Professional Documents
Culture Documents
Rasoul Garmabdari, Mojtaba Moghimi, Fuwen Yang, Evan Gray and Junwei Lu
School of Engineering, Griffith University, Nathan Campus, Nathan, QLD 4111, Australia
Email:rasoul.garmabdari@Griffithuni.edu.au
Abstract—Multi Energy System (MES) concept was introduced Thus, to deal with the shortcomings of renewable resources
to improve the efficiency of conventional energy systems, reduce and high dependency of microgrids on the upstream grid,
air pollution as well as cost reduction. In addition, the flexibility traditional dispatchable power generators such as gas turbines
of MESs allows a higher penetration of renewable resources.
Basically, MES is a combined system to simultaneously produce are considered as a candidate solution. However, to improve
heat, electrical power and even cooling power. This system the technical, economic, and environmental performance of
benefits the advantages of both traditional and renewable energy these systems the multi energy concept is implemented by
carriers. However, when it comes to optimal operation planning which the optimal interaction between various devices are
of the utilised energy converters with the aim of cost reduction defined [3].
and efficiency enhancement, the design of Energy Management
System (EMS) becomes more of a challenge. This paper proposes Amongst various existing MESs [3, 4], Combined Heat and
a generic and accurate dynamic operation model considering Power (CHP) systems have received considerable attention due
the variable efficiencies and the transitional status of energy to the flexibility and security they provide in energy supply,
converters. It also includes the variability of the operational cost owing to their high overall energy utilisation efficiency, which
of energy storages and demand response. The developed model can reach up to 80% [5, 6]. These features would consequently
is applied to achieve the optimal dispatch plan and operation
of MES employed to provide power heat and electricity demand result in economic and environmental benefits [4].
for a university campus. The results verify the effectiveness and The integration of Renewable Energy Resources (RES) and
functionality of the proposed method. traditional energy production methods in CHP systems creates
Index Terms—multi energy systems; system modelling; optimi- a large number of variables, including physical limitations of
sation; combined heating and power system energy carriers and energy sources. Hence, both designing and
planning of these systems require utmost attention, considering
I. I NTRODUCTION all factors contributing to the CHP operation as well as
The demand for energy is drastically increasing due to equipment characteristics. In this regard, much research has
industrialisation and burgeoning population, leading to the been carried out and several techniques proposed to achieve
introduction of new concepts and integrated microgrid systems both optimal equipment capacities and the optimal operating
such as Multi Energy System (MES) [1]. These systems, schedule of the CHP.
consisting of two or more energy converters, enhance the Generally, the MESs are modelled based upon the energy
system efficiency, alleviate the environmental pollution and flow analysis method, segregating the energy hubs and energy
increase the reliability and flexibility in energy supply. In carriers according to the type of energy demand [7]. This
addition, MESs have elevated the penetration of renewable approach focuses on the steady state of devices rather than the
energy technologies in distributed energy applications [2]. In transitional or dynamic characteristics of the system. However,
order to lessen the carbon pollutant and enhance the efficiency the energy flow model provides an adequate accuracy at initial
of the MES, the heating demand is produced simultaneously design concept and planning stage. Considering energy flow
along with electricity demand. Last but not least, employing theory as the modelling technique, at the lower hierarchy
MESs could reduce the cost of energy production effectively of modelling, the CHP can be modelled either statistically
whilst meeting the load requirement. or employing time series, each one of which has its own
University research facilities are considered as critical loads applications and advantages [8].
due to the sensitive equipment operating in a certain condition. In the literature, different models considering various tech-
Hence, providing a consistent and continuous power supply is nical and economic aspects of MESs to size the system com-
necessary to maintain these machines running in their required ponents and scheduling approaches to address the reliability
condition such as the certain temperature level. Although using and economic concerns, have been developed. Authors in [9]
renewables in conjunction with battery energy storage and employed the coupling algorithm, based on statistical mod-
upstream grid delivers a stable power to the research facility, elling, to model and determine optimal MES configuration,
they are still lacking to provide power in the occasion of taking into account the economic, energy and environmental
severe power fluctuations and power outage contingencies. objectives. Furthermore, paper [4] introduced a new concept
Ns binary variables (λk ) into decision variable matrix. The E. Operation Scheduling Optimisation
described constraint in 14 satisfies this condition at each time The optimal operation of CHP systems determines the
interval. In this paper, Nomad Nonlinear algorithm in OPTI required amount of energy carriers to satisfy the load demand
solver in Matlab platform is used to optimise the intervals of at minimum cost. In addition to the aforementioned cost
the piecewise function. factors and operational constraints, fuel cost, electricity cost
being purchased from the grid, and ESS operating cost should
λk (t).Ykmin ≤ Yk (t) ≤ λk (t).Ykmax (13) be included in the objective function. The electricity cost
Ns
X comprises of two main elements; energy cost and peak demand
λk (t) ≤ 1 (14) cost. Although the peak demand cost is monthly calculated,
k=1 it has a significant impact on the electricity bill [15]. The
Due to the thermal stress and mechanical limitations of the objective function to minimise the operation cost is established
energy converters, the starting up and shutting down process as in 20.
duration is extended and therefore changing the status of units
imposes an additional operating cost on the system. Hence, it T
X
is required to consider this cost component in the objective φ= Pgrid (t).Cp,grid (t) + ΨF uel .Cgas (t) .∆t
function. The incurred start-up (αstrn (t)) and shut-down cost t=1
(20)
coefficients (αsdnn (t)) for the particular unit n, which is X
+Csc (t) + CESS,i (t) + Cpeak .Ppeak
modelled as several sub units, is obtained using 15 and 16
i
respectively.
Ns M where Cp,grid (t), i and Cgas (t) are the prices of the electricity
X X
αstrn (t) = 1 − (λk (t − 1)) . (λk (t) (15) purchased from upstream grid, the number of hubs, and gas
k=1 k=1 purchased from gas network at time t. Cpeak , Ppeak , ΨF uel ,
Ns M and CESS,i (t) denote peak demand, fuel consumption, and
αsdnn (t) = 1−
X
(λk (t)) .
X
(λk (t − 1) (16) ESS operating costs, respectively.
k=1 k=1
The fuel consumption of an energy converter is described
as a second order function of its produced power at the time
The associated cost with changing the status of energy con-
t as shown in 21.
verters at each time interval is described as below, where
Cstr,j and Csdn,j are the start-up and shut-down costs of the M
X
particular unit j, and M represents the total number of energy ΨF uel = Aj .Pj2 (t) + Bj .Pj (t) + Cj (21)
converters. j=1
M
X where Aj , Bj , Cj are the coefficients of fuel consumption of
Csc (t) = αstrn (t).Cstr,j + αsdnn (t).Csdn,j (17) unit j and Pj (t) shows the power being produced at time t.The
j=1 operating cost of the ESS can be approximated as a quadratic
max
The other constraint that need to be considered in the mod- function of its power rates as below where the Cch,ESS and
max
elling of energy converters is ramp rate limits. Basically, the Cdis,ESS imply the maximum operation cost of charging and
discharging of the ESS at the highest charging and discharging minimum cost while attenuating the electricity peak demand.
power rates. Employing the proposed dynamic model and performing the
max
Cch,ESS max
Cdis,ESS optimisation algorithm, the dispatch plan and contribution
2 2
CESS (t) = max .Pch,ESS (t) + max .Pdis,ESS (t) of each component to supply electricity demand is achieved
Pch,ESS Pdis,ESS as illustrated in Fig.4.The amount of power purchased from
(22)
the grid during the peak period is maintained at about the
To solve the developed scheduling problem which is a Mixed
average value (200 kW) during the off-peak period to minimise
Integer Quadratic Programming (MIQP) optimisation, the
the peak cost. On the other hand, the gas turbine generates
CPLEX solver in MATLAB platform has been employed.
more power during the overlapping peak period of heat and
III. S IMULATION R ESULTS AND D ISCUSSION electricity to take advantage of the co-produced heat to satisfy
the heat demand.
Developing an accurate mathematical model for multi en-
ergy systems significantly impacts on the optimal performance
of the energy converters. The variable efficiency, ramp rate
constraints, and state change limits of the equipment in energy
hub modelling reflect the dynamic behaviour of the system and
consequently will lead to a reliable optimal scheduling solu-
tion. The primary objective of operation optimisation in this
paper is to minimise the operating cost of the system. Hence,
the peak shaving function which tremendously contributes to
the total electricity cost as well as variable ESS operating
cost are taken into account. To verify the effectiveness and
functionality of the proposed model and schedule optimisation
approach, they are implemented to a CHP system designed
for a research facility centre at Griffith University-Nathan
Campus. The heat and electricity demands of the research
centre are acquired from the data acquisition system [16] as
illustrated in Fig.3.
Fig. 4. Electricity production of components to meet electricity demand