Professional Documents
Culture Documents
MEN
U
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
REGULATION AND Recommended for building Recommended for the Suitable for the provision on
WORKS and engineering works provision of electrical a turnkey basis of a process
designed by the Employer and/or mechanical plant or power plant, of a factory
or his representative, the and for the design and or similar facility, or of an
Engineer. execution of building or infrastructure projector
engineering works. other type of development,
Under the usual where
arrangements for this type Under the usual
of contract, the Contractor arrangements for this type A higher degree of
constructs the works in of contract, the Contractor certainty of final price
accordance with a design designs and provides, in and time is required, and
provided by the Employer. accordance with the The Contractor takes
However, the works may Employer’s requirements, total responsibility for
include some elements of plant and/or other works; the design and
Contractor designed civil, which may include any execution of the project,
mechanical, electrical combination of civil, with little involvement
and/or construction works. mechanical, electrical of the Employer.
and/or construction works.
Under the usual
arrangements for turnkey
projects, the Contractor
carries out all the
Engineering, Procurement
and Construction (EPC):
providing a fully equipped
facility, ready for operation
(at the “turn of the key”).
https://legalbusinessforms.wordpress.com/2015/05/08/fidic-comparison-between-red-book-yellow-book-silver-book/ 1/14
11/7/23, 3:09 PM FIDIC Comparison between Red Book, Yellow Book, Silver Book – Legal Business & Contract
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
RISKS ALLOCATION Risks are allocated on a fair Risks are allocated on a fair A majority of risks is
and equitable basis taking and equitable basis taking allocated to the Contractor
account of such matters as account of such matters as under the Contract,
insurability, and each insurability, and each including any errors in:
party’s ability to foresee, party’s ability to foresee,
and mitigate the effect of the and mitigate the effect of, 1. Errors in the Setting
circumstances relevant to the circumstances relevant Out data (Sub-Clause 4.7);
each risk. to each risk.
2. Site data (Sub-Clause
There are a number of key There are a number of key 4.10);
risks that the Employer risks that the Employer
3. Unforeseeable
retains, for example: retains, for example:
difficulties or costs (Sub-
1. Errors in the Setting 1. Errors in the Setting Out Clause 4.12)
Out data (Sub-Clause 4.7); data (Sub-Clause 4.7);
The Contractor is expected
2. Site data (Sub-Clause 2. Site data (Sub-Clause to:
4.10); 4.10);
Price these risks; and/or
3. “Unforeseeable” Site 3. “Unforeseeable” Site Carryout extensive due
risks (Sub-Clause 4.12) risks (Sub-Clause 4.12) diligence to mitigate
risks.
As a result, the tender time As a result, the tender time
can be relatively short. can be relatively short. A longer period for
preparation of a tender is
therefore usually required,
in particular to inspect the
Site and examine data
hydrological and subsurface
data and also to scrutinise
the Employer’s
Requirements.
https://legalbusinessforms.wordpress.com/2015/05/08/fidic-comparison-between-red-book-yellow-book-silver-book/ 2/14
11/7/23, 3:09 PM FIDIC Comparison between Red Book, Yellow Book, Silver Book – Legal Business & Contract
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
DESIGN The Contractor shall design The Contractor shall carry The Contractor shall be
(to the extent specified in out, and be responsible for, deemed to have
– the Contract), execute and the design of the Works. scrutinised, prior to the Base
complete the Works in Date, the Employer’s
ERRORS IN THE Design shall be prepared
accordance with the Requirements (including
EMPLOYER’S by qualified designers who
Contract and with the design criteria and
REQUIREMENTS are engineers who comply
Engineer’s instructions, and calculations, if any). The
shall remedy any defects in with the criteria (if any) Contractor shall be
the Works. stated in the Employer’s responsible for the design
Requirements. of the Works and for the
Except to the extent accuracy of such
specified in the Contract, the Unless otherwise stated in
Employer’s Requirements
Contractor the Contract, the
(including design criteria
Contractor shall submit to
and calculations), except as
Shall be responsible for the Engineer for consent
stated below.
all Contractor’s the name and particulars of
Documents, Temporary each proposed designer and The Employer shall not be
Works, and such design design Subcontractor. responsible for any error,
of each item of Plant and inaccuracy or omission of
Materials as is required The Contractor warrants
any kind in the Employer’s
for the item to be in that he, his designers and
Requirements as originally
accordance with the design Subcontractors have
included in the Contract
Contract, and the experience and
and shall not be deemed to
Shall not otherwise be capability necessary for the
have given any
responsible for the design.
representation of accuracy
design or specification of or completeness of any
The Contractor undertakes
the Permanent Works. data or information, except
that the designers shall be
as stated below. Any data
The Contractor shall, available to attend
or information received by
whenever required by the discussions with the
the Contractor, from the
Engineer, submit details of Engineer at all reasonable
Employer or otherwise,
the arrangements and times, until the expiry date
shall not relieve the
methods, which the of the relevant Defects
Contractor from his
Contractor proposes to Notification Period.
responsibility for the design
adopt for the execution of
Upon receiving notice under and execution of the Works.
the Works. No significant
Sub-Clause 8.1
alteration to these However, the Employer
[Commencement of Works],
arrangements and methods shall be responsible for the
the Contractor shall
shall be made without this correctness of the
scrutinise the Employer’s
having previously been following portions of the
Requirements (including
notified to the Engineer. If Employer’s Requirements
design criteria and
the Contract specifies that and of the following data
calculations) and the items
the Contractor shall design and information provided
of reference mentioned in
any part of the Permanent by (or on behalf of) the
Sub Clause 4.7 [Setting Out].
Works, then unless Employer:
otherwise stated in the
Within the period stated in
Particular Conditions: § Portions, data and
the Appendix to Tender,
information which are
calculated from the
The Contractor shall stated in the Contract as
Commencement Date, the
submit to the Engineer being immutable or the
Contractor shall give notice
the Contractor’s responsibility of the
to the Engineer of any error,
Documents for this part Employer,
fault or other defect found
in accordance with the
in the Employer’s
procedures specified in § Definitions of intended
Requirements or these items
the Contract; purposes of the Works or
of reference.
These Contractor’s any parts thereof,
Documents shall be in
After receiving this notice,
accordance with the § Criteria for the testing
the Engineer shall
Specification and and performance of the
determine whether Clause
Drawings, shall be completed Works, and
13 [Variations and
written in the language
Adjustments]shall be § Portions, data and
for communications
applied, if so, give notice to information which cannot.
defined in 1.4 [Law and
the Contractor accordingly.
Language],and shall
include additional If and to the extent that
information required (taking account of cost and
by the Engineer to add time) an experienced
to the Drawings for co- contractor exercising due
https://legalbusinessforms.wordpress.com/2015/05/08/fidic-comparison-between-red-book-yellow-book-silver-book/ 3/14
11/7/23, 3:09 PM FIDIC Comparison between Red Book, Yellow Book, Silver Book – Legal Business & Contract
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
§ Prior to the
commencement of the
Tests on Completion, the
Contractor shall submit to
the Engineer the “as-built”
documents and operation
and maintenance manuals
in accordance with the
Specification and in
sufficient detail for the
Employer to operate,
maintain, dismantle,
reassemble, adjust and
repair this part of the
Works. Such part shall
not be considered to be
completed for the purposes
of taking over under Sub-
Clause 10.1 [Taking Over
of the Works and Sections]
until these documents and
manuals have been
submitted to the Engineer.
https://legalbusinessforms.wordpress.com/2015/05/08/fidic-comparison-between-red-book-yellow-book-silver-book/ 4/14
11/7/23, 3:09 PM FIDIC Comparison between Red Book, Yellow Book, Silver Book – Legal Business & Contract
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
CONTRACT PRICE Unless otherwise stated in Unless otherwise stated in Unless otherwise stated in
the Particular Conditions: the Particular Conditions: the Particular Conditions:
§ The Contract Price shall § The Contract Price shall § Payment for the Works
be agreed or determined be the lump sum accepted shall be made on the basis
under Sub-Clause 12.3 and contract amount and be of the lump sum Contract
be subject to adjustments in subject to adjustments in Price, subject to
accordance with the accordance with the adjustments in accordance
Contract. Contract; with the Contract;
§ The Contractor shall pay § The Contractor shall pay § The Contractor shall pay
all taxes, duties and fees all taxes, duties and fees all taxes, duties and fees
required to be paid by him required to be paid by required to be paid by him
under the Contract, and him under the Contract, and under the Contract, and
the Contract Price shall not the Contract Price shallot the Contract Price shall not
be adjusted for any of these be adjusted for any of these be adjusted for any of these
costs except as stated in costs, except as stated in costs, except as stated in
Sub-Clause 13.7 Sub-Clause 13.7 Sub Clause 13.7.
[Adjustments for Changes [Adjustments for Changes
in Legislation]; in Legislation]
https://legalbusinessforms.wordpress.com/2015/05/08/fidic-comparison-between-red-book-yellow-book-silver-book/ 5/14
11/7/23, 3:09 PM FIDIC Comparison between Red Book, Yellow Book, Silver Book – Legal Business & Contract
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
PAYMENT The Employer shall make an The Employer shall make an The Employer shall make an
advance payment, as an advance payment, as an advance payment, as an
interest-free loan for interest-free loan for interest-free loan for
mobilisation, when the mobilisation, when the mobilization and design,
Contractor submits a Contractor submits a when the Contractor
guarantee. Unless and until guarantee. Unless and until submits a guarantee.
the Employer receives this the Employer receives this
guarantee, or if the total guarantee, or if the total Employer shall pay the first
advance payment is not advance payment is not instalment after receiving
stated in the Contract Data stated in the Contract Data
1. A Statement;
(or Appendix to Tender), (or Appendix to Tender),
this Sub Clause shall not this Sub Clause shall not
2. The Performance
apply. apply.
Security
The Engineer shall issue an The Engineer shall issue an
The Contractor shall submit
Interim Payment Interim Payment
a Statement in six copies to
Certificate for the first Certificate for the first
the Employer after the end
instalment after: instalment after:
of the period of payment
stated in the Contract (if not
§ Receiving a Statement § Receiving a Statement
stated, after the end of
and and
each month), in a form
§ after the Employer § after the Employer approved by the Employer,
Receives: Receives: showing in detail the
amounts to which the
1. The Performance 1. The Performance Contractor considers
Security Security himself to be entitled,
2. a guarantee in amounts together with supporting
and currencies equal 2. a guarantee in amounts documents.
to the advance payment and currencies equal to
the advance payment If the Contract includes a
The Contractor shall Schedule of Payments
submit a Statement in six The Contractor shall specifying the instalments
copies to the Engineer after submit a Statement in six in which the Contract Price
the end of each month, in copies to the Engineer after will be paid, then unless
a form approved by the the end of each month, in otherwise stated in this
Engineer, showing in detail a form approved by the Schedule.
the amounts to which the Engineer, showing in detail
Contractor considers the amounts to which the If the Contract includes a
himself to be entitled, Contractor considers Schedule of Payments
together with supporting specifying the instalments
himself to be entitled, in which the Contract Price
documents which shall
together with supporting will be paid, then unless
include the report on the
documents which shall otherwise stated in this
progress during this month.
include the report on the Schedule:
If the Contract includes a progress during this month.
schedule of payments § The instalments quoted in
If the Contract includes a the Schedule of Payments
specifying the instalments in
schedule of payments shall be the estimated
which the Contract Price
specifying the instalments in contract
will be paid, then unless
which the Contract Price
otherwise stated in this
will be paid, then unless § If these instalments are
schedule:
otherwise stated in this not defined by reference to
§ The instalments quoted in schedule: the actual progress
this schedule of payments achieved in executing the
§ The instalments quoted in Works, and if actual
shall be the estimated
this schedule of payments progress is found to be
contract values.
shall be the estimated less than that on which the
§ If these instalments are contract values. Schedule of Payments was
not defined by reference to based, then the Employer
§ If these instalments are
the actual progress may proceed to agree or
not defined by reference to
achieved in executing the determine revised
the actual progress
Works, and if actual instalments, which shall
achieved in executing the
progress is found to be less take account of the extent to
Works, and if actual
than that on which the which progress is less
progress is found to be less
Schedule of Payments was than that on which the
than that on which the
based, then the Engineer instalments were previously
Schedule of Payments was
may proceed to agree or based.
based, then the Engineer
determine revised
https://legalbusinessforms.wordpress.com/2015/05/08/fidic-comparison-between-red-book-yellow-book-silver-book/ 6/14
11/7/23, 3:09 PM FIDIC Comparison between Red Book, Yellow Book, Silver Book – Legal Business & Contract
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
instalments, which shall may proceed toagree or If the Contract does not
take account of the extent to determine revised include a Schedule of
which progress is less than instalments, which shall Payments, the Contractor
that on which the take account of the extent to shall submit non-binding
instalments were previously which progress is less estimates of the payments,
based. than that on which the which he expects to become
instalments were previously due during each quarterly
If the Contract does not based. period.
include a schedule of
payments, the Contractor If the Contract does not The first estimate shall be
shall submit non-binding include a schedule of submitted within 42 days
estimates of the payments, payments, the Contractor after the Commencement
which he expects to shall submit non-binding Date.
become due during each estimates of the payments,
quarterly period. which he expects to Revised estimates shall be
become due during each submitted at quarterly
The first estimate shall be quarterly period. intervals, until the Taking
submitted within 42 days Over Certificate has been
after the Commencement The first estimate shall be issued for the Works.
Date. submitted within 42 days
after the Commencement
Revised estimates shall be Date.
submitted at quarterly
intervals, until the Taking Revised estimates shall be
Over Certificate has been submitted at quarterly
issued for the Works. intervals, until the Taking
Over Certificate has been
issued for the Works.
EXTENSION OF TIME Various rights for the Various rights for the The Contractor shall be
Contractor to claim Contractor to claim entitled to an EOT if (and to
ASSOCIATED COSTS Extension of Time OR Extension of Time OR the extent that)completion
Associated Cost under the Associated Cost under the for the purposes of Taking
Contract for errors: Contract for errors: Over of the Works and
Sections is or will be
§ In the Setting Out data § In the Setting Out data delayed by any of the
(Sub-Clause 4.7) (Sub-Clause 4.7) following causes:
§ In the Site data (Sub- § In the Site data (Sub- § A Variation (unless an
Clause 4.10) Clause 4.10) adjustment to the Time for
Completion has been
§ Unforeseen Site risks § Unforeseen Site risks
agreed under Variation
(Sub-Clause 4.12) (Sub-Clause 4.12)
Procedure;
§ Others. § Others.
§ A cause of delay giving
an entitlement to extension
of time under a Sub-Clause
of these Conditions;
https://legalbusinessforms.wordpress.com/2015/05/08/fidic-comparison-between-red-book-yellow-book-silver-book/ 7/14
11/7/23, 3:09 PM FIDIC Comparison between Red Book, Yellow Book, Silver Book – Legal Business & Contract
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
TESTS ON COMPLETION The Contractor shall carry The Contractor shall carry The Contractor shall carry
out the Tests on out the Tests on out the Tests on
Completion. Completion. Completion.
The Contractor shall give The Contractor shall give The Contractor shall give
to the Engineer not less than to the Engineer not less than to the Engineer not less than
21 days’ notice of the date 21 days’ notice of the date 21 days’ notice of the date
after which the Contractor after which the Contractor after which the Contractor
will be ready to carry out will be ready to carry out will be ready to carry out
each of the Tests on each of the Tests on each of the Tests on
Completion. Completion. Completion.
https://legalbusinessforms.wordpress.com/2015/05/08/fidic-comparison-between-red-book-yellow-book-silver-book/ 8/14
11/7/23, 3:09 PM FIDIC Comparison between Red Book, Yellow Book, Silver Book – Legal Business & Contract
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
https://legalbusinessforms.wordpress.com/2015/05/08/fidic-comparison-between-red-book-yellow-book-silver-book/ 9/14
11/7/23, 3:09 PM FIDIC Comparison between Red Book, Yellow Book, Silver Book – Legal Business & Contract
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
https://legalbusinessforms.wordpress.com/2015/05/08/fidic-comparison-between-red-book-yellow-book-silver-book/ 10/14
11/7/23, 3:09 PM FIDIC Comparison between Red Book, Yellow Book, Silver Book – Legal Business & Contract
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
TAKING-OVER Except as stated in Sub- Except as stated in Sub- Except as stated in Sub-
Clause 9.4 [Failure to Pass Clause 9.4 [Failure to Pass Clause 9.4 [Failure to Pass
Tests on Completion],the Tests on Completion],the Tests on Completion],the
Works shall be taken over Works shall be taken over Works shall be taken over
by the Employer when by the Employer when by the Employer when
§ The Works have been § The Works have been § The Works have been
completed in accordance completed in accordance completed in accordance
with the Contract, with the Contract, with the Contract,
including the matters including the matters including the matters
described in Sub Clause 8.2 described in Sub Clause 8.2 described in Sub Clause 8.2
[Time for Completion] and [Time for Completion] and [Time for Completion] and
except as allowed in except as allowed in except as allowed in
subparagraph (a) below, subparagraph (a) below, subparagraph (a) below,
and and and
The Contractor may apply The Contractor may apply The Contractor may apply
by notice to the Engineer by notice to the Engineer by notice to the Engineer
for a Taking-Over for a Taking-Over for a Taking-Over
Certificate not earlier than Certificate not earlier than Certificate not earlier than
14 days before the Works 14 days before the Works 14 days before the Works
will, in the Contractor’s will, in the Contractor’s will, in the Contractor’s
opinion, be complete and opinion, be complete and opinion, be complete and
ready for taking over. If ready for taking over. If ready for taking over. If
the Works are divided into the Works are divided into the Works are divided into
Sections, the Contractor Sections, the Contractor Sections, the Contractor
may similarly apply for a may similarly apply for a may similarly apply for a
Taking Over Certificate for Taking Over Certificate for Taking Over Certificate for
each Section. each Section. each Section.
The Engineer shall, within The Engineer shall, within The Engineer shall, within
28 days after receiving the 28 days after receiving the 28 days after receiving the
Contractor’s application: Contractor’s application: Contractor’s application:
https://legalbusinessforms.wordpress.com/2015/05/08/fidic-comparison-between-red-book-yellow-book-silver-book/ 11/14
11/7/23, 3:09 PM FIDIC Comparison between Red Book, Yellow Book, Silver Book – Legal Business & Contract
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
If the Engineer fails either If the Engineer fails either If the Engineer fails either
to issue the Taking-Over to issue the Taking-Over to issue the Taking-Over
Certificate or to reject the Certificate or to reject the Certificate or to reject the
Contractor’s application Contractor’s application Contractor’s application
within the period of 28 within the period of 28 within the period of 28
days, and if the Works or days, and if the Works or days, and if the Works or
Section(as the case may be) Section(as the case may be) Section(as the case may be)
are substantially in are substantially in are substantially in
accordance with the accordance with the accordance with the
Contract, the Taking-Over Contract, the Taking-Over Contract, the Taking-Over
Certificate shall be deemed Certificate shall be deemed Certificate shall be deemed
to have been issued on the to have been issued on the to have been issued on the
last day of that period. last day of that period. last day of that period.
The Engineer may, at the The Engineer may, at the Parts of the Works (other
sole discretion of the sole discretion of the than Sections) shall not be
Employer, issue a Taking- Employer, issue a Taking- taken over or used by the
Over Certificate for any Over Certificate for any Employer, except as may
part of the Permanent part of the Permanent be stated in the Contract or
Works. Works. as may be agreed by both
Parties.
The Employer shall not use The Employer shall not use
any part of the Works(other any part of the Works(other
than as a temporary than as a temporary
measure which is either measure which is either
specified in the Contract or specified in the Contract or
agreed by both Parties) agreed by both Parties)
unless and until the unless and until the
https://legalbusinessforms.wordpress.com/2015/05/08/fidic-comparison-between-red-book-yellow-book-silver-book/ 12/14
11/7/23, 3:09 PM FIDIC Comparison between Red Book, Yellow Book, Silver Book – Legal Business & Contract
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
Important Notes:
This information has been prepared by CNC as a general guide only and does not constitute advice on any specific matter. We recommend that you seek professional
advice before taking action. No liability can be accepted by us for any action taken or not taken as a result of this information.
The materials on this Web site may not reflect the most current legal developments, verdicts or settlements and should not be considered an indication of future results
https://legalbusinessforms.wordpress.com/2015/05/08/fidic-comparison-between-red-book-yellow-book-silver-book/ 13/14
11/7/23, 3:09 PM FIDIC Comparison between Red Book, Yellow Book, Silver Book – Legal Business & Contract
(
h
t
t
p
s
:
/
/
w
w
w
.
o
u
t
b
r
a
i
n
.
Sponsored Content c
o
m
/
w
h
a
t
-
i
s
/
d
e
f
a
u
l
t
/
e
n
)
Dwayne 'The Rock' Johnson Buys Georgia Farm - The Home Was Built For Mr. Johnson’s Family Mansion Global | Sponsored
(https://www.mansionglobal.com/articles/dwayne-the-rock-johnson-picks-up-9-5-million-georgia-farm-208876?reflink=outbrain_editorial-toparticles_$sect
La Barra, Uruguay, Is Transforming From an Idyllic Vacation Spot to a Year-Round Retreat Mansion Global | Sponsored
(https://www.mansionglobal.com/articles/la-barra-uruguay-is-transforming-from-an-idyllic-vacation-spot-to-a-year-round-retreat-01628938468?reflink=out
Unsold Furniture Is Being Sold In 2023 For Cheap (Prices May Surprise You) Furniture Deals | Sponsored
(https://trck.tracking505.com/7dfe2caf-ef52-4e7f-a1a6-ca15cf50d969?
campaign_id=00d87c66ee1c87bd480c637b0ba8af36f4&publisher_id=$publisher_id$&publisher_name=$publisher_name$&ad_id=009984cc843a32b9563cd7bd
Posted in Contract, FIDIC Tagged Blue Form, BOT, choice of FIDIC forms, consulting engineers, contractor, design and build, employer, engineer,
EPC/Turnkey Contract, FIDIC, FIDIC Client/Consultant Model Service Agreement, FIDIC Forms of Contract, general conditions, gold book, green book,
MDB, MDB Harmonised Edition, pink book, Red Book, Risk allocation, silver book, yellow book Leave a comment
https://legalbusinessforms.wordpress.com/2015/05/08/fidic-comparison-between-red-book-yellow-book-silver-book/ 14/14