Professional Documents
Culture Documents
DEP 64.24.32.11-Gen.
December 1999
(DEP Circular 39/03 has been incorporated)
This document is confidential. Neither the whole nor any part of this document may be disclosed to any third party without the prior written consent of Shell International
Oil Products B.V. and Shell International Exploration and Production B.V., The Hague, The Netherlands. The copyright of this document is vested in these companies.
All rights reserved. Neither the whole nor any part of this document may be reproduced, stored in any retrieval system or transmitted in any form or by any means
(electronic, mechanical, reprographic, recording or otherwise) without the prior written consent of the copyright owners.
DEP 64.24.32.11-Gen.
December 1999
Page 2
PREFACE
DEPs (Design and Engineering Practice) publications reflect the views, at the time of publication, of:
Shell Global Solutions International B.V. (Shell GSI)
and
Shell International Exploration and Production B.V. (SIEP)
and
Shell International Chemicals B.V. (SIC)
and
other Service Companies.
They are based on the experience acquired during their involvement with the design, construction, operation and
maintenance of processing units and facilities, and they are supplemented with the experience of Group Operating
companies. Where appropriate they are based on, or reference is made to, international, regional, national and industry
standards.
The objective is to set the recommended standard for good design and engineering practice applied by Group
companies operating an oil refinery, gas handling installation, chemical plant, oil and gas production facility, or any other
such facility, and thereby to achieve maximum technical and economic benefit from standardization.
The information set forth in these publications is provided to users for their consideration and decision to implement.
This is of particular importance where DEPs may not cover every requirement or diversity of condition at each locality.
The system of DEPs is expected to be sufficiently flexible to allow individual operating companies to adapt the
information set forth in DEPs to their own environment and requirements.
When Contractors or Manufacturers/Suppliers use DEPs they shall be solely responsible for the quality of work and the
attainment of the required design and engineering standards. In particular, for those requirements not specifically
covered, the Principal will expect them to follow those design and engineering practices which will achieve the same
level of integrity as reflected in the DEPs. If in doubt, the Contractor or Manufacturer/Supplier shall, without detracting
from his own responsibility, consult the Principal or its technical advisor.
The right to use DEPs is granted by Shell GSI, SIEP or SIC, in most cases under Service Agreements primarily with
companies of the Royal Dutch/Shell Group and other companies receiving technical advice and services from Shell GSI,
SIEP, SIC or another Group Service Company. Consequently, three categories of users of DEPs can be distinguished:
1) Operating companies having a Service Agreement with Shell GSI, SIEP, SIC or other Service Company. The
use of DEPs by these operating companies is subject in all respects to the terms and conditions of the relevant
Service Agreement.
2) Other parties who are authorized to use DEPs subject to appropriate contractual arrangements (whether as part
of a Service Agreement or otherwise).
3) Contractors/subcontractors and Manufacturers/Suppliers under a contract with users referred to under 1) or 2)
which requires that tenders for projects, materials supplied or - generally - work performed on behalf of the said
users comply with the relevant standards.
Subject to any particular terms and conditions as may be set forth in specific agreements with users, Shell GSI, SIEP
and SIC disclaim any liability of whatsoever nature for any damage (including injury or death) suffered by any company
or person whomsoever as a result of or in connection with the use, application or implementation of any DEP,
combination of DEPs or any part thereof, even if it is wholly or partly caused by negligence on the part of Shell GSI,
SIEP or other Service Company. The benefit of this disclaimer shall inure in all respects to Shell GSI, SIEP, SIC and/or
any company affiliated to these companies that may issue DEPs or require the use of DEPs.
Without prejudice to any specific terms in respect of confidentiality under relevant contractual arrangements, DEPs shall
not, without the prior written consent of Shell GSI and SIEP, be disclosed by users to any company or person
whomsoever and the DEPs shall be used exclusively for the purpose for which they have been provided to the user.
They shall be returned after use, including any copies which shall only be made by users with the express prior written
consent of Shell GSI, SIEP or SIC. The copyright of DEPs vests in Shell GSI and SIEP. Users shall arrange for DEPs to
be held in safe custody and Shell GSI, SIEP or SIC may at any time require information satisfactory to them in order to
ascertain how users implement this requirement.
All administrative queries should be directed to the DEP Administrator in Shell GSI.
DEP 64.24.32.11-Gen.
December 1999
Page 3
TABLE OF CONTENTS
1. INTRODUCTION.........................................................................................................4
1.1 SCOPE........................................................................................................................4
1.2 DISTRIBUTION, INTENDED USE AND REGULATORY CONSIDERATIONS..........4
1.3 DEFINITIONS .............................................................................................................4
1.4 CROSS-REFERENCES .............................................................................................5
1.5 PROCESS DESCRIPTION AND BASIC REQUIREMENTS ......................................5
2. SELECTION OF REFRACTORY LININGS................................................................7
2.1 GENERAL ...................................................................................................................7
2.2 ANCHORS FOR REFRACTORY LININGS ................................................................9
2.3 LINING DESIGN OF SPECIFIC EQUIPMENT .........................................................10
3. INSTALLATION OF REFRACTORY LININGS ........................................................20
3.1 GENERAL .................................................................................................................20
3.2 ANTI-CORROSIVE COATING..................................................................................20
3.3 BRICKED LININGS...................................................................................................20
3.4 ANCHOR WELDING PROCEDURES ......................................................................20
3.5 INSTALLATION OF CERAMIC FERRULES IN TUBE SHEETS..............................20
4. QUALITY CONTROL................................................................................................23
5. REPAIRS OF TUBE SHEET REFRACTORY LININGS ..........................................24
5.1 GENERAL .................................................................................................................24
5.2 SURFACE REPAIRS OF TUBE SHEET REFRACTORY ........................................24
5.3 PATCHING OF TUBE SHEET CAST OR PLASTIC REFRACTORY.......................24
6. DRYING AND FIRING REFRACTORY LINED EQUIPMENT..................................25
6.1 GENERAL .................................................................................................................25
6.2 DRY-OUT DURING COMMISSIONING ...................................................................25
6.3 REFRACTORY DRY-OUT AFTER A REPAIR AND/OR SHUTDOWN/STAND-
BY..............................................................................................................................26
6.4 COOLING DOWN .....................................................................................................26
7. REFERENCES..........................................................................................................27
APPENDICES
APPENDIX 1 TYPICAL DETAILS FOR BRICK-LINED BURNER EQUIPMENT ..................28
APPENDIX 2 SPECIFICATION FOR MONOLITHIC REFRACTORY MATERIALS .............33
APPENDIX 3 SPECIFICATION FOR CERAMIC FERRULES...............................................35
APPENDIX 4 UNDERGROUND CONCRETE STORAGE TANK DESIGN ..........................38
APPENDIX 5 TYPICAL ARRANGEMENT OF A FLUE GAS DUCT INSULATING
SYSTEM ....................................................................................................40
APPENDIX 6 TYPICAL SPECIFICATION FOR A CLAUS/SCOT UNIT ...............................42
DEP 64.24.32.11-Gen.
December 1999
Page 4
1. INTRODUCTION
1.1 SCOPE
This new DEP specifies requirements and gives recommendations for the design,
installation and inspection of the refractory linings for the equipment of Claus and SCOT
sulphur recovery units (SRUs).
Typical refractory (brick-) lined equipment is: Claus burner and main reaction chamber, the
tube sheet of the waste heat boilers, line burners, reactors, condensers, SCOT burner and
reaction chamber, incinerator, flue ducting, stack and sulphur storage pit.
This DEP is applicable to new and existing SRU equipment.
1.4 CROSS-REFERENCES
Where cross-references to other parts of this DEP are made, the referenced section
number is shown in brackets. Other documents referenced by this DEP are listed in (7).
2.1 GENERAL
With the technical proposals, the Contractor shall submit the thermal design calculations,
indicating temperature profiles, refractory thicknesses, anchor systems and the proposed
refractory material selection.
Standard shaped refractory bricks should be used, however monolithic refractory materials
of equivalent performance may be used. The choice of materials and the method of
application shall be in accordance with DEP 44.24.90.31-Gen., DEP 64.24.32.30-Gen. and
the requirements specified below.
and non-oxidising (such a coating will normally be bituminous and shall be suitable for a
maximum continuous temperature of 205 °C).
DEP 64.24.32.11-Gen.
December 1999
Page 9
Optional:
2nd back-up 1250 minimum 40 mm, 1250 °C Group IFB125 or insulating board (2 ply
board up to 40 mm overlapping)
Note: The air nose is normally supplied as an integral part of the burner
Optional:
2nd. Backup 850 maximum 25 mm 1050 °C grade insulating board
Baffle wall 1600 230 mm minimum HA 70, Mullite based (special creep
resistant)
The connection of the burner to the reaction chamber lining shall be continuous, without a
construction joint. The hot face refractory lining shall be designed to prevent burner bricks
shifting into the chamber due to thermal cycling.
A radial and longitudinal expansion allowance of at least 80% of the induced expansion
movement shall be provided in and between all subsequent refractory layers.
Special care shall be taken at nozzle protrusions to account for refractory expansion and
contraction.
Brick layers shall be constructed in full stretcher-bond configuration. Transitions may be
constructed in separate rings of either keys or end arches, provided that the diametrical
difference is not more than one third of the layer thickness. Larger transitions may be built
up with combinations of key and end arch bricks, thus forming the required conical shape.
The optional second backup lining shall have a compressive strength of at least 2 N/mm2,
or more if needed to withstand the expansion loads induced by the inner refractory lining,.
In case of enhanced ammonia destruction, the typical lining layout shown in Figure 2-3 may
be used.
DEP 64.24.32.11-Gen.
December 1999
Page 12
In the hot face layer, individual standard 114 mm side arch bricks shall be replaced with
standard 152 mm side arch bricks in both the longitudinal and cross-sectional directions at
regular distances, e.g. every second or third brick.
The length of the mixing section, which is commonly the length of the cylindrical section of
a main reactor chamber (MRC), shall be as specified by the Principal.
To prevent excessive cooling of non-insulated lined equipment a shield may be fitted
around the shell with a suitable gap in between. An exhaust should be placed on the top of
the shield to provide adequate ventilation. See Figure 2-4.
Figure 2-4 Protective shield
Because the manhole is normally located in this section, provisions shall be made to open
up the baffle wall for inspection of the main chamber. A refractory cast lintel or low arch
may then be used to prevent bricks from dropping down.
2.3.1.4 Man-way
The refractory lining around man-way openings shall be designed in accordance with
Figure 2-6 and such that the stability from all surrounding refractory layers is assured. At
least the hot face layer shall be arranged with relief arches on the top and bottom in a fully
integrated and bricked and cut-to-suit lining design.
If monolithically cast specially shaped blocks are used, stepped joints shall be formed, at
least in the top half section, to prevent the sagging of blocks. The connection of the man-
way lining to the specially shaped ring shall be designed to prevent separation of the layers
and penetration of hot combustion gases and/or foreign matter.
Figure 2-6: Typical detail of man-way lining design
Large incoming lines (such as gas inlet lines and secondary combustion air inlet lines for
incinerators etc.) shall be designed so that acute angles are avoided and that a thermo-
mechanically sound and reliable refractory lining is assured. Other nozzles (e.g. instrument
connections, peepholes etc.) shall enter at as large an angle as possible in order to avoid
unnecessary brick cutting or use of monolithic materials.
Instrument nozzles, particularly thermowells, should be placed in the head of cylindrical
lined vessels in order to accommodate the thermal expansion of the linings.
DEP 64.24.32.11-Gen.
December 1999
Page 14
The required thickness shall be based on heat transfer calculations, governed by the
maximum allowable tube and tube sheet temperature (thickness of tube sheet should be
maximum 40 mm) and the maximum operating temperature in the MRC. These
temperatures shall be specified by the Principal.
The inside diameter of the ferrules should be such that the inlet velocity is less than 2.5
times the tube gas inlet velocity.
The ceramic ferrules shall be in accordance with Figure 2-7. Inside the tube the ferrules
shall extend at least 20 mm beyond the back face of the metal tube sheet. The inlet of the
ferrule shall be flush with the hot face of the refractory lining on the tube sheet.
For installation details of the ferrules, see (3.5).
Figure 2-7 Typical contours of ceramic ferrules for tube sheets
The ceramic ferrule's outside diameter shall be smaller than the internal tube diameter, to
provide a total gap of between 3 mm and 5 mm depending on the design of the ferrule. The
steel tube shall be clean and without burrs or flaws, otherwise it shall be machined at least
over the length of the inserting ferrule.
If the tubes have been rolled before welding, there will be recesses in the tubes near the
backside of the tube sheet; in which case the smallest diameter shall govern.
An extra collar is sometimes used around the ferrule in order to ensure application of the
nominal required lining thickness. This method facilitates installation and also results in a
smooth lined surface.
Proprietary systems for tube sheet linings (e.g. hex-head ferrules, 2-component hexagon
ferrules) may be used if the Manufacturer/Supplier can provide evidence of long term
reliability of such systems to the Principal.
DEP 64.24.32.11-Gen.
December 1999
Page 15
2.3.5 Reactors
Based on normal operational conditions, the refractory lining of the reactors is as shown in
Table 2-7.
Table 2-7 Refractory materials for reactors
Lining Temperature Thickness Group
(°C)
Internal 400 - 850 minimum 50 mm MW 125li (-L) castable, or
Group FC35 refractory bricks
NOTES: 1. The lining shall be applied to at least 100 mm above the catalyst bed level. The internal surface
may be completely lined.
2.3.6 Condensers
In order to avoid stagnant sulphur in the inlet and outlet headers of the condensers, the
bottom sections are filled with a layer of refractory material, as shown in Table 2-8 and
Figure 2-8.
Table 2-8 Refractory materials for condensers
Lining Temperature Thickness Group
(°C)
Inlet 300 sloped 100 - 25 mm dense 130li castable (left side of Figure 2-8)
(bottom section only, level
with bottom tubes)
2.3.7.1 General
The design of liquid sulphur storage facilities depends largely on local conditions and
regulations.
The preferred storage method is a free-standing, externally-insulated steel tank in a
reinforced concrete pit (2.3.7.3).
Internally-lined reinforced concrete pits below ground level (2.3.7.2) were often used in the
past and are included in this DEP for maintenance purposes.
NOTE: Castables shall either be acid-resistant (e.g. Sauereisen type 72” or equivalent) or a selection shall be
made in accordance with DEP 64.24.32.30-Gen., Appendix 1 (4.3).
Underground sulphur pits consist of a reinforced concrete pit with an internal acid-resistant
refractory lining and an impervious membrane, mainly because concrete is not resistant to
the sulphuric acid which can be formed (e.g. from sulphur dioxide formed during H2S-
degassing or by other causes such as steam coil damage).
The pit is closed with a reinforced concrete slab. An adequate coating shall be applied on
top to avoid attack of the concrete after spillage or leakage. See Figure 2-9.
DEP 64.24.32.11-Gen.
December 1999
Page 18
The major disadvantage of such a pit is that it is virtually impossible to inspect the
reinforced concrete structure once the lining has been placed. Moreover, if the pit is partly
or completely below the ground water level, water ingress could occur over time, causing
unnoticed serious corrosion and decay of the concrete and the lining. An external
impermeable membrane shall therefore be applied.
Unless the pit remains completely above the ground water level, an additional cellular glass
lining should also be applied, for two reasons:
a) properly installed cellular glass is impermeable and gas tight;
b) as an insulating material it reduces the thermal load induced on the reinforced concrete
structure.
The structural design of the pit, i.e. reinforcement and type of concrete, shall be in
accordance with local regulations with regard to the imposed thermo-mechanical loads.
Depending on the overall dimensions of the pit, the lining walls should have a slight
outward curvature to increase its stability.
Expansion joints, if they are needed, shall be adequately designed for the intended duty
and shall be sealed against ingress of liquid sulphur. To form sufficient slope for draining
sulphur (and possibly water) from the bottom, a layer of acid-resistant castable shall be
placed prior to the final lining construction.
If the inside of the top-slab(s) will be lined with acid-resistant tiles, the tiles shall be
designed with “mechanical bond enhancement” and placed in the mould before pouring the
concrete. After hardening and removal of the mould, joints shall be thoroughly cleaned and
sealed with a resin-based, acid-resistant mortar.
below 150 °C. A water tight insulation system should therefore be applied on the outside to
keep the steel, supports and expansion joints above any condensation temperature. A
typical example is given in Appendix 5.
An internal refractory lining should be installed in the duct after the incinerator outlet in
order to protect the duct from the short, steep rises in flue gas temperature which can occur
due to operational upsets. The thickness shall be chosen and checked by calculations in
line with the externally applied insulating system.
2.3.9 Stack
Like the flue gas duct, the connecting stack shall be adequately protected against any
corrosive attack and/or high temperatures. Stacks are normally short, free-standing steel
structures with an external insulation system. Due attention shall be paid to avoiding cold
bridges in the structure.
Because the flue gases often have a high moisture content, installing a droplet separator on
top of the stack should be considered.
For further requirements on stacks, see DEP 34.24.26.31-Gen.
DEP 64.24.32.11-Gen.
December 1999
Page 20
3.1 GENERAL
The Applicator shall provide evidence that his personnel and supervisors have previously
worked on refractory installation projects for SRUs or similar units.
Reference is made to the applicable sections of DEP 44.24.90.31-Gen. and
DEP 64.24.32.30 Gen. with regard to the handling and installation of the various refractory
materials, such as preparation and mixing, installation and finishing.
1½ - 2½
c.f. wraps:
3 - 5 mm Ferrule: Ø 20.622 (+0/-1) mm
Boiler tube in total
3 mm
(± 0.1 mm)
The assembly should be covered with “cling-film” (not PVC) or wide clear adhesive tape to
ease the insertion of the ceramic fibre paper wrapped ferrules. A small amount of natural
soap can also ease the insertion.
Figure 3-2 Ceramic ferrule installation
trefractory t tubesheet
Cast refractory lining
Tube sheet
Directly before placing ferrules in rammed linings they shall be wrapped as described
above, with the remaining free part of the ferrules (at least 50 mm including the front collar)
brush-coated with an air-setting, ready-for-use mortar of a high temperature quality.
All loose, crumbly material shall be removed and the joint surface structure shall be
roughened. The next cast shall be executed as soon as possible, before the previous layer
has set.
The last cast and closure of the tube sheet lining shall have a height of no more than two
ferrule pitches and may be cast by firmly filling between the top ferrules and the connection
with the surrounding refractory. During application it shall be ensured that void-free
refractory is also placed behind the small ferrule flanges.
Immediately after removal of the consecutive shutter boards, any cement paste or other
debris shall be removed from the ferrules to ensure free passage of gases.
After completion of the lining the surface shall be left to set and air dry. A fine mist spray of
potable water shall be applied while curing in accordance with the Manufacturer's
specifications, especially if the ambient temperature is high or the humidity is very low.
If curing compound is used it shall be in accordance with DEP 64.24.32.30-Gen,
Appendix 8.
4. QUALITY CONTROL
A quality control plan shall be prepared by the Contractor/Applicator in compliance with this
DEP.
Appendix 6 shows a sample of a typical specification for guidance.
QA/QC procedures shall comply with DEP 44.24.90.31-Gen. and/or DEP 64.24.32.30-Gen.
The Applicator's procedure qualification shall be in accordance with DEP 64.24.32.30-Gen.
DEP 64.24.32.11-Gen.
December 1999
Page 24
5.1 GENERAL
Local repairs of tube sheet refractory linings may be made only with the approval of the
Principal.
Repairs described below are applicable to both new installations and previously fired
refractory linings.
6.1 GENERAL
The drying and firing schedules given in DEP 64.24.32.30-Gen. and DEP 44.24.90.31-Gen.
for shaped and monolithic refractory materials shall be used.
Adequate dry-out and firing shall be performed for the mortar used for bricking and for any
monolithic refractories that may have been installed.
A typical schedule for the initial dry-out and firing of SRU equipment is given in Figure 6-1,
using as far as possible the operational start-up of the equipment.
In order to keep catalyst free of vapour condensation or deposits, catalyst loading may take
place after the drying sequence is completed but before firing takes place and then
immediately followed by feed cut-in.
The refractory linings can be inspected out after drying and during catalyst loading. After
catalyst loading and possible inspection, the hold periods may be shorter than those
applied earlier but shall not be less than four hours each time in order to allow stabilisation.
The heating rate of the MRC and the downstream equipment shall be no faster than that
allowed by the schedule. The rate of temperature change shall not exceed 2 K/min.
• Circulate with preheated combustion air (includes flushing and checking of the
safeguarding system, instrumentation etc.) through the entire system. This may be done
primarily using the main burner, but also using the line burners. Open stack dampers, if
applicable, on full draught.
• Circulate steam through the WHB and condensers to above 110 °C; use auxiliary
heating equipment for the MRC to raise the temperature to between 110 °C and 180 °C.
• Circulate for at least 18 hours (initially required for drying all refractories, especially the
tube sheet lining and/or other monolithic refractory linings).
• Optional:
Cool down for catalyst loading; restart at front, holding for 4 to 8 hours at between
110 °C and 180 °C; this serves as a "stabilising" period to avoid possible later
interruptions such as trips.
• Raise the temperature of the MRC at a rate of 30 °C/h up to between 350 °C and
400 °C. The main burner is generally too large to perform this step in a controlled
manner. The preferred method is to use an auxiliary burner directly connected to the
main burner and/or an auxiliary burner temporarily in place of the fuel gas burner. The
air pressure drop across the air-register shall be at least 15 mbar in order to prevent
back-firing.
NOTE: Combustion will produce considerable quantities of water vapour in the flue gases, and these can
condense in colder areas of the unit. Where possible, the equipment should either be filled with
hot boiler feed water or heating steam should be turned on and vents should be opened to the
atmosphere before starting the burner.
Maintain the line-burners and the incinerator at operating temperature during further
heating up of the MRC.
• At a rate of 30 °C/hr, raise the temperature of the MRC to service temperature, with a
minimum of 900 °C, and during this period begin circulation of the WHB and condensers
to avoid overheating, but still paying attention to the cooling effects in connected
equipment.
• Hold for between 2 and 4 hours for stabilisation of safeguarding systems, expansion
allowances etc.;
• Start operation.
The above procedures will considerably improve the service life of the refractory
constructions and should be followed each time the equipment is returned to service. The
heating rate and cooling rate shall never be faster than 2 K/min.
Further improvements can be achieved if sacrificial thermocouples are installed in the
various equipment and/or refractory linings, especially during initial drying for evaporation of
free water used for mixing and curing.
Figure 6-1 Drying and firing of an SRU
7. REFERENCES
SHELL STANDARDS
Index to DEP publications and standard DEP 00.00.05.05-Gen.
specifications
Welding of metals DEP 30.10.60.18-Gen.
Steel stacks DEP 34.24.26.31-Gen.
Refractory bricks and shapes DEP 44.24.90.31-Gen.
Insulating and dense refractory concrete linings DEP 64.24.32.30-Gen.
DEP 64.24.32.11-Gen.
December 1999
Page 28
Dimensions for design and calculation of refractory materials for main and line burners
depend on the requirements of the Principal for a specific unit.
In general, burners are standardized by the Manufacturer, which result in an internal
diameter and length for a given capacity. Thermal gradient calculations will further be used
for the dimensions and layout of the internal refractory lining. The typical thickness of
various layers is given in Figure A1-1. The preferred brick patterns are given in Table A1-1.
Hole to be drilled
on mounting
±20°
Lining to continue
Ø 34-50 jointless into
mixing chamber
215 45°
A C D
B
115 or 152
115
High alumina brick
64 or 76
HT insulating brick
Insulating brick or board
(optional: microporous)
NOTE: The dimensions A, C, D and R should be derived from the burner drawings.
NOTE: s = stretcher
h = ½s
q = ¼s
For the type and size of side arch bricks and the number of bricks per ring, use Figure A1-2
and Figure A1-3.
DEP 64.24.32.11-Gen.
December 1999
Page 29
Number of bricks
80
with 2 mm joint: C
70 E = 230 x 114 x 84/44
A = 230 x 114 x 76/52
60 B = 230 x 114 x 72/56
C = 230 x 114 x 69/59
50 D = 230 x 114 x 67/61 B
40
34 LM V 70
A
30
E c
20
a
10 b
0
0 100 200 300 400 500 600 700 800
Inside radius (mm)
Example:
for LMV 70, choose either:
c type E + (34 - c) Std bricks (best ratio)
a type A + (34 - a) type B, (poor ratio)
b type E + (34 - b) type B, (worst ratio)
Number of bricks
400
with 2 mm joint: D
350 A = 230 x 114 x 76/52
B = 230 x 114 x 72/56
300 C = 230 x 114 x 69/59
D = 230 x 114 x 67/61
250
200
C
150
B
100
A
50
0
0 500 1000 1500 2000 2500 3000 3500 4000
Inside radius (mm)
DEP 64.24.32.11-Gen.
December 1999
Page 31
Figure A1-5 LMV burner layout with ceramic anchor for monolithic lining
Note: At least the top half of the burner shall be provided with ceramic anchors.
DEP 64.24.32.11-Gen.
December 1999
Page 33
NOTES: 1. Cold crushing strength after 6 months' storage (and thereafter) shall be at least 75 % of the
original "as supplied" values.
2. Refractory products from different manufacturers shall never be mixed. Storage life shall be at
least 12 months in a dry, cool warehouse.
DEP 64.24.32.11-Gen.
December 1999
Page 34
NOTE: Refractory products from different manufacturers shall never be mixed. Storage life shall be 12 months
in a dry, cool warehouse.
DEP 64.24.32.11-Gen.
December 1999
Page 35
NOTES: 1. Ferrules may be smoothed lightly with sandpaper. No more than 5% of the ferrule wall thickness
may be removed at any time.
2. The outside diameter of the ferrules may be checked by inserting the ferrules in a sample of the
tubes of the WHB.
NOTES: 1. Ferrules may be smoothed lightly with sandpaper. No more than 5% of the ferrule wall thickness
may be removed at any time.
2. The outside diameter of the ferrules may be checked by inserting the ferrules in a sample of the
tubes of the WHB.
(*) During 'heat soak operation', process temperature range is 280 °C to 360 °C.
(**) During 'runaway', temperature may rise to 750 °C in 15 min.
NOTE: Material specification is given sequentially from inside (hot face) towards the shell.
HA 70: refractory material based on Mullite.
HA 60: refractory material based on Sillimanite/Andalusite.
FC XX: refractory material based on (enriched) Fireclay
Refractory mortars shall be dedicated for the refractory materials being used, air-setting or
chemical/heat-setting, ready-for-use.