37 Excavation before new construction Bldg
38 Permanent fences, water systems and sidewalks (provided not part of blueprint) LI
39 Driveways & walk paths –part of building plan Bldg.
40 Cost of trees and other landscaping (provided not part of blueprint) LI
41 Streetlights and parking lots ( provided not part of blueprint) LI
42 Sale of scrap from old building Ded. From Bldg
43 Salvage materials from demolition Ded. From Bldg
44 Expenditures incurred during the construction period such as borrowing cost and Self-Const Bldg
insurance
45 Architect fee Self-Const Bldg
46 Superintendent fee Self-Const Bldg
47 Cost of excavation Self-Const Bldg
48 Building perm it or license Self-Const Bldg
49 Safety inspection fee Self-Const Bldg
50 Cost of temporary safety fence around construction site and cost of subsequent Self-Const Bldg
removal thereof. However, the construction of a permanent fence after the
completion of the building is recognized as land improvement.
51 Cost of temporary building used as construction office and tools or materials shed Self-Const Bldg
52 Expenditures for service equipment and fixtures made as permanent part of the Self-Const Bldg
structure
53 Materials used, labor employed and overhead directly attributable to construction Self-Const Bldg
(direct construction cost)
54 Ventilation systems, plumbing and lighting systems (provided not part of blueprint) Bldg. Improv
Otherwise, it is included as cost of the constructed building.
55 Cost of elevator, escalator and similar items (provided not part of blueprint) Bldg. Improv
Otherwise, it is included as cost of the constructed building.
56 Immovable fixtures attached to the building (provided not part of blueprint) Bldg. Improv
Otherwise, it is included as cost of the constructed building.
57 Purchase price of equipment Equipmt
58 Freight, handling charge, storage and other cost related to the acquisition Equipm
59 Insurance while in transit Equipm
60 Installation cost, including site preparation and assembling Equipm
61 Cost of testing and trial run, and other cost necessary in preparing the machinery for Equipm
use
62 Initial estimate of cost of dismantling and removing the machinery and restoring the Equipm
site on which it is located, for which the entity has a present obligation.
63 Fee paid to consultants for advice on the acquisition of the machinery Equipm
64 Cost of safety rail and platform surrounding machine Equipm
65 Cost of water device to keep machine cool Equipm
66 Irrecoverable taxes Equipm
67 Major spare parts and stand-by equipment are treated as PPE when the entity Equipm
expects to use them during more than one period.
68 Supervision by management during construction Bldg.