PROJECT IMPLEMENTATION: COMMISSIONING AND START-UP
Commissioning (sometimes called systems completion) is the final step in preparing to start up a facility. It's generally carried out on a system-by-system basis and in a certain order. For example, much of the work done during commissioning requires electrical power. The power system is, therefore, one of the first systems to be commissioned, so that power is readily available on the site. Recall that the prerequisite for starting the commissio
PROJECT IMPLEMENTATION: COMMISSIONING AND START-UP
Commissioning (sometimes called systems completion) is the final step in preparing to start up a facility. It's generally carried out on a system-by-system basis and in a certain order. For example, much of the work done during commissioning requires electrical power. The power system is, therefore, one of the first systems to be commissioned, so that power is readily available on the site. Recall that the prerequisite for starting the commissio
PROJECT IMPLEMENTATION: COMMISSIONING AND START-UP
Commissioning (sometimes called systems completion) is the final step in preparing to start up a facility. It's generally carried out on a system-by-system basis and in a certain order. For example, much of the work done during commissioning requires electrical power. The power system is, therefore, one of the first systems to be commissioned, so that power is readily available on the site. Recall that the prerequisite for starting the commissio
PROJECT IMPLEMENTATION: COMMISSIONING AND START-UP
Commissioning (sometimes called systems completion) is the final
step in preparing to start up a facility. It's generally carried out on a system-by-system basis and in a certain order. For example, much of the work done during commissioning requires electrical power. The power system is, therefore, one of the first systems to be commissioned, so that power is readily available on the site. Recall that the prerequisite for starting the commissioning of the power system is that it be mechanically complete—that the proper certificates are signed or entered electronically into a mechanical completion and commissioning database. This means that the equipment is safely installed and tested, and that the wires are pulled into place and terminated at the proper contacts. The circuits are then loop-tested to verify correctness before the high voltage is turned on. Often, a joint group, consisting of construction, commissioning, and future operating personnel, walk the system, inspecting it, and recording a punchlist of items that must be corrected by construction workers. The commissioning team uses commissioning procedures (prepared earlier by them and the engineering team) to ensure a safe, systematic approach. Sometimes the commissioning team function tests subsystems according to the procedures before eventually operating the whole system. When the electrical system is running stably, it's formally handed over to the operating team that keeps it running and maintained. The project now has power to continue commissioning the rest of the systems. From a quality standpoint, commissioning is a significant step. It validates the design with tangible inspections and tests of the entire system under controlled operating conditions. It's the ultimate test that the design is correct. Minor deficiencies are corrected on the spot. Changes with overall systems’ impacts are engineered and implemented (on a crash basis) through the project's change management process. From an operations standpoint, commissioning allows for the gradual start-up and handover of the facility in a safe and controlled manner. Operations personnel are often assigned to the project team to fill positions on the commissioning team. The client's equipment operators are sometimes mobilized to run major equipment in order to benefit from the knowledge of project experts, at the same time testing their operating procedures before operations actually start. Once all the essential systems are commissioned, the start-up team comes on the scene. The core start-up team often consists of operations personnel who have been part of commissioning. The leadership of the start-up team may transition from the project team to the operating team, to avoid an abrupt hand-off. When the bugs have been eliminated from the systems and the acceptance criteria are met, control passes to the operating team. The project is essentially over, except for some closeout activities, like delivering documents to operations, and commercially closing out all the remaining contracts and purchase orders (as discussed under engineering and procurement)