Professional Documents
Culture Documents
S.H. Cheng
National Taiwan University of Science and Technology, Taipei, Taiwan
ABSTRACT: This paper presents a case study of the ground improvement works on TBM tun
neling for Taipei MRT in the east district of Taipei City. The TBM tunnel is mainly drilled in the
composite strata which consist of alluvial deposits, colluvium deposits, and rock formation. The
upper half of the improvement zone is a soft soil layer and the lower half of the improvement is
a hard rock layer (Sandstone or Shale). The soft soil layers outside of the tunnel-shaft interface
require jet grouted body to increase their strength and decrease their permeability. Also, in order
to tunnel through the composite stratum, it needs to carry out jet grouting in the soft ground to
increase the strength of the soil layer to homogenize the excavation section. Since the hard rock
cannot be used by jet grouting, permeability grouting is used to decrease its permeability. In this
case, the jet grouting and the permeability grouting were used to overcome the strata with differ
ent geological conditions to meet the strength (self-supporting) and to reduce the permeability of
the ground. The ground improvement results show that for the jet grout zone, the total core
recovery is greater than 90%, the in-situ permeability tests and the laboratory uniaxial compres
sion strength meets the specification requirements. For the TAM grouting zone, the permeability
coefficient k carried out by in-situ permeability tests was less than 1×10-5 cm/sec. Before breaking
the cutter face on the diaphragm wall for the TBM to enter from the shaft, the horizontal leakage
tests of the up track and down track at the west side station have been completed. Without sup
plementary grouting, the permeability coefficient k of all horizontal permeability tests is less than
1×10-5 cm/sec.
1 INTRODUCTION
Various ground improvement methods have been adopted in the construction of the Taipei
Mass Rapid Transit system (Taipei MRT system). The jet grouting and the chemical grouting
technique have been widely used in the tunnel-shaft interface for the TBM launching and
arrival works. This study reports the ground improvement works for the Taipei MRT Xinyi
East Extension Line in the east district of Taipei City. The TBM tunnels pass through the
composite stratum when the TBM arrives at the shaft of the station. The soft soil layers of the
tunnel-shaft interface require jet grouted to increase their strength and decrease their perme
ability. Also, to tunnel through the composite stratum, it needs to carry out jet grouting in the
soft ground layer to increase the strength of the soil layer to homogenize the excavation
section. Since the hard rock cannot be used by jet grouting, chemical grouting is used to
decrease its permeability. In this study, the commercial Rapidjet jet grouting method and the
TAM grouting with chemical grouting are used to overcome the strata with different geo
logical conditions to meet the self-supporting and water-proofing required for TBM tunneling.
The grouting results show that the total core recovery in the jet grouting zone is greater than
DOI: 10.1201/9781003299127-86
659
90%, the permeability coefficient k is less than 1×10-5 cm/sec and the uniaxial compression
strength (UCS) meets the specification requirements (28-days UCS of sand and clay layers is
not less than 2.0 MPa and 1.2 MPa). In addition, in-situ permeability tests were carried out in
the TAM grouting zone, and the permeability coefficient k was found to be less than 1×10-5
cm/sec. The performance and the results of the jet grouting and the TAM grouting works are
presented in the following sections.
2 SITE CONDITIONS
The location and layout for the study case of Taipei MRT are shown in Figure 1. It consists
of the R03 station, the cross-over, the R03 tail rail ventilation shaft with the cut and cover
method, and the shield tunnels with shield machines. The shield tunnel in this study adopts
a circular section with an inner diameter of 5.6 m and an outer diameter of 6.1 m. The shield
machine adopts the earth pressure balance critical, in which the total length of the shield
machine is 8.5 m with an outer diameter of 6.24 m as shown in Figure 2. The lengths of the
shield tunnels from the east side of the R03 station to the R03 tail rail ventilation shaft are
about 524 m, and the overburden depth is about 20.8 m to 22.0 m. The shield tunnel is mainly
drilled in the composite strata which consist of alluvial deposits, colluvial deposits, and rock
formations.
The soil condition near the ground surface mainly consists of fill material (SF), alluvial
deposit (CL/CH/ML/SM) with a thickness of 10-20 m and a very soft to weak consistency,
and underneath is soft to medium-hard, moderately weathered to fresh sandstone (SS), shale
(SH). The soil-rock interface is occasionally mixed with colluvial deposits; the main compo
nents are gravel and rock blocks. The physical properties of soil near the east side/west side of
the R03 station and R03 tail rail ventilation shaft are shown in Table 1. Additionally, the soil
and rock properties along the R03 station to the R03 tail rail ventilation shaft are shown in
Figure 3. It indicates that the qu value of the rock formation is > 1000 kgf/cm2, and the RQD
of the rock formation is between 0 and 100. The groundwater level was about 0 ~ 1.8 m below
the ground surface.
Figure 1. The location and layout for the study case of Taipei MRT.
Figure 2. The TBM shield machine of this study case (Chen et al., 2020).
660
Figure 3. Soil and rock properties along R03 station to R03 tail rail ventilation shaft (Chen et al., 2020).
Table 1. The soil properties at the west side, east side, and tail rail ventilation shaft of R03 station.
at the west side:
Soil Layer Depth (m) Soil Type SPT-N (Avg.) Unit Weight (kN/m3) Water Content (%)
1 1.6 SF - - -
2 16.5 CH-CL 2.2 15.89~17.85 41~52
3 21.4 CL 4.5 18.05~18.34 31~37
4 22.8 SM 53 17.95~18.25 29~32
5 35.0 SS/SH 100 - -
at the east side:
Soil layer Depth (m) Soil type SPT-N (Avg.) Unit weight (kN/m3) Water content (%)
1 1.6 SF - - -
2 8.3 CH 2.5 16.30 61
3 15.0 ML-SM 8.8 18.24~19.72 24~34
4 23.3 CL 6.7 16.38~17.10 42~49
5 33.5 SS 100 - -
at the tail rail ventilation shaft:
Soil layer Depth (m) Soil type SPT-N (Avg.) Unit weight (kN/m3) Water content (%)
1 1.6 SF - - -
2 11.8 CH~CL 5.1 16.48~18.25 28~43
3 20.0 SM-CL-ML 65 19.32~21.29 16~23
4 35.0 SS/SH 100 - -
3 GROUTING WORKS
661
to offset when drilling and digging. The strength of mixed strata varies significantly in some areas
of this study case. To minimize the impact of drilling on the surrounding area, ground improve
ment is carried out for these areas. This study introduces the grouting method of the soil-rock
interface located on the east side of the R03 station as shown in Figure 5. The soil layer above the
soil-rock interface is performed by jet grouting (Rapidjet method) to ensure that the shield
machine does not shift up or cause the ground to collapse due to improper digging. Figure 5
shows the position of the soil-rock interface, grouting zone, and adopted grouting method. How
ever, the TAM grout of the soil-rock interface area is always for building protection.
Figure 4. Grouting plan and profile for launching and arrival shield of the study case (Chen et al.,2020).
Table 2. Grouting method and improved zone for launching and arrival shield of the study case.
Improved range (m)
Center of Grouting
Location tunnel EL (m) method L1 L2 H1 H2 H3 W1 W2 W3 W4
East Tunnel Launc 85.6 R-Jet/ TAM Grout 7.8 2.2 4 2 6.5 2 2 2.7 0.5*
hing TAM
Grout
Arrival 84.6 R-Jet/ TAM Grout 8.8 2.2 2.5 2 5.5 2 2 2.7 2.7
TAM
Grout
West Tunnel Launc 85.6 R-Jet/ TAM Grout 8.8 2.2 2.5 2 4.4 2 2 2 2
hing TAM
Grout
Arrival 89.9 JSG ** - 10.5 2.5 2 10.8 - - 2 2
4 GROUTING METHOD
662
drilling machine to drill first. The drilling is used directly in the subsequent double tube
double packer grouting. The construction process of Rapidjet is shown in Figure 6.
Figure 5. The soil-rock interface, grouting zone, and adopted grouting method the at east side of R03
station.
663
Table 3. Jet grouting parameters used in the Rapidjet grouting.
Parameter Value
664
Figure 7. TAM grouting procedure.
Remark: If the filling is completed according to the grouting rate but the pressure is low, the MK material will
be used to inject about 3 to 5% of the inspection and supplement grouting.
665
grout pressure was recorded for 1st grout, 2nd grout, and supplement grout as shown in Table 8.
The average pressures on the clayey, sandy, and sandstone/shale range from 6.4~8.0, 11.8~13.0
and 7.0~13.3 kg/cm2, respectively.
5.3 Core sampling and permeability test of the jet grouted zone
According to the construction specification, every 100 grout holes should be sampled with at least
3 holes. The total core recovery (TCR) of sampling was ≥ 90%, the 28-day uniaxial compressive
strength (UCS) of each sample ≥ 20.0 kgf/cm2 for sandy soil, and ≥ 12.0 kgf/cm2 for clayey(silty)
666
soil, and the permeability coefficient k ≤1×10-5 cm/sec. Table 10 shows the results of coring, UCS,
and permeability of the Jet grout zone. All test results meet the design requirement.
Table 10. The core sampling and permeability test results of jet grouted zone.
Test TCR Age UCS (kgf/cm2) Top/ Permeability k,
Location No % (Day) Mid./Bot. (cm/sec)
667
Figure 8. Horizontal leakage tests at the west side of the R03 station for launching.
This study reports the grouting works for the Taipei MRT Xinyi East Extension Line in the
east district of Taipei City. The TBM tunnels through the composite stratum at the east side
of the R03 station. The upper half of the improvement zone is a soft soil layer and the lower
half of the improvement is a hard rock layer (Sandstone or Shale). The Rapidjet Method and
the TAM grouting were used to overcome the strata with different geological conditions to
meet the self-supporting and water-proofing required for the TBM break-in and break-out.
The following conclusions can be drawn:
1) All the tests carried out in the jet grouted and TAM grouted zone meet the design require
ment. For the jet grouted zone: the 28-day uniaxial compressive strength (UCS) of each
sample was ≥ 20.0 kgf/cm2 for sandy soil, and ≥ 12.0 kgf/cm2 for clayey (silty) soil, and the
permeability coefficient k ≤1×10-5 cm/sec. For TAM grouted zone: the permeability coeffi
cient k ≤1×10-5 cm/sec. For the horizontal leakage test in the grouting zone at the west side
of the R03 station, the permeability coefficient k was ≤1×10-5 cm/sec.
2) The TBM at the west side of the up-track tunnel of the R03 station was launched
smoothly and without supplementary grouting. Therefore, careful planning of grouting
methods can significantly shorten construction time and reduce construction costs.
3) In addition, the construction of the diaphragm wall for the TBM launching and arrival
works may have an adverse effect on the grouting works (such as the verticality of the
grout holes, the impermeability of grouting, etc.), a row of low-pressure inspection grout
(TAM grout) can be accessional at the interface between the diaphragm wall and the
ground, it can let the grouting works effect more perfect.
REFERENCES
Burke, G.K., 2004. “Jet Grouting Systems: Advantages and Disadvantages.” GeoSupport 2014: Drilled
shafts, Micropiling, Deep mixing, Remedial method, and Specialty foundation systems, Orlando, Flor
ida, American Society of Civil Engineers, New York, pp. 218–234.
BES Engineering Corporation/DAIHO Corporation Taiwan Branch (2018),” Shield tunnel launching and
arrival/soil-rock interface ground improvement works for Xinyi East Extension Line CR285” (In Chinese).
Chen Jian Ren, Zhang Zheng Lin, Yang Gwo Rong, Guo Jin Wei 2020, “Design Consideration and Con
struction Plan of Shield Tunneling Through Composite Stratum in Edge of Taipei Basin”, Rapid Tran
sit Systems and Technology”, N0.55, pp. 99–119 (In Chinese).
Hayashi K. and Matsubayashi Y. 1996. “Chemical grouting contributed to the urban development in
Hiroshima city”, Proceedings of Grouting and Deep Mixing, Japan, pp. 299-302.
i-Grout association 2020. 4. Chemical Grouting Guideline (Version 1). Japan: i-Grout association.
Lunardi, P., 1997. “Ground Improvement by Means of Jet-Grouting.” Proc. Inst. Civ. Eng. Ground
Improv., Vol. 1, Issue 2, pp. 65–85. https://doi.org/10.1680/gi.1997.010201
Rapidjet association 2019. Rapidjet Method Jet Grouting Guideline (Version 1). Japan: Rapidjet association.
668