Professional Documents
Culture Documents
Project Risk Management A Combined Analytic Hierar
Project Risk Management A Combined Analytic Hierar
net/publication/40499015
CITATIONS READS
149 6,973
1 author:
SEE PROFILE
All content following this page was uploaded by Prasanta Kumar Dey on 16 May 2014.
2
1
c.
e
ag
e
et
ag
ck
3
ck
pa
e
pa
ag
k
ck
or
k
ssm ri ag e
or
pa
se a ck h
W
W
en sk es
as eed pa of t
k
or
n rk ny
Yes
W
wo o a
t?
D
Risk Assessment
• Identify Risks
No • Assess Risks
• Determine Consequence
scenarios
• Determine Control Measure
Implement
e Review the
th l
Is idua No
work package
s
re risk ble? plan
ra
le
to
Yes
duration and which activities are critical in lyzing project risk of petroleum pipelines gories: classical models (i.e. probability
determining that duration. Many authors [8]. analysis and Monte Carlo simulation), and
have presented the distribution of time Recently, a number of systematic mod- conceptual models (i.e. fuzzy-set analysis).
duration of activities as classical Beta distri- els have been proposed for use in the risk- They noted that probability models suffer
bution [10]. J. Berny, [1] proposed his own evaluation phase of the risk-management from two major limitations. Some models
distributions for practical simulations. P.K. process. R. Kangari and L.S. Riggs [13] require detailed quantitative information,
Dey used Monte Carlo simulation for ana- classified these methods into two cate- which is not normally available at the time
of planning, and the applicability of such
Table 1—Scale of Relative Importance for Pair-Wise Comparison models to real project risk analysis is limit-
ed, because agencies participating in the
Intensity Definition Explanation project have a problem with making pre-
cise decisions. The problems are ill
1 Equal importance Two activities contribute equally defined and vague, requiring subjective
to the object evaluations that classical models cannot
3 Moderate importance Slightly favors one over another handle.
5 Essential or strong importance Strongly favors one over another There is a need for a subjective
7 Demonstrated importance Dominance of the demonstrated approach to project risk assessment, with
importance in practice objectivity in the methodology. The ana-
9 Extreme importance Evidence favoring one over lytic hierarchy process (AHP) developed by
another of highest possible order T.L. Saaty [16] provides a flexible and easi-
of affirmation ly understood way of analyzing project
2, 4, 6, 8 Intermediate values When compromise is needed risks. It is a multi criteria decision-making
methodology that allows subjective as well
Source: T.L. Saaty, The Analytic Hierarchy Process [16]. as objective factors to be considered in
project risk analysis. The AHP allows the archy has been constructed, the decision- ed, the process moves on to the phase in
active participation of decision-makers in maker begins the prioritization procedure which relative weights are derived for the
reaching agreement and it gives managers to determine the relative importance of the various elements. The relative weights of
a rational basis on which to make decisions. elements in each level of the hierarchy. the elements of each level with respect to
Formulating the decision problem in The elements in each level are compared an element in the adjacent upper level are
the form of a hierarchical structure is the pair wise with respect to their importance computed as the components of the nor-
first step. In a typical hierarchy, the top in making the decision that is under con- malized eigenvector associated with the
level reflects the overall objective or focus sideration. The verbal scale used in an largest eigenvalue of their comparison
of the decision problem. The elements AHP enables the decision-maker to incor- matrix. The composite weights of the deci-
affecting the decision are represented in porate subjectivity, experience, and knowl- sion alternatives are then determined by
intermediate levels. The lowest level com- edge in an intuitive and natural way. After aggregating the weights through the hierar-
prises the decision options. Once the hier- the comparison matrices have been creat- chy. This is accomplished by following a
path from the top of the hierarchy to each
Table 3—Likelihood of Risk in a Project alternative at the lowest level, and multi-
plying the weights along each segment of
Factors Likelihood Sub-factors Likelihood the path. The outcome of this aggregation
LP GP is a normalized vector of the overall
Technical Risk 0.479 Scope change 0.36 0.172 weights of the options. The mathematical
Technology selection 0.124 0.059 basis for determining the weights has been
Implementation methodology 0.13 0.062 established by T.L. Saaty [16].
Equipment risk 0.073 0.035 Conventionally, risk analysis is per-
Materials risk 0.08 0.038 formed at the overall project level. The risk
Engineering and design change 0.233 0.112 analysis should show the effects of the risk
factors on the project performance in terms
Financial 0.228 Inflation risk 0.152 0.035 of time, cost, and quality goals. Although
& Economical Fund risk 0.383 0.087 risk analysis at the project level may be suf-
Risk Changes in local law 0.105 0.024 ficient for a small project from the invest-
Changes in Govt. policy 0.105 0.024 ment-decision and feasibility-study point of
Improper estimate 0.255 0.058 view, the technique has its limitations for
large projects.
Organizational 0.146 Capability of owner’s project 0.106 0.015 D.F. Cooper [4] suggested that, in the
Risk group risk-engineering approach, systematic risk
Contractor’s capability 0.283 0.041 evaluation could be performed by subdi-
Vendor’s Capability 0.448 0.065 viding a project into its major elements,
Consultant’s Capability 0.163 0.024 and analyzing the risk and uncertainty asso-
ciated with each in detail. Moreover, the
Acts of God 0.064 Calamity Normal 0.44 0.028 severity of risk pertaining to a project varies
Calamity abnormal 0.56 0.036 from activity to activity. Some activities are
Clearance risk 0.083 Environmental clearance 0.026 0.022 more responsive to a specific risk than oth-
Land acquisition 0.461 0.038 ers. To risk analyze a project, the level of
Explosive clearance 0.133 0.011 activity for which risks are to be analyzed
Other clearances 0.142 0.012 has to first be determined.
M.A. Mustafa and J.F. Al-Bahar [14]
LP—Local percentage applied the AHP in risk analysis for the
GP—Global percentage assessment of risk in a construction project
16 Cost Engineering Vol. 44/No. 3 MARCH 2002
Table 3—Likelihood of Risk in a Project (continued)
LP GP LP GP LP GP LP GP
Scope change 0.17 0.029 0.39 0.067 0.31 0.053 0.13 0.022
technology selection 0.29 0.017 0.23 0.014 0.11 0.007 0.37 0.022
implementation methodology 0.47 0.029 0.26 0.016 0.17 0.011 0.1 0.006
equipment risk 0.33 0.012 0.21 0.007 0.28 0.010 0.18 0.006
materials 0.17 0.007 0.35 0.013 0.26 0.010 0.22 0.008
eng.. and design change 0.37 0.041 0.33 0.037 0.13 0.015 0.17 0.019
Capability of owner’s project 0.33 0.005 0.3 0.005 0.27 0.004 0.1 0.002
group Contractors capability 0.37 0.015 0.33 0.014 0.22 0.009 0.08 0.003
Vendors Capability 0.21 0.014 0.29 0.019 0.4 0.026 0.1 0.007
Consultant Capability 0.49 0.012 0.13 0.003 0.15 0.004 0.23 0.005
Calamity Normal 0.41 0.012 0.35 0.010 0.14 0.004 0.1 0.003
Calamity abnormal 0.32 0.011 0.47 0.017 0.09 0.003 0.12 0.004
Rank 2 1 3 4
from the evaluation perspective. P.K. Dey, multiple-stage decisions. These are a series • Identifying the work packages for risk
[5] applied AHP for cost risk analysis of a of decisions over time[9]. analysis.
construction project A decision tree approach does the fol- • Identifying the factors that affect the
This article adopts AHP for analyzing lowing. time, cost, and quality achievement of
risk in the project and uses decision tree a specific work package.
analysis (DTA) for selecting specific risk • It logically structures risk management • Analyzing the effect by deriving the
responses for specific work packages from philosophy by identifying alternative likelihood of the occurrences in an
various alternatives. responses in mitigating risk. AHP framework.
Decision trees use calculations of • It provides a basis for quantitative risk • Determining severity of failure by
expected monetary value (EMV) to meas- management. guess estimation.
ure the attractiveness of alternatives. They • It incorporates management percep- • Driving various alternative responses
also use graphical models to display several tions. for mitigating the effect of risk factors.
relevant aspects of a decision situation. • Estimating cost for each alternative.
These graphical models consist of treelike • Determining the probability and sever-
structures (hence the name) with branches Methodology ity of failure of a specific work package
to represent the possible action-event com- The methodology adopted for risk after a specific response.
binations. The conditional payoff is written management in this article is explained in • Forming a decision tree.
at the end of each branch. A tree gives the following steps. • Deriving expected monetary value
much the same information as a matrix, EMV or the cost of risk response in
but, in addition, it can be used to depict this case.
Cost Engineering Vol. 44/No. 3 MARCH 2002 17
Table 4—Risk Mapping in Project Level
Probability
• Selecting the best option through sta- India. The pipeline has a length of 1300 stations, four delivery stations, and two ter-
tistical analysis. km. Its diameter is 22 inches for a length of minal stations. The project cost was esti-
1112 km, 18-inches for a length of 218 km, mated as 600 million in US dollars. A
and 10.75 inches for a length of 123-km (a detailed description of the project is avail-
branch line). The pipeline is designed for 5 able in Dey’s Planning for Project Control
Application million metric tons per annum (MMTPA) Through Risk Analysis, A Case of a
The above steps will be explained throughput. The project also consists of the Petroleum Pipeline Laying Project [5].
through the case of a cross-country petrole- construction of three pump stations, one Figure 3 shows a flow chart for risk
um pipeline project in the western part of pumping-cum-delivery station, two scraper management. A risk management group
was formed to do a risk analysis study for
Table 5—Probability and Severity of Risk Factors the project in this article. The group con-
sisted of one member each from mechani-
Risk Factors Probability Severity cal, electrical, civil, tele-communication,
instrumentation, finance, and materials of
Time Cost project function. They were entrusted with
over-run Over-run collecting data, analyzing, interpreting and
(in months) (in Millions) preparing recommendations with active
US $) interactions with the project groups.
Scope change 0.172 8 90
Engineering and design change 0.112 5 30 Identification of Work Packages
Technology selection 0.059 6 20 The total project scope was decom-
Land acquisition 0.038 4 0 posed and classified to form a work break
Contractors capability 0.041 6 30 down structure (see figure 4). The first level
is project, the second and third levels are
Vendors Capability 0.065 8 30
work packages, and the forth level is activi-
Calamity abnormal 0.036 12 90 ties of each work package. Based on the
Implementation methodology 0.062 3 0 importance of achieving time targets, the
Fund availability 0.087 2 0 following work packages were considered
for risk management.
Improper estimate 0.058 2 0
Materials risk 0.038 3 0 • river crossing;
18 Cost Engineering Vol. 44/No. 3 MARCH 2002
Table 6—The Cost Data (Million US $) for Each Package Against Various Responses
Responses Pipeline River Station Telecommun- Building
laying crossing Construction ication & CP & colony
construction
Carrying out detailed survey with the objective 12 6 6 3 3
of minimum scope and design change
Selecting technology and implementation 3 6 4 1.5 1.5
methodology on the basis of owner’s /
consultant’s expertise, availability of
contractors and vendors and lifecycle costing
Executing design and detailed engineering on 1 1 1 1 1
the basis of selected technology and
implementation methodology and detailed
survey
Selecting superior contractors, consultants and 22 16 10 2 2
vendors on the basis past performance
Scheduling project by accommodating 6 - 4 - -
seasonal calamities
Planning contingencies and acquiring 11 2 6 1 1
insurance
Ensuring the availability of all statutory 1 1 1 1 1
clearance before design and detailed
engineering
Total 56 32 32 10 10
Grand total 140
ing packages, as improper selection could political risk (F&ER) and organizational improper estimates because there are more
cause major time and cost overruns. The risk. Among F&ER, fund flow problems uncertainties in the design and implemen-
unavailability of pipe materials and delayed and improper estimates are the major caus- tation methodology selection. Although
delivery of pumping unit sometimes results es of concerns. All the packages are equal- the organizational risk is less vulnerable for
in a considerable time overrun. ly vulnerable from fund flow problems. the project under study, consultant and
Other major risk categories for project However, the river crossing and pipeline contractor’s capabilities are of concern to
achievement are financial, economic, and laying packages are prone to problems from the management of the project. The river
crossing work package is the most suscepti-
Table 11—The Decisions Emerge From the Decision Tree Approach of Risk ble to problems from the performance of
Management for Each Work Package consultants and contractors. The capabili-
ty of the owner’s project group is required
Work package Risk response for achievement of all the work packages.
Although the project under study is
pipeline laying Carrying out detailed survey not that vulnerable from statutory clear-
ance risk, care should be taken in getting
pipeline laying across river Taking all responses as indicated in table environmental clearance and explosive
station construction Engaging expert project team clearance on time for a trouble free imple-
mentation.
telecommunication and SCADA system Do nothing Normal and abnormal calamities are
the part and parcel of any pipeline project.
Total cost for risk responses is 65.65 million US$ which is much lower than 140 mil- Many times project executives rate these as
lion US$. unimportant and not likely to occur.
Cost Engineering Vol. 44/No. 3 MARCH 2002 21
Figure 4—Work Breakdown Structure of “Cross-country Petroleum Pipeline” project
However, these factors are vulnerable for calamity and land acquisition. The river Risk Mapping
all work packages and appropriate contin- crossing work package with a probability of All the factors were organized as per
gency plans are strongly recommended for failure of 0.286 comes next. The main con- their probability and severity (effect on
each package. tributing factors are scope changes, imple- time and cost) characteristics as indicated
The pipeline laying work package is mentation methodology selection, engi- in table 4. The factor scope change has
the most risky package with a probability of neering and design change, and improper been identified as the most vulnerable for
failure of 0.317. The major factors for pos- estimates. The station construction work the project under study as it has a high
sible failure are changes in scope, changes package is vulnerable from scope changes probability of occurrence, as well as high
in engineering and design, fund availabili- and has a 23 percent probability of failure. severity. If there is a change in scope of any
ty, vendors capability, abnormal natural of the work packages, there will be consid-
∫ Χ r f(x)dx
Time Cost
Do nothing
Failure (Months) (Million US $) µ’r = Ε(Χ r) = −∝
P = 0.286 15 40
No failure if X is continuous (equation 2)
Detailed survey 0 0
and superior P = 0.714
Failure 15 40 The first moment about zero is the
technology
P = 0.143
mean or expected value of the random vari-
-12 No failure able and is denoted by µ; thus µ’1 = µ =
0 0 E(X).
P = 0.857
Failure
Expert project team Again, the rth central moment of X or
8 20
P = 0.246 the rth moment about the mean of X is
No failure defined by
-16
0 0
All response
P = 0.714
Failure µr = Ε(Χ − µ )r= Σ (x-µ )r p(x)
2 8 x
P = 0.05 if X is discrete, (equation 3)
No failure or +∝
-32
∫(x-µ )r f(x)dx
0 0
µr = Ε(Χ − µ )r = −∝
P = 0.95
Figure 7—Decision Tree for River Crossing Work Package if X is continuous (equation 4)
Cost Engineering Vol. 44/No. 3 MARCH 2002 23
The expected cost overrun = 26.44
Time Cost million in US dollars,
Failure (Months) (Million US $) The standard deviation = 34.72 mil-
Do nothing 12 24 lion in US dollars.
P = 0.229
No failure The approved cost was 600 million in
Detailed survey 0 0 US dollars.
P = 0.771
and superior Failure 6 12 No management can be satisfied with
technology
P = 0.115 a 50 percent chance of achievement. A
-9 No failure more realistic time target was derived with
0 0
P = 0.885 the application of a statistical model as
Failure shown by K.T. Yeo [20]. Accordingly, an
Expert project team
2 4 increase in duration of the project with
P = 0.229 respect to initial planning was determined
No failure
-12 with the application of following mathe-
0 0
P = 0.771 matical relationships:
All response
[Χt - µ] / σ=Ζ
Failure
2 4
P = 0.05
No failure
-32 (equation 5)
0 0
P = 0.95
Xt = increase in duration of time of
Figure 8—Decision Tree for Station Construction Work Package project/ work package
µ = Expected increase in project dura-
The second central moment, Therefore, using the data from Table 4 tion, 4.88 months
and equation 1 and 3, the following statisti- σ = Standard deviation of duration dis-
•
ability of contractors and vendors and
lifecycle costing.
Execute design and detailed engineer-
ing on the basis of selected technology
and implementation methodology and
T agement model with the applica-
tion of risk management princi-
ples. A decision support system
(DSS) has been developed in an analytic
hierarchy process (AHP) and decision tree
approach. It combines identification
of risk factors, analyzes their effects,
allows responses through desired
actions and controls these responses in
an interactive way by involving all
a detailed survey. analysis (DTA) framework. This helps the project stakeholders. Using sensitivity
• Select superior contractors, consult- management of projects and helps in mak- analysis at each step provides manage-
ants and vendors on the basis of past ing objective decisions. The DSS identifies ment with an ongoing bases for deci-
performance. risk factors that are inherent in the project, sions.
• Schedule project by accommodating analyzes their effect on various activities,
seasonal calamities. and derives responses in line with project General benefits can be achieved from
• Plan contingencies and acquire insur- objectives, the organization’s policy, and the application of risk management in any
ance. business opportunities. type of project, including the following
• Ensure the availability of all statutory Risk is by nature subjective. However, benefits.
clearances before doing design and AHP allows one to objectively analyze the
detailed engineering work. effect of risk on a project by determining • The issue/problems are clarified and
the probability of its occurrences. The allowed for from the start of the proj-
Table 6 shows the estimated cost of the probability and severity of each risk factor ect.
above risk responses for each work package. are determined through the active involve- • Decisions are supported by thorough
Sources for the cost data are the detailed ment of field experienced persons in an analysis of available data.
feasibility report and cost estimate for the interactive environment. The information • The structure and definition of the
project along with looking at other recently is collected in a very structured format in project are continually and objectively
completed projects and quotations from line with AHP requirements and processed monitored.
vendors and contractors. using available computer programs. • Contingency planning allows prompt,
The next step is to form a decision tree Additionally, sensitivity utility of AHP pro- controlled, and pre-evaluated respons-
for each work package considering the vides an opportunity to the risk manage- es to risk issues that materialize.
probability and severity of failure and vari- ment group to observe the nature of model • There are clearer definitions of the
ous possible responses. outcomes in different alternative decision specific risk associated with a project.
The group arrived at the following situations. DTA helps in selecting from • It builds-up of a statistical profile of the
decision alternatives. among various decision alternatives. Risk historical risk and this allows better
management using a combined AHP and modeling for future projects.
• do nothing; DTA approach provides the following ben- • It encourages problem solving and
• carrying out detailed survey (or addi- efits. provides innovative solutions to the
tional survey work); risk problems within a project.
• using superior technology; • Although most of the risk analysis • It provides a basis for project organiza-
• engaging an expert project team; and methodologies quantify risk by deter- tional structure and appropriate
• taking all responses as indicated in the mining probability and severity of risk responsibility matrix.
tables included with this article. factors, they do not identify responses
objectively. However, the combined Specific benefits, achieved by applying
Figures 6, 7, 8, and 9 show the deci- AHP and DTA approach not only risk management techniques in managing
sion trees for the work packages (pipeline determines probability and severity of the study project, include the following.
laying, pipe laying across river, station con- risk factors, but also identifies risk
struction, and telecommunication and responses for each work package using • Problems encountered while execut-
cathodic protection) of the project under an expected monetary value concept. ing a project were identified during
study. The probability and severity (time This approach is especially required the planning phase. This helped in
and cost) for each decision alternative are for large-scale projects because there making suitable responses for effective
derived from the risk analysis study of each are many outcome uncertainties. project management. Responses
package and the expert opinions gained • It provides an objective basis to man- included alternative design and engi-
through brainstorming. agement for additional investment in neering, engaging superior consult-
The expected money values (EMV) planning or for engaging superior con- ants, contractors and vendors.
are then calculated for each alternative sultants, contractors, and suppliers for • Critical activities were identified and
decision for all the packages. Tables 7-10 specific work packages or items. appropriate responsibilities were pre-
show the calculations of decision tree • It defines the roles of project stake- pared for managing these critical activ-
approach of risk management. Table 11 holders in responding to specific risk ities.
shows the decisions emerge from the deci- factors and it provides a basis of control • Use of a risk management methodolo-
sion tree approach of risk management. to the owner or management. gy helped complete the project with-
• It develops an algorithm to model a out any time or cost overruns.
computerized decision support system