Professional Documents
Culture Documents
Preface
Before the single station and system commissioning of SDH equipment, it is
necessary to emphasize the following points:
1) The monitoring scope should cover most of the hardware paths, the more
the better, including those unused in current services, to ensure smooth
upgrading and expanding in the future.
2-1
OptiX High-level Training Manual Part 2 Equipment Commissioning
Chapter 2 Single Station Commissioning of SDH
Equipment – General Items
Acceptance testing items should be discussed with the customer before the
single station commissioning stage. The items and the interfaces to test
should be determined at that time and the corresponding memo is prefered.
(or to record in Summary of Negotiation Meeting before Installation)
The testing under the engineer's individual opinion might result in the
rejection of customer, and this case should be avoided.
Such test mainly includes the reliability of protection switching and reliability
of resetting (restarting) etc..
Ÿ Whether the screws on the front and back of cabinet are complete and tightened
Ÿ Ensure that Order-wire telephone , anti-static wrist strap and network cable are not lost,
and maintenance personnel is informed not to take them for other use.
2-2
OptiX High-level Training Manual Part 2 Equipment Commissioning
Chapter 2 Single Station Commissioning of SDH
Equipment – General Items
Ÿ Make sure there is no such things like small screws and broken belts
etc. in subrack.
2) Four copper cabling posts: PGND and GND (BGND) ; two -48V power
copper cabling posts: -48V1 and -48V2.
3) Four subrack power switches: two upper rack power switches-- UPPER
SUBRACKs (dual system), and two lower rack power switches -- LOWER
SUBRACKs (dual system).
4) Alarm sound cutting out switch MUTE and acousto-optic test switch
TEST.
5) SS02PMU: supports hot plug. There are two indicators on its front
panel ,the upper is running indicator (green) and the lower is alarm indicator
(red) .
2-3
OptiX High-level Training Manual Part 2 Equipment Commissioning
Chapter 2 Single Station Commissioning of SDH
Equipment – General Items
Before the shipment of OptiX equipment ,the BGND and PGND posts is
connected with a shorting wire ,and the same as -48V1 and -48V2 posts.
Test the resistance between -48V1 (or -48V2) and BGND (or PGND) posts
with the shorting wires on its position before the power cables are
connected. The normal result should be as follows: When the -48V1 and -
48V2 are switched on, no matter the subrack power switches are all
switched on or off , the resistance between -48V1 (or -48V2) and BGND (or
PGND) posts should be ∞; and when the -48V1 and -48V2 are all switched
off, no matter the subrack power switches are all switched on or off , the
resistance between -48V1 (or -48V2) and BGND (or PGND) posts should
be tens of K ohm. If the resistance is less than 20 ohm when one subrack
power switch is switched on, there may exist short-circuit inside the subrack
. This fault must be cleared before switch on the power!
If two individual -48V power supply ia applied, the shorting wire bwteen -
48V1and -48V2 posts should be removed, otherwise the power supply
device may be damaged due to the current backflow which is caused by the
voltage difference between the two power supplies. If there is only one
power supply, keep the shorting wire between -48V1 and -48V2 posts.
When power on OptiX equipment, the two -48V master switches should be
both switched on. Meanwhile, the "use the secondary power supply" item in
PMU parameter dialog box should be selected in NMS, otherwise the PMU
unit may report the alarms as "PWR-MAJ-ALM" or "PWR-MIN-ALM" .
The shorting wire between BGND and PGND posts should not be pull down
( have the function of thunderstreak-proof ). If the customer doubts about
this, guide and explain to them refering to the answer of "telecommunication
protection technical support center of China Telecom Bureau General" or to
ITU-T K.27 recommendation.
There are two power input ports in OptiX 155/622H,located on the right of
the casing back.Set the power switch to the state of OFF and test the
resistance respectively between PGND,GND,BGND and -48V using the
multimeter to see whether there is short circuit.In case of short
circuit,power-on wiht a view to finding out the reson for short circuit is
strictly prohibited.Notice both of the power input ports must be measured.
2-4
OptiX High-level Training Manual Part 2 Equipment Commissioning
Chapter 2 Single Station Commissioning of SDH
Equipment – General Items
Ÿ Check whether each board can be inserted into its own slot smoothly,
forced pull-and-plug is forbidden.
2.1.7 Ensure all the power switches are off after the single station hardware
examination is finished
2-5
OptiX High-level Training Manual Part 2 Equipment Commissioning
Chapter 2 Single Station Commissioning of SDH
Equipment – General Items
Make sure the customer's power engineer is present, when connect power
supply wire and ground wire to customer's power supply device. It is
recommended to connect the wires to power supply device by customer's
engineer, but we must point out which is power supply wire and which is
ground wire. This duty may also refer to the devison of engineering
interface.
3) After all these examinations passed, power on the two master power
switches at top of OptiX cabinet. Now the green indicator at the top of
cabinet should be ON, and other indicators are all OFF.
2-6
OptiX High-level Training Manual Part 2 Equipment Commissioning
Chapter 2 Single Station Commissioning of SDH
Equipment – General Items
Set the acousto-optic test switch TEST at the top of cabinet to ON, the red
and yellow indicators on the top should both be ON, accompanying with
alarm sound.
2.2.4 Availability Examination of Alarm Sound Cutting Out Switch at the Top of
Cabinet
Then set the Alarm sound cutting out switch MUTE at the top of rack to OFF
to mute the alarm sound.
After these two tests are completed, set the MUTE key to ON and TEST
key to OFF.
In SS03PBS at the top of OptiX cabinet, there is a PMU board called Power
and Environment Monitoring unit, and its location is as illustrated in Figure
2-2:
power box
SS01LVC
SS01PDA
cabinet
The alarm signals output from J9 or J10 socket connector of PDA board
(the positon of PDA is shown above). The pins of these two socket
connectors are entirely the same, including one critical alarm output and
one non-critical alarmoutput, as shown in Figuer 2-3:
2-7
OptiX High-level Training Manual Part 2 Equipment Commissioning
Chapter 2 Single Station Commissioning of SDH
Equipment – General Items
non-critical alarm
1
6 ground of alarm circuit
2
7
3
8 ground of alarm circuit
4
9
5
critical alarm
Each socket connector extends four alarm output wires provided by Huawei
Co., the colors are as follows:
After the alarm output wires is properly connected, the alarm signals should
be sent to external alarm equipments (such as column-head cabinet) to
drive its acousto-optic indicator. So obviously the extenal alarm equipment
should have the function of shutting down the alarm sound.
2-8
OptiX High-level Training Manual Part 2 Equipment Commissioning
Chapter 2 Single Station Commissioning of SDH
Equipment – General Items
-œ
4ÿ
8V
BG ND
mute groundof alarmcircuit
critical alarm
non-critical alarm
ringingpower ringingpower
GND
I¬4 xO¬šæ‡O'«O¨UD§
Figure 2-4 subrack power feeding socket connector
Check whether the three green indicator are ON and the red alarm indicator
is OFF. Detect the upper and lower parts of subrack by hand, there should
be wind blowing (please note not to touch fan). It is necessary to
demonstrate how to clean the dust filter mesh of fan to the customer's
maintenance personnel, and emphasize the importance of periodic cleaning
with the period of 2-4 times every month.
After a unit is in service, the running indicator (green) should flash in the
frequency of 1s on and 1s off. If there exists a alarm, the alarm indicator
(red) should also flash in the frequency of 1~3 times every other second. If
the indicator of a unit is OFF or ALWAYS ON, it indicates that this unit is not
inserted properly, there is a fault in hardware or there is a toppled pin on
motherboard. First check whether there is a toppled pin on motherboard,
2-9
OptiX High-level Training Manual Part 2 Equipment Commissioning
Chapter 2 Single Station Commissioning of SDH
Equipment – General Items
then check the unit, and replace the unit after you are sure of a hardware
fault of it.
If a unit doesn't come into operation, you can pull and plug it first. If the
problem is not solved, there might be the loss of configuration data of SCC
unit or the failure of board's mailbox. Download configuration data again, if
the problem remains, replace this unit or SCC.
2.3.3 When the Optical Aggregate Unit is Looped Back, its Alarm Indicator
Should be OFF.
For single optical interface aggregate unit, the alarm indicator should flash 3
times every other second indicating critical alarm due to loss of signal. After
the interface is looped back, the alarm indicator should be OFF, showing
this aggregate unit is normal in the main.
For aggregate unit with multiple optical interfaces, no alarm will be reported
if no traffic is distributed to the optical interface. In this case, assign traffics
to all optical interfaces, then the indicator of this unit should flash 3 times
every other second. Loopback all the optical interfaces, and the indicator
should come into OFF.
If the alarm indicator is still ON, examine the unit and check the optical
power. If the alarm indicator doesn't flash 3 times every other second, the
optical interface is generally normal. If it flashes 2 times, it may be the
AUAIS, AULOP or HPLOM alarm due to no source of signal.
2.3.4 Examine the State of PMU and Communication Via Serial Port
SS02PMU is adopted in SS03PBS at the top of cabinet, and there are also
running indicator (green), alarm indicator (red) on the front panel of it. After
the cabinet is powered on for 1~2 minutes, the running indicator should
flash in the frequency of 1s on/1s off, indicating normal running state. The
red indicator only indicates the alarm of power box instead of the subrack,
which is different from SS01PMU.
There is a 4-bit toggle switch on PMU, and its position at PMU unit is
illustrated in Figure 2-5:
2-10
OptiX High-level Training Manual Part 2 Equipment Commissioning
Chapter 2 Single Station Commissioning of SDH
Equipment – General Items
SS02PMU
green indicator
1 2 3 4
ON
1 2 3 4
Figure 2-6 4-bit toggle switch
There is no need to touch bit 1,3,4 of the toggle switch. Bit 2 indicates
whether the PMU communicates with upper subrack or lower subrack,
toggling to ON indicates the communication with lower subrack, toggling to
OFF indicates the communication with upper subrack.Check whether the
settings of these four bits are in compliance with the actual situation.
If you want to modify the setting of this toggle switch, please pull out PMU
unit first, then modify the switch setting, and then plug in the unit. SS02PMU
is hot-pluggable, so it can automatically come into operaiton without
deplayment after it's plugged in, and finally it's needed to create this unit in
NMS interface.
Use the command ":ptp:bid,10,0;" to query the version of PMU, where "bid"
stands for the board position of PMU. As for OptiX155/622/2500+
equipment, the board opsition of PMU is 28 ( 1c in hexadecimal); and for
OptiX2500+ the board position is 19 (13 in hexadecimal). If this command
returns proper result, the seial port communication is normal in the main.
2-11
OptiX High-level Training Manual Part 2 Equipment Commissioning
Chapter 2 Single Station Commissioning of SDH
Equipment – General Items
If the ALC switch is moved downward and the alarm buzzer still rings,
check whether the settings of PMU toggle switches are proper (whether in
communication with corresponding subrack), and check the configuration of
PMU board in NMS (when there are two subracks in one cabinet, if the
PMU toggle switch is set to communicate with lower subrack, PMU board
should be created in the lower subrack's board position window in NMS).
As for 155/622H,set the alarm cut-off switch on the front of the casing to ON
and meanwhile the alarm cut-off switch on the back of the casing other than
ALMCUT.In this case,if the red or yellow alarm indicator is on,the alrm
sound can be heard.Set the alarm cut-off switch on the front of the casing to
OFF or set the alarm cut-off switch on the back of the casing to ALMCUT
and the alarm sound will be cut-off.Note that if the alarm switch is on,the
casing will let out the alarm sound whether there is an alarm until the alarm
is gone or the alarm is cut off.
2-12
OptiX High-level Training Manual Part 2 Equipment Commissioning
Chapter 2 Single Station Commissioning of SDH
Equipment – General Items
As for 155/622H,The RST key on the SCB board is a reset key.Press this
key to reset the SCC unit.Reset is complete 2-3 minutes later and the board
enters a normal operation status.The indicator blinks one time per
second.The ETN indicator on the SCB is an Ethernet indicator(a yellow
indicator).Dark yellow indicator indicates the NE is not connected to NM by
cable;Luminent yellow indicator shows the NE is normanlly connected to
NM;blinking yellow indicator means there are data being transmitted on the
network.
During the test, connect the portable computer to the Ethernet interface of
OptiX equipment, this ETN indicator should be ON. When there is data
transmission between SCC unit and portable computer, this ETN indicator
flashs.
The method of observing RJ45 connector is as follows: put the side with
pins upward and let the cable in your side, the numbers of pins from left to
right are 1~8 respectively. The connections of cross-connected UTP cable
and standard UTP cable are as illustrated in Figure 2-7:
2-13
OptiX High-level Training Manual Part 2 Equipment Commissioning
Chapter 2 Single Station Commissioning of SDH
Equipment – General Items
1 1 TX+ 1 1
2 2 TX- 2 2
3 3 RX+ 3 3
6 6 RX- 6 6
Figure 2-7 The connections of pins of cross-connected UTP cable and standard UTP
cable
In the portable computer, install SBS Navigator programme, and create the
shortcut icon named SBS Navigator on the desktop. Install the NES
matching with the NE software, and create the shortcut icon named SBS
NES on the desktop.
3) If the NMS terminal is SUN workstation, the subnet mask code will
appear on the screen while power-on, make sure it's 255.255.0.0. Then
enter CDE environment using superuser's identity, open the TERMINAL
windows, and input "#vi /etc/hosts" command to check whether the IP of
this workstation is like 129.9.0.X. If the IP is not like this, modify the hosts
file as follows:
#vi /etc/hosts
Modify the IP address which is in the same line with "SYBASE loghost" into
the determined IP of workstation as 129.9.0.X. Notice that maybe the hosts
2-14
OptiX High-level Training Manual Part 2 Equipment Commissioning
Chapter 2 Single Station Commissioning of SDH
Equipment – General Items
file is a read-only file, you need to use "#chmod 777 filename" command to
modify its attribute into writeable.
After all the items checked and modified, input command "ping NE IP
address" in TERMINAL window. If "alive" is returned , it indicates that the
connection between workstation NMS terminal and NE is normal.
4) After the connection between NMS terminal and OptiX network element
is properly established, run "SBS Navigator" software and click <retrieve>
button to search for IP of NE. Normally the NE IP will emerge on the "NE IP
address" window and if it doesn't emerge, input the IP manually. Then click
<connect> to enter the MML dialog box. If there's "ready" in the nethermost
status bar of the dialog box, the connection is normal, otherwise the
examination of items mentioned above is necessary.
Then, compare these versions with those listed in shipping list and its
appending software version table. If the same, record these versions in
engineering technical documents after the shipping list and its appending
software version table. If the defferent, record these versions after the
2-15
OptiX High-level Training Manual Part 2 Equipment Commissioning
Chapter 2 Single Station Commissioning of SDH
Equipment – General Items
Create files (text files or *.cmd files) for single station test in the portable
computer. The so-called files for single station test refer to the files for
testing a series performances of single station such as the performance of
the installed tributary unit, the performance of motherboard, the correctness
and reliability of connectings between PDH ports of OptiX equipment and
DDF, and the switching reliability etc.
The principle of creating a single station test file is: Configure the traffics to
cover all the allocated units and all the data buses. The details are as
follows:
(1) All the PDH ports of all the allocated tributary interface units should be
configured with traffic for test.
(2) Traffic configured for test should cover all the data buses of every line
interface units.
There are two configuration schemes according to the two principles above:
One is to concentrate the traffics of all PDH ports to one VC4 of one LU,
then configure all the VC4 of all LU in series, to test all the VC4 of LUs. In
this scheme, the configuration should be in accordance with the loopback of
optical interfaces ,and this scheme is called " VC4 in series method ".
Configure 4 VC12 traffics of the first VC4 of STM-16 PP ring, to 1~4 ports of
PD1, 4 VC12 traffics of the second VC4 to 5~8 ports......, and 4 VC12
traffics of the eighth VC4 to 31~32 ports of PD1. This test file covers all the
existing PDH ports and 1~8 data buses of two S16.
As for the second test file, configure the VC12 traffics of 9~16 VC4s of the
ring to 32 ports of PD1, to test 9~16 data buses of two S16s. Two files are
requested only because the traffics from S16 to VC12 cross-connect metrix
must be within 16 VC4s.
2-16
OptiX High-level Training Manual Part 2 Equipment Commissioning
Chapter 2 Single Station Commissioning of SDH
Equipment – General Items
(3) All the data buses of LUs of every logic system should be covered if
there are more than one logic system. For example, S16s of IU5 and IU6
constitute a PP logic system, S16 of IU7 constitutes a LINE logic system,
then configure the traffics of these 3 optical interface units to TUs or SD1s,
to cover all the data buses of these 3 units for test.
The advantage is not only the path protection function of TUs can be tested,
but also the performances of active bus and standby bus on LUs and TUs
can be tested, so the testing paths are most complete.
(6) If there are OptiX2500+ main subrack and extended subrack, test the
main subrack and extended subrack as a whole. Download the test file to
main subrack and extended subrack covering all PDH ports and all data
buses, then loopback the optical interfaces on main subrack, test the
tributary paths on main subrack and extended subrack. If main subrack
connects other equipment via SDH interfaces, test these interfaces using
SDH tester.
Create single station test files test according to the allocated units of each
station. The sample files can be seen in each OptiX equipment's special
items of single station commissioning.
2-17
OptiX High-level Training Manual Part 2 Equipment Commissioning
Chapter 2 Single Station Commissioning of SDH
Equipment – General Items
For the testing method, you can also refer to Acceptance Manual.
2-18
OptiX High-level Training Manual Part 2 Equipment Commissioning
Chapter 2 Single Station Commissioning of SDH
Equipment – General Items
power ON/OFF
LCD screen
tail fiber
For the testing method, you can also refer to Acceptance Manual.
2-19
OptiX High-level Training Manual Part 2 Equipment Commissioning
Chapter 2 Single Station Commissioning of SDH
Equipment – General Items
RX TX
TX
2M
error
code
detector
RX
For the testing method, you can also refer to Acceptance Manual.
At the OptiX optical interface unit side, measure the actual receiving optical
power sent from the opposite station, record the result in single station
commission record table. The actual receiving optical power must meet the
following demands:
· If the actual receiving optical power is too small, check whether the
fiber cable is too long, or the optical connector is not in good connection
(including dirt on connector) , or the attenuation of fiber cable is too large. If
2-20
OptiX High-level Training Manual Part 2 Equipment Commissioning
Chapter 2 Single Station Commissioning of SDH
Equipment – General Items
the attenuation is too large, suggest the customer to solve the problem. If
the transmission distance is too long for optical interface unit, then judge
whether the surveyed distance has mistake or the allocation of optical
interface unit is mistaken, then feedback this information to company, and
think upon changing optical interface unit or add optical amplifer unit.
· As for the actual receiving optical power is too large, from Sep of 2000,
the principle of allocating attenuator before shipment is specified for
OptiX155/622 and OptiX2500+, according to the surveyed fiber cable
distance. In most cases, it can meet the need of on-site application. If
there's only several optical interface unit which receiving optical power is
too large, apply for the attenuators from the branch office, to ensure the
receiving optical power meets the request. If the attenuators are far less for
the optical units and transmission distance, feecback the information to
company for settlement according to specified flow.
Attention: the acual receiving optical power must be in the aforesaid range
when commissioning. As for the maintenance of in-service equipments, if
the mismatch of optical power is found, it must be settled too.
5. Check the attenuation of fiber cable and tail fiber via optical power
measurement
Measure the actual receiving optical power at ODF. Compare this power
and the output optical power of adjacent NE, and refer to the standard value
of fiber cable's attenuaiton, to estimate whether the attenuation of this fiber
cable is too large. If so, suggest the customer to find out the fault point and
solve it. Never to leave it aside only because the traffic is OK.
Measure the receiving optical power at ODF and optical unit side. The
comparison of these two values should be less than 1.5dB. If not so, the tail
fiber can be judged not OK, when the fault of optical connector is
eliminated and the tail fiber is not tied up too tight. In this case, thange the
tail fiber according to specified flow. If the attenuation of tail fiber is
excessive due to too tight colligation, the layout of tail fiber must be
modified.
2-21
OptiX High-level Training Manual Part 2 Equipment Commissioning
Chapter 2 Single Station Commissioning of SDH
Equipment – General Items
After sending files for single station test, enter OptiX Network Management
System in the portable computer, create NE, and set it as network gateway
NE, then perform Configuration data uploading, refer to OptiXMN NES
Operation Manual for details. Have the receiving/sending optical interface of
the optical interface board self-looped, refer to the optical interface self-loop
method in Testing Path Protection switching Function for details. Then
connect the bit error detector to the first 2M interface of DDF rack (or
E75/D75), now the bit error detector alarm should disappear (if the alarm
does not disappear, try to interchange the receiving and sending ends of bit
error detector). Then set the first 2M interface to Remote loop back (in-loop)
in the network management, now the bit error detector should give an
alarm, indicating it is actually the first 2M interface that the bit error detector
is connected with. Then test the second 2M interface similarly, and proceed
in turn till all 2M interfaces are tested. Please note that all 2M interfaces
must be set to Not loop back after the test.
2-22
OptiX High-level Training Manual Part 2 Equipment Commissioning
Chapter 2 Single Station Commissioning of SDH
Equipment – General Items
Please note that both connection and disconnection states should be tested,
so as to prevent traffic from looping back or prevent cable from cross-
connecting. That is, when Remote loop back is not set, there is no alarm in
the meter (connection); after Remote loop back is set, an alarm is
generated in the meter (disconnection).
On the common extended subrack, since there is no STG board, the bit
error detector will give an alarm if you have receiving/sending SL2 board
self-looped to test 2M signal. Although the test can be done if you have
tributary looped back locally, the equipment in subrack can not be tested
thoroughly since signals only pass through a part of tributary board.
Testing method: have the optical interface on main subrack self-looped. The
faulty boards in single station can be cleared basically in this testing
method.
For PL3, PL4, SE1 and SE2 boards, if the equipped instrument can not do
the test, they can be looped back on DDF rack to view whether LOS alarm
disappear. But the system commissioning test of the network must be done.
Connect 2M bit error test instrument (or the 2M electricity interface of SDH
test instrument) and D75 coaxial connector assemblies in the following
mode, the connecting lines in the coaxial connector assemblies are
connected in series, as illustrated in Figure 3-3: (connect to DDF rack if the
rack is available)
2-23
OptiX High-level Training Manual Part 2 Equipment Commissioning
Chapter 2 Single Station Commissioning of SDH
Equipment – General Items
Rx Tx
Rx
IN
Tx
OUT
attenuator
Connect the bit error detector to D75 board or DDF rack in the mode
illustrated in Figure 3-3 for bit error testing. You should observe for 1~2
minutes, and there should be no bit error. (Note: if TSE flashs occasionally,
(i. e., there is few bit errors), you can divide the coaxial connector
assemblies into two segments, each segment is connected with 8
tributaries in series for testing, it is required that no error appears after the
segment is tested for 1~2 minutes). Disconnect the optical fiber (active ring)
between W←E (IN of W and OUT of E), the alarm indicator of the bit error
detector should be OFF after flashing once, simultaneously, PS protection
switching alarm of tested 2M interface can be queried from NMS, indicating
2-24
OptiX High-level Training Manual Part 2 Equipment Commissioning
Chapter 2 Single Station Commissioning of SDH
Equipment – General Items
the protection switching function is normal. Observe for 1~2 minutes, there
should be no bit error.
Connect the optical fiber between W←E properly till there is no alarm on
both W and E optical interface boards. Then disconnect the optical fiber
(standby ring) between W→E (OUT of W and IN of E), the alarm indicator
of the bit error detector should be OFF after flashing once, simultaneously,
PS protection switching alarm of the tested 2M interface in NMSshould end,
indicating the ending of protection switching. Observe for 1~2 minutes,
there should be no bit error.
Disconnect the optical fiber in active ring, after traffics are switched over to
standby ring, connect the optical fiber in active ring properly till there is no
alarm on optical interface board, now you should not perform any operation
on the optical fiber on standby ring. After 10 minutes, the alarm indicator of
the bit error detector should be OFF after flashing once, simultaneously, PS
protection switching alarm of the tested 2M interface in NMS should end,
indicating the protection switching is recovered normally.
Connect the optical fiber in active ring (receiving from west and sending to
east), disconnect the optical fiber in standby ring, test the bit error for 10
minutes, there should be 0 bit error.
Disconnect the optical fiber in active ring, connect the optical fiber in
standby ring (receiving from east and sending to west), test the bit error for
10 minutes, there should be 0 bit error.
2-25
OptiX High-level Training Manual Part 2 Equipment Commissioning
Chapter 2 Single Station Commissioning of SDH
Equipment – General Items
Before test, check whether the emergency interrupt auto report of K bytes
from west and east optical interface units to SCC is activated:
:ptp:6,12,99;
If the return value is "1", the interrupt report is activated, otherwise the value
should be set to be "1". The setting command is:
:apsc-set-mbrep:5,true;
2) Insert K1, K2 bytes respectively as "1" and "2" into westward S16: (of
course other legal K1 and K2 bytes are available)
:apsc-ptp:5,92,1,2;
Note: this test should cover the test of last 3 bits of K2 byte, for example: for
the first time run the above command with K bytes of "1" and "2"; the
second time with K bytes of "1" and "3", using this method the test whether
the hardware process of last 3 bits of K2 byte is normal.
More inportant: if insert the same K bytes twice using the command above,
the K bytes inserted for the second time will not be reported automatically.
Only when the latter inserted K bytes is different from the former, they will
be automatically reported.
2-26
OptiX High-level Training Manual Part 2 Equipment Commissioning
Chapter 2 Single Station Commissioning of SDH
Equipment – General Items
BID PARA
COUNT
This report shows that the westward S16 actually received K1 and K2
bytes as "01" and "02". Because of the loopback of westward S16, the
sent K bytes are received by itself, so the received K1 and K2 bytes
should be the same as sent, and should be able to automatically report.
In this case, the rest result is normal.
4) Insert other K1 and K2 bytes for test. If the interrupt reported K1 and K2
bytes are the same as the sent, this test of westward s16 is passed.
According to the same steps, test the K bytes interrupt report of eastward
S16 (board position 6) , and check whether its reporting time is normal.
2-27
OptiX High-level Training Manual Part 2 Equipment Commissioning
Chapter 2 Single Station Commissioning of SDH
Equipment – General Items
1) First loopback the westward and eastward optical board, then execute
the following command to activate the interrupt report of westward S16:
:apsc-set-mbrep:5,true;
2) Set the westward S16 into the state of K byte pass through:
:apsc-ptp:5,91,1;
If the westward optical board is in K byte pass through state, it will send the
K bytes received by eastward optical board directly, i.e., the eastward
optical board will send its receiving K bytes not only to SCC unit, but also to
westward optical board, and the westward board sends these K bytes out.
3) Insert K1, K2 bytes respectively as "1" and "2" into eastward S16:
:apsc-ptp:6,92,1,2;
After this command is executed, there should have interrupt auto report of
K1 and K2 bytes from westward optical board, the report result is already
illustrated in step 3 of "1. Test the interrupt report of K bytes".
The theory of this test is:first the eastward optical board sends the inserted
K bytes out, then via the eastward loopback tail fiber, the K bytes are
received by the eastward optical board itself. Because of the passing
through of westward optical board, the eastward board broadcast its
received K bytes to westward board, and westward board sends these K
bytes. Also because the westward optical board is looped back, it receives
these K bytes, and activate the interrupt auto report.
4) Insert K1 and K2 bytes as "3,4", "5,5" and "6,0" into the eastward optical
board, check whether the K bytes interrupt report of westward board is
normal.
1) First loopback eastward and westward optical board, and activate the K
byte interrupt auto report of eastward optical board.
2-28
OptiX High-level Training Manual Part 2 Equipment Commissioning
Chapter 2 Single Station Commissioning of SDH
Equipment – General Items
deactivate: :apsc-ptp:5,91,0
activate: :apsc-ptp:6,91,1
3) Then insert K bytes into westward board, examine the interrupt report of
eastward.
After test, the K byte interrupt report of eastward and westward optical
board must be deactivated:
:apsc-set-mbrep:5,false;
:apsc-set-mbrep:6,false;
:apsc-ptp:5,91,0;
:apsc-ptp:6,91,0;
2.4.10 Test blank board positions, for NEs of head office or those with the
possibility of extension
The purpose of this test, is to check whether the pins of each blank board
position and its corresponding D75/E75 are normal, and whether the data
buses of all board position are normal.
1) In test file, configure TUs for all possible tributary board position, and
configure traffics to the 2M paths of each TU. For those actually allocated
TUs, test whether the traffic of each 2M path is normal. For those blank
board positions which are configured with TUs, insert TUs and D75/E75
from other board position, and proceed the test mentioned above.
2) The principle of test file is similar to the single station test file, section "1.
Create batch files for single station test" can be refered.
For OptiX2500+ subrack, all the data buses can be tested via inserting SQ1
in board position 1 and 14, and inserting SL4 or S16 in other position.
2-29
OptiX High-level Training Manual Part 2 Equipment Commissioning
Chapter 2 Single Station Commissioning of SDH
Equipment – General Items
4) If any problem appears during the test, you should do the test after the
problem is solved.
After the single station commissioning is performed in this station, the final
provisioning files of this station should be downloaded for a test:
After the final configurations are sent, the NE software databases should be
backed up. Backup can be implemented via NMS, or the following
commands:
:dbms-backup-all:fdb0;
2-30
OptiX High-level Training Manual Part 2 Equipment Commissioning
Chapter 2 Single Station Commissioning of SDH
Equipment – General Items
:dbms-backup-all:fdb1;
This test means that all NEs in the station should be able to log in to each
other when there are multiple NEs (such as a main subrack and several
extended subracks) in a station.
The conditions that the ECC between the main subrack and extended
subrack is blocked often appear since the optical fiber is connected
improperly or the settings are incorrect, which must be solved during single
station debugging, otherwise, it will waste time and energy when this station
is connected with.
1) This station is powered on after it is powered off for 10 minutes, all units
should be in normal service and no manual intervention is necessary.
5. Others
1) Make sure the ALC switch on SCC unit is upward before you leave this
station.
2) Before you leave this station, make sure the ring switch of order-wire
telephone is set to ON, in order to avoid that the telephone does not ring,
which results in the wrong judgment that a fault occurs to order-wire unit,
when there is an incoming order-wire call. Simultaneously, make sure the
talk key of order-wire telephone is shut down, so as to avoid that the order-
wrie telephone is always in off-hook status, resulting that the order-wire
calls of other stations can not get through.
2-31
OptiX High-level Training Manual Part 2 Equipment Commissioning
Chapter 2 Single Station Commissioning of SDH
Equipment – General Items
3) Please be cautious to remove all the self-looped optical fiber and the
software loopback settings in the system which might be left during the test.
2-32
OptiX High-level Training Manual Part 2 Equipment Commissioning
Chapter 2 Single Station Commissioning of SDH
Equipment – General Items
Preface.............................................................................................................................2-1
2.1.3 Resistance Measurement Between power cabling posts of Power Box at the
Top of Cabinet...........................................................................................................2-3
2.1.6 Finish the Engineering Technical Documents which Can Be Filled In at Single
Station Commissioning Stage...................................................................................2-5
2.1.7 Ensure all the power switches are off after the single station hardware
examination is finished..............................................................................................2-6
2.2.3 Availability Examination of Acousto-optic Test Switch at the Top of Cabinet. 2-7
2.2.4 Availability Examination of Alarm Sound Cutting Out Switch at the Top of
Cabinet......................................................................................................................2-7
2.3.3 When the Optical Aggregate Unit is Looped Back, its Alarm Indicator Should
be OFF....................................................................................................................2-10
2.3.4 Examine the State of PMU and Communication Via Serial Port...................2-10
2-33
OptiX High-level Training Manual Part 2 Equipment Commissioning
Chapter 2 Single Station Commissioning of SDH
Equipment – General Items
2.4.10 Test blank board positions, for NEs of head office or those with the possibility
of extension..........................................................................................................2-2-29
2-34