Professional Documents
Culture Documents
Book Reference
Project Management: A managerial Approach
by
Jack R. Meredith, Samuel J. Mantel, JR
Project Management
Project
A single time activity undertaken to
achieve a specific objective in a
specific time period.
Project
Characteristics
• Purpose: A one time activity with a well-defined
set of desired end results
• Life cycle: Project has a life cycle. From a slow
beginning they progress to buildup of size, then
peak, begin a decline, and finally must be
terminated.
• Interdependencies: Projects often interact with
other projects being carried out simultaneously
by their parent organization;
Project
• Look at each job or task scientifically to determine the “one best way” to
perform the job.
• Hire the right workers for each job, and train them to work at maximum
efficiency.
• Monitor worker performance, and provide instruction and training when
needed.
• Divide the work between management and labor so that management can
plan and train, and workers can execute the task efficiently.
• Administrative Theory
General administrative theorists
-Henri Fayol (France)
Fourteen principles of management: fundamental and universal principles of
management practice
-Max Weber (Germany)
Bureaucracy: ideal type of organization characterized by division of labor, a
clearly defined hierarchy, detailed rules and regulations, and impersonal
relationship.
• Systems Approach
A system is an interrelated set of elements functioning as a whole. An
organization as a system is composed of four elements:
Inputs — material or human resources
Transformation processes — technological and managerial processes
Outputs — products or services
Feedback — reactions from the environment
• Contingency Approach
The contingency school of management can be summarized as an “it
all depends” approach. The appropriate management actions and
approaches depend on the situation. The contingency approach is
highly dependent on the experience and judgment of the manager in a
given organizational environment.
Chapter 2: Project Selection
Project selection is the process of evaluating individual projects,
and then choosing the best project/s to implement so that the
objectives of the parent organization will be achieved.
Project A Project B
Project costs Tk. Project costs Tk.
15,00,000 20,00,000
Net cash inflows per Net cash inflows per
year Tk. 5,00,000 year Tk. 5,50,000
Problem 2. An industry is considering investment in a project
which cost tk. 6,00,000. Cash inflows are as following. Calculate
payback period of the project.
Decision rule:
• If the result is a positive NPV, then the project is accepted.
• If the NPV is negative, the project is rejected.
Format to calculate NPV:
NPV XXX
Problem 1: Calculate the following two projects and suggest which
one should be selected assuming discount rate is 10%.
Project X Project Y
Initial Investment Tk. 40,000 Tk. 60,000
Estimated Life 5 Years 5 Years
Cash Inflows
Year 1 2 3 4 5
Project X 10,000 20,000 20,000 6,000 4,000
Project Y 40,000 20,000 10,000 6,000 4,000
Year 1 2 3 4 5
PV Factor 0.909 0.826 0.751 0.683 0.621
@ 10%
o Internal Rate of Return (IRR)
IRR is a method of calculating an investment’s rate of return. The
IRR represents the discount rate at which the NPV of an investment is
zero.
NPV zero indicates the rate where project’s cash flows are equal to
project’s costs.
Steps to calculate IRR
Step 1: Calculate two NPVs for the project at two different
discounting factors.
Step 2: Use the formula to find out the IRR
1 30,000
2 40,000
3 60,000
4 30,000
5 20,000
Year 1 2 3 4 5
PV factor 0.909 0.826 0.751 0.683 0.621
@ 10%
@12% 0.893 0.797 0.712 0.636 0.567
o Profitability Index (PI)
The PI measures the ratio between present value of future
cash inflows and the present value of cash outflows.
Decision Rule
If PI > 1 then accept the project
If PI < 1 then reject the project
Problem 1:
Suppose we have three projects involving discounted cash
outflow of Tk. 5,50,000, Tk. 75,000, and Tk. 3,15,000
respectively. Suppose further that the sum of the
discounted cash inflows for these projects are Tk. 6,50,000,
Tk. 95,000 and Tk. 3,25,000 respectively. Calculate the
profitability index for the three project.