Professional Documents
Culture Documents
This work is a dedication to Martin who spent even half of it’s life for nature
protection along Sava and Drava, August 2012
Seite 1
Assessment of the Restoration Potential in the MDD-TBR
Table of contents
Table of contents 2
Summary 6
1. Introduction 28
2. Assessment approach 30
2.1 Restoration principles 31
2.2 Base data assessment 33
2.2.1 Hydromorphology and floodplains 33
2.2.2 Landuse/ main habitats 36
2.2.3 Birds 37
2.3 Short review of existing restoration projects 37
2.4 Proposal of potential restoration areas and measures 38
2.5 Floodplain prioritisation for reconnection 42
3. Results 46
3.1 Hydromorphological reference conditions 46
3.2 Land use/ main habitats 64
3.3 Status of river banks/channels 66
3.3 Status of floodplains 75
3.4 Restoration potential 78
3.4.1 Banks/channel 78
3.4.2 Floodplains 100
6. References 166
Seite 2
Assessment of the Restoration Potential in the MDD-TBR
List of Acronyms
AT Austria
DCPO WWF Danube-Carpathian-Programme Office
DEM Digital Elevation Model
DRB Danube River Basin
EU European Union
FD Floods Directive
FFH-D Flora Fauna Habitat Directive (Natura2000 network)
GIS Geographical Information Systems
HR Croatia
HU Hungary
ICPDR International Commission for the Protection of the Danube
River
JDS 2 Joint Danube Survey 2, 2007
of the Danube River
NGO Non Governmental Organisation
rkm River Kilometer
RS Serbia
SI Slovenia
WFD EU Water Framework Directive
TBR MDD Transboundary UNESCO Biosphere Reserve “Mura-Drava-
Danube”
Seite 3
Assessment of the Restoration Potential in the MDD-TBR
Bank reinforcement All structures stabilising the river banks (see rip-
and/or bank rap) and preventing the lateral shift of the
revetment channel
Seite 4
Assessment of the Restoration Potential in the MDD-TBR
Seite 5
Assessment of the Restoration Potential in the MDD-TBR
Summary
Inventory
Seite 6
Assessment of the Restoration Potential in the MDD-TBR
Figure ES 1: Map overview of project area (886,400 ha), the TBR MDD
Seite 7
Assessment of the Restoration Potential in the MDD-TBR
Seite 8
Assessment of the Restoration Potential in the MDD-TBR
Seite 9
Assessment of the Restoration Potential in the MDD-TBR
Seite 10
Assessment of the Restoration Potential in the MDD-TBR
< 100% = very high (in the best case floodplains could expand
towards natural terraces or at least significantly decrease the length
of existing dikes)
Seite 11
Assessment of the Restoration Potential in the MDD-TBR
> 120% = moderate (not only the construction costs but also the land
purchase for the area covered directly by the dike is expensive)
1 = very high
2 = high
3 = moderate
From the scientific point of view two aspects were further tackled:
The amount of gravel gained by newly initiated steep banks and
lateral erosion reducing the bedload deficit in the main channel as
well as an estimation of new breeding sites of sand martin colonies
1
The Mura was subdivided in an upper anabranching and lower meandering part,
the Drava was subdivided in two stretches upstream the Mura confluence (partially
braiding river system) and two part downstream of Mura confluence (anabranching
an meandering). Finally the Danube was split into two parts, north of the Drava
confluence in a purly meandering river system and downstream in a system limited
by loess steep terrace on southern bank building a river system with truncated
mender and many side-arms.
Seite 12
Assessment of the Restoration Potential in the MDD-TBR
2. Results:
First of all the still remaining natural banks like high dynamic steep
and shallow banks (often with point bars) were identified.
Additionally a class called “other banks (mostly near-natural)”
characterise banks with low dynamics, intermediate slope which can
be found in-between of meanders, having not specific features of
steep or shallow banks or being partially protected by very old
overgrown bank reinforcement (Fig. ES 2).
Two classes were defined for the impacted banks (fully maintained
with rather new structures and old less maintained structures, e.g.
collapsed rip-rap or groynes). Two main groups of structures were
identified. First the river banks which are mostly fixed by rip-rap
(revetments) along the steep banks preventing any lateral shift of the
channel. Secondly groynes, reflectors, guiding walls and in particular
Seite 13
Assessment of the Restoration Potential in the MDD-TBR
Figure ES 2: Status of river banks (total length, percentage for both river
banks in km (not channel length in rkm; main and permanent side channels
were analysed for this study)
Seite 14
Assessment of the Restoration Potential in the MDD-TBR
Seite 15
Assessment of the Restoration Potential in the MDD-TBR
The Drava and a certain part of lower Mura provide some still intact
large steep bank sections. The Danube is mostly fixed, however due
to reduced maintenance within the last 20 years some free banks can
be found close to Kopacki Rit Nature Park, but in particular along the
natural steep banks (loess terrace) downstream of the Drava
confluence.
In total the area of open gravel and sand bars sums up to some
731 ha (calculated for app. mean water level), which seems at first
sight not very much. Considering a number of some 514 banks with
an average size of 1.4 ha (of course those banks differ in size from
Mura to Danube), a reasonable size e.g. for bar breeding birds or
sensitive pioneer species is given. Historical analysis indicates a loss
of at least 70% of this typical riparian habitat types.
For this study the navigation issue was not yet considered, as non-
structural measures are proposed for improving navigation
conditions in these unique river sections of the TBR MDD. Therefore
this study focuses on the protection of settlements, bridges and flood
dikes (where there is no chance to relocate them).
Seite 16
Assessment of the Restoration Potential in the MDD-TBR
Figure ES 4: Map of all proposed restoration measures for banks and side-
arms.
Seite 17
Assessment of the Restoration Potential in the MDD-TBR
Seite 18
Assessment of the Restoration Potential in the MDD-TBR
Seite 19
Assessment of the Restoration Potential in the MDD-TBR
Seite 20
Assessment of the Restoration Potential in the MDD-TBR
Seite 21
Assessment of the Restoration Potential in the MDD-TBR
For the areas with the highest prioritisation about 123,5 km of dikes
must be relocated or removed (app 13,7 km per project area).
Seite 22
Assessment of the Restoration Potential in the MDD-TBR
Seite 23
Assessment of the Restoration Potential in the MDD-TBR
Seite 24
Assessment of the Restoration Potential in the MDD-TBR
Seite 25
Assessment of the Restoration Potential in the MDD-TBR
4. Conclusions
The definition and total list of potential restoration sites will serve as
a strategic tool for the future planning, regarding the floodplain
extension the prioritization tries to focus on a sub-set of areas. The
long-time experience shows that the realisation of individual projects
strongly depend on various other factors and feasibility all along
financing and public acceptance or the support by local stakeholders.
Seite 26
Assessment of the Restoration Potential in the MDD-TBR
Seite 27
Assessment of the Restoration Potential in the MDD-TBR
1. Introduction
Seite 28
Assessment of the Restoration Potential in the MDD-TBR
Seite 29
Assessment of the Restoration Potential in the MDD-TBR
2. Assessment approach
Seite 30
Assessment of the Restoration Potential in the MDD-TBR
Seite 31
Assessment of the Restoration Potential in the MDD-TBR
Seite 32
Assessment of the Restoration Potential in the MDD-TBR
Floodplain delineation
Seite 33
Assessment of the Restoration Potential in the MDD-TBR
Seite 34
Assessment of the Restoration Potential in the MDD-TBR
Entry data:
Seite 35
Assessment of the Restoration Potential in the MDD-TBR
Working scale for the mapping was app. 1:10,000 – 1:25,000 (for
Danube for some remote areas 1: 50,000). In total about 17,000
habitat polygons were digitized in 14 summarizing classes allowing a
basic assessment. The mapping can of course not substitute national
mapping or even habitat mappings on ground vegetation data,
therefore the assessment of FFH annex habitats or even EUNIS
habitat classes is not possible (with the exception of some stretches
with higher resolution of the data)
Seite 36
Assessment of the Restoration Potential in the MDD-TBR
2.2.3 Birds
Data from 2005-2012 for Mura and Drava and from 2010-2012 also
for Danube gives a concise monitoring overview of breeding sites for
steep bank and gravel/sand bar breeders prepared by Darko Grlica
and Borut Stumberger underlining the hydromorphological
assessment.
In the year 2010 so called “river watch” maps were prepared showing
the distribution of important species during the past 10 years. For
this study only the breeding density per km of intact steep bank was
considered for basic estimations on how the population could
increase after successful restoration.
Seite 37
Assessment of the Restoration Potential in the MDD-TBR
Based on the analysis of the extensive background data and the list of
already existing projects new comprehensive list were elaborated.
New areas/stretches were added iteratively (see figure 2) and based
on criteria like the landuse and habitats inside and outside of the
flood dikes; the exclusion of existing settlements/infrastructure;
protection status (in particularly based on the zonation proposal for
the TBR MDD); the suitability for flood retention (size, shape and
position) and lateral channel shift development; as well as main river
section types (hydromorphological main units, which increase the
feasibility of certain measures to improve the sediment deficit, lateral
activity or oxbow management).
Seite 38
Assessment of the Restoration Potential in the MDD-TBR
Figure 2: Proposal of new potential restoration areas used as basis for this
study (from Schwarz 2010).
Seite 39
Assessment of the Restoration Potential in the MDD-TBR
Measures:
Bank removal:
Seite 40
Assessment of the Restoration Potential in the MDD-TBR
Seite 41
Assessment of the Restoration Potential in the MDD-TBR
Seite 42
Assessment of the Restoration Potential in the MDD-TBR
Seite 43
Assessment of the Restoration Potential in the MDD-TBR
< 100% = very high (in the best case floodplains could be expand
towards natural terraces or at least significantly decreasing length of
existing dikes)
> 120% = moderate (not only the construction costs but also the land
purchase for the area covered directly by the dike is expensive)
1 = very high
2 = high
3 = moderate
2
The Mura was subdivided in an upper anabranching and lower meandering part,
the Drava was subdivided in two stretches upstream the Mura confluence (partially
braiding river system) and two part downstream of Mura confluence (anabranching
an meandering). Finally the Danube was split into two parts, north of the Drava
confluence in a purly meandering river system and downstream in a system limited
by loess steep terrace on southern bank building a river system with truncated
mender and many side-arms.
Seite 44
Assessment of the Restoration Potential in the MDD-TBR
Seite 45
Assessment of the Restoration Potential in the MDD-TBR
3. Results
The first sub-chapter presents the hydromorphological reference
conditions as a basic tool for the understanding of the riparian
landscape and the main outline for large scale river restoration
projects. The next three chapters summarise the results for the
habitats/landuse, the status of river banks/channel as well as the
floodplains. The fifth and sixth sub-chapters highlight the restoration
potential for banks/channels and floodplains. In the final sub-chapter
75 potential restoration areas are proposed and visualized in detail
maps.
Seite 46
Assessment of the Restoration Potential in the MDD-TBR
some special places of main capitals, locally for ship mills or small
harbours.
Seite 47
Assessment of the Restoration Potential in the MDD-TBR
Seite 48
Assessment of the Restoration Potential in the MDD-TBR
Seite 49
Assessment of the Restoration Potential in the MDD-TBR
Figure 5:
“Upper
Drava” near
Prelog
Figure 4: Lower Mura (see map and image series on next page): The
strongly meandering lower Mura was characterised by permanent natural
meander cut offs and large floodplain forests.
Seite 50
Assessment of the Restoration Potential in the MDD-TBR
Figure 6:
Lower Drava
south of
Ormansag
plain
Seite 51
Assessment of the Restoration Potential in the MDD-TBR
Figure 7:
Meandering
Danube near
Batina
Seite 52
Assessment of the Restoration Potential in the MDD-TBR
Figure 8:
Danube
along the
steep bank
near Illok
Seite 53
Assessment of the Restoration Potential in the MDD-TBR
So called “River section types” explain main river reaches with similar
parameters regarding discharge, slope, fluvial morphological
indicators and features (e.g. plan form –if meandering or braided or
Number and size of bars and islands) and floodplain types. There are
necessary to estimate the deviation in the current state and to
formulate general restoration outlines for a certain river reach. The
following maps and tables summarise those river section types for all
rivers with focus und Mura and Drava rivers.
Seite 54
Assessment of the Restoration Potential in the MDD-TBR
Table 1: Description of River section types for Lower Mura and Drava
River-section-type Mura M-I rkm 85 (Mura near Transition type from a braided
Ljutomer) – rkm 45 towards a sinuous and meandering
(near Letenye) river type, moderate anabranching
with small side channels, medium-
large lowland river with gravel
River-section-type Drava D-II rkm 235 (Mura Transition type from D-I towards a
confluence, sinuous and meandering river type,
Örtilos/Legrad) – only partial anabranching, large
lowland river with gravel and coarse
rkm 185 (near
sand
Babocsa)
Seite 55
Assessment of the Restoration Potential in the MDD-TBR
Figure 10: Main river section Types for Danube (not translated from
Schwarz 2005) showing the two section types (up- and downstream from
Drava confluence). North of the Drava confluence a purly meandering river
system can be found. Downstream a system limited by loess steep terrace
on southern bank building a river system with truncated mender and
many side-arms can be described.
Seite 56
Assessment of the Restoration Potential in the MDD-TBR
Figure 11: Visualisation of River section type (example for lower Drava))
Seite 57
Assessment of the Restoration Potential in the MDD-TBR
(reference / (reference /
current situation) current situation)
Reach length in km 47 / 40 54 / 45
V (10%) / (0%)
Seite 58
Assessment of the Restoration Potential in the MDD-TBR
Seite 59
Assessment of the Restoration Potential in the MDD-TBR
The overall loss of the river length is for the Mura moderate with only
15% in comparison with the reference length. However, the
reduction of the lower meandering Drava is considerable and reaches
nearly 40%. The average channel width of the Mura was lowered by
about 30-40%. The upper Drava reach D-I lost about 40-80% of its
former average channel width and most of its width variability. But
also the anabranching D-II section lost about 35% and the lower
meandering reach about 30%. In the regulated sections, the lower
Drava lost more than 50%.
Seite 60
Assessment of the Restoration Potential in the MDD-TBR
Seite 61
Assessment of the Restoration Potential in the MDD-TBR
Seite 62
Assessment of the Restoration Potential in the MDD-TBR
Seite 63
Assessment of the Restoration Potential in the MDD-TBR
The data is rather homogenous across the entire area and highlights
the international importance of the TBR MDD:
Seite 64
Assessment of the Restoration Potential in the MDD-TBR
Seite 65
Assessment of the Restoration Potential in the MDD-TBR
Figure 16: Natural shallow bank (as gravel point bar) in a sinuous channel
reach. (© Darko Grlica)
Seite 66
Assessment of the Restoration Potential in the MDD-TBR
Figure 18: „Other banks“ as recorded for most of this category with
invariant slope, less erosion, but near-natural conditions. (© Darko Grlica)
Seite 67
Assessment of the Restoration Potential in the MDD-TBR
Seite 68
Assessment of the Restoration Potential in the MDD-TBR
Seite 69
Assessment of the Restoration Potential in the MDD-TBR
First of all the still remaining natural banks like high dynamic steep
and shallow banks (often with point bars, see figure 17) were
identified. Additionally a class called “other banks (mostly near-
natural)” characterise banks with low dynamics, intermediate slope
which can be found in-between of meanders, having not specific
features of steep or shallow banks or being partially protected by
very old overgrown bank reinforcement (Map 2).
Two classes were defined for the impacted banks (fully maintained
with rather new structures and old less maintained structures, e.g.
collapsed rip-rap or groynes). Two main groups of structures were
identified. First the river banks which are mostly fixed by rip-rap
(revetments) along the steep banks preventing any lateral shift of the
channel. Secondly groynes, reflectors, guiding walls and in particular
closures of side-arm can be seen as significant structures preventing
also lateral shift of the river system and concentration of the flow in
the main channel. For better calculation for the “length of modified
channel” and overview reasons only the length of banks were
calculated (considering groynes and channel closures as regulation).
Seite 70
Assessment of the Restoration Potential in the MDD-TBR
Seite 71
Assessment of the Restoration Potential in the MDD-TBR
The Drava and a certain part of lower Mura provide some still intact
large steep bank sections. The Danube is mostly fixed, however due
to reduced maintenance within the last 20 years some free banks can
be found close to Kopacki Rit Nature Park, but in particular along the
natural steep banks (loess terrace) downstream of the Drava
confluence.
In total the area of open gravel and sand bars sums up to some
731 ha (calculated for app. mean water level), which seems at first
sight not very much. Considering a number of some 514 banks with
an average size of 1.4 ha (of course those banks differ in size from
Mura to Danube), a reasonable size e.g. for bar breeding birds or
sensitive pioneer species is given. Historical analysis indicates a loss
of at least 70% of this typical riparian habitat types.
Seite 72
Assessment of the Restoration Potential in the MDD-TBR
Banks/channel AT HR HU RS SI
Highly dynamic - 81.3 15.2 1.8 3.8
banks (steep (7.5%) (3.5%) (1.2%) (1.1%)
banks with
erosion)
Shallow banks - 61.4 11.9 4.4 9
(associated with (5.6%) (2.8%) (3%) (2.7%)
point bars)
Major bank 33.1 424 179.9 54.3 235.8
revetments and (95.9%) (39%) (41.6%) (37.3%) (70.4%)
structures (rip-
rap, groynes, side-
arm closures)3
3
Groynes and side-arm closures measured as app. equivalent bank sections; in case
of rip-rap and groynes no extra count
Seite 73
Assessment of the Restoration Potential in the MDD-TBR
Banks/channel AT HR HU RS SI
Old structures - 64.9 54.7 14.2 20
(collapsed rip-rap (6%) (12.6%) (9.8%) (6%)
and groynes)
Other, nearly 1.4 455.5 170.8 71 66.2
natural banks (4.1%) (41.9%) (39.5%) (48.7%) (19.8%)
Total in km 34.5 1,087.1 432.5 145.7 334.8
Number of 1 239 165 25 3
4
groynes
Gravel and sand - 477 (65%) 155 65 34
bars in ha (21 %) (9 %) (5%)
Table 6: Status of river banks (total length, percentage for both river banks
in km (not channel length in rkm); (main and permanent side channels were
analysed for this study)
4
Only larger and good visible groynes (length was not surveyed in detail)
Seite 74
Assessment of the Restoration Potential in the MDD-TBR
Figure 24 and 25: The Kopački Rit area (during the August flood 2002) is
one of the last large near natural floodplain areas along the entire Danube
(© Mario Romulić).
Seite 75
Assessment of the Restoration Potential in the MDD-TBR
ha countries)
floodplain
Morphological 5,118 243,282 208,229 100,237 40,611 597,477
floodplain
Loss 65.7% 70.4% 82% 89.7% 74.1 77.8%
AT HR HU RS SI Total (all
countries)
Floodplain 604 40,940 29,139 15,930 4,427 91,040
remnants,
oxbows, forests,
grasslands
(Former
floodplain) in ha
Seite 76
Assessment of the Restoration Potential in the MDD-TBR
Seite 77
Assessment of the Restoration Potential in the MDD-TBR
3.4.1 Banks/channel
Seite 78
Assessment of the Restoration Potential in the MDD-TBR
Map 4: Map of all proposed restoration measures for banks and side-arms
Seite 79
Assessment of the Restoration Potential in the MDD-TBR
This investigations focus on the steep banks and those banks with a
high potential for lateral erosion and channel shift. For this study the
navigation issue was not yet considered, as non-structural measures
are proposed for improving navigation conditions in these unique
river sections of the TBR MDD. Therefore this study focuses on the
protection of settlements, bridges and flood dikes (where there is no
chance to relocate them).
Seite 80
Assessment of the Restoration Potential in the MDD-TBR
It should be pointed out that the 398,2 km for the minimum option
contain some banks along inner bend (point bars) and a majority of
invariant banks which could be both easily removed without danger
for flood protection or immediately channel shift. This is different for
the expected steep banks: In this minimum variant without floodplain
extension those banks will not endanger flood dikes or infrastructure
within the next 10-20 years, however for the long-time planning
adjacent land proposed in this study outside the flood dikes should
be keep clear from infrastructure and settlements. In worst case after
that initial erosion and channel shift it become necessary to
reconstruct some banks near infrastructure and flood dikes.
Seite 81
Assessment of the Restoration Potential in the MDD-TBR
erosion (also to cut former side channels behind existing natural bank
levees (coarser material walls)).
Feasible without
floodplain extension
Feasible only with
floodplain extension
Seite 82
Assessment of the Restoration Potential in the MDD-TBR
5
If the side-arm is located alongside the active floodplain margin in the former
floodpain the rkm indication is an approximation of a rectangular line to the river
axis
Seite 83
Assessment of the Restoration Potential in the MDD-TBR
Seite 84
Assessment of the Restoration Potential in the MDD-TBR
Seite 85
Assessment of the Restoration Potential in the MDD-TBR
Seite 86
Assessment of the Restoration Potential in the MDD-TBR
Seite 87
Assessment of the Restoration Potential in the MDD-TBR
Seite 88
Assessment of the Restoration Potential in the MDD-TBR
Seite 89
Assessment of the Restoration Potential in the MDD-TBR
Seite 90
Assessment of the Restoration Potential in the MDD-TBR
Seite 91
Assessment of the Restoration Potential in the MDD-TBR
Seite 92
Assessment of the Restoration Potential in the MDD-TBR
Seite 93
Assessment of the Restoration Potential in the MDD-TBR
Seite 94
Assessment of the Restoration Potential in the MDD-TBR
Seite 95
Assessment of the Restoration Potential in the MDD-TBR
Seite 96
Assessment of the Restoration Potential in the MDD-TBR
Seite 97
Assessment of the Restoration Potential in the MDD-TBR
Seite 98
Assessment of the Restoration Potential in the MDD-TBR
Seite 99
Assessment of the Restoration Potential in the MDD-TBR
3.4.2 Floodplains
AT HR HU RS SI Total (all
countries)
Maximum 2,009 37,875 109,823 58,852 16,888 225,447
floodplain
extension
(considering
tributary
confluences) in
ha
Seite 100
Assessment of the Restoration Potential in the MDD-TBR
Seite 101
Assessment of the Restoration Potential in the MDD-TBR
The table 16 on the next but one page shows the assessment matrix
allowing also the individual comparison of areas.
Seite 102
Assessment of the Restoration Potential in the MDD-TBR
Seite 103
Assessment of the Restoration Potential in the MDD-TBR
Table 16: Proposed restoration areas and prioritisation matrix for floodplain
extension (compare the chapter 2.5 for methodology and scoring and 3.5
and 3.6 for more area details):
Very High
High
Low
Seite 104
Assessment of the Restoration Potential in the MDD-TBR
Seite 105
Assessment of the Restoration Potential in the MDD-TBR
6
Only very small area (200 ha) south oft he main Gemenc area
Seite 106
Assessment of the Restoration Potential in the MDD-TBR
some smaller areas along impounded stretch of the Upper Drava. For
those areas the parameters “flood retention” and “dike relocation”
was omitted. Neverless those areas and all portions of the active
floodplains for all other proposed areas it would be necessary to
improve the situation of active floodplains which are suffering by
channel incision, fine material aggradation (strong succession) and
forestry management (poplar plantations). Further the role of the
portion of active river-floodplain corridor as part of the potential
restoration areas must be considered as very high, because without
improved hydromorphological dynamics the floodplain extension will
be not work sufficiently.
Seite 107
Assessment of the Restoration Potential in the MDD-TBR
Seite 108
Assessment of the Restoration Potential in the MDD-TBR
7
For several areas (marked by *) along very upper Drava and Mura and middle Drava no
continouse dike lines exist. Therefore the area comprises also higher areas used by
agriculture.
Seite 109
Assessment of the Restoration Potential in the MDD-TBR
Seite 110
Assessment of the Restoration Potential in the MDD-TBR
Seite 111
Assessment of the Restoration Potential in the MDD-TBR
Restoration measures
Seite 112
Assessment of the Restoration Potential in the MDD-TBR
3.6.1 Mura
Seite 113
Assessment of the Restoration Potential in the MDD-TBR
Seite 114
Assessment of the Restoration Potential in the MDD-TBR
Seite 115
Assessment of the Restoration Potential in the MDD-TBR
Seite 116
Assessment of the Restoration Potential in the MDD-TBR
Seite 117
Assessment of the Restoration Potential in the MDD-TBR
Seite 118
Assessment of the Restoration Potential in the MDD-TBR
Seite 119
Assessment of the Restoration Potential in the MDD-TBR
Seite 120
Assessment of the Restoration Potential in the MDD-TBR
10
9
Seite 121
Assessment of the Restoration Potential in the MDD-TBR
11
12
Seite 122
Assessment of the Restoration Potential in the MDD-TBR
13
14
Seite 123
Assessment of the Restoration Potential in the MDD-TBR
15
16
Seite 124
Assessment of the Restoration Potential in the MDD-TBR
3.6.2 Drava
17
18
Seite 125
Assessment of the Restoration Potential in the MDD-TBR
Seite 126
Assessment of the Restoration Potential in the MDD-TBR
Seite 127
Assessment of the Restoration Potential in the MDD-TBR
23
21
22 24
Seite 128
Assessment of the Restoration Potential in the MDD-TBR
25
26
27
Seite 129
Assessment of the Restoration Potential in the MDD-TBR
28
29
Seite 130
Assessment of the Restoration Potential in the MDD-TBR
Seite 131
Assessment of the Restoration Potential in the MDD-TBR
32
31
Seite 132
Assessment of the Restoration Potential in the MDD-TBR
34
33
Seite 133
Assessment of the Restoration Potential in the MDD-TBR
35
36
Seite 134
Assessment of the Restoration Potential in the MDD-TBR
38
37
39
Seite 135
Assessment of the Restoration Potential in the MDD-TBR
Seite 136
Assessment of the Restoration Potential in the MDD-TBR
41 42
44
43
Seite 137
Assessment of the Restoration Potential in the MDD-TBR
46
45
Seite 138
Assessment of the Restoration Potential in the MDD-TBR
47
48
Seite 139
Assessment of the Restoration Potential in the MDD-TBR
Seite 140
Assessment of the Restoration Potential in the MDD-TBR
50
51
Seite 141
Assessment of the Restoration Potential in the MDD-TBR
Seite 142
Assessment of the Restoration Potential in the MDD-TBR
3.6.3 Danube
54
53
Seite 143
Assessment of the Restoration Potential in the MDD-TBR
Seite 144
Assessment of the Restoration Potential in the MDD-TBR
56
58
Seite 145
Assessment of the Restoration Potential in the MDD-TBR
57
59
Seite 146
Assessment of the Restoration Potential in the MDD-TBR
60
61
Seite 147
Assessment of the Restoration Potential in the MDD-TBR
62
64
Seite 148
Assessment of the Restoration Potential in the MDD-TBR
63
65
Seite 149
Assessment of the Restoration Potential in the MDD-TBR
66
67
Seite 150
Assessment of the Restoration Potential in the MDD-TBR
69
68
Seite 151
Assessment of the Restoration Potential in the MDD-TBR
Seite 152
Assessment of the Restoration Potential in the MDD-TBR
71
72
Seite 153
Assessment of the Restoration Potential in the MDD-TBR
Seite 154
Assessment of the Restoration Potential in the MDD-TBR
74
75
Seite 155
Assessment of the Restoration Potential in the MDD-TBR
4.1 Feasibility
Land ownership, the most critical issues for all projects (costs for
land purchase can prohibit larger projects, but also in case of
compensation payments if the land falls after the restoration in the
active floodplain should be not underestimated: predestinated are
public owned areas along the rivers).
Proposed measures and proposed costs of the restoration project
in detail. Often a lot of data is missing, different variants must be
developed.
Legal framework, not only EU legislation, but especially national
regulations to keep/increase retention areas, how is compensation
managed (agriculture), are there agricultural programmes in the
area, the legal certainty to foster and materialize planning and
implementation steps, and political willingness (which is
immeasurable).
Involvement of local administration, local population (perception,
interest in restoration projects), NGOs and other stakeholders.
Multi-use concepts for and benefits of restoration projects
(recreation, nutrient reduction, sustainable forestry/fishery), i.e.
local people will participate and profit from those projects.
The (monetary) valorisation of floodplain and ecosystem services
and floodplain goods has a certain tradition (e.g. within the Ramsar
Convention). They should support cost-benefit analysis to decide
upon usage concepts in floodplains. Floodplains under a broad use
Seite 156
Assessment of the Restoration Potential in the MDD-TBR
concept are still not very developed. Local usage concepts can
significantly accelerate and support the restoration of floodplain
areas, and can also include touristic concepts.
Seite 157
Assessment of the Restoration Potential in the MDD-TBR
Large scale restoration projects can take at least 5-10 years; land
procurement and planning approval can take years and therefore require
well-developed administrative structures and sufficient funding.
Restoration is often not limited to changes in dike lines, but requires
changes in the management of the adjacent river and floodplain areas. In
most cases improvements of lateral connectivity and changes in landuse
(e.g. less intensive forestry, hunting or meadow management) are
necessary to accelerate the reconnection and to improve the ecological
conditions along the respective river stretch. Monitoring is a necessary tool
to assess the restoration progress over years or decades. Restoration areas
must be protected and integrated in the existing protection network.
For the TBR MDD some further specific recommendations can be given:
Seite 158
Assessment of the Restoration Potential in the MDD-TBR
Seite 159
Assessment of the Restoration Potential in the MDD-TBR
Costs for land: Where larger parts of the areas are under public property
(e.g. the river and its adjacent land is in most cases public property)
restoration measures can be carried out efficiently. Regarding private
ownership the different property structures in the different countries can
be different, e.g. the large scale agriculture with huge field size as an
outcome of socialistic agroeconomy in Hungary could accelerate the
purchase negotiations as e.g. in Croatia where a lot of landusers posses only
a small part of the land. Prices are also significant different but in general
the big gap between upper and lower corridor countries within the first 10-
15 years after the political change decrease. One ha agricultural land costs
in Hungary about 3,000 € in Austria up to 13,000 €. The compensation for
land which will be fall into the active floodplain after the restoration
measure is about 4,500 € / ha in Austria (and respectively less in Hungary).
Costs for flood dike relocation: The most expensive part of large scale
restoration projects is the slitting or removal of existing flood dikes and the
construction of new dams. Therefore the new dike line has to be planned
carefully and should be shorter than the former one. By widening of the
floodplain the pressure on the dike will be reduced and could theoretically
reduce the height of the necessary new dikes crest. In cases where only
Seite 160
Assessment of the Restoration Potential in the MDD-TBR
Seite 161
Assessment of the Restoration Potential in the MDD-TBR
The definition and total list of potential restoration sites will serve as a
strategic tool for the future planning, the prioritization tries to focus on a
sub-set of areas. The long-time experience shows that the realisation of
individual projects strongly depend on various other factors and feasibility
all along financing and public acceptance or the support by local
stakeholders.
Seite 162
Assessment of the Restoration Potential in the MDD-TBR
Seite 163
Assessment of the Restoration Potential in the MDD-TBR
Seite 164
Assessment of the Restoration Potential in the MDD-TBR
Seite 165
Assessment of the Restoration Potential in the MDD-TBR
6. References
BUNDESAMT FÜR NATURSCHUTZ (BfN) (2009): Auenzustandsbericht, Flussauen
in Deutschland (Floodplain assessment for Germany). Bonn
HABERSACK, H.; HAUER, C.; SCHOBER, B.; DISTER, E.; QUICK, I.; HARMS, O.; WINTZ,
M.; PIQUETTE, E.; SCHWARZ, U.; (2008): Flood risk reduction by preserving and
restoring river floodplains – Pro Floodplain. In: Conference Proceedings
“FloodRisk 2008 - The European Conference on Flood Risk Management
Research into Practice”, Oxford. Balkema, The Netherlands / Taylor and
Francis, Engineering, Water and Earth Sciences, London.
ICPDR (2010): Danube River basin management Plan (DRBMP) 2009. Vienna
Seite 166
Assessment of the Restoration Potential in the MDD-TBR
ICPDR (2010): Danube River basin management Plan (DRBMP) 2009. Vienna
Seite 167