FORO: ADMINISTRACION DE OBRAS

FRANCISCO HERMENEGILDO IXCHOP CHIVALAN

TIEMPO TIEMPO MAS TIEMPO


ACTIVIDAD PREDECESOR DURACION OPTIMISTA a PROBABLE m PESIMISTA b te σ2
A 10 3 4 6 4.16666667 0.25
B A 25 3 5 6 4.83333333 0.25
C A 15 2 3 4 3 0.11111111
D A 20 3 4 5 4 0.11111111
E B,C 5 1 1 5 1.66666667 0.44444444
F E 15 2 4 5 3.83333333 0.25
G E 10 3 3 4 3.16666667 0.02777778
H D,F,G 20 4 3 5 3.5 0.02777778