You are on page 1of 13

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/275999294

Consistent Application of Risk Management for Selection of


Engineering Design Options in Mega-Projects

Article in International Journal of Risk and Contingency Management · October 2014


DOI: 10.4018/ijrcm.2012100104

CITATIONS READS

5 92,323

1 author:

Yuri Raydugin
Royal Statistical Society
36 PUBLICATIONS 67 CITATIONS

SEE PROFILE

All content following this page was uploaded by Yuri Raydugin on 05 December 2018.

The user has requested enhancement of the downloaded file.


44 International Journal of Risk and Contingency Management, 1(4), 44-55, October-December 2012

Consistent Application of Risk


Management for Selection
of Engineering Design
Options in Mega-Projects
Yuri Raydugin, Risk Services & Solutions Inc., Calgary, AB, Canada

ABSTRACT
Traditional application of project risk management is limited to identifying and addressing project risks and
then developing cost along with schedule contingencies. This paper proposes a method to consistently utilize
the project risk management methods during Front End Engineering Design (FEED) phase of project develop-
ment to select engineering design options. This method was called for recently to make several key engineer-
ing design decisions in a mega-project (case study). It allows significantly accelerate decision making and
successfully manage various types of bias through leveraging the structure and visualization it provides. The
proposed method is also applicable for engineering change management in any phase including operations.

Keywords: Capital Expenditure (Capex), Decision Tree, Front End Engineering Design (FEED),
Operational Expenditure (Opex), Present Value (PV), Risk Assessment Matrix (RAM), Risk
Ranking Score

INTRODUCTION features of options are compared, with the other


project objectives and option’s risks being left
Traditionally project risk management is con- out. As a result, it is not unusual that a most
sidered one of project services functions. Its attractive option performance-wise or cost-wise
primary focus is to identify and address project could be a source of unacceptable schedule,
risks of various categories. Its secondary goal is safety, environmental or credibility risks.
to come up with adequate project cost and sched- It is widely recognized that project objec-
ule contingencies (Chapman & Ward, 2003; tives are inter-dependent and “compete” with
Wideman, 1992; ISO, 2009; Raydugin, 2012). each other imposing constraints on project
Role of project risk management in engineering delivery (Chapman & Ward, 2003). Same time,
design option selection is rather overlooked. It notions such as “a cost-driven” or “a schedule-
is not unusual that only performance and cost driven” project are used by practitioners in an
attempt to implicitly introduce a hierarchy of
objectives. A robust trade-off between project
DOI: 10.4018/ijrcm.2012100104 objectives should be explored instead. Other-

Copyright © 2012, IGI Global. Copying or distributing in print or electronic forms without written permission of IGI Global is prohibited.
International Journal of Risk and Contingency Management, 1(4), 44-55, October-December 2012 45

wise, a situation could emerge when a project is that various types of psychological bias
was delivered, to say, on cost (and/ or on scope, normally represented in the option selection
and/ or on schedule, etc.) but resulted in multiple process are effectively addressed and managed
fatalities (and/ or dramatic impact on environ- owing to structure and visualization it brings up.
ment, and/ or ruined company’s reputation, etc.). In addition, the approach described in this
Following this logic, a “project objective’s paper can be used as part of engineering change
mix” could be introduced meaning that any management including Operations. Needles to
change in (or deviation from) one objective say, this method could be used at higher level
gives rise to changes in (or deviation from) the for conceptual design option selection.
rest of objectives. (Similar idea is widely used
in marketing as “4P marketing mix” where 4P
stands for Product, Price, Promotion and Place- LITERATURE REVIEW
ment (Wilson & Gilligan, 1997). A change in
Decision tree analysis in its various forms has
one of these components requires adjustments
been used in several disciplines. General over-
of the others to keep marketing program suc-
view of probabilistic decision tree analysis in
cessful.) Project objectives and deviations from
project risk management is done by Schuyler
them for each reviewed engineering design
(2010).
option should not be considered independently
Portfolio selection and evaluation of com-
from each other.
plex publicly sensitive nuclear project proposal
Multiple engineering design decisions
is described by Strung (2011) considering scope,
are done in FEED phase of a project develop-
budget and schedule of the proposals. A pipeline
ment which defines associated project risks in
project represented as few main work packages
Execute and Operate. They (along with project
is analyzed using probabilistic decision tree by
execution) eventually shape final project scope/
Dey (2002) to select an alternative that is most
quality, cost, duration, etc. Hence, this points
attractive economically. A general decision-
to important role of project risk management
making framework is formulated using decision
in engineering design decisions. Namely, the
trees to identify expected monetary values of
risk-based engineering design option selec-
project alternatives (Dey & Mukherjee, 2005).
tion is a control to assure that all stated project
Another example of probabilistic decision tree
objectives are reached, or almost reached with
application is done for analysis of technical risk
minimal and acceptable deviations.
responses by Kujawaski (2002). Risk response
The author led several risk-based engi-
actions were developed using Monte Carlo
neering design studies of a mega-project of the
assessments.
energy industry. However, this method is not
Decision tree analysis and an economic
seemingly restricted by any type of industry
model are used to identify technical options
or project. At least, it should be applicable to
and their ranking for development of project
any capital project. The only condition is that
cost estimates of deepwater developments
methods and tools of a standard project Risk
(Collins, 2003). Engineering economic analysis
Management System should be fully developed
of project alternatives including decision trees
and implemented by a project team (Wideman,
is proposed by Eschenbach, Lewis, Heune,
1992; ISO, 2009).
Baker, and Hartman (2007) when considering
Besides quality of the risk-based engineer-
technical options.
ing design decisions, much shorter timelines
Several decision tree based methodolo-
of option selection should be pointed out. The
gies were developed to predict outcomes of
method allows structure and visualizes infor-
IT projects (Hu, Mo, Zhang, Zeng, Du, & Xie,
mation in a way that substantially accelerates
2012; Gemino, Saur & Reich, 2010), petroleum
decision making. Another benefit of this method

Copyright © 2012, IGI Global. Copying or distributing in print or electronic forms without written permission of IGI Global is prohibited.
46 International Journal of Risk and Contingency Management, 1(4), 44-55, October-December 2012

exploration initiatives (Siddiqui, Al-Yateem & “soft” project objectives in decision making is
Al-Thawadi (2007)), agricultural investments emphasized to assure project’s success.
(Zhu, 2008). Development of cleaning options
for contaminated sites (Sorvari & Seppala,
2010) and handling infrastructure hazards in a METHODS
small community using a value tree approach
Project and Option’s
(Li, Apostolakis, Gifun, VanSchalkwyk, Leite,
Objectives (Baselines)
& Barber, 2009) introduce additional variants
of decision tree analyses. This article was based on the approach to
In addition, several articles describe ap- treat project risks as deviations from project
plication of decision tree analyses in education objectives. Every engineering design option
(Strang, 2009), commercial bidding process selection should be conditionally considered
(Eldukair, 1995), handling contractor’s li- as a mini-project with its own objectives that
abilities (Jeljeli & Russel, 1995) and conflict are fully aligned with overall project objectives.
resolution during negotiations (Rodrigues, De Standard set of “hard” (easily quantifi-
Souza, & de Paula, 2008). Strictly speaking, able) objectives traditionally includes “project
these works are outside of project risk manage- triangle” of three constraints:
ment discipline although shed additional light
on decision tree analysis.
• Scope/Quality;
Most of the works cited are featured by
• Capital expenditure (CapEx);
using variants of probabilistic decision tree
• Schedule.
analyses when alternative branches of the deci-
sion trees are described by a certain probabilities
of occurrence. As a rule, monetary values of These objectives imply constraints on each
nodes are in focus of these analyses. Economic other to exclude dichotomies, as fast delivery
evaluations of project alternatives are done in of a good project cheaply is not quite possible.
some cases that again are described by monetary Besides these, some “soft” objectives are
values. Evaluations of monetary outcomes are widely used these days as follows:
traditionally done either using expected values
for branches (product of probability and cost) • Safety;
or, in more complicated cases, applying proba- • Environment;
bilistic (Monte Carlo) analyses. In some cases • Reputation.
non-probabilistic decision trees are considered
describing options by three traditional “hard” These “soft” objectives are normally treated
project goals, namely, scope/ quality, cost and as additional goal-zero types of constraints: no
schedule. fatalities and injuries, no negative impacts on
Taking consistently into account “soft” environment and reputation. However, positive
project objectives (safety, environmental, repu- impact on environment and reputation could be
tation, stakeholder’s management, etc.), when achieved as a result of project delivery.
selecting project alternatives or engineering In addition to the typical objectives put for-
design options seems rather challenging, has ward, one “hard” objective is often overlooked
yet to be done. Same time, it is paramount for as it is relevant to operations, not project deliv-
success of any project. ery. Project lifetime operational expenditures
This paper bridges the gap in consistent (OpEx) should be part of the picture. Normally,
consideration of all project objectives (both OpEx is considered in project economic mod-
“hard” and “soft”) when making project option els. It is required to compare CapEx and OpEx
selections. Equal importance of both “hard” and “apple-to-apple” when considering costs and
cost risk exposures during project delivery and

Copyright © 2012, IGI Global. Copying or distributing in print or electronic forms without written permission of IGI Global is prohibited.
International Journal of Risk and Contingency Management, 1(4), 44-55, October-December 2012 47

in Operations. Standard Present Value (PV) The “hard” objectives directly depend on
approach should be used to convert annual (scaled to) the scope of the option study,
lifetime OpEx budgets to base period’s money whereas “soft” baselines are rather independent
and directly compare resulting PV of OpEx of this. For instance, comparable impact on
with CapEx budget (Mills, Robertson, Print, & safety, environment and reputation could result
Rowbotham, 1999). A discounting factor equal from both small project and a mega- project.
to average company’s cost of capital (normally This approach elevates “soft” objectives (or
5 – 7%) should be used to get the PV of OpEx. deviations from them) and allows them to be-
As a result, for the purpose of this paper, cost come screening factors in option selection.
objective could be treated as a sum of CapEx The six objectives put forward could be
and PV of OpEx, where applicable. used as building blocks of project’s Risk As-
Hence, according to discussion, follow- sessment Matrix (RAM) introduced.
ing project objectives will be considered in
this paper: Option’s Differentiators and
Method’s Foundation
• Scope/Quality: Performance including
As mentioned, an option selection study should
reliability, availability, maintainability
be treated as a sub-project. Key approach to
(Ebeling, 2005);
outline its scope is to consider any factors that
• Cost: CapEx and PV of OpEx;
could differentiate one option from another.
• Schedule: Project duration/completion
(However, a situation could emerge when the
date;
same Critical or Serious risks pertain to all
• Safety;
options. This would require reviewing and
• Environment;
selecting better set of options or assure proper
• Reputation.
risk addressing.) If at least one cost element
or risk of any type pertains to at least one op-
It is not unusual that initial risk assessment tion, it should be kept in the study to become
points out serious or critical deviations from a differentiator.
objectives for some engineering design op- Scope/Quality of any option before con-
tions. (Definitions of Serious and Critical risks sidering risks should meet overall project per-
are given by Table 1) Additional engineering, formance objectives. For instance, any option
organizational, safety, etc. measures could be ap- should assure that required number of barrels
plied to address (i.e., avoid, mitigate or transfer) of oil per day is produced/ processed/ deliv-
corresponding risks in attempt to make them ered, etc. in a “risk free world” (baseline). So
Acceptable. Addressing could be done during it cannot be used as a differentiator. However,
project delivery and after - in operations. Cost deviation from this could occur due to option’s
of addressing of any risk should be included to risk exposure. Risks with impact on Scope/
either CapEx or OpEx, correspondingly.

Table 1. Risk categories

Risk Ranking Score Color Code Level of Risk Level of Severity


1-5 Green Low Acceptable
6 - 12 Yellow Medium Serious
15 - 25 Red High Critical

Copyright © 2012, IGI Global. Copying or distributing in print or electronic forms without written permission of IGI Global is prohibited.
48 International Journal of Risk and Contingency Management, 1(4), 44-55, October-December 2012

Quality could become differentiators. In some • Reputation risks (score);


cases, an option of interest would not meet • Cost of addressing: Δ CapEx or PV of Δ
the baseline Scope/Quality requirements. The OpEx to address risks ($).
Scope/Quality deficiency should be considered
a risk with 100% probability. This option still All differentiators are measured either
might become preferable in case the other directly in monetary values or indirectly by
options have even worse costs as well as risk scores. Using scoring method is an attempt
exposures. to simplify quantification of deviations from
All technologies considered in engineer- “hard” objectives (Schedule and Scope/ Qual-
ing design options should be commercial. ity) and introduce quantification of deviations
Risks associated with them are supposed to be from “soft” and intangible objectives (Safety,
known because of previous applications. This Environment and Reputation) following an
corresponds to at least one successful demo approach justified by Hubbard, 2010.
or pilot project. In case a technology is still in
R&D phase of development, unknown risks Option’s Baseline Cost
(“unknown unknowns”) could make application
of methodology described in this paper impos- As discussed, the risk-based option selection
sible (Raydugin, 2012). Unknown risks cannot method could be applicable to any type of capital
be integrated to the methodology presented in project. That is why we don’t put forward a
this paper. particular case study but describe the method
Similarly, any considered option should in general terms. For simplicity and demonstra-
comply with an approved project schedule in tion purposes, let’s consider two basic options
the “risk free world” as related to any relevant (e.g., two different sets of equipment). Let’s
activities in permitting, engineering, procure- also assume that each could have two different
ment, construction, commissioning, etc. If an maintenance programs in operations. According
option of interest has longer baseline duration to this, Figure 1 represents a decision tree that
than approved, the exceeding duration should be has four nodes.
treated as schedule risk with 100% probability. This type of decision tree differs from
This should become a differentiator along with probabilistic decision trees used in traditional
the other option’s schedule risks. risk analyses when probabilities are assigned
The goal-zero type “soft” objectives to each branch (Schuyler, 2001). Here each
(baselines) are supposed to be the same for any branch/ node represents an option. One of them
option. However, deviations from the “soft” should be selected.
objectives could tell various options apart being In reality, the decision tree could have mul-
differentiators in decision making. tiple branches reflecting variants of scope (and
According to discussion, following dif- CapEx) as well as operational budgets (OpEx).
ferentiators could be introduced: OpEx could also reflect not only expenditures
but lost revenue too due to break-down and
• Baseline costs: CapEx and PV of OpEx ($); maintenance down-times (Ebeling, 2005). In
• Scope/Quality risks (score); this case the down-times are considered as part
• Cost risks (score); of option’s OpEx baseline, not risks. In practice
• Schedule risks (score); 8 – 12 or more nodes could be introduced to
• Safety risks (score); cover all major viable options.
• Environmental risks (score);

Copyright © 2012, IGI Global. Copying or distributing in print or electronic forms without written permission of IGI Global is prohibited.
International Journal of Risk and Contingency Management, 1(4), 44-55, October-December 2012 49

Figure 1. Decision tree of four nodes

Being a decision visualization tool, the • Organizational context: Project team


decision tree contains information on option’s member’s responsibilities.
risk ranking scores along with cost information.
Standard Project Risk Management approach Typical risks management process is shown
is used to define the risk scores as described. by Figure 2. Only four steps of this process are
directly relevant to the subject of this study.
Namely,
DISCUSSION
Project Risk Management System 1. Identify risks;
2. Assess risks before addressing;
In order to support the method introduced in 3. Develop addressing actions;
this article a standard project Risk Management 4. Assess risks after addressing.
System should be in place. This includes fol-
lowing three key components: Step 3 includes estimating of addressing
costs.
• Process: Steps to treat risks; Ideally, risk inventory for each option
• Tools: Risk Assessment Matrix and Risk should be developed. Standard industry practice
Register; is to use three part naming for risks (cause –

Copyright © 2012, IGI Global. Copying or distributing in print or electronic forms without written permission of IGI Global is prohibited.
50 International Journal of Risk and Contingency Management, 1(4), 44-55, October-December 2012

Figure 2. Project risk management process

event – impacts on project objectives) to exclude ranges of impacts and five ranges of probabil-
ambiguity in their definitions (ISO, 2009). ities. More detailed definitions should be de-
veloped for ranges that are not measured as
Risk Register numbers. For example, it would be worthwhile
to know what “Massive Effect” on environment
A standard Risk Register template adopted by means for this particular project, etc. Each of
a project could be used for the option selection. the 25 cells of the RAM could be represented
The only difference is that each risk that was by a risk ranking score (product of impact and
selected as a differentiator should be listed probability scores). The risk ranking scores
several times. Figure 3 represents a sample could be grouped to three risk level/severity
template for a case when two risks (R1 and R2) categories (Table 1).
are considered differentiators for four nodes 1A, Different grouping of risks could be pos-
1B, 2A, and 2B. The template structure is based sible depending on risk policy of a project. As a
on application of the project Risk Assessment case in point, Acceptable category could include
Matrix described. scores 1 – 6, or number of groups/colors could
be four, etc. Similarly, different definitions of
Risk Assessment Matrix (RAM)
ranges/probabilities could be introduced or
and Option Selection Criterion
even different set of objectives may be used
Typical 5x5 Risk Assessment Matrix for a depending on size and nature of a project. (For
mega-project of $1B – $5B of CapEx is shown instance, Scope/Quality objective for a Carbon
by Figure 4. Capture & Storage (CCS) project could be
The six project objectives discussed are defined through quantification of CO2 capture
included to the RAM. Deviations from these efficiency, reservoir storage capacity, monitor-
objectives (baselines) are measured using five ing, measuring and verification, etc. in place

Copyright © 2012, IGI Global. Copying or distributing in print or electronic forms without written permission of IGI Global is prohibited.
International Journal of Risk and Contingency Management, 1(4), 44-55, October-December 2012 51

Figure 3. Sample risk register

Copyright © 2012, IGI Global. Copying or distributing in print or electronic forms without written permission of IGI Global is prohibited.
52 International Journal of Risk and Contingency Management, 1(4), 44-55, October-December 2012

Figure 4. Risk assessment matrix

of number of barrels of oil per day recovered/ top score of 10. As a result, the top score of 15
delivered/processed, etc.) Important is consis- is attached to the option 1A.
tency in applications of once accepted RAM. Acceptable level of severity (risk ranking
Key principle here is that risks of equal score 1 – 5) is used as a criterion for an option
ranking scores are treated as equals indepen- to be selectable. If any option’s ranking score
dently of their nature. For instance, a Critical including top score is equal to or higher than
risk of reputational damage (score 20), a Critical 6 (Serious or Critical), the option requires ad-
risk of overspending (score 20) or a Critical risk dressing to reduce corresponding risk ranking
of fatality or permanent disability (also score scores to Acceptable level. Selectable options
20) are considered equally unwelcome even in should be compared in terms of total costs as
case of so called “cost-driven” or “schedule- a next step.
driven” projects. In the example, all risk ranking scores
According to the Risk Management Pro- require addressing but one. Impact of risk R1
cess of Figure 2, the RAM should be used for on Schedule has Acceptable level even before
assessment of selected risks before addressing addressing (score equal to 3). Presumably,
first. Maximum risk ranking score for each after developing addressing plan and spending
option should be identified when considering amount of money “G” risk level of option 1A
impacts of all risks on all six project objectives. after addressing becomes Acceptable for all
For instance, let’s assume two risks identi- risks and impacts (top score equal to 5).
fied as differentiators for considering engineer- The decision tree of Figure 1 summarizes
ing design options: R1 and R2. Let’s also assume not only option’s cost information but also top
that one of the options (1A node of Figure 1) risk ranking scores for each node before and
has impact of risk R1 on Cost with score 9, after addressing. In the example of Figure 1,
on Schedule with score 3, on Reputation with options 1B and 2B should be screened out as
score 12 and Safety with score 15. And risk R2 their top risk scores are not acceptable even after
makes impact on Environment with score 8 and addressing. Final selection between options 1A
Scope/Quality with score 10. As a result, risk R1 and 2A depends on their total costs (CapEx, PV
produces the top score of 15 and risk R2 – the of OpEx and Costs of Addressing).

Copyright © 2012, IGI Global. Copying or distributing in print or electronic forms without written permission of IGI Global is prohibited.
International Journal of Risk and Contingency Management, 1(4), 44-55, October-December 2012 53

Organizational Context of all ranges could be used as one-point range’s


representatives.
In general organizational context of Risk Man- Safety objective and corresponding risks
agement describes responsibilities of project are trickiest in terms of consistent consideration
team members to support the Risk Management in the option selection studies. As a matter of
Process. It also outlines types and frequency of fact, H&S teams have their own corporate
risk review meetings. When option selection guidelines and manuals using very different
study is initiated, it is critical that project team safety risk assessment tools. Moreover, due to
members involved in engineering, estimating, zero-level Safety goals, level of tolerance is
planning as well as in safety, environmental, very low. Same time, to apply “apple-to-apple”
procurement, quality and risk management work comparison of risks, Safety objective should
closely together. They should be available to be part of the project RAM. As a result, we
take part in risk identification and assessment recommend using Very Low probability level
workshops. These workshops are usually held in the RAM of less than 0.1% (Figure 4). This
when CapEx and PV of OpEx information for corresponds to Acceptable risk ranking scores
each option is fully developed and available. 1 – 5 and symbolizes very low acceptable fre-
When initial results and conclusions are quency of Safety risk events.
developed, a broader group of stakeholders Different set of objectives could be in-
could be invited to validate all cost assumptions, cluded to a project RAM and different size of
risk assessments and conclusions. RAM (3x3, 4x4, 6x6, etc.) could be selected.
One of advantages of this approach is that Important is consistency of application of the
it brings up enough structure and visualization adopted RAM in all risk management activities
to suppress various types of psychological bias. including option selection studies. Same time
At least, sources of bias could be identified we believe that 5x5 RAM is optimal for these
and addressed. purposes. RAM’s smaller than 5x5 don’t provide
required level of detail to differentiate risks
and compare them before and after addressing.
CONCLUSION Whereas, RAM’s bigger than 5x5 put forward
too much detail.
In the method described in this paper, Accept-
Some risks could have quite high ranking
able risks (risk ranking scores 1 – 5) doesn’t
scores before addressing (e.g., node 2A of Fig-
require addressing. They have Low level of
ure 1). Same time if they are manageable, their
residual risks that could be simply neglected.
severity could be reduced to Acceptable level,
The risks with higher scores are screened out
assuming cost of addressing is not prohibitive
and don’t take part in the final round of option
(cost “I” for node 2A). Supposedly, it is not
selection. This simple approach allows avoid
always a case. Despite some nodes could have
estimating residual risks after addressing.
relatively low risk score initially (e.g., node 1B
All CapEx, OpEx, Δ CapEx and Δ OpEx
of Figure 1), level of their risk manageability
costs should be considered as ranges initially.
could be low. Practically this means that cost of
Even discounting factor used to obtain PV of
addressing could be uneconomical. Probably,
OpEx and Δ OpEx could be considered as a
it would be possible to reduce corresponding
range. Probabilities and cost impacts could
risks to Acceptable level for such options. But
be also assessed as ranges. This opens a door
prohibitively high cost of addressing should
to probabilistic cost risk analysis (Hubbard,
make those uncompetitive cost-wise.
2009). However, we believe that in majority of
The proposed method of engineering
cases this would be overshooting. Mid-points
design option selection provides high level of

Copyright © 2012, IGI Global. Copying or distributing in print or electronic forms without written permission of IGI Global is prohibited.
54 International Journal of Risk and Contingency Management, 1(4), 44-55, October-December 2012

visualization and allows identify and manage Hubbard, D. W. (2009). The failure of risk manage-
psychological bias of various origin and type. ment: Why it’s broken and how to fix it. New York,
NY: John Wiley & Sons.
It also allows substantially reduce time spent on
decision making. The method proposed could Hubbard, D. W. (2010). How to measure anything:
be also used in engineering change manage- Finding the values of ‘intangibles’ in business. New
ment to justify engineering design changes in York, NY: John Wiley & Sons.
all phases of project development as well as ISO. (2009). ISO 31000 International Standard: Risk
in Operations. management – Principles and guidelines. Geneva,
Switzerland: ISO.
Jeljeli, M. N., & Russel, J. S. (1995). Coping with
REFERENCES uncertainty in environmental construction: Decision-
analysis approach. Journal of Construction Engineer-
Chapman, C., & Ward, S. (2003). Project risk ing and Management, 121(4), 370–380. doi:10.1061/
management. Processes, techniques and insights. (ASCE)0733-9364(1995)121:4(370)
Chichester, UK: John Wiley & Sons.
Kujawaski, E. (2002). Selection of technical risk re-
Collins, I. (2003). Scale management and risk as- sponses for efficient contingencies. System Engineer-
sessment for deepwater developments. World Oil ing Journal, 5(3), 194–212. doi:10.1002/sys.10025
Journal, 224(5), 62–69.
Li, H., Apostolakis, G. E., Gifun, J., VanSchalkwyk,
Dey, P. K. (2002). Project risk management: A W., Leite, S., & Barber, D. (2009). Ranking the risks
combined analytical hierarchy process and deci- from multiple hazards in a small community. Risk
sion tree approach. Coastal Engineering Journal, Analysis Journal, 29(3), 438–456. doi:10.1111/
44(3), 13–26. j.1539-6924.2008.01164.x

Dey, P. K., & Mukherjee, S. K. (2005). Project risk Mills, A., Robertson, J., Print, C. F., & Rowbotham,
management in analytic framework. International. S. A. (1999). Fundamentals of managerial account-
Journal of Industrial Engineering: Theory Applica- ing and finance. UK: Mars Business.
tions and Practice, 12(4), 419–433.
Raydugin, Y. G. (2012). Quantifying unknown un-
Ebeling, C. (2005). An introduction to reliability knowns in an oil and gas capital project. International
and maintainability engineering. Long Grove, IL: Journal of Risk and Contingency Management, 1(2),
Waveland Press. 29–42. doi:10.4018/ijrcm.2012040103

Eldukair, Z. A. (1995). Computerized proto-type Rodrigues, S. A., De Souza, J. M., & De Paula,
model for evaluating the failure in bidding strategies. M. (2008). Negotiation supported through risk as-
In Proceedings of the 3rd International Symposium sessment. In Proceedings of the 10th International
on Uncertainty Modeling and Analysis and Annual Conference on Enterprise Information Systems (pp.
Conference of the North American Fuzzy Information 488-491).
Processing Society (pp. 772-776).
Schuyler, J. (2001). Risk and decision analysis in
Eschenbach, J., Lewis, N., Heune, M., Baker, E., projects. Newtown Square, PA: Project Manage-
& Hartman, J. C. (2007). Real optional and real ment Institute.
engineering projects. Engineering Management
Journal, 19(4), 11–19. Siddiqui, M., Al-Yateem, K., & Al-Thawadi, A.
(2007). A new tool to evaluate the feasibility of
Gemino, A., Saur, C., & Reich, B. H. (2010). Using petroleum exploration projects using a combination
classification trees to predict performance in Informa- of deterministic and probabilistic methods. In Pro-
tion technology project. Journal of Decision Systems, ceedings of the 15th Middle East Oil and Gas Show
19(2), 201–223. doi:10.3166/jds.19.201-223 and Conference (Vol. 3, pp. 1402-1409).

Hu, Y., Mo, X., & Zhang, X. (2012). Intelligent Sorvari, J., & Seppala, J. (2010). A decision sup-
analysis model for outsourced software project port tool to prioritize risk management options for
risk using constraint-based Bayesian Network. contaminated sites. Science of the Total Environ-
Journal of Software, 7(2), 440–449. doi:10.4304/ ment Journal, 408(8), 1786–1799. doi:10.1016/j.
jsw.7.2.440-449 scitotenv.2009.12.026

Copyright © 2012, IGI Global. Copying or distributing in print or electronic forms without written permission of IGI Global is prohibited.
International Journal of Risk and Contingency Management, 1(4), 44-55, October-December 2012 55

Strang, K. D. (2009). Using recursive regression to Wilson, R. M. S., & Gilligan, C. (1997). Strategic
explore nonlinear relations and interactions: A tutorial marketing management. Planning, implementation
applied to a multicultural education study. Practical and controls. Oxford, UK: Butterworth – Heinemann.
Assessment, Research & Evaluation, 14(3), 1–13.
Zhu, X. (2008). Method for risk analysis of agricul-
Strang, K. D. (2011). Portfolio selection methodology tural investment project and its applications. Chinese
for a nuclear project. Project Management Journal, Society of Agricultural Engineering Journal, 24(12),
42(2), 81–93. 297–301.
Wideman, R. M. (1992). Project & program risk
management: A guide to managing project risks &
opportunities. Newtown Square, PA: Project Man-
agement Institute.

Yuri Raydugin has been working on more than a dozen capital mega-projects related to Oil and
Gas Industry as either an employee of major Oil and Gas companies or independent consultant
of Risk Services & Solutions Inc. He has a PhD degree in Physics & Mathematics from Rus-
sia’s Academy of Sciences, an Engineering degree in Applied Physics from Ural’s Polytechnics
University (Russia), and an MBA degree from Henley Management College (UK). Dr. Raydugin
is a Practicing Engineer and a member of The Association of Professional Engineers and Geo-
scientists of Alberta (APEGA).

Copyright © 2012, IGI Global. Copying or distributing in print or electronic forms without written permission of IGI Global is prohibited.

View publication stats

You might also like