by means
large-scale building tests. wall system when the wall lifts off and of flexural yielding of the plates. The
rocks, together with its effect on de- unbonded post-tensioning is designed
sign forces. An appropriate level of to re-center the wall system when the
Wall System hysteretic damping is added to the load is removed so there will be no
For the past several years, the PCI wall system through the connection residual drift after a design-level earth-
Ad Hoc Committee on Precast Walls devices located at the vertical joint be- quake. Re-centering is ensured by re-
has been promoting precast shear tween the wall panels. lating the elastic capacity of the post-
walls as seismic resisting systems for Due to limitations on the building tensioning system to the yield strength
all seismic zones. 5 This work has fo- size, imposed by the dimensions of the of the panel-to-panel connections.' 2
Fig. 16 shows the shear wall eleva-
tion, with unbonded post-tensioning
located at the center of each panel.
The shear wall is expected to displace
TCYFrame Prestressed
Frame
laterally to approximately 2 percent
UnbondedPT
UFP Connectors

I r j story drift under a design-level earth-


quake. This is consistent with the drift
limits specified in both the UBC 2 and
NEHRP provisions. 3
This lateral displacement requires a
vertical panel-to-panel displacement
of about 2 in. (51 mm) for the 9 ft
'
"'' (2.74 m) panel. Thus, the UFP connec-
tion shown in Fig. 17 was chosen for
Panel3 Wall its ability to retain its force capacity
through this large displacement. The
post-tensioning was designed to be
just at the point of yielding at 2 per-
cent drift. Should the designer desire a
smaller design story drift, or less en-
ergy dissipation, simpler panel con-
Ill
nections could be used.

DIRECT DISPLACEMENT
"'' Wall Panel! Wall BASED DESIGN
As noted previously, Force Based
Design represents the behavior of
jointed precast systems poorly. The
method relies on an initial elastic pe-
riod, which is not only difficult to
compute in a system whose flexibility
resides largely in the connections, but
15 ' - 0" 15'- 0 "
also has little influence on the post-
elastic behavior of the structure. The R
factors included in design codes are
also not intended to be applied to sys-
Fig. 16. Elevation of jointed shear wall system. Note: 1 ft = 0.3048 m; 1 in.= 25.4 mm. tems, such as some of those used here,
36 PCI JOURNAL
which do not emulate monolithic con-
4 114" crete structures. Thus, the results ob-
tained by representing the seismic per-
formance of precast systems using
FLEXURE PL to
EMBED PL a Force Based Design approach are
questionable.
For this reason, the test building was
ASTM TYPE 304 STAINLESS
STEEL BENT FLEXURE PL
designed using a more consistent Di-
J/B~lsl 3/4"1NSIDE
RADIUS - TYPICAL OF 2
rect Displacement Based Design
(DBD) procedure,< in which the design
3/4"11 ERECTION BOLT
(TYPICAL OF 2) is based directly on an inelastic target
displacement and effective stiffness.
The target structural displacement is
EMBED PL5/8KBK2'-0" determined from an allowable inter-
W/ (B) 5/B"tl~<6" LONG story drift permitted by design codes
WELDED STUDS (2 ROWS
OF 4) and (4) /5~<2'-6"
A706, GRADE 60 BARS while the effective stiffness is approxi-
(2 ROWS OF 2) WELDED
TO PL mated to the secant stiffness of the
building corresponding to its expected
fundamental mode of response. Use of
both the elastic stiffness for determin-
ing inelastic structural displacements
and arbitrary reduction factors, as in
Fig. 17. Detail of U-shaped flexure plate. Note: 1 ft =0. 3048 m ; 1 in . = 25.4 mm. Force Based Design, are completely
eliminated in this design approach.

Direct Displacement Based


Design Procedure
Choose the design drift ad and
thus&- Direct Displacement Based Design
(DBD) is a process that is intended to
ensure that the structure reaches, but
does not exceed, a target displacement
Estimate 1; -overall damping of
the structure
selected by the designer, in response to
a given ground motion. In this method
the true hysteretic behavior is replaced
by a linear system in which the stiff-
Model structure as a SIXJF. ness is equal to the true secant stiffness
Define mode shape and M.H. and the viscous damping provides the
same energy dissipation per cycle.
The DBD design procedure , as
Obtain Te« for SIXJF from&-
adopted in the test building, is illus-
trated in Fig. 18. Once the target drift
Establish true structural dampinJt is chosen, the damping is estimated for
the building using prior component
test results. Representing the building
, . . - - - - 1;=25% with a SDOF system, the fundamental
period corresponding to the target dis-
placement is found from the displace-
ment spectrum. The effective stiffness
is computed from the known mass and
the estimated period.
Design structural members The design base shear is then ob-
tained from the effective stiffness and
target displacement. Member sizes and
reinforcement are chosen to resist this
Compute design base sheer Compute member forces base shear. The true physical proper-
Vd=I<dt&- corresponding to vd. ties of the members are used to gener-
ate a more refined, hysteretic, force-
displacement curve. The effective
Fig. 18. Flowchart showing Direct-Displacement Based Design method. damping is calculated from the hys-
March-April 1999 37
li)

-m
Q.
:i2 5000 +--"""""--'-__;.....;.-.o....-,,...__,......,=::::= c------l

.c
4000 +---------------~-4
(/)

~ 3000 +---r---~--~~~
~ • Force Based Design ~~
8. 2000 • Direct Displacement Based
&;o Design
g 1000 '-------
e
a.
Fig . 19. 0
Comparison of Frame System Wall System
design base shears.

teresis loop area and is checked University of California at San Diego, gram if its benefits are to be fully uti-
against the assumed value. If they dif- as of the publication date of this lized. Then, precast concrete will truly
fer significantly , the process is re- paper. Following the comp letion of be the "solution of choice" in all seis-
peated with a new value of assumed the building in April 1999, testing is mic regions of the world.
damping. This final step is only neces- scheduled to begin in May. Testing is
sary because of the lack of informa- expected to be complete by July 1999,
ACKNOWLEDGMENTS
tion on global hesteretic damping for with analysis and reports to follow.
the systems used in the test building. The report on design recommenda- The PRESSS research program is
tions is scheduled for completion by funded by grants from the National
August 2000. Science Foundation, the Precast/Pre-
Results of Direct Displacement
stressed Concrete Institute, the Pre-
Based Design
cast/Prestressed Concrete Manufactur-
For the PRESSS III prototype build- CONCLUDING REMARKS ers Association of California, Inc., and
ing , Direct Displacement Based De- The PRESSS Phase III test building by various precasters and suppliers.
sign resulted in a design base shear and Design Recommendations will val- Their contributions are gratefully ac-
noticeably lower than would be used idate the seismic performance of five knowledged.
for force based design. For the proto- different ductile precast concrete sys- In addition to the design and testing
type building, the design base shears tems. These systems are economical components of the PRESSS III project
are as follows : even using Force Based Design, but (NSF Grant Numbers CMS 97-10735
Frame direction: will be even more advantageous once (UW) and CMS 97-00125 (UCSD) ,
Design base shear= 1467 kips (6525 kN) their beneficial attributes can be di- analysis of the test structure is being
rectly taken into account using Direct performed by Lehigh University (NSF
Wall direction: Displacement Based Design (DBD). Grant Number CMS 97-08627). Their
Design base shear = 2223 kips (9888 kN) As is clear in the design of the test analysis is based on the methods de-
In the frame direction, this is 65 per- building, the benefits of the DBD ap- veloped in Refs. 13, 14 and 15.
cent of the equivalent Force Based De- proach to precast concrete buildings The technical input provided by
sign base shear, resulting in a substan- are substantial. Following validation many PCI members, especially by
tial cost savings. In the wall direction, of this design method by the PRESSS PCI 's Ad Hoc Committee on ATLSS
the savings are similar, even if the III test building, a coordinated effort and PRESSS under the chairmanship
lengthened period is used in Force can hasten the development of design of Mario Bertolini, has played a sig-
Based Design. The wall direction DBD recommendations. Once the design nificant role in the planning, develop-
base shear is just 45 percent of the recommendations are published, the ment, and execution of this program.
equivalent Force Based Design value precast industry should be well posi- Also, M. J. Nigel Priestley, the princi-
(see Fig. 19). Clearly, the improved tioned to implement the DBD ap- pal coordinator of the PRESSS re-
performance of these systems can also proach and facilitate its acceptance search program, played a key role in
result in substantial cost savings over into building codes. providing leadership through all
traditional structural systems. Recently, several codes have in- phases of this research.
cluded sections on precast concrete During the design of the test build-
seismic systems, but they apply pri- ing , the following members of the
TESTING SCHEDULE marily to emulative systems. These PRESSS Phase III research team and
The PRESSS III test building is sections should be expanded to cover Industry Advisory Group provided in-
under construction in the Charles Lee jointed systems and to incorporate the valuable guidance and their contribu-
Powell Structural Laboratory of the results of the PRESSS research pro- tions are greatly appreciated:
38 PCI JOURNAL
Industry Advisory Group Pomeroy Corporation Washington, Seattle, W A, March
Spancrete of California 1999.
Mario J. Bertolini, Chairman
Sumiden Wire 9. Palmieri, L., and French, C., "Ductile
Robert Clark
Their support and donations are Moment-Resisting Connections for
Ned M. Cleland Precast Frames in Seismic Regions:
Thomas J. D'Arcy gratefully acknowledged.
Experimental Study," Manuscript
Robert E. Englekirk submitted to PCI JOURNAL for
S. K. Ghosh REFERENCES publication.
Paul Johal 10. Palmieri, L., and French, C., "Ductile
1. Priestley, M. J. N., "The PRESSS Pro-
Robert Konoske Moment-Resisting Connections for
gram - Current Status and Proposed
H. S. Lew Precast Frames in Seismic Regions:
Plans for Phase III," PCI JOURNAL,
Robert F. Mast Numerical Simulation," Manuscript
V. 41, No. 2, March-April 1996, pp.
Doug Mooradian submitted to PCI JOURNAL for
22-40.
John G. Nanna publication.
2. Uniform Building Code, International
David C. Seagren 11. Schultz, A. E., and Magana, R. A.,
Conference of Building Officials,
"Seismic Behavior of Connections in
Edward A. Wopschall Whittier, CA, 1997.
Precast Concrete Walls," Paper No.
3. Building Seismic Safety Council,
SP162-12, Mete A. Sozen Sympo-
PRESSS Researchers NEHRP Recommended Provisions for
sium, ACI SP 162, American Concrete
Seismic Regulations for New Buildings
M. J. Nigel Priestley, Principal Institute, Farmington Hills, MI, 1996,
and Other Structures, National Earth-
Coordinator quake Hazard Reduction Program, pp. 273-311.
Catherine French Washington, D.C., 1997. 12. Kurama, Y., Pessiki, S., Sause, R., and
Neil M. Hawkins 4. Priestley, M. J. N., "Displacement- Lu, L.-W., "Seismic Behavior and De-
Rebecca Hix Based Approaches to Rational Limit sign of Unbonded Post-Tensioned Pre-
States Design of New Structures," Pre- cast Concrete Walls," PCI JOURNAL,
Michael E. Kreger
sented at the Eleventh European Con- V. 44, No.3, May-June 1999.
Le-WuLu
ference on Earthquake Engineering, 13. Perez, F., Pessiki, S., and Sause, R.,
Suzanne D. Nakaki "Lateral Load Behavior and Design of
Paris, September 1998.
Stephen P. Pessiki U nbonded Post-Tensioned Precast
5. PCI Ad Hoc Committee on Precast
Richard Sause Concrete Walls with Ductile Vertical
Walls, "Design for Lateral Force Re-
Frieder Seible sistance with Precast Concrete Shear Joint Connectors," ATLSS Report No.
S. (Sri) Sritharan Walls," PCI JOURNAL, V. 42, No. 5, 99-01, Center for Advanced Technol-
John F. Stanton September-October 1997, pp. 44-65. ogy for Large Structural Systems,
6. Stanton, J. F., Stone, W. C., and Lehigh University, Bethlehem, PA,
In addition, various producers and January 1999.
Cheok, G. S., "A Hybrid Reinforced
suppliers have donated significant Precast Frame for Seismic Regions," 14. El-Sheikh, M., Sause, R., Pessiki, S.,
products and effort to allow the five PCI JOURNAL, V. 42, No. 2, March- Lu, L.-W., and Kurama, Y., "Seismic
different systems to be tested. They April1997, pp. 20-32. Analysis, Behavior, and Design of Un-
are: 7. Palmieri, L., Sagan, E., French, C., bonded Post-Tensioned Precast Con-
A. T. Curd Structures, Inc. and Kreger, M., "Ductile Connections crete Frames," PRESSS Report No.
for Precast Concrete Frame Systems," 98/04 (also Report No. EQ-97-02),
Charles Pankow Builders, Ltd.
Paper No. SP162-13, Mete A. Sozen Department of Civil and Environmen-
Clark Pacific tal Engineering, Lehigh University,
Symposium, ACI SP 162, American
Coreslab Structures, L.A. Bethlehem, PA, November 1997.
Concrete Institute, Farmington Hills,
Dywidag Systems International MI, 1997, pp. 313-355. 15. El-Sheikh, M., Sause, R., Pessiki, S.,
ERICO 8. Stanton, J. F., MacRae, G., Sugata, M., and Lu, L.-W., "Seismic Behavior of
Fontana Steel and Day, S., "Preliminary Test Report Unbonded Post-Tensioned Precast
Headed Reinforcement Corporation of a Hybrid Frame Exterior Beam-Col- Concrete Frames," PCI JOURNAL, V.
NMB Splice Sleeve umn Specimen Test," University of 44, No.3, May-June 1999.

March-April 1999 39

You might also like