A ABD-HMY-G-000 COVER
1 ABD-HMY-G-001 COVER PEKERJAAN GAS 16/02/2023 17/02/2023 A
C ABD-HMY-G-200 SKEMATIK
1 ABD-HMY-G-201 SKEMATIK INSTALASI PIPA GAS 16/02/2023 17/02/2023 A
A ABD-HMY-EL-000 COVER
1 ABD-HMY-EL-001 COVER PEKERJAAN ELEKTRIKAL 20/02/2023 17/03/2023 A
C ABD-HMY-EL-200 SIMBOL
1 ABD-HMY-EL-201 SIMBOL PEKERJAAN ELEKTRIKAL 20/02/2023 08/03/2023 C
D ABD-HMY-EL-300 SKEMATIK
1 ABD-HMY-EL-301 SKEMATIK UTAMA KELISTRIKAN 20/02/2023 28/02/2023 C
2 ABD-HMY-EL-302 SKEMATIK BAHAN BAKAR GENSET 20/02/2023 28/02/2023 C
3 ABD-HMY-EL-303 SKEMATIK PENTANAHAN LVMSB-9 & TRAFO 20/02/2023 28/02/2023 C
4 ABD-HMY-EL-304 SKEMATIK PENTANAHAN NETRAL & BODY GENSET 20/02/2023 28/02/2023 A
ABD-HMY-EL-401 LANTAI GF
1 ABD-HMY-EL-401-A1 INSTALASI LAMPU EX PARKSON LANTAI GF 14/01/2023 14/02/2023 A
2 ABD-HMY-EL-401-A2 INSTALASI STOP KONTAK EX PARKSON LANTAI GF 14/01/2023 14/02/2023 A
3 ABD-HMY-EL-401-B1 INSTALASI LAMPU LOBBY LAMPU DROP OFF LANTAI GF 14/01/2023 14/02/2023 A
4 ABD-HMY-EL-401-B1 INSTALASI LAMPU LOBBY LAMPU RAMP LANTAI GF 14/01/2023 14/02/2023 C 20/02/2023 08/03/2023 A
ABD-HMY-EL-402 LANTAI UG
5 ABD-HMY-EL-402-A1 INSTALASI LAMPU SECOND CORRIDOR LANTAI UG 18/01/2023 06/02/2023 A
6 ABD-HMY-EL-402-A2 INSTALASI STOP KONTAK SECOND CORRIDOR LANTAI UG 18/01/2023 06/02/2023 A
ABD-HMY-EL-403 LANTAI 1
14 ABD-HMY-EL-403-A1 INSTALASI LAMPU SECOND CORRIDOR LANTAI 1 16/01/2023 06/02/2023 A
15 ABD-HMY-EL-403-A2 INSTALASI STOP KONTAK SECOND CORRIDOR LANTAI 1 16/01/2023 06/02/2023 A
ABD-HMY-EL-404 LANTAI 2
21 ABD-HMY-EL-404-A1 INSTALASI LAMPU SECOND CORRIDOR LANTAI 2 13/01/2023 03/02/2023 A
22 ABD-HMY-EL-404-A2 INSTALASI LAMPU TOILET PUBLIK BARU LANTAI 2 13/01/2023 03/02/2023 A
23 ABD-HMY-EL-404-A3 INSTALASI STOP KONTAK TOILET PUBLIK BARU LANTAI 2 13/01/2023 03/02/2023 A
ABD-HMY-EL-405 LANTAI 3
24 ABD-HMY-EL-405-A1 INSTALASI LAMPU MANAGEMENT OFFICE LANTAI 3 20/02/2023 08/03/2023 C
25 ABD-HMY-EL-405-A2 INSTALASI STOP KONTAK MANAGEMENT OFFICE LANTAI 3 20/02/2023 08/03/2023 A
ABD-HMY-EL-502 LANTAI LG
2 ABD-HMY-EL-502-A1 INSTALASI TRAY LANTAI LG 14/04/2023
ABD-HMY-EL-503 LANTAI GF
3 ABD-HMY-EL-503-A1 INSTALASI TRAY LANTAI GF 14/04/2023
ABD-HMY-EL-504 LANTAI UG
5 ABD-HMY-EL-504-A1 INSTALASI TRAY LANTAI UG 14/04/2023
ABD-HMY-EL-505 LANTAI 1
7 ABD-HMY-EL-505-A1 INSTALASI TRAY LANTAI 1 14/04/2023
ABD-HMY-EL-506 LANTAI 2
9 ABD-HMY-EL-506-A1 INSTALASI TRAY LANTAI 2 14/04/2023
ABD-HMY-EL-507 LANTAI 3
11 ABD-HMY-EL-507-A1 INSTALASI TRAY LANTAI 3 14/04/2023
ABD-HMY-EL-602 LANTAI LG
6 ABD-HMY-EL-602-A1 INSTALASI KABEL FEEDER LANTAI LG 14/04/2023
ABD-HMY-EL-603 LANTAI GF
6 ABD-HMY-EL-603-A1 INSTALASI KABEL FEEDER LANTAI GF 14/04/2023
ABD-HMY-EL-604 LANTAI UG
8 ABD-HMY-EL-604-A1 INSTALASI KABEL FEEDER LANTAI UG 14/04/2023
ABD-HMY-EL-605 LANTAI 1
11 ABD-HMY-EL-605-A1 INSTALASI KABEL FEEDER LANTAI 1 14/04/2023
ABD-HMY-EL-606 LANTAI 2
14 ABD-HMY-EL-606-A1 INSTALASI KABEL FEEDER LANTAI 2 14/04/2023
ABD-HMY-EL-607 LANTAI 3
16 ABD-HMY-EL-607-A1 INSTALASI KABEL FEEDER LANTRAI 3 14/04/2023
MCC-FCU-TOILET-1 BY MVAC
PP/AC-GF (NEW) BY MVAC
PP/AC-OU-ATAP 1 (NEW) BY MVAC
PP/AC-FAN-ATAP (NEW) BY MVAC
PP/AC-FAN-ATAP-2 BY MVAC
A ABD-HMY-EL-000 COVER
1 ABD-HMY-EL-001 COVER PEKERJAAN ELEKTRIKAL
C ABD-HMY-EL-200 SIMBOL
1 ABD-HMY-EL-201 SIMBOL PEKERJAAN ELEKTRIKAL
D ABD-HMY-EL-300 SKEMATIK
1 ABD-HMY-EL-301 SKEMATIK UTAMA KELISTRIKAN
2 ABD-HMY-EL-302 SKEMATIK BAHAN BAKAR GENSET
3 ABD-HMY-EL-303 SKEMATIK PENTANAHAN LVMSB-9 & TRAFO
4 ABD-HMY-EL-304 SKEMATIK PENTANAHAN NETRAL & BODY GENSET
3 ABD-HMY-EL-401-B1 INSTALASI LAMPU LOBBY DROP OFF & LAMPU RAMP LANTAI GF
ABD-HMY-EL-402 LANTAI UG
4 ABD-HMY-EL-402-A1 INSTALASI LAMPU SECOND CORRIDOR LANTAI UG
5 ABD-HMY-EL-402-A2 INSTALASI STOP KONTAK SECOND CORRIDOR LANTAI UG
ABD-HMY-EL-403 LANTAI 1
11 ABD-HMY-EL-403-A1 INSTALASI LAMPU SECOND CORRIDOR LANTAI 1
12 ABD-HMY-EL-403-A2 INSTALASI STOP KONTAK SECOND CORRIDOR LANTAI 1
ABD-HMY-EL-404 LANTAI 2
17 ABD-HMY-EL-404-A1 INSTALASI LAMPU SECOND CORRIDOR LANTAI 2
16 ABD-HMY-EL-404-A2 INSTALASI LAMPU TOILET PUBLIK BARU LANTAI 2
19 ABD-HMY-EL-404-A3 INSTALASI STOP KONTAK TOILET PUBLIK BARU LANTAI 2
ABD-HMY-EL-405 LANTAI 3
20 ABD-HMY-EL-405-A1 INSTALASI LAMPU MANAGEMENT OFFICE LANTAI 3
21 ABD-HMY-EL-405-A5 INSTALASI STOP KONTAK MANAGEMENT OFFICE LANTAI 3
ABD-HMY-EL-502 LANTAI LG
2 ABD-HMY-EL-502-A1 INSTALASI TRAY LANTAI LG
ABD-HMY-EL-503 LANTAI GF
3 ABD-HMY-EL-503-A1 INSTALASI TRAY LANTAI GF
ABD-HMY-EL-504 LANTAI UG
4 ABD-HMY-EL-504-A1 INSTALASI TRAY LANTAI UG
ABD-HMY-EL-505 LANTAI 1
5 ABD-HMY-EL-505-A1 INSTALASI TRAY LANTAI 1
ABD-HMY-EL-506 LANTAI 2
6 ABD-HMY-EL-506-A1 INSTALASI TRAY LANTAI 2
ABD-HMY-EL-507 LANTAI 3
7 ABD-HMY-EL-507-A1 INSTALASI TRAY LANTAI 3
ABD-HMY-EL-602 LANTAI LG
ABD-HMY-EL-603 LANTAI GF
3 ABD-HMY-EL-603-A1 INSTALASI KABEL FEEDER EX PARKSON LANTAI GF
ABD-HMY-EL-604 LANTAI UG
5 ABD-HMY-EL-604-A1 INSTALASI KABEL FEEDER KONTRAK & TAMBAHAN SECOND CORRIDOR LANTAI UG
6 ABD-HMY-EL-604-A2 INSTALASI KABEL FEEDER EX PARKSON LANTAI UG
ABD-HMY-EL-605 LANTAI 1
8 ABD-HMY-EL-605-A1 INSTALASI KABEL FEEDER KONTRAK & TAMBAHAN SECOND CORRIDOR LANTAI 1
9 ABD-HMY-EL-605-A2 INSTALASI KABEL FEEDER EX PARKSON LANTAI 1
ABD-HMY-EL-606 LANTAI 2
11 ABD-HMY-EL-606-A1 INSTALASI KABEL FEEDER KONTRAK & TAMBAHAN SECOND CORRIDOR LANTAI 2
ABD-HMY-EL-607 LANTAI 3
13 ABD-HMY-EL-607-A1 INSTALASI KABEL FEEDER & KABEL POWER AC LANTAI 3
ABD-HMY-EL-609 TOB-SDB-1
16 ABD-HMY-EL-609-A1 INSTALASI KABEL FEEDER TOB-SDB-1 LANTAI LG
17 ABD-HMY-EL-609-A2 INSTALASI KABEL FEEDER TOB-SDB-1 R. PANEL 1 LANTAI GF
18 ABD-HMY-EL-609-A3 INSTALASI KABEL FEEDER TOB-SDB-1 R. PANEL 2 LANTAI GF
19 ABD-HMY-EL-609-A4 INSTALASI KABEL FEEDER TOB-SDB-1 LANTAI ATAP
ABD-HMY-EL-610 TOB-SDB-5
20 ABD-HMY-EL-610-A1 INSTALASI KABEL FEEDER TOB-SDB-5 LANTAI LG
21 ABD-HMY-EL-610-A2 INSTALASI KABEL FEEDER TOB-SDB-5 R. PANEL 2 LANTAI GF
22 ABD-HMY-EL-610-A3 INSTALASI KABEL FEEDER TOB-SDB-5 LANTAI ATAP
ABD-HMY-EL-611 TOB-SDB-6
23 ABD-HMY-EL-611-A1 INSTALASI KABEL FEEDER TOB-SDB-6 R. PANEL 2 LANTAI GF
24 ABD-HMY-EL-611-A2 INSTALASI KABEL FEEDER TOB-SDB-6 R. PANEL 2 LANTAI UG
25 ABD-HMY-EL-611-A3 INSTALASI KABEL FEEDER TOB-SDB-6 R. PANEL 2 LANTAI 2
ABD-HMY-EL-612 TOB-SDB-7
26 ABD-HMY-EL-612-A1 INSTALASI KABEL FEEDER TOB-SDB-6 R. PANEL 2 LANTAI GF
27 ABD-HMY-EL-612-A2 INSTALASI KABEL FEEDER TOB-SDB-6 R. PANEL 2 LANTAI UG
28 ABD-HMY-EL-612-A3 INSTALASI KABEL FEEDER TOB-SDB-6 R. PANEL 2 LANTAI 2
23 ABD-HMY-EL-723 HDB-UG
24 ABD-HMY-EL-724 HDB-L1
25 ABD-HMY-EL-725 DB-SUB-HTL-G
26 ABD-HMY-EL-726 SUB-HDB-GF-2
27 ABD-HMY-EL-727 SUB-HDB-UG-2
28 ABD-HMY-EL-728 MCC-FCU-TOILET-1
29 ABD-HMY-EL-729 PANEL HOIST MAIN ATRIUM
29 ABD-HMY-EL-730 PANEL TOB - SDB
Ground Floor
4 DB/RTL-GF 1 (NEW) 25/09/2021 B 11/02/2022 B 08/03/2022 ON SITE
5 DB/RTL-GF 2 (NEW) 25/09/2021 B 11/02/2022 B 30/03/2022 B 27/05/2022 ON SITE
6 DB-AUX 25/09/2021 B 24/12/2021 B 31/01/2021 C 22/02/2022 ON SITE
7 HDB-GF-2 25/09/2021 B 24/12/2021 B 12/02/2022 B 08/03/2022 ON SITE
Upper Ground
8 DB/RTL-UG 1 (NEW) 25/09/2021 B 29/03/2022 04/10/2021 ON SITE
9 DB/RTL-UG 2 (NEW) 25/09/2021 B 29/03/2022 C 23/06/2022 27/04/2021 ON SITE
10 PP/RTL-UG-KIOS 25/09/2021 B 12/02/2022 B 12/03/2022 ON SITE
11 HDB-UG-2 25/09/2021 C 09/02/2022 B 22/02/2022 ON SITE
1st Floor
12 DB/RTL-L1 1 (NEW) 25/09/2021 B 12/02/2022 B 29/03/2022 B 13/06/2022 ON SITE
13 DB/RTL-L1 2 (NEW) 25/09/2021 B 29/03/2022 B 13/05/2022 ON SITE
14 PP/RTL-L1-KIOS 25/09/2021 B 12/02/2022 B 12/03/2022 ON SITE
15 HDB-L1-2 25/09/2021 B 09/02/2022 B 22/02/2022 ON SITE
2nd Floor
16 DB/RTL-L2 (NEW) 25/09/2021 B 06/01/2022 B 29/03/2022 20/01/2022 ON SITE
17 HDB-L2.1 25/09/2021 B 24/12/2021 B 12/02/2022 B 08/03/2022 ON SITE
3rd Floor
18 DB/OFF-L3 (NEW) 25/09/2021 B 26/10/2021 ON SITE
PANEL PEKERJAAN AC
19 PP/AC-GF (NEW) 25/09/2021 B 12/02/2022 B 12/03/2022 ON SITE
20 PP/AC-OU-ATAP 1 (NEW) 25/09/2021 B 24/12/2021 B 12/02/2022 B 23/06/2022 B 14/07/2022 ON SITE
21 PP/AC-FAN-ATAP (NEW) 25/09/2021 C 24/12/2021 B 09/02/2022 B 23/03/2022 ON SITE
GROUNDING BOX
28 GROUNDING BOX-1 (BODY GENSET) 28/07/2022 PP
29 GROUNDING BOX-2 (BODY GENSET) 28/07/2022 PP
30 GROUNDING BOX-3 (NETRAL GENSET) 28/07/2022 PP
MONITORING ASBUILT DRAWING ELEKTRIKAL 1/12/2023
PROYEK HARTONO MALL YOGYAKARTA PHASE 1
SCHEDULLE
A COVER
1 COVER PEKERJAAN ELEKTRIKAL
B DAFTAR GAMBAR
1 DAFTAR GAMBAR PEKERJAAN ELEKTRIKAL
C SIMBOL
1 SIMBOL PEKERJAAN ELEKTRIKAL
D SKEMATIK
1 SKEMATIK UTAMA KELISTRIKAN
3 INSTALASI LAMPU LOBBY DROP OFF & LAMPU RAMP LANTAI GF ON PROSES
LANTAI UG
4 INSTALASI LAMPU SECOND CORRIDOR LANTAI UG ON PROSES
5 INSTALASI STOP KONTAK SECOND CORRIDOR LANTAI UG ON PROSES
LANTAI 1
12 INSTALASI LAMPU SECOND CORRIDOR LANTAI 1 ON PROSES
13 INSTALASI STOP KONTAK SECOND CORRIDOR LANTAI 1 ON PROSES
LANTAI 2
19 INSTALASI LAMPU SECOND CORRIDOR LANTAI 2 ON PROSES 13/01/2023
20 INSTALASI LAMPU TOILET PUBLIK BARU LANTAI 2 ON PROSES 13/01/2023
21 INSTALASI STOP KONTAK TOILET PUBLIK BARU LANTAI 2 ON PROSES 13/01/2023
LANTAI 3
22 INSTALASI LAMPU MANAGEMENT OFFICE LANTAI 3
23 INSTALASI STOP KONTAK MANAGEMENT OFFICE LANTAI 3
24 INSTALASI DATA & TELEPON MANAGEMENT OFFICE LANTAI 3
F INSTALASI TRAY
LANTAI GF
1 INSTALASI TRAY LANTAI GF
2 DETAIL INSTALASI TRAY R. PANEL LANTAI GF
LANTAI UG
3 INSTALASI TRAY LANTAI UG
4 DETAIL INSTALASI TRAY R. PANEL LANTAI UG
LANTAI 1
5 INSTALASI TRAY LANTAI 1
6 DETAIL INSTALASI TRAY R. PANEL LANTAI 1
LANTAI 2
7 INSTALASI TRAY LANTAI 2
8 DETAIL INSTALASI TRAY R. PANEL LANTAI 2
SCHEDULLE
LANTAI 3
9 INSTALASI TRAY LANTAI 3
10 DETAIL INSTALASI TRAY R. PANEL LANTAI 3
LANTAI ATAP
11 INSTALASI TRAY LANTAI ATAP
LANTAI UG
3 INSTALASI KABEL FEEDER KONTRAK & TAMBAHAN SECOND CORRIDOR LANTAI UG
4 INSTALASI KABEL FEEDER EX PARKSON LANTAI UG
LANTAI 1
5 INSTALASI KABEL FEEDER KONTRAK & TAMBAHAN SECOND CORRIDOR LANTAI 1
6 INSTALASI KABEL FEEDER EX PARKSON LANTAI UG
LANTAI 2
7 INSTALASI KABEL FEEDER KONTRAK & TAMBAHAN SECOND CORRIDOR LANTAI 2
8 INSTALASI KABEL FEEDER EX PARKSON LANTAI UG
LANTAI 3
9 INSTALASI KABEL FEEDER SECOND CORRIDOR LANTAI 3
10 INSTALASI KABEL POWER AC LANTAI 3
LANTAI ATAP
11 INSTALASI KABEL POWER AC LANTAI ATAP
I DETAIL PANEL
1 LV-MDP-9 + CAPACITOR BANK
2 DB/RTL-LG 2 (NEW)
3 DB-PH-LG
4 DB/RTL-GF 1 (NEW)
5 DB/RTL-GF 2 (NEW)
6 DB-AUX
7 HDB-GF-2
8 DB/RTL-UG 1 (NEW)
9 DB/RTL-UG 2 (NEW)
10 PP/RTL-UG-KIOS
11 HDB-UG-2
12 DB/RTL-L1 1 (NEW)
SCHEDULLE
13 DB/RTL-L1 2 (NEW)
14 PP/RTL-L1-KIOS
15 HDB-L1-2
16 DB/RTL-L2 (NEW)
17 HDB-L2.1
18 DB/OFF-L3 (NEW)
19 PP/AC-GF (NEW)
20 PP/AC-OU-ATAP 1 (NEW)
21 PP/AC-FAN-ATAP (NEW)
22 MCC-FUEL PUMP
23 HDB-UG
24 HDB-L1
25 DB-SUB-HTL-G
26 SUB-HDB-GF-2
27 SUB-HDB-UG-2
28 MCC-FCU-TOILET-1
29 PANEL HOIST MAIN ATRIUM
30 PP/AC-FAN-ATAP-2
J POWER HOUSE
1 INSTALASI KABEL LAMPU RUANG POWER HOUSE
2 INSTALASI TRAY & PENGKABELAN RUANG POWER HOUSE
3 INSTALASI KABEL POWER AC RUANG POWER HOUSE
K DETAIL STANDAR
1 DETAIL STANDAR