You are on page 1of 8

KEY PLAN SHOP DRAWING

NOTES

AA

AA
PARKING

PRODUCTION

AA
AA
AA

AA
AA

AA
AA
PT. LA M I P A C K A GI N G I N D ON E S I A
OWNER APPROVAL:

ARSA ARSA
2686.25 2686.25

CONTRACTOR :

DETAIL A
PT. CHINA STATE CONSTRUCTION
OVERSEAS DEVELOPMENT SHANGHAI
DISCIPLINE :
ARSA
2686.25
DETAIL B ARSA
2686.25
ARCHITECTURE
REFERENCES :
S6325SA-02-201

CHECK'D
DATE SIGN
BY

PM
Buffer

Airtight Room Buffer Airtight Room Buffer Buffer Airtight Room

CHIEF
TECH
platform

platform
STR

ARC

MEP

DRAWN
19-09-2023 YG
BY
PROJECT TITLE :

LAMIPAK INDONESIA NEW


PLANT PROJECT
BUILDING NAME :

WAREHOUSE
DRAWING TITLE :

BUILDING LAYOUT PLAN AAC WALL

CONTRACT / MOC. NO : SCALE : REV :

CSA 1 : 750 0
DRAWING NO : SHEET :
BUILDING LAYOUT PLAN AAC WALL
SCALE 1:750 CSCODS-LMIND-02-ARS-DWG-013 1/8
KEY PLAN SHOP DRAWING
NOTES

CORRIDOR TO WAREHOUSE

CORRIDOR TO WAREHOUSE

CORRIDOR TO WAREHOUSE

CORRIDOR TO WAREHOUSE
Distribution room

ARSA Distribution room


2774.49㎡ 7.2
ARSA
2612.25.00㎡

ARSA
ARSA 2526.25㎡
2686.25

Distribution room
Distribution room Buffer Buffer
Buffer Buffer

10 % 10 %

KP1
KP1 KP1 KP1 KP1
KP1 KP1 KP1

KP1
KP1 KP1 KP1 KP1 KP1 KP1 PT. LA M I P A C K A GI N G I N D ON E S I A
KP1 OWNER APPROVAL:

KP1
KP1 KP1 KP1 KP1 KP1 KP1
5% CONTRACTOR :
KP1

KP1
KP1 KP1 KP1 KP1 KP1 KP1 PT. CHINA STATE CONSTRUCTION
KP1 OVERSEAS DEVELOPMENT SHANGHAI
DISCIPLINE :
ARCHITECTURE
REFERENCES :
13950

KP1 KP1 KP1 KP1 KP1 KP1


12750

S6325SA-02-201
KP1 KP1 CHECK'D
DATE SIGN
BY

KP1 PM
KP1 KP1 KP1 KP1 KP1 KP1
KP1 CHIEF
TECH

STR
350

ARC

MEP

DRAWN
19-09-2023 YG
BY
PROJECT TITLE :

LAMIPAK INDONESIA NEW


PLANT PROJECT
BUILDING NAME :

WAREHOUSE
DRAWING TITLE :

BUILDING LAYOUT PLAN AAC WALL


WAREHOUSE - ELEVATION A
CONTRACT / MOC. NO : SCALE : REV :
BUILDING LAYOUT PLAN AAC WALL WAREHOUSE (ELEVATION - A) 1 : NTS 0
CSA
SCALE :NTS DRAWING NO : SHEET :

CSCODS-LMIND-02-ARS-DWG-013 2/8
KEY PLAN SHOP DRAWING
NOTES

CORRIDOR TO WAREHOUSE

CORRIDOR TO WAREHOUSE

CORRIDOR TO WAREHOUSE

CORRIDOR TO WAREHOUSE
Distribution room

ARSA Distribution room


2774.49㎡ 7.2
ARSA
2612.25.00㎡

ARSA
ARSA 2526.25㎡
2686.25

Distribution room
Distribution room Buffer Buffer
Buffer Buffer

BP1 BP1 BP1 BP1 BP1 BP1 BP1 BP1 BP1 BP1 BP1 BP1 BP1 BP1 BP1 BP1 BP1 BP1 BP1 BP1 BP1 BP1 BP1 BP1 BP1 BP1 BP1 BP1 BP1 BP1 BP1 BP1 BP1 BP1 BP1 BP1 BP1
KP1 KP1 KP1
KP1
KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1

KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1

KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1

KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1

KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1

KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1

BUILDING LAYOUT PLAN AAC WALL WAREHOUSE (ELEVATION B)


SCALE :NTS PT. LA M I P A C K A GI N G I N D ON E S I A
OWNER APPROVAL:

CONTRACTOR :

BP1 BP1 BP1 BP1 BP1 BP1 BP1 BP1 BP1 BP1 BP1
KP1 KP1

KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 PT. CHINA STATE CONSTRUCTION
OVERSEAS DEVELOPMENT SHANGHAI
DISCIPLINE :
ARCHITECTURE
REFERENCES :
KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 S6325SA-02-201

CHECK'D
DATE SIGN
BY

PM
KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1
CHIEF
TECH

STR
KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1
ARC

KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 MEP

DRAWN
19-09-2023 YG
BY
PROJECT TITLE :
KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 LAMIPAK INDONESIA NEW
PLANT PROJECT
BUILDING NAME :

WAREHOUSE
DRAWING TITLE :
BUILDING LAYOUT PLAN AAC WALL
ELEVATION B - PARTIAL A
CONTRACT / MOC. NO : SCALE : REV :

CSA 1 : NTS 0
DRAWING NO : SHEET :

BUILDING LAYOUT PLAN AAC WALL ELEVATION B (PARTIAL A)


CSCODS-LMIND-02-ARS-DWG-013 3/8
SCALE :NTS
SHOP DRAWING
NOTES

BP1 BP1 BP1 BP1 BP1 BP1 BP1 BP1 BP1 BP1 BP1

KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1

KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1

KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1
PT. LA M I P A C K A GI N G I N D ON E S I A
OWNER APPROVAL:

KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1
CONTRACTOR :

KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1
PT. CHINA STATE CONSTRUCTION
OVERSEAS DEVELOPMENT SHANGHAI
DISCIPLINE :
ARCHITECTURE
REFERENCES :
KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 S6325SA-02-201

CHECK'D
DATE SIGN
BY

PM

CHIEF
TECH

STR

ARC

MEP

DRAWN
19-09-2023 YG
BY
PROJECT TITLE :

LAMIPAK INDONESIA NEW


PLANT PROJECT
BUILDING NAME :

WAREHOUSE
DRAWING TITLE :

BUILDING LAYOUT PLAN AAC WALL


ELEVATION B - PARTIAL B
CONTRACT / MOC. NO : SCALE : REV :

CSA 1 : NTS 0
BUILDING LAYOUT PLAN AAC WALL ELEVATION B - PARTIAL B DRAWING NO : SHEET :

SCALE :NTS CSCODS-LMIND-02-ARS-DWG-013 4/8


SHOP DRAWING
NOTES

BP1 BP1 BP1 BP1 BP1 BP1 BP1 BP1 BP1 BP1 BP1

KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1

KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1

KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 PT. LA M I P A C K A GI N G I N D ON E S I A
OWNER APPROVAL:

KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 CONTRACTOR :

KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 PT. CHINA STATE CONSTRUCTION
OVERSEAS DEVELOPMENT SHANGHAI
DISCIPLINE :
ARCHITECTURE
REFERENCES :
S6325SA-02-201
KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 CHECK'D
DATE SIGN
BY

PM

CHIEF
TECH

STR

ARC

MEP

DRAWN
19-09-2023 YG
BY
PROJECT TITLE :

LAMIPAK INDONESIA NEW


PLANT PROJECT
BUILDING NAME :

WAREHOUSE
DRAWING TITLE :
BUILDING LAYOUT PLAN AAC WALL
ELEVATION B - PARTIAL C
BUILDING LAYOUT PLAN AAC WALL ELEVATION B - PARTIAL C
CONTRACT / MOC. NO : SCALE : REV :
SCALE :NTS
CSA 1 : NTS 0
DRAWING NO : SHEET :

CSCODS-LMIND-02-ARS-DWG-013 5/8
SHOP DRAWING
NOTES

BP1 BP1 BP1 BP1 BP1 BP1 BP1 BP1 BP1 BP1
KP1
KP1
KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1

KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1

PT. LA M I P A C K A GI N G I N D ON E S I A
OWNER APPROVAL:
KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1

CONTRACTOR :

KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1

PT. CHINA STATE CONSTRUCTION


OVERSEAS DEVELOPMENT SHANGHAI
KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 DISCIPLINE :
ARCHITECTURE
REFERENCES :
S6325SA-02-201

CHECK'D
DATE SIGN
BY
KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 KP1 PM

CHIEF
TECH

STR

ARC

MEP

DRAWN
19-09-2023 YG
BY
PROJECT TITLE :

LAMIPAK INDONESIA NEW


PLANT PROJECT
BUILDING NAME :

WAREHOUSE
DRAWING TITLE :

BUILDING LAYOUT PLAN AAC WALL


ELEVATION B - PARTIAL D
BUILDING LAYOUT PLAN AAC WALL ELEVATION B - PARTIAL D CONTRACT / MOC. NO : SCALE : REV :

SCALE :NTS CSA 1 : NTS 0


DRAWING NO : SHEET :

CSCODS-LMIND-02-ARS-DWG-013 6/8
SHOP DRAWING
NOTES
PRACTICAL COLUMN COLUMN STEEL

WELDING
WELDING
STEK Ø10 - 600 STEK Ø10 - 600

WELDING
WELDING

STEK Ø10 - 600 STEK Ø10 - 600

BLOCK WALL BLOCK WALL BLOCK WALL BLOCK WALL

PT. LA M I P A C K A GI N G I N D ON E S I A
WELDING
WELDING OWNER APPROVAL:

STEK Ø10 - 600 STEK Ø10 - 600


CONTRACTOR :

PT. CHINA STATE CONSTRUCTION


OVERSEAS DEVELOPMENT SHANGHAI
DISCIPLINE :
ARCHITECTURE
REFERENCES :
S6325SA-02-201

CHECK'D
DATE SIGN
BY

PM

CHIEF
TECH

STR

ARC
DETAIL CONNECTION KP1 DETAIL CONNECTION STEEL COLUMN
SCALE :NTS SCALE :NTS MEP

DRAWN
19-09-2023 YG
BY
PROJECT TITLE :

LAMIPAK INDONESIA NEW


PLANT PROJECT
BUILDING NAME :

WAREHOUSE
DRAWING TITLE :

BUILDING LAYOUT PLAN AAC WALL


DETAIL
CONTRACT / MOC. NO : SCALE : REV :

CSA 1 : NTS 0
DRAWING NO : SHEET :

1 DETAIL A CSCODS-LMIND-02-ARS-DWG-013 7/8


SCALE :NTS
SHOP DRAWING
NOTES

PT. L AM I P ACKA GI NG I NDO NE S IA


OWNER APPROVAL:

CONTRACTOR :

PT. CHINA STATE CONSTRUCTION


OVERSEAS DEVELOPMENT SHANGHAI
DISCIPLINE :
ARCHITECTURE
REFERENCES :
S6325SA-02-201

CHECK'D
DATE SIGN
BY

PM

CHIEF
TECH

STR
DETAIL B
SECTION 1
SCALE :NTS ARC
SCALE :NTS
MEP

DRAWN
19-09-2023 YG
BY
PROJECT TITLE :

LAMIPAK INDONESIA NEW


PLANT PROJECT
BUILDING NAME :

WAREHOUSE
DRAWING TITLE :

BUILDING LAYOUT PLAN AAC WALL


DETAIL
CONTRACT / MOC. NO : SCALE : REV :

CSA 1 : NTS 0
DRAWING NO : SHEET :

CSCODS-LMIND-02-ARS-DWG-013 8/8