Concrete Quality Control Planning According To UNI EN 13670
Concrete Quality Control Planning According To UNI EN 13670
ABSTRACT: Concrete quality control on site in Italy is generally poor: lack of reliable execution
specifications and inspection practices is one of the causes.
Concepts introduced by recent standard UNI EN 13670 give the opportunity of change: the fulfilment of
specific requirements may improve significantly the actual situation.
QC management options, namely concerning execution and curing classes are outlined.
A r.c structures effective inspection plan should rely on a detailed coordinated concreting planning : basic
criteria for its drafting are illustrated.
Systematic analysis of records of real quantities of components batched and times printed in delivery
tickets can help to better check on site compliance of actual w/c ratio with specified values and prevent
problems arising during unloading and placement.
1
structure (with the help of annex A)
The importance of EN 13670 among the system of European Standards related to con-
crete works is shown in the following Figure 1.
Figure 1. System of European Standards as basis for design, execution and materials
selection for concrete works (only main modules)
While other European States like France, U.K and Germany (which holds the secretariat
of CEN/TC 104 who has prepared EN 13670) are familiar with detailed Standards or
Standards like documents dealing with this matter Italy only recently (february 2008)
has issued through STC (Servizio Tecnico Centrale del Consiglio Superiore dei Lavori
Pubblici ) a Guidance concerning some aspects of the execution of concrete structures.
2
A new revision of NTC is on the way.
3
structure.
This includes inspection of formwork, reinforcement , cleaning before casting concrete,
concreting and curing, prestressing etc.
The above scenario is quite normal in most European countries.
General concrete execution specifications have been issued and updated by competent
authorities in France and Germany (CCTG and VOB) without speaking of BS and NEN
in U.K. and Netherlands.
The italian context shows significant deficiences and UNI EN 13670 gives the
opportunity of a strong improvement.
First of all it shall be stressed the need of updated, detailed and project related execution
specifications : Table A1 of Annex A should be currently used by structural designers.
Effective inspection planning procedures should be practiced: nowadays in Italy most of
construction companies are certified ISO 9001 but inspection plans are too often
documents without the necessary effectiveness.
Few inspection reports are recorded in the “Journal of works“ : results of inspection
should be systematically and fully recorded.
Some civil engineering works like railways (managed by ITALFER) and highways
(managed by AUTOBRENNERO, AUTOVIE VENETE, SPEA) have already a QC
management not too far from that provided by execution class 3 in UNI EN 13670
especially for materials: execution inspection plan should be improved according to
UNI EN 13670 requirements.
Items like formwork detailing (clause 5.4) , inserts and embedded components (clause
5.6), installation of reinforcement and concrete cover (clause 6.5), protection and curing
(clause 8.5) should get more attention through specific inspection plans, procedures and
records.
Construction joints rarely are designed and concreting in very hot weather conditions is
too often allowed without reliable precautions: see clause 8.2 (4) and (10).
Many other important and critical structures, technologies and projects (e.g. special
foundations , prestressed structures, strategic buildings in class IV, buildings in seismic
zones 1 and 2) should have assigned and fully implemented execution class 3.
Clause 4.2.2 (see also Art.43 of DPR 207/2010) state that QC management should rely,
when provided in the execution specifications, on a quality plan.
In Italy where roughly half of the territory is in seismic zones 1 and 2 execution class 2
could concern mainly low rise residential and commercial building without particular
structural criticities in seismic zones 3 and 4; then class 1 should be limited to minor
urbanization structures and buildings with negligible risks .
There are rare examples of implementation of execution inspection plans class 2 like,
provided that construction companies, to which the italian law assigns almost all
responsabilities, are not used to plan inspections nor to record their results and
supervision by site engineers on behalf of the client is often lacking and limited to a
survey of the floor structures just before pouring .
A mandatory more detailed “Journal of works“ recording results of the inspections
concerning main items as per clauses 5 , 6 , 8 and 10 should be in such cases advised.
Execution record documentation (Clause 4.2.3 and A.4.2.3) should include:
a) Sources of materials, materials test reports and/or suppliers declaration of
performance; applications for variations and the responses;
b) As built drawings;
c) Non conformities and corrective actions taken;
d) Record of accepted changes to the project specification;
e) Documentation of the inspections and records of checks at hand over;
f) Events of significance for the properties of the finished structure;
g) Weather conditions during casting and curing.
This approach necessarly implies a radical cultural change in all professionals in Italy:
project manager (Responsabile Procedimento) , designers and site engineers (Direttore
Lavori , Collaudatore), and site managers.
They have now the opportunity to use a complete set of updated standards.
Not less responsibility is assigned to associations and regulation bodies.
4
2.3 Curing classes
Curing and protection of concrete in its early life is maybe the most neglected
requirement in italian construction sites despite often harmful weather conditions.
Most of cracks due to excessive shrinkage are due to lack of curing.
Technical specifications rarely are detailed to this regard and almost never respected.
Natural curing is sufficient only when conditions throughout the required curing period
are such that evaporation rates from the concrete surface are low, e.g. in damp, rainy or
foggy weather.
The increase of the use of mixes with low bleeding tendency, like high strength and self
compacting concrete advises special considerations in order to prevent plastic shrinkage
cracking on free surfaces; this applies also for concreting under weather conditions that
cause strong evaporation like hot weather, wind as well as in cold and dry air.
Curing shall start without delay on completion of compaction and finishing operations.
The duration of applied curing shall be function of the development of the concrete
properties in the surface zone.
UNI EN 13670 provides four curing classes
Curing class 1 specifies a curing period of 12 hours provided that the set does not
exceed 5 hours and surface concrete temperature is above 5° C.
The other three curing classes are related to the percentage of the specified characteristic
28 days compressive strength :
Curing class 2 35%
Curing class 3 50%
Curing class 4 70%
The development of concrete properties in the surface zone may be estimated by
different methods more or less accurate.
Tables F1 , F2 , F3 of Annex F give the duration of curing in number of days deemed to
satisfy the curing classes 2 , 3 and 4 in relation to surface concrete temperature (from 5°
C to above 25° C) and rates (rapid, medium and slow) of concrete strength development
The curing class shall be stated in the execution specification.
This requirement obliges the designer to be fully aware of concrete characteristics and
behaviour provided that the choice of curing classes is dependant on exposure classes,
choice of concrete composition and concrete cover to the reinforcement, without
neglecting climatic conditions and size of elements.
Methods for protecting and curing concrete are well known and resumed in Annex F.8.5
of UNI EN 13670 ; they shall achieve low evaporation rates from the concrete surface or
keep the surface permanently wet.
Rate of evaporation depends on concrete and air temperature, relative umidity and wind
velocity (wich can be minimized only with windbreaks).
Concrete temperature can be controlled by using low heat cements and keeping cold the
main components: aggregates, cement and water.
In most sites in Italy in summer time concrete temperature is often exceeding 30° C with
peaks near 40° C ; measures to cool concrete components are rare.
Aggregates are almost never protected and water sprayed.
Curing shall be an important part of execution specification, inspection planning and
recording: responsabilities involved in implementation of correct curing methods and
periods as well as associated inspection procedures should be defined.
Once curing class has been specified, the site engineer shall verify the correct starting of
related activities; easy spot checking by rebound hammer can confirm the achievement
of the provided concrete strength: results shall be recorded.
Methods of curing should be well known by designers and site engineers: no concreting
plan should be approved without full knowledge and availability by all project
participants of methods of curing, class of curing and materials/devices to be employed.
Time of pouring concrete should be choosed in order to minimize air temperature peaks
and allow curing activities to be started and carried out properly: in hot weather
afternoon pours should be avoided.
5
3 CONCRETING PLANNING
3.1 General
A concreting plan shall be prepared where required by the execution specification:
Clause 8.2 (1).
Every day experience learns that without a suitable concreting planning problems are
inevitably arising.
It may seem trite to say that the site should be fully ready before concrete is ordered.
It is surprising how often this is not done with detrimental consequences.
UNI EN 13670 underlines that the concrete structures designer, who should have the
necessary experience and knowledge, when writing the execution specifications, has to
decide if the project needs a general concreting plan or to identify within the project
which specific pours should require a concreting plan.
Some common examples of specific pours may be:
Unusual volume or timing;
Access and placement facilities/techniques not easy to be managed;
Concrete working life lasting more than two and half hours;
Special finishing;
Mix not easy to be managed (e.g. air entrained XF3-F4 with type IV cement).
It is understood that a concreting plan consists of written documents.
The designer may give a guideline on how carry on this activitiy that will concern
necessarly all partecipants: owner, designer, site engineer, safety engineer, general
contractor , concrete structures subcontractor , concrete producer, admixture supplier,
concrete delivery and pumping subcontractor, concrete finisher, testing laboratory and
any other involved in the project.
Without a reliable coordinated concreting plan which is an important part of the
construction plan it is very difficult if not impossible to conceive and implement an
effective concrete quality control on site.
6
Defects encounterd in most italian sites show that forms and jointing are worthy of
further analysis.
UNI EN 13670 says at Clause 5.4 (1) that a method statement , where required by the
execution specification, shall describe the methods of support, erection and dismantling;
it shall specify the requirements for handling, adjusting, tying, intentional precambering,
loading, unkeying, striking and dismantling.
About forms the checklist ask to define responsabilities both for installation and
inspection of reinforcement (namely with regard to location and spacing to allow for
concrete cover, vibration equipment access and aggregates size), embedded items,
waterstops, drains and opening frames.
It underlines the need to plan three inspections at different stages.
Inspection just before concreting is at least not effective: it is very difficult to make
reliable corrections when all reinforcement is on place.
Last minute changes when concrete has already been ordered or is waiting on site risk to
create additional problems.
The inspection plan should provide a preliminary check prior to rebar placement to
verify correct geometry of the forms: to do this coordinated placing drawings with
details of opening frames shall be provided.
It is not the job of site carpenters to take informations/dimensions from mechanical,
electrical and plumbing drawings to concrete structures drawings.
The second inspection should take place when rebars, embedded items, waterstops and
drains are on place: then there is time to make corrections if any and to clean properly
the forms.
The third final inspection should be done just before placing concrete.
Construction joints in mat foundations, walls, floors very rarely are
specified/detailed/planned/inspected: too often the matter is left to the improvisation.
Construction joints should not be made at critical positions Annex F.8.2 (1).
While other aspects are supposed to be well known by concrete structures engineers
items concerning ordering and scheduling concrete are often wrongly underestimated.
The cheklist analyzes specific problems like minimum notice required for most
placements and large and specialty placements, procedure for handling will-call orders
and revised orders, responsabilities for ordering concrete and reviewing delivery ticket
before placement and turnaround time for trucks.
7
4 CHECK OF DELIVERY TICKET PRIOR TO DISCHARGE
4.1 General
Check of the delivery ticket prior to discharge is a normative requirement whatever is
the execution class: Clause 8.3 (1)
Test methods and criteria for determining the conformity and identity of concrete are
given in EN 206-1.
Tests are necessarly concerning only a part of delivered concrete.
Further useful informations may be obtained from data recorded on delivery tickets.
Most of ready mix concrete plants are now able to print on the delivery documents
records of real quantities of components batched and other relevant data (e.g. estimated
aggregates humidity) .
Some admixture may be dosed manually in small quantities as well as fibers; they have
normally to be recorded by hand.
Significant times have also to be recorded on delivery ticket as well as water and
admixtures added after batching.
Such corrections after batching are often unavoidable and shall be carefully planned,
managed and controlled: a single water addition at delivery to bring the slump up to the
specified limit without affecting w/c ratio should be evaluated and agreed if considered
to be necessary and correct.
Concrete inspectors should have full knowledge of batching facilities and related
automation software to be able to analyse relevant records in order to verify conformity
before unloading and to evaluate how to carry on corrections if needed.
Data recorded may also be used to analyse “a posteriori“ arised problems to make
possible to carry on effective corrective actions.
8
Design activities of concrete mix should give all the necessary attention to the
evaluation of the consistence retention time.
Checking the w/c actual ratio is one of the main objectives of concrete quality control on
site; provided that testing according to CEN CR 13902 is time consuming and not
enough accurate the only effective method is to analyse reliable records
It is quite evident that if only one of the above water quantities is not taken in account
all records concerning w/c ratio are useless.
There are many other uncertainties/fluctuations: e.g. aggregates water absorption,
admixtures behaviour, real weight of batched aggregates, temperature of cement and
aggregates.
All involved variables concerning components characteristics bring to a precision not
less than 15 liters of water /cum of concrete: that means that often water corrections are
unavoidable to get the specified consistence.
Sistematic corrections with admixtures are quite difficult to be managed.
Only the complete analysis of these corrections can give information on anomalies to
allow for their reduction and finally ensure the constancy of concrete properties related
to w/c ratio: it may bring to review the mix or to better adjust the batching plant
equipment.
In the view of screening the problems percentages of corrections more than 10/15 liters
per cum should be investigated.
No recorded corrections does not mean necessarly that everything is OK.
An effective concrete quality control on site should include coordinated checking at the
batching plant and on delivery tickets.
9
5 CONCLUSIONS
Most concrete defects are due to lack of planning and implementation of an effective
quality control concerning execution activities.
In Italy there is not a good practice of specification writing.
UNI EN 13670 introduces here for the first time detailed specification concerning the
planning, execution and inspection of concrete structures.
Italian designers should get familiar with the content of this standard to be able to define
QC management options and specific requirements.
All project partecipants should experience the practice of coordinating concreting
planning and implementing reliable inspection routine.
Testing fresh and hardened concrete on site can detect only a part of the problems.
Systematic analysis of records of real quantities of components batched (including
corrections) and times printed in delivery tickets can help to prevent many anomalies.
REFERENCES
American Society of Concrete Contractors (ASCC) American Concrete Institute (ACI).
(2005). The Contractor’s Guide to Quality Concrete Construction.