In control valve , Like

 Reply

 S san
 2 days ago

Hi,

 What is input and output of PLC & DCS Systems?


 All DCS has 2 types of inputs AI (Analogue Input), DI (Digital Input) and 2 types of
outputs AO (Analogue Output), DO (Digital Output).
 All the inputs and outputs may a contact signal or mA or mV
 .

 What are the Types of fault of control valve and


petitioners?
 1) Actuator loses air supply or diaphragm leaks
 2) Positioner loses control signal input
 3) Positioner mechanical feedback is damaged or disconnected
 4) Air supply does not meet instrument air requirements, dirt and moisture
accumulate and cause positioner shuttle valve to stick
 5) Stiction – valve internals are sticky, stem does not move smoothly through its
range
 6) Poor positioner tuning creates overshoot
 7) Mechanical backlash creates deadband that causes poor control action .

 What is commissioning & pre commissioning


 john
 3 days ago

Commissioning is the process of assuring that all systems and


components of a building or industrial plant are designed, installed, tested, operated,
and maintained according to the operational requirements of the owner or final
client. A commissioning process may be applied not only to new projects but also to
existing units and systems subject to expansion, renovation or revamping.

In practice, the commissioning process comprises the integrated application of a set of


engineering techniques and procedure to check, inspect and test every operational
component of the project, from individual function, such as instrument and equipment, up
to complex amalgamations such as modules, subsystems and systems.

Commissioning activities, in the broader sense, are applicable to all phases of the project,
from the basic and detailed design, procurement, construction and assembly, until the final
handover of the unit to the owner, including sometimes an assisted operation phase.

 Like
 Reply

 Vignesh
 3 days ago

Commissioning is the start up of the equipment for the first time. It is


when you run the equipment and carry out tests to verify it is running as intended i.e.
to design specifications. Commissioning tests are normally run against a design data
baseline. Commissioning also includes things like checking oil levels, fluid levels,
temperatures, pressures and for general issues that are contradictory to the
intended correct operation of the equipment.

 .