Professional Documents
Culture Documents
Network Standard
Volume 1
Network Standard NS0116 Design Standards for Distribution Earthing provides the
criteria for earthing of distribution substations to be connected to EnergyAustralia’s
network.
It is the responsibility of the user of this document to ensure that only the current
version is being used.
Network Standard NS 0116
1 October 1997
CONTENTS
FOREWORD............................................................................................. 1
SCOPE ..................................................................................................... 1
1. INTRODUCTION.................................................................................... 2
1.1 General............................................................................................ 2
1.2 Geographic Area............................................................................... 2
1.3 Life of Document ............................................................................... 2
2. DEFINITIONS ........................................................................................ 3
3. GENERAL REQUIREMENTS .................................................................. 4
4. ELECTRODE TYPES............................................................................. 5
4.1 Former Sydney Electricity Area.......................................................... 5
4.2 Former Orion Energy Area................................................................. 5
5. SUBSTATION EARTHING ...................................................................... 6
5.1 General............................................................................................ 6
5.2 Combined Earthing System................................................................ 6
5.3 Segregated Earthing System ............................................................. 8
5.4 Pole Transformer Earthing ................................................................. 8
5.5 Kiosk Substation Earthing Arrangement .............................................. 9
5.6 Chamber Substation Earthing Arrangement ....................................... 11
5.7 High Resistivity Soils........................................................................ 11
6. OVERHEAD LINE EQUIPMENT ............................................................ 12
6.1 Former Sydney Electricity Area........................................................ 12
6.2 Former Orion Area.......................................................................... 13
7. ENVIRONMENTAL............................................................................... 14
7.1 Containment of Silt .......................................................................... 14
8. TESTING............................................................................................. 14
8.1 Methods of Measuring Resistance.................................................... 14
8.2 Soil Resistivity................................................................................. 17
8.3 Electrode Resistance ...................................................................... 18
8.4 Earthing Resistance Testers ............................................................ 19
8.5 Test Hints....................................................................................... 20
APPENDIX A - SOIL RESISTIVITIES........................................................ 21
1 1 October 1997
Foreword
This Network Standard lays down the requirements for distribution earthing
that meet the requirements of EnergyAustralia.
Scope
NS 0116
1 October 1997 2
1. INTRODUCTION
1.1 General
This Network Standard sets out the standards for the design of distribution
earthing system requirements for the connection of equipment to the
EnergyAustralia’s network.
This Network standard does not cover the installation and testing of the
earthing system. These topics are specified in other Network Standards.
The former Sydney Electricity supply district comprises the area between the
Pacific Ocean in the east, the Royal National Park in the south, the southern
boundaries of Lake Macquarie in the north and Auburn in the west.
The former Orion Energy supply district comprises the area between the
Pacific Ocean in the east, Lake Macquarie in the south, to Port Stephens in the
north and the Upper Hunter Valley in the northwest .
NS 0116
3 1 October 1997
2. DEFINITIONS
NS 0116
1 October 1997 4
3. GENERAL REQUIREMENTS
The earthing system must be designed with due regard to any potentially
hazardous situation arising from metallic structures in contact with or near the
electrical apparatus. Such structures include but are not limited to metallic
fences, swimming pools, flammable gas or liquid storage tanks, electric
railway lines, pipelines, high voltage substations, high voltage transmission
lines, operating theatres or similar medical facilities, communication centres,
pits, pillars and metallic sheathed communication cable.
• to minimise the risk to personnel and the general public from voltages which
may appear on or near equipment or structures within authorised or easy
access during fault conditions.
Other requirements:
• the MEN system of earthing is installed throughout the low voltage supply
network.
• the low voltage neutral connections are to be continuous throughout the low
voltage network ie. Across open points in the low voltage phase conductors.
• all bolts nuts and washers must be 3016 grade stainless steel, minimum size
10 mm.
NS 0116
5 1 October 1997
4. ELECTRODE TYPES
The earth grids must consist of a deep electrode system interconnected with
earthing cable. The following types are acceptable and apply only in the
Geographic area in which the substation is to be installed:
The above installation depth of electrodes are minimum values only and in
some geographic areas, greater depths or additional rods will be required to
achieve the required earthing system impedance.
NS 0116
1 October 1997 6
joined with the approved friction joint couplings. Minimum depth of rod is
3.6 metres.
5. SUBSTATION EARTHING
5.1 General
All low voltage neutral terminals of transformers and neutrals of outgoing low
voltage cable and busbar supplies must be connected to the neutral busbar. The
neutral busbar must be one piece of copper bar, without joints.
NS 0116
7 1 October 1997
(a) Joined to the earthing systems of at least two other substations by continuous
low voltage neutral conductors.
OR
NS 0116
1 October 1997 8
The earthing installation must comply with drawing 36377 Pole Transformer
Earth Rod installation Layout and special requirements for the type of pole
transformer being installed. The following drawing number detail these special
requirements:
NS 0116
9 1 October 1997
Substation Ω)
Maximum Resistance Value (Ω
HV LV
Single Pole > 750 kVA 30 15
Single Pole ≤ 50 kVA 30 30
• the earth conductors shall be covered with PVC earthwire troughing form
150 mm below the ground to a minimum height of 2.4 metres above ground.
NS 0116
1 October 1997 10
The combined earthing system shall have a resistance to earth not exceeding
1 ohm and an individual electrode group resistance to earth not exceeding
15 ohms.
The earthing system for kiosk type substations shall comply with
• electrodes shall be driven in two diagonally opposite corners under the base
of the substation.
• all electrodes and cables shall be kept clear of the cable entry hole
• the HV1 and HV2 earth tails shall be sufficient length to project one metre
above the base of the kiosk.
Where segregated earthing is specified the HV and LV earth system shall not
exceed
Substation Type Ω)
Maximum Resistance Value (Ω
HV LV
Rating ≥ 500 kVA 30 10
500 kVA ≥ Rating > 50 kVA 30 15
Rating ≤ 50 kVA 30 30
The HV earth shall consist of two electrodes driven in the corners under the
bare area and connected in parallel with 70 mm2 copper stranded cable, which
shall be compression clamped to each electrode.
The LV earth shall consist of two electrodes connected in parallel with 70 mm2
copper stranded cable, which shall be of compression clamped to each
electrode.
NS 0116
11 1 October 1997
The minimum separation between the HV and LV earths shall be 2 metres. This
also applies for separation between HV earths and any street light LV pillars
water pipes or other equipment bonded to the LV earth.
All electrodes and cables are to be kept clear of cable entry holes.
The HV and LV earth tails shall be laid in their respective entry hole position
and be of sufficient length to project one metre above the base.
The earthing installation must comply with drawing 25121 Substation Earthing
Typical Installation of Earth Electrodes. The earthing system must be
installed under the foot print of the substation chamber.
A combined earthing system must be used, however the earthing system must be
stand alone type not connected to building reinforcement bars or grading rings
and must be well clear of the building lightning protection system
The earthing system must be installed before any waterproof membranes are
laid and before the substation floor is constructed. Earth electrodes must be
installed at no less than 3 metres apart and in two groups. The connection from
the two groups A and B must be up through the floor directly to the position of
the substation earthing bar.
In upper level substations the two group A and B electrodes must be bought up
to the substation with the high voltage feeder risers.
The high voltage and low voltage cable sheathes must be connected to the earth
mat at the high voltage switchgear earth bar and the low voltage switchboard
earth/neutral bar respectively.
Where the above minimum values of earth impedance, for each type of
substation, cannot be achieved with the minimum number of 5 metre electrodes,
additional or longer electrodes must be installed up to an equivalent of three
10 metre electrodes per group. In some locations to obtain a suitable resistance
value, it may be necessary to drill to depths exceeding 10 metres.
NS 0116
1 October 1997 12
Table 1
Pole mounted recloser or sectionaliser Two groups, each with two electrodes
Note: Surge arresters, rod gaps and tanks of equipment associated with air break
switches such as OH line reclosers and sectionalisers are earthed by a second
installation. The two installations must be isolated from each other and nearest
elements of each must be separated in the ground by a distance of not less than
2 metres. The connection from the pole foot to the nearest electrode of the
arrester and frame earthing installation must be insulated, and not closer than 2
meters from any element of the air break switch handle earthing installation.
HV Line surge arrester installation Two groups, each with two electrodes
HV UG/OH cable sealing ends and surge Pole butt electrode and the earth lead
arresters (cables with continuous metal must also be bonded to the sheath of the
sheaths or screen) cable
Note: The tanks of static balancers must not be earthed. At each static balancer
location, a notice must be displayed warning staff that the frame of the
equipment must be considered "live" until proved otherwise.
Line air break switchgear with insulated One electrode or pole-butt electrode
rod extension to handle
NS 0116
13 1 October 1997
Table 2
NS 0116
1 October 1997 14
7. ENVIRONMENTAL
The Service Provider must comply with all EPA regulations regarding the
prevention of silt and or other spoil resulting from earth electrode hole boring,
entering any drain, creek, river or natural water course.
8. TESTING
8.1.1 General
There are two methods for measuring the resistance of an electrode or a group
of electrodes: the Two-Spike (Fall-of-Potential) Method and the Two-Point
Method. Both use a null-reading bridge earth resistance tester.
NS 0116
15 1 October 1997
Warning, a buried metallic object such as a water pipe has the effect of nullifying
electrode A with the result that the voltage V is that measured between electrodes E and
B. This results in an incorrect excessive reading (see figure below) and hence the Two-
Point Method must be used as a check.
NS 0116
1 October 1997 16
Current from the Earth Tester is passed from electrode E under test to the
buried metallic object (e.g. water pipe) and the voltage between them is
measured (see figure below).
Both the resistance of the water pipe and that of the electrode or group under
test is measured but since the resistance of the buried object (e.g. water pipe) is
very low, the reading obtained is assumed to be that of electrode or group E.
WARNING
Traffic Lights,
Two-Point method
NS 0116
17 1 October 1997
The purpose of measuring the soil resistivity (ρ) is to establish the resistance
represented by the soil between the electrodes. It is measured using test
electrodes and a null-reading bridge. Known as the Wenner 4-point method, the
procedure is set out below.
When determining soil resistivity on site, a number of readings are taken for
various values of test-electrode spacing and depth. From values obtained,
either a curve is drawn or the value of soil resistivity calculated. Calculation
requires that the ratio of test-electrode spacing to depth is maintained at a
maximum value of 20:1. For accurate results, electrode spacing should not be
less that 1.5 metres.
(a) Set out four test electrodes in a straight line and space them at equal
intervals of a metres (e.g. 10 metres).
(b) Drive the electrodes into the ground to a depth of a/20 metres or to as close
to that depth as possible. Do not exceed that depth.
(c) Connect the electrodes and earth - tester as shown in Figure 4.1.
(d) Operate the earth tester and obtain a null balance. Note the reading (R).
ρ = 2πaR
(f) Calculate the average value of ρ (ρav) from the values obtained from the
calculation.
NS 0116
1 October 1997 18
Electrode resistance can be calculated from the length and diameter of the
electrode and the average soil resistivity (ρav), as follows:
(a) Measure the length of an electrode (L), in metres, and its diameter (D), in
millimetres.
ρav 1000 L
Re = 2.3 log10 + 11
.
2πL D
where
NS 0116
19 1 October 1997
Three types of earth-resistance testers all of which are of the null-reading type
are being used.
The two older testers differ only in the method of voltage generation. One uses
a hand-operated generator while the other a replaceable battery with push-
button operation. The newer 'Geohm' tester is an electronic instrument and is
push-button operated. With these instruments the correct reading is that
obtained when the meter reads centre scale.
NS 0116
1 October 1997 20
• Set the test cable reels at right-angles when they are in close proximity.
• If the test instrument has two or more ranges, note the results for each
voltage/current combination. Variations in results may indicate that
insufficient current is being injected.
Where there is insufficient test current due to high contact resistance, try one or
more of the following:
• Drive additional electrodes. Install them near each other and connect them
together so that they form a common electrode.
• To reduce contact resistance, pour water (or salt-water) around the current
electrodes.
NS 0116
21 1 October 1997
General
Soil resistivity (ρ) is a measure of the resistance of the soil across a theoretical
cubic metre with electrodes of one square metre on either side.
Soil resistivity is expressed in ohm metres (Ω.m) not ohms per metre. It is
sometimes wrongly described as specific resistance.
Soil resistivity varies depending upon the physical nature of the soil, its
chemical composition, dissolved salts and moisture content. Below is a list of
typical soil resistivities.
Soil ρ (Ω
Ω .m) at 20oC
Swampy earth 10
Clays 8 to 50
When the resistivity is not known, a value of 100 Ω.m is taken to the
representative of an average soil with a moisture content of around 25%.
Lowering the moisture content to 5% can raise the resistivity to 500 Ω.m.
Completely dry soil can have resistivities of thousands of ohm metres. A
simple guide for resistivity values is given below.
Soil ρ (Ω
Ω .m)
Mud or coal 1
Wet soil 10
Rock 10 000
NS 0116
1 October 1997 22
Revision History
Document Control
UNCONTROLLED COPY
NS 0116