You are on page 1of 135

Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

TRIBAL DEVELOPMENT DEPARTMENT


GOVERNEMENT OF GUJARAT

Name of Work: Construction of Babarghat GRLS complex and its allied


Infrastructure works At Ta.Babarghat Dist. Tapi

TENDER NO. GITEP-88

Schedule: - B

1
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

PREAMBLE TO BILL OF QUANTITIES:


(a) General
This is Item rate Contract. The Items in the Bill of Quantities in this Bid Document do not
necessarily contain full descriptions of the required work and, when pricing, the Bidder is to
refer to all parts of the Bid Document i.e., the drawings, specifications etc, as also Standards
referred to, and assess the site conditions and performance requirements in totality. The rates will
be deemed to include for the full cost of work as described in the Bid Documents.
(b) Contract Price
The Prices quoted against the items in the Bill of quantities should cover the full value of the
finished work described including, but not limited to, for the cost of all the obligations on the
Bidder as set down in all the Contract Documents (which are to be read together), for co-
operation and co-ordination of his work with other Contractors, if any, working in the area and
with various Authorities, for all temporary work required and for the provision and use of all
plant, whether mechanical or non-mechanical, required for the expeditious execution of the
Works in their proper sequence, fulfilling other obligations laid down in various clauses of this
Contract Document and for shifting plant, etc. as may be required during the progress of the
Works and removing on completion and making good any surfaces disturbed.
The rates should also include for all necessary services for the Works, for the cost of preparing
the bid, for profit and for all other establishment charges and on costs of whatever nature,
including the following:
i. Labour and all associated costs
ii. Locating and transporting construction materials.
iii. Providing at site materials and goods in accordance with the Specification.
iv. Temporary works.
v. Establishments charges, overheads and profit.

vi. Setting out of the works and liaison with all concerned authorities for approval of the
same.
vii. Ascertaining from the concerned authorities the locations to which the storm drainage can
be discharged, before commencing the project.
viii. Paying all statutory dues and taxes, housing, paying salaries and bonus etc for employees
of the Contractor.
ix. Providing and maintaining throughout the entire construction period, safety barriers
around all excavations and making them visible during night. Providing motorable access
to the industrial units or other plots where entry is obstructed by the road works.
x. Obtaining permission, where necessary, to cross land, for use of public or private land,
paying compensation, if any, for damage to property or for other effects due to the
presence of the Contractor’s labourers and equipment on such land, protecting any
fencing, private or public property, repairing any damage caused by the Contractor’s
plant to public utility services (oil, water, electricity, telephone, sewers, etc.).
xi. Assistance to the Engineer as required, all reporting requirements including taking and

2
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

printing of photographs.
xii. General foreseen and unforeseen expenses of the Contractor.
xiii. Removing all construction debris to a tip approved by the local authorities,
xiv. Any other expenses required for the execution, completion and maintenance of the works
until the final handing-over of the Works, without any exceptions or reservations and the
Contractor shall have no right to claim any compensation or extra cost of any necessary
work for the execution, completion and maintenance of the works.
xv. Insurance charges wherever applicable both for protection of work and contractor’s
labour.
xvi. Maintaining the commissioned parts of the Works for a maintenance period as specified
in the Contract Data.
xvii. Night work wherever necessary to complete the work expeditiously and to limit public
inconveniences to the minimum.
xviii. In case, any retest at factory for any permanent material to be used in the Works,
becomes necessary to ascertain the quality of materials, the entire cost of re-inspection
and retests including cost of travel, accommodation etc. of the inspecting official will be
charged to the contractor if the retest confirms poor quality of the material.
xix. Providing and maintaining traffic diversion arrangements as described in the special
specifications
The cost of meeting the above mentioned obligations during the entire period of Contract
is deemed to be distributed amongst all billed items.
(c) Completion Period of Work
The Contractor is to commence the work soon as he receives the Commencement Order and
complete the work in the period indicated in the memorandum, failure to which will attract a
penalty for the delay of works, as liquidated damages, as specified in tender.
(d) Provisional Items
Provisional Item means an item included in the Contract and so designed for the execution of
work or the supply of goods, materials or services, which item may be used by the Employer by
appointing Nominated Contractors or by instructing the Main Contractor, in whole or in part or
not at all, at the discretion of the Engineer in Charge, and the Contractor shall not have any right
at any time to claim for delays or extra expenditure suffered by him if the Provisional Items are
executed only in part or not at all.
(e) Items for Which Separate Payment will not be made
The following items are to be performed as part of the Contract. The cost of these works is
deemed to be distributed in the pay items of the Contract.
i. Site Survey for establishing reference points in each road and fixing alignment of sewers.
ii. Providing and maintaining proper markers and profile rails.
iii. Supporting sides of deep excavations.
iv. Selection of materials for backfilling of trenches and against permanent structures.
3
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

v. Compacting of backfill against structures with hand held equipments.


vi. Testing of concrete at frequencies specified.
vii. Supplying and laying warning tapes above service lines at depths specified by the
Engineer in Charge at site.
viii. Preparing working drawings and manhole schedules in AutoCAD.
ix. Testing of materials brought at site to ensure quality.
x. Provision of safety measures at site for the works as well as the public utilities.

xi. The contractor shall provide, during the Defect Liability Period, a facility of on call at
project location in case of need, which will attend immediately and undertake the
rectification.
xii. Appropriate marking and labeling of electrical machinery relating them to the pumps and
motors and instrumentation equipments.
xiii. All risks, liabilities and obligations set forth or implied in the tender document.
xiv. Displaying framed drawings of all electrical and mechanical equipment/single line
diagrams inside the control rooms.
xv. Mobilization and demobilization to and from site, all plant, machinery, equipment and
staff as given in the schedule of information.
xvi. Contractor's facilities as specified in Specifications.
xvii. Obtaining permission, no objection certificate/ approvals from statutory authorities.
xviii Meeting the requirements during Defects Liability Period as explained in Special
Conditions of Contract.
xiv Any other expense that may be incurred in fulfilling any Contractual Clause, which is not
mentioned specifically here.

General Description
This project is to be constructed At Chaparvad Ta. Singvad Dist Dahod. The construction Works includes
Civil, Plumbing, Electrical works; Steel Fabrication works for School Buildings, Hostel Building and
its allied Infrastructure.
The brief overview of the project details are enlisted below
Sr. Description of Works / Buildings / Block Approximate Total Built-up
No. area in Sq. Mts.
1 School Building 3730.00
2 Hostel Buildings -1 5440.00
3 Staff Quarter 1076.00
4 Class –IV Quarter 165.00
5 Mess Building 730.00

4
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

TENTATIVE SCOPE OF WORK:

Salient features of the proposed building:


Architectural description:
Structure
 Composite structure of R.C.C. footing,columns ,beams and Brick masonry wall
Basic Finishes
 Brickwork – Fly ash Brick masonry load bearing wall with outside and inside Plaster

 Flooring: Polished kota stone flooring and glazed tiles for Bathrooms
 Internal wall surfaces: Mala plaster with Plastic paint with wall putty.
 External wall surfaces: Flakes Textured Finish.
 Roof: RCC Slab with necessary Water Proofing

 Doors/Windows: Wood Flush door, Alluminium glazed windows & Louvers.


 External areas: Chequred Tiles ,Rough Stone and Paver Block flooring in common area ,foot
path and road side area.

 Water s upply: PVC pipes with conventional gravit y system/pressurized water system

 Electrical works: Open/concealed electrification in conduits with LED and T5 light fixtures

Note: General Description of the Project, Scope of work and Finishes mentioned above with
drawings are indicative and variation is envisaged during detail designing. The above
information must be considered as provisional advance information to assist the bidder.

5
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

SCHEDULE –B
Form-B2

I.
No. Description Quantity Unit RATE Amount
Excavation for foundation upto 1.5 m depth including sorting out
and stacking of useful materials and disposing off the excavated
1 stuff upto 50 Meter lead.(A) Loose or soft soil 30.72 Cmt.
Excavation for foundation upto 1.5 m depth including sorting out
and stacking of useful materials and disposing off the excavated
2 stuff upto 50 Meter lead.(B) Dense or Hard soil 7350.451 Cmt.

Excavation for foundation upto 1.5 m depth including sorting out


and stacking of useful materials and disposing off the excavated
3 stuff upto 50 Meter lead.(B) Soft rock not requiring Blasting 1076.415 cmt
Excavation for foundation for depth from 1.5 m to 3.0 m including
sorting out and stacking of useful materials and disposing off the
excavated stuff upto 50 Meter lead. (D) Soft rock not requiring
4 Blasting 3176.972 cmt

Excavation for foundation for depth from 1.5 m to 3.0 m including


sorting out and stacking of useful materials and disposing off the
5 excavated stuff upto 50 Meter lead.(E) Hard Rock 626.6618 cmt
Filling available excavated earth (excluding rock) in trenches
plinth, slides of foundations etc. in layers not exceeding 20 cm in
depthconsolidating each deposited layer by ramming and
6 watering. 5859.7 Cmt.
Filling in foundation & plinth with murrum or selected soils in
layers 20 cm. thicknessincluing watering, ramming,
7 consolidating etc. comp. Up to 5.0Km 11477.41 Cmt.

Filling in foundation & plinth with sand under floors including


8 watering, ramming, consolidating and dressing etc. comp. 686.74 Cmt

1
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

Add Extra for Disposing off the excavated stuff of above items for
9 lead of 5.0 Km 2156.58 Cumt
Carrying out plinth treament to post constrction/existing
structure by spraying chemjcal solutionfor termite control
treament including labour and materials constituents with I.S.I
10 Specification 5834.84 Smt
Providing and laying cement concrete( 1:4:8)(1 cement : 4 coarse
sand : 8 hand broken stone aggregate 40 MM nominal size) and
curring complete excluding the cost of form work
11 (A)Foundation and plinth 840.99 Cmt.

Providing and laying controlled cement concrete M 15 and curing


complete excluding the cost of formwork and excluidng cost of
reinforcement for reinforce concrete work in a) Foundations,
12 Footings, base of columns and mass concrete 2466.57 Cmt.
Providing and laying controlled cement concrete M 20 and curing
complete including the cost of formwork and excluidng cost of
reinforcement for reinforce concrete work in lintels, beams,
girders and cantilever up to floor two level. (For all sizes of all
13 members) 880.93 Cum
Providing and laying controlled cement concrete M 20 and curing
complete including the cost of formwork and excluidng cost of
reinforcement for reinforce concrete work in lintels, beams,
girders and cantilever for Second Floor( Above First Floor & For all
14 sizes of all members) 325.25 Cum
Providing and laying controlled cement concrete M 20 and curing
complete including the cost of formwork and excluidng cost of
reinforcement for reinforce concrete work in lintels, beams,
girders and cantilever for Third Floor( Above Second Floor & For all
15 sizes of all members) 26.03 Cum

2
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

Providing and laying controlled cement concrete M 200 and curing


complete including the cost of formwork and excluidng cost of
reinforcement for reinforce concrete work in (F) Vertical and
16 Horizontal Fins, up to floor two level. 64.08 cum
Providing and laying controlled cement concrete M 200 and curing
complete including the cost of formwork and excluidng cost of
reinforcement for reinforce concrete work in (F) Vertical and
17 Horizontal Fins, Second Floor level. 25.95 Cum
Providing and laying controlled cement concrete M.250 exposed
work with curing etc. complete including the cost of formwork but
excluding the cost of reinforcement for R.C.C. work in (B)
COLUMNS:(ii) Having cross‐sectional area more than 0.08 Sq.M
18 and upto 0.18 Sq.M up to floor two level 38.39 Cum
Providing and laying controlled cement concrete M.250 exposed
work with curing etc. complete including the cost of formwork but
excluding the cost of reinforcement for R.C.C. work in (B)
COLUMNS:(ii) Having cross‐sectional area more than 0.08 Sq.M
19 and upto 0.18 Sq.M For Second floor 8.05 Cum
Providing and laying controlled cement concrete M.250 exposed
work with curing etc. complete including the cost of formwork but
excluding the cost of reinforcement for R.C.C. work in (B)
COLUMNS:(ii) Having cross‐sectional area more than 0.08 Sq.M
20 and upto 0.18 Sq.M For Third floor 8.05 Cum

Providing and laying controlled cement concrete M 20 and curing


complete including the cost of formwork and excluidng cost of
reinforcement for reinforce concrete work in ( C) Slabs, Landings,
21 up to floor two level. (For all sizes of all members) 1330.81 Cum

Providing and laying controlled cement concrete M 20 and curing


complete including the cost of formwork and excluidng cost of
reinforcement for reinforce concrete work in ( C) Slabs, Landings
22 for Second floor ( Above First Floor‐For all sizes of all members) 503.84 Cum

3
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

Providing and laying controlled cement concrete M 20 and curing


complete including the cost of formwork and excluidng cost of
reinforcement for reinforce concrete work in ( C) Slabs, Landings
23 for Third floor 29.05 Cum
Providing and laying controlled cement concrete M‐200 and
curing complete including the cost of form work and
reinforcement for R C C work in‐For RCC(E) Stair case steps &
24 landing…up two Floor level 59.35 Cmt
Providing and laying controlled cement concrete M‐200 and
curing complete including the cost of form work and
reinforcement for R C C work in‐For RCC(E) Stair case steps &
25 landing…For Second Floor 24.45 Cmt

Providing and laying controlled cement concrete M 25 and


curing complete including the cost of formwork and excluding cost
of reinforcement for reinforce concrete work in a) Foundations,
26 Footings, base of columns and mass concrete 1458.3 Cum
Providing and laying controlled cement concrete M 25 and
curing complete including the cost of formwork and excluding cost
of reinforcement for reinforce concrete work in (D) Columns,
pillars posts and struts up to floor two levels ( For all columns of all
27 sizes) 497.03 Cum
Providing and laying controlled cement concrete M 25 and
curing complete including the cost of formwork and excluding cost
of reinforcement for reinforce concrete work in (D) Columns,
pillars posts and struts for Second Floor ( Above First Floor Slab) (
28 For all columns of all sizes) 142.39 Cum
Providing and laying controlled cement concrete M 25 and curing
complete including the cost of formwork and excluding cost of
reinforcement for reinforce concrete work in (D) Columns, pillars
29 posts and struts for Third Floor 40.47 Cum

4
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

Providing and laying controlled cement concrete M 25 and curing


complete including the cost of formwork and excluding cost of
reinforcement for reinforce concrete work in (D) Columns, pillars
30 posts and struts for Forth Floor 7.66 Cum
Providing and laying controlled cement concrete M 25 and
curing complete including the cost of formwork and excluidng cost
of reinforcement for reinforce concrete work in lintels, beams,
girders and cantilever up to floor two level.Below plinth (For all
31 sizes of all members) 658.76 Cum
Extra for additional height of propping and centering where the
height of propping and centering exceeds more than 7.00 mt to
32 11 mt between supporting floor to ceiling. 111.72 Smt
Providing ISI mark T.M.T. bars Fe 415/ Fe 500 reinforcement for
R.C.C. work including bending, binding and placing in position
33 complete for Up tofloor two level 548511.8 Kg
Providing ISI mark T.M.T. bars Fe 415/ Fe 500 reinforcement for
R.C.C. work including bending, binding and placing in position
34 complete for Second Floor ( Above First Floor Slab) 111981.5 Kg
Providing ISI mark T.M.T. bars Fe 415/ Fe 500 reinforcement for
R.C.C. work including bending, binding and placing in position
35 complete for Third Floor 15633.78 Kg
Providing ISI mark T.M.T. bars Fe 415/ Fe 500 reinforcement for
R.C.C. work including bending, binding and placing in position
36 complete for Forth Floor 1471.07 Kg

Brick work using common burnt clay building bricks havingcrushing


strength not less than 35 kg./Sq.Cm. in foundationand plinth in
Cement Mortar 1:5. (1‐ Cement : 5 ‐finesand)(C) Fly Ash Bricks
37 (more than 10 ton) (a) Conventional .For foundation and plinth 1407.494 Cmt.

5
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

Brick work using common burnt clay building bricks havingcrushing


strength not less than 35 kg./Sq.Cm. in foundationand plinth in
Cement Mortar 1:5. (1‐ Cement : 5 ‐finesand)(C) Fly Ash Bricks
(more than 10 ton)(a) Conventional in super structure above
38 plinth to floor two level i.e for GF &FF 1566.38 Cmt.
Brick work using common burnt clay building bricks
havingcrushing strength not less than 35 kg./Sq.Cm. in
foundationand plinth in Cement Mortar 1:5. (1‐ Cement : 5
‐finesand)(C) Fly Ash Bricks (more than 10 ton) (a) Conventional ‐ ‐
39 ‐ for Second Floor 635.77 Cmt.

Brick work using common burnt clay building bricks havingcrushing


strength not less than 35 kg./Sq.Cm. in foundationand plinth in
Cement Mortar 1:5. (1‐ Cement : 5 ‐finesand)(C) Fly Ash Bricks
40 (more than 10 ton) (a) Conventional ‐ ‐‐ for Third Floor 325.85 cmt

Brick work using common burnt clay building bricks havingcrushing


strength not less than 35 kg./Sq.Cm. in foundationand plinth in
Cement Mortar 1:5. (1‐ Cement : 5 ‐finesand)(C) Fly Ash Bricks
41 (more than 10 ton) (a) Conventional ‐ ‐‐ for Forth Floor 45.27 cmt

(i) Half brick masonry in common brunt clay buildingbricks having


crushing strength not less than 35 Kg/Sq.Cm.in Cement mortar 1:4
(1‐ Cement : 4 ‐coarse sand )(C)Fly Ash Bricks (more than 10
42 ton).in super structure above plinth to floor two level 1501.53 Smt
(i) Half brick masonry in common brunt clay buildingbricks having
crushing strength not less than 35 Kg/Sq.Cm.in Cement mortar 1:4
(1‐ Cement : 4 ‐coarse sand )(C)Fly Ash Bricks (more than 10 ton)
43 .in super structure For Second floor 280.49 Smt

6
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

Providing and fixing 35mm thick flush door shutters , solid core
construction with frame of first class hard wood with cross band
and face veneer or plywood face panels and wood polished Teak
wood beading to door shutter iron plug screws plugs and priming
coat on unexposed surface and laminated with 1.5 mm thick high
pressure laminated Sheet of Plain / Wood Grain in Gloss/ Matt
finish with high density protective Surface layer and reverse side
of adhesive bonding quality confirming to IS 2046 including cost of
Adhesive of appoved quality and with C P Brass fixturesand
fastenings ( Hinges, handles, secrews,Aldrop and latches etc of
approved make)and providing and fixing in 40x40x6 mm MS
Angle section frame with 15cm long hold fast of 20x5mm 6 nos
and 12mm square spacer bars as per drawing with three coats of
44 oil painting . etc complete. 550.69 Smt

Providing and fixing FRP frame size 100 x 50 mm and 28 mm thick


FRP shutter with depressed panel SHUTTER having extra
reinforcement on sides and edges and in GEL coat finish. The core
of shutter is to be filled up with injected fiber extinguishing grade
polyurethane foam done in situ along with embedded wooden
pieces for stiffening and also for taking hinges and fixtures. The
whole FRP frame and shutter is to be water proof, weatherproof,
termite proof and resistance to mild acid / Alkali resistance
including S.S. hinges with necessary screws and aluminum fixtures
and fastening.Products should have 3 years performance
45 gyarantee and company have ISO9001‐2000 certificate. 298.04 Sqm

7
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

Providing and Fixing windows having extruded aluminium colour


powdered coated section frame main outer size 95mm x 24mm x
1.17mm (of Jindal Section No.2459 @ wt of 0.738 kg/mt)
horizontal Three Track member size 92mm x 31.75mm x 1.3mm
(of Jindal Section No. 8688 @ wt. 1.07 kg/mt) vertical member of
size 92mm x 31.75mm x 1.50mm (of Jindal Section No. 8933 @ wt.
1.06kg/mt ) with sliding shutters of horizontal memeber size
40mm x 18mm x 1.29mm (of Jindal Section No. 8947 @ wt. of
0.456 kg/mt) vrtical member of size 40 mm x 18 mm x 1.29 mm (of
Jindal Section No. 8949 @ wt of 0.456 kg/mt ) with 5 mm thick
transparent bronze colour tinted float glass with powder
coated/colour anodized alumunium fittings and fixtures and
46 transparent silicon sealant glass fixing to frame as per details etc. 479.88 Smt

Providing and Fixing windows having extruded aluminium colour


powdered coated section frame main outer size 63.50mm x
38.10mm x 1.95mm (of Jindal Section No.4605 @ wt of 1.094
kg/mt) horizontal Two Track member size61.85mm x 31.75mm x
1.2 mm (of Jindal Section No. 8687 @ wt. 0.695 kg/mt) vertical
member of size 61.85 mm x 31.75mm x 1.30mm (of Jindal Section
No. 8758 @ wt. 0.659 kg/mt ) with sliding shutters of horizontal
memeber size 40mm x 18mm x 1.29mm (of Jindal Section No.
8949 @ wt. of 0.456 kg/mt) ,vertical member of size 40 mm x 18
mm x 1.29 mm (os jindal Section No.8948 @ wt. 0.456 kg/mt
/Section No. 8948 @ wt. 0.457 kg /mt with 5 mm thick transparent
bronze colour tinted float glass with powder coated/colour
anodized alumunium fittings and fixtures and transparent silicon
47 sealant glass fixing to frame as per details etc. 561.37 Smt

8
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

Providing and fixing standared extruded of alluminium section of


size 63.50 x 38.10 x 1.95 mm(of Jindal Section no:4605, @ Wt
1.094Kg / Rmt with colour Powder Coated alluminium frame with
5 mm thick transparent bronze colour tinted float glass with
powder coated/colour anodized alluminium frame for ventilation
with 5 mm thick frosted glass as details etc complete for.window
48 Design As Per Architectural Drawing 105.67 Smt

Providing & Fixing of standard extruded of alluminium section of


size 63.50 mm x 38.10 mm x 1.95 mm (Jindal Section No.4605 @
wt. 1.094 kg per mt ) with powder coated/colour anodized
alluminium frame with 5 mm thick transparent bronze colour
49 tinted float glass as per deatils etc complete for Fixed Windows. 802.98 Smt

Providing and fixing Expansion joints, SILFLEX/Capcell HD100


Supreme or equivalent (Polyurethane foam filler) of the best
quality, including in all shapes and all levels etc. and filling the
expansion joints for 25mm width & 12mm depth, with
polysulphide sealant with application of primer including
scraping/removing the expansion filler materials from joints,
cleaning, repairing of the edges with epoxy mortar of approved
color and make, fixing of abrotapes on the edges to prevent the
50 adjoining surface, etc. complete as directed by Engineer‐in‐Charge 79.04 Smt

Providing and fixing M.S grills or railing of required pattern to


window gapes and terrace railing with M.S sections at required
spacingsa and frame alround, square or round bars with round
headed boltsand nuts or screws or M.S hold fast including of one
51 coat of primer with two coats of oilpainting etc complete. 42203.95 Kg.

9
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

Providing 20 mm thick double coat mala cement plaster on


interior brick/ concrete work for plastering comprising of base
coat of 12 mm thick cement plaster in cement mortar (1 Cement :
4 coarse sand) in rough finishing and 8 mm thick top coat of
cement mortar 1:2 ( 1 Cement : 2 coarse sand) finished with trovel
52 including scaffolding curing etc. complete. for Floor to level 13260.17 Smt

Providing 20 mm thick double coat mala cement plaster on


interior brick/ concrete work for plastering comprising of base
coat of 12 mm thick cement plaster in cement mortar (1 Cement :
4 coarse sand) in rough finishing and 8 mm thick top coat of
cement mortar 1:2 ( 1 Cement : 2 coarse sand) finished with trovel
53 including scaffolding curing etc. complete. for Second floor 4778.94 Smt

Providing 20 mm thick double coat mala cement plaster on


interior brick/ concrete work for plastering comprising of base
coat of 12 mm thick cement plaster in cement mortar (1 Cement :
4 coarse sand) in rough finishing and 8 mm thick top coat of
cement mortar 1:2 ( 1 Cement : 2 coarse sand) finished with trovel
54 including scaffolding curing etc. complete. for THird floor 1574.01 Smt

Providing 20 mm thick double coat mala cement plaster on


interior brick/ concrete work for plastering comprising of base
coat of 12 mm thick cement plaster in cement mortar (1 Cement :
4 coarse sand) in rough finishing and 8 mm thick top coat of
cement mortar 1:2 ( 1 Cement : 2 coarse sand) finished with trovel
55 including scaffolding curing etc. complete. for Forth floor 201.92 Smt

20 MM thick sand faced cement plaster on walls upto height 10


Mts aboveground level consisting of 12 MM thick backing of coat
CM 1:3 (1 cement : 3 sand ) and 8 MM thick finishing coat of CM
56 1:1 (1 cement : 1 sand ) etc. complete Gutka Finish 3153.59 Smt

10
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

Providing 10mm thick cement plaster in single coat for


plastering on ceilings and soffits of stairs and finish even and
smooth in C M 1:4 (1 cement 4 coarse sand) for up to floor
57 two level 10157.86 Smt
Providing 10mm thick cement plaster in single coat for
plastering on ceilings and soffits of stairs and finish even and
smooth in C M 1:4 (1 cement 4 coarse sand) for above
58 floor two level‐i.e For Second Floor 3705.9 Smt
Providing 10mm thick cement plaster in single coat for
plastering on ceilings and soffits of stairs and finish even and
smooth in C M 1:4 (1 cement 4 coarse sand) for above
59 floor two level‐i.e For Third Floor 293.71 Smt

Providing and Fixing heritage flakes texture homogenous wall


finishing system from bankelite hylam ltd consisting of two
component of dry flakes(9.5 kg pr pack)made of special grade of
heat treated china clay with rigid homopolymer bonding agent (5
kg per pack) with the applied thickness of the coating between
0.80mm ti 1.2 mm to be applied on cured smooth level plaster
without keying as per the sades/combination approved as per the
manufature directions/ supervision of the etc.The above texture
coating should confirm to surface spred of flam class one of BS475
part 1971 and pull off strength of coating of meet JISA6909(all
floors) including 20mm thick double coat gutka finished cement
plaster on wall up to height 36mt above ground level consisting of
15 mm thick backing coat in cement mortar 1:4 (1 cement : 4
sand) and 6 mmm thick finishing coat of in cement mortar 1:1 (1
60 cement :1 sand) etc completed. 8082.24 Smt

11
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

Providing & applying Wall painting with ( Two Coats) with Plastic
Emulsion Paint of Approved brand and manufacture on
undecorated wall surface to give an even shade including
thoroughly brushing the surface free from mortar dropping and
other foreign matter and making smooth by levelling the surface
with approved wall putty ( Birla or Equivalent), applying one coat
of primer & then applying two coats of plastic emulsion paint.
Cost should be inclusive of supply & application of Putty & Primer
, scaffolding , remove the dirt, making the surface clean etc.
61 completed. 33972.42 Smt

Wall painting with weather proof acrylic emulsion APEX type paint
of approved brand & manufacturer and of required shade of
exterior wall surface to give an even shade over and including a
priming coat of approved brand after thoroughly brushing the
surface to remove all dirt and remains of loose powdered material
62 etc. complete for all heights. 6914.59 smt
Providing throating of plaster drip and moulding(Tapak) to RCC
63 chajjas and slab projections 1655.72 Rmt
Providing & Making 10 mm wide and 8 mm deep evenly smooth
finished Groove in External Plaster as per drawing & instructions
given by Engineer in charge including cost of scaffolding etc.
64 Completed, 5538.42 Rmt

Providing & Making 75 mm wide and 8 mm deep evenly smooth


finished Groove patta in External Plaster as per drawing &
instructions given by Engineer in charge including cost of
65 scaffolding etc. Completed, 813.75 Rmt

Providing & fixing 15 cm wide chicken mesh jali with nails & then
application of 15 mm plaster on R.C.C. & masonary joints as per
66 dir. of engg. In charge. 10674.68 Rmt

12
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

Filling in sunken portion of toilet units & chajjas over windows


with brick batsof small size(less than 20 mm )/Chhara filling under
floors including watering ramming, consolidating and dressing
67 complete 353.07 cum

P & L 24" x 24" vitrified 8 mm thick tile flooring and skirting over
20 mm (average) base of cement mortar 1:6 ( 1 cement: 6 coarse
sand) on new surface or fixing on existing flooring by adhesive
material including dismentaling of existing flooring and jointed
with color cement slurry including finised with flush pointing &
68 cleaning the surface etc. complete for antiskit (more than 10 ton) 7610.8 Sqm

Providing & Laying Chequered Precast cement concrete tiles of 22


mm thick with aggregate sizes up to 6mm laid on floors, treads of
steps, and landing on 20mm thick bed of cement mortar 1:6 ( 1
cement : 6 Coarse sand ) jointed with neat cement slurry with
69 pigment to match the shade of tiles complete 267.56 Smt
Providing and laying Kota stone slab flooring over 20mm( avrage
thick base of cement mortar 1:6(1cement : 6 coarse sand) or
L.M.lime mortar 1:1.5 laid over and jointed with grey cement
including Chiseling rubbing and polishing etc. complete.‐‐‐25m.m
70 thick. ‐‐ 2432.02 Smt
Providing and laying Kota stone slab 25 mm thick in risers and
steps of steps, dedo and pillars laid on 10 mm thick cement mortar
1:3 (1Cement :3 Coarsesand) and jointed with grey cement slury
71 including rubbing and polishing etc complete. 161.39 Smt
Providing and laying Ceramic Tiles 6 mm to 8 mm thick in
flooring ,treads, of steps & landing laid on a bed of 12 mm thich
Cement Mortor 1:3(1Cement : 3 Coarse sand) finished with flush
72 pointing in white cement. 928.02 Smt

13
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

Providing and laying Ceramic Tiles 6 mm to 8 mm thick in skirting,


risers of steps and dedo laid on 10 mm thick cenent plaster
Cement Mortor 1:3(1Cement : 3 Coarse sand) and jointed with
73 white cement . 3563.14 Smt

Providing and lying cement based waterproofing on roofs with a


minimum slope of 1:100 and average thickness of 100 mm using
brickbats of appropriate size and shape suitable to achive the
required slope laid over 15mm thick waterproof cement mortar
1:4 on well prepared/cleaned RC roofs with joints between
brickbats thoroughly grouted with waterproof cement mortar 1:4
and finished with 20 mm thick waterproof. plaster using cement
mortar 1:4 and making false squares of 300 mm size including
rounding of the junction of roof and parapet walls for a height of
300 mmm with brickbats nd 20mm thick waterproof plaster and
counducting necessary leakage/dampness tests, furnishing ten
years guarantee etc. all complete as directed.(waterproofing
admixures shall be of approved quality and dosage as
recommended by the manufacture ‐ Plastcone AW PLUS)
Providing &laying the flooring of broken china‐mosaic (brocken
pieces of china glazed tiles)white set in 25 mm, average bed of
cement mortar 1:3 with waterproofing compound to correct level
and slope(1:100) well compacted and finished; such that minimum
coverage of china mosaic chips is about 90% of the total area of
slab.the above treatment shall continue along the inner side of
parapet or the adjioining wall upto 30cm. height as per the above
specification.. Special Agency to be occupied and Warrenty Of 10
year . 100rs Bond paper to be submit by Contractor. and on latter
74 head Submitted By Executed Agency 5056.34 Smt

14
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

Providing and Laying Cement Concrete Flooring 1:2:4 ( 1‐Cement,


2 Coarse Sand, 4 Graded Stone Aggregate 20 mm Nominal size )
laid in one layer finish with Floating Coat of neat cement (B)
75 50mm thick 781.07 Smt

Providing and applying water proofing for toilets with veritcal


walls of toilet and sunck portion all inculsive(bbc, IPS,grouting)
with 2 coats two components acrylic polymer modified
elastomeric cementitious water proof membrane coating
(polycoat BB) on depressed/sunken slabs which shall be mixed as
per manufacture's technical specification, after throughly cleaning
the surface by mechanical means to making it free of any loose
mortar, unsound substrate, "v" grooves cut along the construction
joints, cracks and joints of slab /wall on the external face and same
shall be filled with polymermodified mortar (CM 1:3 mixed with
approved water proofing compound (platcone AW Plus)in the
praportion recommended by the manufactures, cracks in the slab
(if any), pressure grouting pump with a pressure of 3 to 4 kg/sqm,
strictly maintaing the coverage specified by the manufacture ,
application of 20 mm thick plaster with water proofing compound
(AW Plus) in cement mortar 1:4 over the water proofing
treatment.including cost . Special Agency to be occupied and
Warrenty Of 05 year . Bond paper to be submit by Executed
76 Agency and Contractor. 1738.55 Smt
Constructing a cooking platform with fixing black granite stone
20mm thick laid on Polished Kota Stone , Provision of Polished
Kota Stone Shelf and Sandwich Polished kota stone Support as per
Drawing inclu ding rubbing Polishing and Making the surface level
77 and Clean etc. Completed 302.66 Smt
Providing and Laying of Window Sill & Jambs of Keshariyaji Green
Marble of 20 mm thickness as per instructions by Architect or
78 Engineer ‐ in ‐ Charge 2291.12 Smt

15
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

Steel work welded in built up sections framed work including


cutting, hoisting, fixing in position and applying a priper coat of red
lead paint (A) In beams, joist,channels,angles,Tees,flats with
connectiong plates or angles cleatsetc for fabrication and
errection of Main gate including M S hold fast and locking
arrengments complete including painting with two coats of
synthetic enamel paint, brushing to give an even shade including
79 cleaning the surface of all dirt and other foreign matter. 43951.9 Kg.
Providing and laying Granite Slab 18 mm thick in flooring ,treads of
steps and landing laid on a bed of 12 mm thick cement mortar 1 :6
(1 cement :6 coarse sand) finished with flus pointing in white or
80 colour cement. 1212.19 Sqmt
Providing & Fixing Colored SHERA PLANK on Extirier or interier
wall.Rate includes fixing plank with nail / screw Flushing with plank
surface.Rate also include all labour and scafolding etc complete as
81 per architect instruction. 262.5 Sqm

Providing and Laying Precast difference size and pattern Blocks


using M‐250 Graded Concrete without Reinforcement having
minimum 250 kg/Sq.cm Crushing Strenth ,in Super structure in
Cement Mortar Cement mortar 1:2 (1 Cement : 2 sand) including
poring cement slurry at junction of block in Cement Mortar 1:1 (1
Cement : 1 Water), including water proofing cement paint of
different colour on it for Exteriour building works which includes
all labour, tools, takel. Equipment, required scaffolding and
machinery. , Shape and Size and Dimension of Precat Block as
82 Directer by Architect and Engineer In Charge. 969.45 Sqm

16
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

Providing and laying Expose Brick work using common burnt clay
building brick size 220X75X21 mm thick having crushing strength
not less than 35 kg/sq.cm. in superstructure in Cement mortar 1:4
(1 Cement : 4 fine sand) including groove 10mm in Cement mortar
and including 10mm groove pointing with Cement mortar 1:2 (1
Cement : 2 sand) and including Fixoplus Cladding Epoxy Adhesive
in proposaion of 1:3.5 (1Liter water : 3.5Kg Adhesive) in with all
floor (B) Conventional with all labor, tools, takel. Equipment,
required scaffolding and machinery laid on 12 mm thick cenent
83 plaster Cement Mortor 1:3(1Cement : 3 Coarse sand). 1787.51 Sqm

Providing & Fixing in true horizonts llevel 600mm x 600mm false


ceiling system using hot dipped galvanised steel section, exposed
surface with pre coated cappping, main tee of size 24x32 mm,
having 0.27 gauge at every 1200mmcentre to centre maximum &
rotary stitched cross tee of size 24mm x 27 mm, having 0.27mm
gauge at every 600mm c/c.and sub cross tee of size 24 x 27mm,
having 0.25mm gauge at 1200mm c/c.and wall angle of sized
19mm x 19mm, having 35mm gauge fixed to periphery of the wall.
The above grid is suspended at every 1200mm c/c. in both
directions using 2.0mm thick pre‐straightened GI wire laying
ceiling tiles of size 600mmx600mmx15mm having NRC 0.55, Light
refectance of 84% (WT), thermal conductivity k=0.052‐0.057
W/mOk, Humidity Resistance of 99%, having Fire Performance
CLASS 0/ClASS 1 (BS476), surfacehaving 3 coats of white paint with
Fine Fissured, back of the tile duly sanded andfinished with a coat
of protective paint over the formed grid complete item inclusive of
all level all equipmernt all material which is not mention and
84 required. 835.16 Sqm

17
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

Providing and fixing rolling shutters of approved makemade of 80


mm wide M.S. laths inter‐locked togetherthrough their entire
length and jointed together at theends by end locks mounted on
specially designed pipeshaft with bracket plates, guide channels
and arragementsfor inside and outside locking with push‐pull
operationincluding the cost of hood cover and spring etc.
85 complete. A) Shutters having width below 3.5 M. 3.21 Sqm

Grassing with selection of No.1 grass with 20c.m bedding of Good


soil and Manure etc.levelling ,watering and maintaining of the
lawn till the grass forms athick lawn,free from weeds and fit for
moving including supplying spreding ,watering ,levelling of mixture
86 of good earth and manure and maintain for 180 days 6700 Sq.mt

Digging Holes in ordinary soil and refelling the same with


excavated earth mixed with manure in the ratio of 2:1 by volum (2
part of stacked volume of earth :1 part of stacked volume of
manure flooding with water, dressing including removal of
rubbish and surpluus earth,if any,with all leads and lifts....Holes
87 1mt dia and 1.2mt. Deep 236 No .
Supplying & planting best quality trees inclusive of cultivation of
trees nead to required depth .All trees/plants to be approved
before planting including watering & maintainance for 180 days.
88 Fox Tail Palm‐3 mt in height 16 No .
Supplying & planting best quality trees inclusive of cultivation of
trees nead to required depth .All trees/plants to be approved
before planting including watering & maintainance for 180 days.
89 Erica Palm‐1.5mt in height 12 No .
Supplying & planting best quality trees inclusive of cultivation of
trees nead to required depth .All trees/plants to be approved
before planting including watering & maintainance for 180 days.
90 Latania Palm‐1.5mt in height 12 No .

18
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

Supplying & planting best quality trees inclusive of cultivation of


trees nead to required depth .All trees/plants to be approved
before planting including watering & maintainance for 180 days.
91 Ficus‐1mt in height 12 No .
Supplying & planting best quality trees inclusive of cultivation of
trees nead to required depth .All trees/plants to be approved
before planting including watering & maintainance for 180 days.
92 Pectinata Cucas‐1 mt in height 12 No .
Supplying & planting best quality trees inclusive of cultivation of
trees nead to required depth .All trees/plants to be approved
before planting including watering & maintainance for 180 days.
93 Bambo‐2 mt in height 12 No .
Supplying & planting best quality trees inclusive of cultivation of
trees nead to required depth .All trees/plants to be approved
before planting including watering & maintainance for 180 days.
94 Raphis Palm‐ 0.6mt in height 30 No .
Supplying & planting best quality trees inclusive of cultivation of
trees nead to required depth .All trees/plants to be approved
before planting including watering & maintainance for 180 days.
95 Limdo‐3mt in height 50 No .
Supplying & planting best quality trees inclusive of cultivation of
trees nead to required depth .All trees/plants to be approved
before planting including watering & maintainance for 180 days.
96 Asopalav‐3mt in height 50 No .
Supplying & planting best quality trees inclusive of cultivation of
trees nead to required depth .All trees/plants to be approved
before planting including watering & maintainance for 180 days.
97 Champo‐3mt in height 10 No .
Supplying & planting best quality shrubs inclusive of cultivation of
shrubs nead to required depth .All shrubs to be approved before
planting including watering & maintainance for 180 days. Mehdi
98 Red 2000 No .

19
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

Supplying & planting best quality shrubs inclusive of cultivation of


shrubs nead to required depth .All shrubs to be approved before
planting including watering & maintainance for 180 days. Mehdi
99 Green 2000 No .
Supplying & planting best quality shrubs inclusive of cultivation of
shrubs nead to required depth .All shrubs to be approved before
planting including watering & maintainance for 180 days. Mehdi
100 White 2000 No .

Supplying & planting best quality shrubs inclusive of cultivation of


shrubs nead to required depth .All shrubs to be approved before
101 planting including watering & maintainance for 180 days. Duranta 2000 No .
Supplying & planting best quality shrubs inclusive of cultivation of
shrubs nead to required depth .All shrubs to be approved before
planting including watering & maintainance for 180 days. Mor
102 Pankhi 2000 No .
Supplying & planting best quality shrubs inclusive of cultivation of
shrubs nead to required depth .All shrubs to be approved before
planting including watering & maintainance for 180 days.
103 Eranthimum 50 No .
Supplying & planting best quality shrubs inclusive of cultivation of
shrubs nead to required depth .All shrubs to be approved before
planting including watering & maintainance for 180 days. Citrasia
104 purple 100 No .
Supplying & planting best quality shrubs inclusive of cultivation of
shrubs nead to required depth .All shrubs to be approved before
planting including watering & maintainance for 180 days. Tincasia
105 Green 100 No .

Supplying & planting best quality shrubs inclusive of cultivation of


shrubs nead to required depth .All shrubs to be approved before
106 planting including watering & maintainance for 180 days. Canna 50 No .

20
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

Earthwork for embankment including breaking clods,dressing with


all lead and lift and including watering rolling and consolidation of
filled up area in layers at O.M.C to required dry density including
filling the depression which occur during the process using power
107 roller(E) From borrow area within 3 Km 5669.52 Cum
Earthwork in cutting including preparing the slope and camber and
stacking or utilising the cutting stuff in bank as directed upto 200
Meters from the end of cutting with all lead and lift.(i) Hard
108 murrum 1801 Cum
Supplying & stacking of crushed stone aggregate ,chipping etc .of
hard stone of following nomonal size free of disintigrated pieces.
Detetarious and organic matter and grading as per IRC code…..40
109 to 63 mm size 321.34 Cum
Supplying & stacking of crushed stone aggregate ,chipping etc .of
hard stone of following nomonal size free of disintigrated pieces.
Detetarious and organic matter and grading as per IRC code…40
110 to 20 mm size 321.34 Cum
111 Supply and stacking of of selected murrum at site 531.4 Cum
Spreading the stone aggregate for solling and WBM including
filling the interstics forming the surface to required camber and
gradient ‐‐ in two layer ‐‐...(a) 40 mm to 63 mm size aggregate
112 (H.B.) 321.34 Cum
Spreading the stone aggregate for solling and WBM including
filling the interstics forming the surface to required camber and
113 gradient ‐‐ in two layer …40 to 20 mm size 321.34 Cum
Spreading of blindage on road crush filling the gaps in metal &
114 levelling to camber and gradient 531.4 Cum
Rolling and cosolidation of solling including filling in depressions
which occurs during the process with power roller 8 tonne to 12
115 tonne 4400 Sqm

21
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

Providing and laying controlled cement concrete M 25 and


curing complete including the cost of formwork and excluding cost
of reinforcement for reinforce concrete work in a) Foundations,
116 Footings, base of columns and mass concrete 330 Cum

Providing expansion joint in RCC road slab including requried


material & labour & filling the 80/100 grade ashphalt/bitumen
including heating filling in joint cleaning the joint before filling with
117 Ashphalt\bitumen finishing smooth at top etc. complete 66 Rmt
Applying vaccum dewatering procdure to RCC Road slab flooring
by using vibrating scred, vaccum pump, suction mat, filter pads &
118 other requied accessories 2200 Sqm
119 Longitudinal Joint 10mm x 25mm cutting 200 Rmt
120 Contraction Joint 10 mm x 6 mm Cutting 35 Rmt

Providing and fixing pre cast Rubber dye interlocking concrete


block 60 mm thick with grade of Concrete M‐250 pnumatic
compressed by Mechanicallly pressed and as per approved design
including 75 mm sand layer for leveling and filling the joints with
121 sand in proper line and level etc complete. 6552 Sqm
Providing and fixing Pre cast curb stone of grey cement based
concrete block of 30 cms in length , 30 cms fheight and 15 cms
thick of M250 grade concrete a per approved design and including
excavation for fixing in proper line and level, filling in joints with
122 C.M 1:3( cement : 3Sand) etc complete. 840 Rmt

Providing and laying rough chiseled dressed stone flooringover


20mm average thick base of cement mortar 1:5 (1‐Cement :
5‐coarse sand) or L.M. 1:1.5 (1‐Lime putty : 1.5 ‐coarse sand)
including pointing with cement mortar 1:2 (1‐cement : 2‐stone
123 dust) etc. complete. (A) 25mm thick(upto 10 ton) 105 Smt

22
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

Providing and fixing Rajula stone 75mm thick 60mm x 45mm size
124 including fixing in cement mortar as directed. 105 Smt

20 mm thick Kundla Grey stone Flooring for Planter,Toe wall of


parking etc with Fine or River wash polished and all edges are
moulded and fine polished and also groove making as per drawing
and detail by Architect etc completed including ordinary cement
and joints are fiiled uo with same colour pigment mix with white
125 cement. 105 Smt
Glow Sign Board : 8'' inch depth with 1''X 1'' M.S. pipe structre
joind with gas welding, Inside Box ISI Marking Electical Parts
(Tube,Choke) Like Surya,Wipro,Philips Etc, All Side Black Powder
Coation All Side G.I.Sheet, Background With G.I. Sheet, 4pass Star
126 Slovent Base Flex Printing With Mounting . 65.562 Sqmt
Painting lines, deashes, arrows, letters etc on roads, Walls,
Floorings , Air fields and like in one coats with Oil paint, brushing
including cleaning the surface of all dirt, dust and other foreign
127 matter. , Design AS per Architectural Drawings 220 Sqmt
Name Plates:3mm Foam Sheet With Vinyl Printing Sticker Or
Vinyle Cutting Letter As Per Your Required White Background &
128 White Letter 19.8 Sqmt

Providing and laying Yellow Kota stone slab flooring over 20mm(
avrage thick base of cement mortar 1:6(1cement : 6 coarse sand)
or L.M.lime mortar 1:1.5 laid over and jointed with grey cement
129 including rubbing and polishing etc. complete.‐‐‐30m.m thick. ‐‐ 525 Cum

23
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

Providing and Fixing 0.60 mt high fencing with 0.75 mt long M.S
Angle posts of 40 x 40 x 6 mm size including oilpainting 3 coats
fixed at about 3.0 mt c/c with four Horizontal lines and two
diagonals of Galvanized steel barbered wire weighing 9.38 kg per
100 mt strained and fixed to posts with G.I.staples including fixing
the post in existing R C C/Masonry cloumns in line and levels etc
complete.including providing and fixing brocken glass pieces on
130 the top surface of compound wall with cement mortar CM(1:3) 682.5 Rmt

Providing and laying controlled cement concrete M.250 and


curing complete excluding the cost of formwork and
reinforcement for reinforced concrete work in (B) Walls, from top
131 of foundation level upto floor two level (more than 10 ton) 363.25 Cmt.

24
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

RCC ESR ( description of item for turnkey tender) designing


structurally (and aesthetically) complying provisions of relevant
Indian standards and constructing RCC Elevated service Reservoir
of the following capacity and height , using data of S.B.C of
proposed site , Seismic zone, Wind speed Zone.Including (1)
Container shape any suitable type(or as specified), (2) Staging
consisting of column brace trestle / shaft / combination column‐
brace trestle and shaft as appropriate(or as specified) and (3)
Appropriate foundation system. This includes excavation in all
types of soil strata (including hard rock ), casting100 mm thick
P.C.C. levelling course in M‐10 , Refilling the pit with proper soil
and disposing of the surplus stuff within a lead of 50 meters. (4)
This will also include cement plaster in CM 1:2 with approved
water proofing compound to inside face of container. (5) All types
of labour & material charges of lowering , laying, erecting /
hoisting & joining of pipe assembly of Inlet, Outlet
overflow,washout and bye pass arrangement as per hydraulic
design are including. (6) Providing and fixing
accessories(specified) like MS / GI Ladder CIManhole frame and GI
Pipe railing around walk way, at roof level, at gallery and around
landing of inside shaft, Adequate cowl type ventilators or lantern
type ventilator with stainless steel jali. (7) Scope of work includes
constructing RCC spiral staircase with adequate tie beams
,staircase footing ,B.B. Masonry chambers for valves. ventilating
shaft and ventilators as well as door in shaft .(8) including
providing and applying three coats of cement paint/snowcem (as
specified) to the whole structure. (9) It also includes satisfactory
water tightness test as per relevant I.S. Code and painting name of
scheme & capacity on the tank as per direction of engineer in
charge.List of Indian Standards for design of ESR: Note:The
structural design of ESR shall be in accordance with provisions of
relevant Indian Standards (1) I.S. 3370 part I & II 2009 or latest
revised (1.1) I.S. 3370 part III & IV 1965 or latest revised (2) IS 456‐
2000 or latest revised (3) IS 11682‐ 1985 or latest revised (4) IS
1893‐2002 part I to V or latest revised (5) IS 13920‐1993, or latest
revised (6) IS 875 part I to III,1987 or latest revised (7) IS 11089‐
132 1987 or latest revised General specifications: (1) The Min. 1 No

25
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

concrete grade for RCC shall be M :30. Proportion of concrete


ingredients shall be as per Mix design using weigh batching. (2)
HYSD( Fe 415)or higher grade reinforcing bars confirming to IS
1786/1139 or CRS /TMT bars shall be used as per detailed
specification.(3) Incase of column –brace trestle type staging
having more than 6 columns internal horizontal bracing is
obligatory. One bracing shall be at foundation level incase of
Individual footings.(4) Min. size/ thickness of various components
shall be provided as per design criteria/specifications ( or as per
std. practice ) . (5) Minimum dimensions specified for various
components in tender data /specifications shall be provided
without fail. (6) The Safe bearing capacity (SBC) /allowable
pressure on soil shall be referred from SBC test report or tender
datasheet. If poor soil strata is met with or ground water table is
met with ,the SBC shall have to be reascertained scientifically and
the design shall be revised. (7) Maximum spacing between
horizontal bracings shall be 5 m(storey height (8) The BB Masonry
cabin with MS door shall be constructed when spiral staircase is
outside the staging. (9) M.S. ladder shall be provided and fixed for
access to roof when height of roof from G.L. is up to 10 m. For ESR
having more than 10 m height RCC spiral staircase or suitable RC
staircase shall be constructed (10) For ESR‐having staging height
more than 15 m the spiral staircase shall be provided inside the
staging with effective tie beams in more than one direction.(11)
Water level indictor shall be provided and fixed float type
/electronic (as specified ).(12) The rate shall include providing and
fixing pipes, specials, and valves required for inlet, outlet , wash
out, over flow and bye pass arrangement. The scope of work
includes constructing supporting RC pillars, erecting, laying ,fixing
and joining pipes and specials etc up to 5m length from face of
staging (outer most column). (13) CI pipes & specials shall only be
used .(14) The rate shall include cost of dewatering during
execution making all arrangement and any dewatering
technic.(15) The structure shall be designed properly for uplift due
to Ground water table specified in data or GWT met with during
execution. No extra shall be paid.(16) Effective curing shall be
carried out as per specifications.(17) Agency shall engage qualified

26
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

(at least graduate)consulting engineer for designing the structure


and he/she shall visit the site for guidance of work at least 3 times
. (18) 75 % part rate shall be payable for Concrete, Reinforcement
and Plastering items of container until satisfactory hydraulic
testing for water tightness is performed as per tender condition .
Till then the work shall be treated as incomplete. Above conditions
/ general specifications Sr. No. 1 to 17arepart & parcel of
tender(contract) . G W S & S Board SOR‐2011‐12‐ Section ‐ D
I.No.26 P.No.81(A) Upto stagging height(L.S.L.) 12m from G.L. and
S.B.C.10)Capacity of ESRs (shell type container like cylindrical,
conical, intze, folded plates & its combination) Seismic Zone ‐ III,5.
Cost of 50,000 litre capacity

(B) Extra stagging height above 12 mt onward for each 1000 liter
per meter height Esr of 50,000 Litres capacity & 20 mt Hight(3).
133 Above 25000 to 50000 liters 10 Stage

27
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

Preparing structural design of RCC Under Ground / Partially under


ground / above high ground level Reservoir of required capacity as
per relevant I.S. standards and constructing the same, including
excavation in all types of soil strata (including rock) including
shoring strutting if required, for loose soil / to protect from
collapse, casting 100 mm thick P.C.C. levelling course in M‐ 15,
Refilling the pit with proper soil and disposing of the surplus stuff
at all lead. Including cement plaster in CM 1:2 with approved
water proofing compound to all over inside container (i.e. walls,
base, top slab/dome bottom etc. all). Including all types of labour
and material charges of lowering, laying, erecting / hosting and
jointing of pipe assembly to inlet, outlet overflow, washout and
bye pass arrangement as per hydraulic design. Providing and fixing
accessories, CI Manhole frame and cover, water level indicator,
adequate cowl type ventilators or lantern type ventilator with
stainless steel jail. RCC chambers for valves.Providing and applying
three coats of cement paint / snowcem to the out side face of
structure. It also includes satisfactory water tightness test as per
relevant I.S. code and painting name of scheme and capacity on
the tank as per direction of engineer in charge. List of Indian
Standards for Design of GSR / SUMP:‐The structural design of GSR
shall be in accordance with provisions relevant I.S standards (1) I.S.
3370 part I & II 2009 or Its latest revision (1.1) I.S. 3370 part III & IV
1965 or Its latest revision (2) I.S. 456 – 2000 or Its latest revision.
(3) I.S. 1893 – 2000 – 1984 or Its latest revision. (4) I.S. 875, Part –
1 to 3, 1987 or Its latest revision. General Specifications:‐ (1)
Water depth in container shall be adopted as per data of tender.
Capacity shall be calculated excluding free board of the reservoir.
If water depth is not specified, the suitable water depth /
acceptable to field engineer in accordance with hydraulic
requirement (2) Shape of Container (in Plan) or Specified By in
data shall be adopted in absence circular shape shall be
adopted.(3) Size shall be fixed as per availability of space (land
area) at site / acceptable engineer in charge. (4) Effect of
overlapping of pressure bulbs on soil due near by structure and
proposed sump should be considered. (5) Care shall be taken that
134 no damage should occur to nearby existing structure. 1 no

28
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

Compensation shall be paid for the same by agency. (6) The


minimum concrete grade for RCC shall be M‐30. (7) HYSD Fe 415 /
500 grade reinforcing bars confirming to I.S. 1786 / 1139 shall be
considered in design. CRS / TMT bars shall be provided. In saline
atmosphere corrosion resistance stainless steel / HCR rebar shall
be provided. Any other steel can be used with approval of C.E./ in
situation of non availability in market without extra cost. (8)
Minimum size (or thickness) of various components shall be
provided as per tender criteria / specifications in absence as per
I.S./ Std. practice of G.W.S.S.B. Minimum dimensions specified for
various components in tender data / specifications shall be
provided without fail. (9) The safe bearing capacity (SBC) shall be
referred from SBC test report. In absence of report it shall be
referred from data sheet. If poor soil is found / water table is met
with during excavation SBC shall be scientifically ascertained and
design shall be revise. No extra shall be paid for increase in
quantity. (10) DI pipes and special shall only be used if type is not
specified in tender. (11) The rate shall include cost of dewatering
during excavation making all arrangement when water table
meets within depth. (12) The structure shall be designed properly
to resist uplift due to ground water table specified in data or
actual ground water table meets with during excavation. If GWT /
Uplift is mentioned in tender and during excavation it dose not
meet 7.5% rate shall be reduced. (13) SS pipes railing shall be
provided over sump perifery when sump height is ≥ 1.5 meter
above ground level. (14.a) RCC staircase/RCC Steps should be
provided from GL to sump top slab based on the height of the GSR
above/below the ground. (14.b) RCC Staircase with SS railing to be
provided inside reservoir container. BB Masonry staircabin to be
provided to cover the same with MS safety door having locking
arrangement. (15) Appearance of structure should be aesthetically
good looking acceptable to authority. (16) Any change in size,
shape, depth below GL, height above GL, water depth, F.B., size of
member etc can be permitted in exceptional case due to site
condition or hydraulic design requirement by C.E. No extra shall be
paid for change. (17) Any change in data, dimensions, shape,
water depth, reduction in size if permitted by competent authority

29
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

and if it reduces quantity then payment shall be reduced prorate.


(18) When capacity of GSR / Sump is > 20 lakh litres two or
suitable compartments acceptable to executive engineer shall be
designed and provided. (19) Agency shall engage qualified (at least
graduate) consulting engineer for designing the structure and he /
she shall visit the site for guidance of work. (20) 75% part rate shall
be payable for concrete, reinforcement and plastering items of
container until satisfactory hydraulic testing for water tightness is
performed as per tender condition. Till the work shall be treated
as incomplete. Above conditions / general specifications Sr. No. 1
to 20 are part and parcel of tender (contact) and prevail over
other provisions in tender. As above rectangular sump without
water table Cost of 1,00,000.00 litres

30
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

Drilling & Assembly lowering charges for 8" Dia bore well up to
minimum 180 Mtr or up to required depth with Gravel Packing
,Air compressor with clay paackingwith sealing with cement with
mud pit digging & removing the mud to make the surface
cleanwith electro logging chart preparation with 8" dia. UPVC
casing pipe with 8" dia strainer UPVC pipe with supply of
submercible pump of 12.5HP of approved make including
installation with supply and installation of control panel board
with necessary fittings like clamp,bolt,coupler etc.& all other
required accessories including supply and installation of 2.5
Sq.mm cable for pump with supply and installation of 2" delivery
pipe ( Column) M.S pipe of Heavy Class with supply and
installation of 2" delivery pipe ( column)M.S pipe of medium class
135 & supply and installation of column accessories. 2 No

Providing lying and jointing in true line and level 15 mm dia.


U.P.V.C. Pipe (as per ASTM D 1785 SCH ‐ 40) line including fittings
make or equivalent as approved by Engineer In Charge. Pipe shall
be fixed on the wall with the help of clamp at every two meter C/C
or shall be connected as directed including testing of pipe and
joints and fixing the same with adhesive solvent, including cost of
136 all materials. 152 Meter

31
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

Providing lying and jointing in true line and level 20 mm dia.


U.P.V.C. Pipe (as per ASTM D 1785 SCH ‐ 40) line including fittings
make or equivalent as approved by Engineer In Charge. Pipe shall
be fixed on the wall with the help of clamp at every two meter C/C
or shall be connected as directed including testing of pipe and
joints and fixing the same with adhesive solvent, including cost of
137 all materials. 677 Meter

Providing lying and jointing in true line and level 25 mm dia.


U.P.V.C. Pipe (SCH ‐ 40) line including fittings make or equivalent
as approved by Engineer In Charge. Pipe shall be fixed on the wall
with the help of clamp at every two meter C/C or shall be
connected as directed including testing of pipe and joints and
fixing the same with adhesive solvent, including cost of all
138 materials. 476 Meter

Providing lying and jointing in true line and level 32 mm dia.


U.P.V.C. Pipe (SCH ‐ 40) line including fittings make or equivalent
as approved by Engineer In Charge. Pipe shall be fixed on the wall
with the help of clamp at every two meter C/C or shall be
connected as directed including testing of pipe and joints and
fixing the same with adhesive solvent, including cost of all
139 materials. 302 Meter

Providing lying and jointing in true line and level 40 mm dia.


U.P.V.C. Pipe (SCH ‐ 40) line including fittings make or equivalent
as approved by Engineer In Charge. Pipe shall be fixed on the wall
with the help of clamp at every two meter C/C or shall be
connected as directed including testing of pipe and joints and
fixing the same with adhesive solvent, including cost of all
140 materials. 355 Meter

32
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

Providing lying and jointing in true line and level 50 mm dia.


U.P.V.C. Pipe (SCH ‐ 40) line including fittings make or equivalent
as approved by Engineer In Charge. Pipe shall be fixed on the wall
with the help of clamp at every two meter C/C or shall be
connected as directed including testing of pipe and joints and
fixing the same with adhesive solvent, including cost of all
141 materials. 413 Meter

Providing lying and jointing in true line and level 65 mm dia.


U.P.V.C. Pipe (SCH ‐ 40) line including fittings make or equivalent
as approved by Engineer In Charge. Pipe shall be fixed on the wall
with the help of clamp at every two meter C/C or shall be
connected as directed including testing of pipe and joints and
fixing the same with adhesive solvent, including cost of all
142 materials. 298 Meter

Providing lying and jointing in true line and level 75 mm dia.


U.P.V.C. Pipe (SCH ‐ 40) line including fittings make or equivalent
as approved by Engineer In Charge. Pipe shall be fixed on the wall
with the help of clamp at every two meter C/C or shall be
connected as directed including testing of pipe and joints and
fixing the same with adhesive solvent, including cost of all
143 materials. 165 Meter
Providing & Fixing concealed center point to wall ceiling & floor
CPVC (13.5) pipe having NationalSanitation Foundation (NSF) seal
for potable water of following dia. Nominal bore tube fittings &
clamps making good the wall, cieling, floor,etc complete (A) 15
144 mm 49 Meter
Providing & Fixing concealed center point to wall ceiling & floor
CPVC (13.5) pipe having NationalSanitation Foundation (NSF) seal
for potable water of following dia. Nominal bore tube fittings &
clamps making good the wall, cieling, floor,etc complete (B) 20
145 mm 405 Meter

33
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

Providing & Fixing concealed center point to wall ceiling & floor
CPVC (13.5) pipe having NationalSanitation Foundation (NSF) seal
for potable water of following dia. Nominal bore tube fittings &
clamps making good the wall, cieling, floor,etc complete (C) 25
146 mm 60 Meter
Providing & Fixing concealed center point to wall ceiling & floor
CPVC (13.5) pipe having NationalSanitation Foundation (NSF) seal
for potable water of following dia. Nominal bore tube fittings &
clamps making good the wall, cieling, floor,etc complete (D) 32
147 mm 30 Meter
Providing & Fixing concealed center point to wall ceiling & floor
CPVC (13.5) pipe having NationalSanitation Foundation (NSF) seal
for potable water of following dia. Nominal bore tube fittings &
clamps making good the wall, cieling, floor,etc complete (E) 40
148 mm 25 Meter

Providing & Fixing concealed center point to wall ceiling & floor
CPVC (13.5) pipe having NationalSanitation Foundation (NSF) seal
for potable water of following dia. Nominal bore tube fittings &
149 clamps making good the wall, cieling, floor,etc complete (F) 50 mm 160 Meter

150 Providing & fixing in position cowl vent to pipes of 75 mm 29 Each

151 Providing & fixing in position cowl vent to pipes of 110 mm 68 Each

Providing and Laying & Jointing 75 mm dia uPVC Pipe Type B


conforming to IS 13592‐1992 with one end plain & other end
socketed with solvent/rubber ring & fittings conform to IS:14735
with clamps at 2 mtr center to center on wall including testing of
152 pipes, adhesive solvent cement, etc complete 554 Meter

34
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

Providing and Laying & Jointing 110 mm dia uPVC Pipe Type B
conforming to IS 13592‐1992 with one end plain & other end
socketed with solvent/rubber ring & fittings conform to IS:14735
with clamps at 2 mtr center to center on wall including testing of
153 pipes, adhesive solvent cement, etc complete 1160 Meter
Providing & Fixing PVC SWR Trap IS 14735 for drain ‐ 100 mm
diameter with jali of 150 mm diameter with self cleansing design
with CI scread down or hinged grating including cost of cutting &
154 making the good walls 139 Each

Providing and fixing wash down water closet


( European type, WC pan) with integral P or S trap including
jointing the trap with soil pipe in cement mortar 1:1 (1 Cement : 1
fine sand) ( Seal and cover to be measured and paid for
separately)
155 A) Vitreous China, white colour 1 Each
Providing and fixing viterous china Anglo Indian type water closet
with solid plastic seat & lid fixed with CP brass hinges, rubber
buffer with all civil work making the good floor

156 A) Vitreous China, white colour 103 Each

Providing and fixing water closet squatting pan (Indian type WC)
157 size 580 mm (A) Viterous China long pattern white colour 13 Each
Providing and fixing 100 mm size P or S trap for WC Squatting pan
(Indian type) / Anglo indian type WC including jointing the trap
with the pan and soil pipe with cement mortar 1:1 ( 1 Cement : 1
fine sand)with foot rests
158 A) Vitreous China, white colour 117 Each
159 Providing & fixing 110 mm UPVC P trap with Jali 105 Each
Providing and fixing 25 mm half turn CP flush cock with all
160 accessories 118 Each

35
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

Providing & fixing of Jet spray to each EWC with all accessories &
161 tubing 90 Each
Providing & fixing of Hand Shower (Health Faucet), ABS body, 1
Rmt Long pvc Tube and Wall Hook accessories to complete the
162 item. 54 Each
Providing & fixing in position 15 mm C.P. brass 2 way bib cocks of
163 best quality 104 Each

164 Providing and fixing GI inlet connection for flush pipe with WC pan 97 Each

Providing and fixing plastic seat and cover for wash down water
closet with C.P. brass hinges and rubber buffers A) Black plastic
165 seat and cover 88 Each
Providing and fixing table top type wash basin with single hole for
pillar trap including cutting holes and making good the same but
excluding granite/marble platform
a) Vitreous china table top wash basin 560mm X 400mm size in
166 white colour, oval/rectangular shape 124 Each
Providing and fixing C.P. brass waste for wash basin or sink of 32
167 mm 106 Each
Providing and fixing M.I. fisher union for wash basin or sink. of 32
168 mm 143 Each

Providing & Fixing of Stainless stell AISI 304 wash basin 530x345
169 mm size with one 15 mm CP brass pillar tap 38 Each
Providing and Fixing C.P. brass shower rose with 15mm or 20mm
inlet.
170 (A) 100mm dia. Each 20 Each

Providing & fixing of 20 mm concealed CP stop cocks with wall


171 flange, etc. For shower 95 Each

36
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

Providing and fixing 600mmX450mm bevelled edge mirror of


superior glass mounted on 6mm thick A.C. sheet or plywood sheet
172 and fixing to wooden plug with C.P. brass screws and washers. 31 Each

Providing and fixing CP brass towel rail complete with C.P. brass
brackets fix to wooden plug with CP brass screws. I) 600 mm X 20
173 mm 27 Each
Providing and fixing of CP angle valve of following size
174 15 mm 182 Each

Providing and fixing of screwed down bib taps of following size


175 C) GM Bib tap of 15 mm 200 Each
Providing and fixing pillar tap capstan head screw down high
176 pressure with screw and back nuts of 15mm of 15 mm size 127 Each

Providing & fixing Urinal of approved quality including connecting


Urinal with waste pipe, tap etc. Complete. (A) White earthenware
177 flat back/corner type ize 430mmx260mmx350 mm 2 Each
Providing and fixing gun metal check or non return full way wheel
178 valve of 50 mm 9 Each

Providing and fixing gun metal check or non return full way wheel
179 valve of 40 mm 4 Each

180 Providing and fixing gun metal full way wheel valve of 20 mm 4 Each

181 Providing and fixing gun metal full way wheel valve of 25 mm 35 Each

182 Providing and fixing gun metal full way wheel valve of 32 mm 15 Each

183 Providing and fixing gun metal full way wheel valve of 40 mm 29 Each

37
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

184 Providing and fixing gun metal full way wheel valve of 50 mm 19 Each

185 Providing and fixing gun metal full way wheel valve of 65 mm 12 Each

186 Providing and fixing gun metal full way wheel valve of 75 mm 5 Each
187 Providing and fixing 50 mm Float Velve 8 Each

Providing and fixing Chromium plated bottle trap with necessary


188 coupling of approved quality for wash basin. 123 Each

Supplying, installing, testing & commissioning of instantanous type


6 ltr. El. geysers Racold/Bajaj/ equivalent make with all safety &
189 protections, piping connections, hardwares, etc. complete 26 Each

Providing erecting and fixing double coated Syntex or equivalent


HDPE. (ISI) mark water tank of required capacity each with all
190 necessary fittings & connections etc. completed on terrace. 50000 Per. Ltr.

Supplying, installing, testing & commissioning of SOLAR WATER


heating system comprising of Solar flat locket collector, stainless
steel hot water storage isolated tank with S.S. heat exchanger,
absorber made of copper sheet & copper tube of following
capacity in liter / day (LPD) with "B" size aluminium box collector
with appropriate capacity electrical backup arrangement
(Excluding inlet & outlet pipe lines)
191 [A] Capacity of 1000 LPD (i.e. 500 LPDx2) 6 Each

38
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

Providing & erecting water cooler with inbuilt RO & having storage
tank capacity 80 Ltr. & cooling capacity 40 Ltr.per hour @ an
ambient temp of 45 deg C. The outlet temp. of the water should
drop by 15 deg C within a hour, The water cooler should be
comprising of hermetically sealed compressor, fan motor,
condensing unit, water tank surrounded by evaporating, coil,
thermostats, relay etc.complete with necessary inlet & outlet
connection. The body of water cooler will be made from Stainless
Steel. The scope shall cover inbuilt reverse osmosis plant of 50
192 ltr./hr purification capacity 13 Each

Supplying & erecting 5 stage single reverse osmosis water


purification system with M.S. powder coated frame, prefilter
housing with 'O' ring presediment filter GAC filter, carbon filter
suitable buster DC pump capacity 80 psi, mention with 40 Osg
inline type post carbon filter auto low & high pressure switches
with following size of storage tank & LPH capacity & erected as
directed with one year comprehensive maintenance guarantee.
193 [1] 50 Ltr / Hr with 250 psi inlet pressure 13 Each
Providing and laying in trenches galvanized MS tube of following
nominal bore and tube fitting (Earth work in trenches to be
194 measured and paid for separately) of 150 mm 0 Meter
Providing and laying in trenches galvanized MS tube of following
nominal bore and tube fitting (Earth work in trenches to be
195 measured and paid for separately) of 100 mm 150 Meter
Providing and laying in trenches galvanized MS tube of following
nominal bore and tube fitting (Earth work in trenches to be
196 measured and paid for separately) of 80 mm 75 Meter
Providing and laying in trenches galvanized MS tube of following
nominal bore and tube fitting (Earth work in trenches to be
197 measured and paid for separately) of 65 mm 75 Meter

39
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

Providing and laying in trenches galvanized MS tube of following


nominal bore and tube fitting (Earth work in trenches to be
198 measured and paid for separately) of 50 mm 425 Meter
Providing and fixing in trenches 10 kg/cm2 working pressure
polyethylene pipes of following outside diameter , low density
complete with flange compression type fittings, supports, etc.
199 compelte 50 mm 500 Meter
Providing and fixing in trenches 6 kg/cm2 working pressure
polyethylene pipes of following outside diameter , low density
complete with flange compression type fittings, supports, etc.
200 compelte 20 mm 75 Meter

Providing and laying in trench uPVC pipe as per IS‐15328 class SN 4


pipes to the specified invert level and slope and full leak proof
joining with rubber ring click ring jointing etc., complete with
testing. The scope includes excavation, refilling, bedding, encasing
etc. all civil work, connection to the exisiting network as required
201 to complete the system as per site condition. Size 110 mm 150 Meter

Providing and laying in trench uPVC pipe as per IS‐15328 class SN 4


pipes to the specified invert level and slope and full leak proof
joining with rubber ring click ring jointing etc., complete with
testing. The scope includes excavation, refilling, bedding, encasing
etc. all civil work, connection to the exisiting network as required
202 to complete the system as per site condition. Size 160 mm 475 Meter

Providing and laying in trench uPVC pipe as per IS‐15328 class SN 4


pipes to the specified invert level and slope and full leak proof
joining with rubber ring click ring jointing etc., complete with
testing. The scope includes excavation, refilling, bedding, encasing
etc. all civil work, connection to the exisiting network as required
203 to complete the system as per site condition. Size 200 mm 400 Meter

40
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

Providing and laying in trench uPVC pipe as per IS‐15328 class SN 4


pipes to the specified invert level and slope and full leak proof
joining with rubber ring click ring jointing etc., complete with
testing. The scope includes excavation, refilling, bedding, encasing
etc. all civil work, connection to the exisiting network as required
204 to complete the system as per site condition. Size 250 mm 400 Meter
Providing and laying Cement concrete 1:5:10 (1‐Cement : 5 ‐ fine
sand : 10‐Graded stone aggregate 40mm nominal size) all around
205 including bedding for 100 mm dia uPVC pipe 150 Meter
Providing and laying Cement concrete 1:5:10 (1‐Cement : 5 ‐ fine
sand : 10‐Graded stone aggregate 40mm nominal size) all around
206 including bedding for 150 mm dia uPVC pipe 475 Meter
Providing and laying Cement concrete 1:5:10 (1‐Cement : 5 ‐ fine
sand : 10‐Graded stone aggregate 40mm nominal size) all around
207 including bedding for 200 mm dia uPVC pipe 400 Meter
Providing and laying Cement concrete 1:5:10 (1‐Cement : 5 ‐ fine
sand : 10‐Graded stone aggregate 40mm nominal size) all around
208 including bedding for 250 mm dia uPVC pipe 150 Meter

Providing and fixing S.W. gully trap with C.I. grating brick masonry
chamber and water tight C.I. cover with frame of 300mmX300mm
size (inside) with standard weight. I) Square mouth traps.
209 a) 150mmX110mm size P type 106 Each
210 Providing & fixing 3/4" PVC graden hose taps for irrigation 40 Each
Providing & Laying ( to level or Slope) and jointing reinforced
concrete Light Duty NoN Pressure I.S. Class NP2 of the following
internal diameter with collars and butt ends prepared for collar
joints including testing of joints for of
211 150 mm 600 Meter

41
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

Providing & Laying ( to level or Slope) and jointing reinforced


concrete Light Duty NoN Pressure I.S. Class NP2 of the following
internal diameter with collars and butt ends prepared for collar
joints including testing of joints for of
212 250 mm 125 Meter
Providing & Laying ( to level or Slope) and jointing reinforced
concrete Light Duty NoN Pressure I.S. Class NP2 of the following
internal diameter with collars and butt ends prepared for collar
joints including testing of joints for of
213 300 mm 25 Meter

Constructing Manhole with R.C.C. top slab in 1:2:4 mix (1‐cement :


2‐coarse send : 4‐graded stone aggregate 20mm nominal size)
foundation concrete 1:3:6 mix (1‐cement : 3‐coarse sand : 6‐ Brick
bats 40 + 50mm size) inside plastering 15mm thick with Cement
a) With 230mm thick walls of brick masonary using brick having
crushing strength not less than 35Kg. / Sq.cm. in Cement Mortar
1:5 (1‐ Cement : 5‐ Coarse sand) (I) Inside size 900mm X
1200mm and 1.5M. deep including C.I. cover with frame size
560mm diameter total weight of cover and frame to be not less
than 128 kgs. (Wt. of cover 64 kg. and Wt. of frame 64 Kg.)
214 1) A type depth 0.90 Meter for 150 mm diameter sewer. 40 Each

42
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

Constructing brick masonry chamber for underground C.I.


Inspection chamber and bends with bricks having crushing
strength not less than 35kg. Cm2 in C.M. 1:5 C.I. cover with frame
(Light duty) 455mm X610mm internal dimensions, total weight of
cover with frame to be not less than 38kg. (Wt. of cover 23 kg.)
and Wt. of frame 15Kg.) (R.C.C. top slab with 1:2:4 mix (1‐cement :
2‐ coarse sand : 4‐ graded stone aggregate 20mm size) foundation
concrete 1:5:10 inside plaster 15mm thick with cement mortar 1:3
finished smooth with a floating coat of neat cement on walls and
bed concrete etc. complete.
ii) Inside dimensions 500mmX700mm and 450mm deep for pipe
215 line with one or two inlets. 50 Each
Construction of 600mmx600 mm valve chamber 60x60 cm inside
in brick work in cement mortar 1:4 with RCC tope slab 1:2:4 with
necessary excavation, foundation concerete 1:5:10, inside
plastering with cement mortar 1:3, 12 mm thick, finished with a
216 flating coat of neat cement complete 10 Each
Constructing Brick masonry road Gully chamber 500mm x 450
mmincluding 500x450 mm CI horizontal grating with frame
217 complete 35 Each
Constructing Brick masonry road Gully chamber 450mm x 450
mmincluding 500x450 mm CI horizontal grating with frame
218 complete 40 Each
Constructing Brick masonry road Gully chamber 1100mm x 775
mm including 500x450 mm CI horizontal grating with & vertical
219 grating frame complete 20 Each

43
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

Construction Septic tank inside dimention of 6 m in length & 3 m


in width & 3 m depth including excavating any type of soil as
shown and mentioned in the drawing,providing and laying 0.10 m
thick plain cement concrete 1:3:6 ( 1 cement : 3 coarse sand : 6
graded stone agg.) 40 mm thick IPS flooring at bottom with brick
masonary 0.23 m thick walls CM 1:5 ( 1 cement : 5 coarse sand )
and intermediate partition CM 1:4 & RCC Top slabs12 cms thick in
1:2:4 (1 cement : 2 coarse sand : 4 graded stone agg) including
reinforcement as per design and 15 mm thick cement plaster in
CM 1:4 with floating coat of neat cement slurry inside, top and
around tank below 15 cm on ground level, Also provide Two nos CI
Manhole frame and cover of size 60 cm x 45 cm & 75 mm dia. PVC
6 kgf / Sq cm pressure air vent pipe in 3.00 length with cowl etc
220 complete as per direction of Engineer in charge. 3 Each
Construction of Percolation Well with all required connections as
per detailed design and drawing.
221 3mtr dia X 4 mtr liquid depth for cathbasin 5 Each

Providing and constructing SOAK WELL of 2.50m internal dia and


5.00 depth depth internal clear dimention including the cost of
execavation,PCC 1:4:8 foundation for honey combed masonary in
C.M. 1:4 (1cement : 4 sand) , casting R.C.C. 1:2:4 (1cement : 2 sand
: 4 graded stone aggregate 20mm nominal size) top slab 12 thick
with C.I. manhole cover 600mm x 450mm size of 35 kg. weight and
75mm dia C.I. pipe 1800mm long with 75mm dia cowel vent and
filling the wall 1000mm in depth with dry brick bats including
providing vata in C.M. 1:3 (1cement : 3 sand), curing including cost
of reinforcement etc. complete as per detailed drawing and
222 directed by E.I.C. 3 Each

44
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

Construction of MBBR type sewage treatment plant with all


electro mechanical equipments, required civil work (excluding RCC
tanks), pre fab aeration / settling & chlorine contact tanks, piping,
valaves, gauges, consumables required for Primary, secondary &
teratiary treatments with all necessary accessories including
traning to clinet's staff, 3 years of operation & maintennace.
Capacity : 100 KLD,Item Include from starting of west water inlet
to treated water utilisasion all equipments , machinary,Tanks,
223 pipes any supporting things at any level of work. 1 Each
Supply & erecting 3 phase open well horizontal mono block /
monoset pump set suitable for 150 LPM @ 30 Mtr head suitable
for 40 mm dia delivery pipe. CAT‐III (1W +1S) with necessary valve
224 fittings. 5 Each

Supplying & erecting approved make motor control cubical panel


[Star delta] made from 16G CRCA sheet duly epoxy powder
painted inside and outside with hinged doors and locking with
suitable size of ON ‐ OFF isolator (AC 3 / 23 duty) main fuses.
Digital volt and current meter (in a single unit) with micro
controller based control unit and current sensing single phasing
preventer electronic overload protection, over voltage
(Programmable) protection and under voltage (Programmable)
protection, prod less dry run protection programming facility for
setting of all parameter like overload current, high voltage limit,
low voltage limit, dry run limit with digital indication on seven
segment LED display for any fault like over load, high voltage, low
voltage, dry running single crimped, electronic star delta timer,
feather touch start / stop push buttons to be erected on angle iron
frame.

225 (a) DOL up to 5.0 H.P. (1W +1S) 5 Each

45
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

226 50 mm GI Pipe with necessary fittings and accessories. 50 Meter


DG SET ,Supply, Installation, Testing and Commissioning of
Radiator based water cooled D.G. set along with necessary
Residential silencer, expansion bellows, exhaust piping with
necessary support structure of MS channels & I‐Beams, harmonic
filter if required, fuel piping, battery and battery charger (Float &
boost), AVM pad and all other accessories required for
installation of D.G. set as per specification and datasheet.
The set should have following specifications.
The set should be mounted inside 2 mm thick CRCA sheet acoustic
enclosure.
The DG Set shall be suitable for outdoor application and should
have the required IP Protection.
The final rated capacity of D.G. set should be decided after
considering total chimeny height and derating due to the travel of
exhaust gas.
The day tank shall be part of acoustic enclosure, otherwise, all
necessary arrangement to be provided for storage and pumping of
diesel etc.
The scope includes,
1)Supply of DG Sets with Acoustic Enclosure with fuel tank and
MCCB within canopy.
2)To submitt drawing showing, overall layout with dimensions,
plan, elevations, foundation detais and sections and got approved
prior to commencing of manufacturing.
3)To submitt drawing showing, SLD with rating of equipments /
make etc., and get it approved prior to commencing of
manufacturing.
4)To test the DG set for factory test witnessed by Client's
represantative and/or consultant prior to dispatch of following:‐
1. Load trial test for equal ratings of load for continous 4 Hrs.
2. Sudden shock load at every One hour during above test.
3. Vibration Test
4. Noise level test.
5. Fuel gas analysis.
227 6. Delta ` t ' inside acoustic enclosure. 1 Each
46
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

7. Fuel specific consumption test.5)Delivery of the DG set at site


6)Unloading of the DG set at Required Location of Installation.
7)Installtion of DG set on it's foundation.
8)To get Battery charged and to test Battery charger at site.
9)Testing of the DG Set with Supply of Consumable at site.
10)Painting of the parts damaged during Transportation or
Installation
11)To connect Power & Control cabling between D.G. Panel & D.
G. Set syncronising Panel & alternator to ACB inside the
enclosure.
12)Supply and erectionof exhaust chimney oulets of Suitable size
as per statutory requirement with suitable M.S. structure
complete between exhaust of engine till out let point for
discharging fule gas. Drawing of which shall be submitted for
approval.
13)The rate quoted shall be for the entire job including exhaust
piping complete up to trial test. No extra rates to be quoted for
any items for the DG set.
14)To co‐ordinate with other agencies working at site
15)To prepare submission drawing and to take approval of
consultant at each stage.
16)To prepare & submit as‐built drawing and handing over
document to end user.
17)To prepare and submit drawings to relavent statutory
authorities and to take approval for DG Set.,Supply of 160 kVA DG
set with acoustic enclosure suitable for 75 db(A) sound level
reduction to be measured at 1 mtr. from the enclosure. Cost
should cover Exhaust Piping as per statutory requirements and
necessary control and metering, indication /annuciation & other
accessories.

47
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

LT PANELSSupply, installation, assembling, connection, testing and


commissioning of Panels as per Specification, Technical Data
sheet, IS & relevant drawings.
All panels and DBs shall be manufacturerd CPRI approved (for
50kA in last two years) panel manufacturer with inhouse 7‐tank
process and painting facility.
The unit rate for each item shall include :
1) Supply of panels Testing of panels as per specifications at
manufacturer's works in presence of client's representative and/or
consultant.
2) Delivery of the panels / DB's to site.
3) Shifting of the panels from site store to the suitable location.
4) Assembly and wiring of component supplied separately.
5) Installation of panels as per Location arranged by site Engineer
in charge including removing packing.
6) Earthing all components, frame etc. to a common internal earth
bar.
7) Touching of body with powder coating for demaged parts. All
the nuts bolts & joints exposed to the air shall be covered with
suitable anti ‐ oxtidant material or as directed by the Engineer
incharge.
8) Supply and fixing all accessories and supporting structure.
9) Checking of Internal connection & wiring, operation of switches,
MCCB, MCB etc..
10) Supply of necessary tools, hardware, testing hardware, testing
equipment during testing at site.
11) Supply & fixing of 75 mm main steel [No rolling mill material
shall be allowed] MS channels for fixing the panel, alongwith all
the required civil materials required to complete the job as per the
instruction of Engineer Incharge.
12) To carry out the insulation test at site and all the readings shall
be submitted in duplicate to the consultant or engineer‐in‐charge.
13) To co‐ordinate with other agencies working at site
14) To prepare submission drawing and to take approval of
consultant at each stage.
15) To prepare & submit as‐built drawing and handing over
228 document to end user.Supply, installation, assembly, connection, 1 Each

48
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

testing and commissioning of DG PANEL as per Specification,


Technical Data sheet, IS & SLD

49
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

LT PANELSSupply, installation, assembling, connection, testing and


commissioning of Panels as per Specification, Technical Data
sheet, IS & relevant drawings.
All panels and DBs shall be manufacturerd CPRI approved (for
50kA in last two years) panel manufacturer with inhouse 7‐tank
process and painting facility.
The unit rate for each item shall include :
1) Supply of panels Testing of panels as per specifications at
manufacturer's works in presence of client's representative and/or
consultant.
2) Delivery of the panels / DB's to site.
3) Shifting of the panels from site store to the suitable location.
4) Assembly and wiring of component supplied separately.
5) Installation of panels as per Location arranged by site Engineer
in charge including removing packing.
6) Earthing all components, frame etc. to a common internal earth
bar.
7) Touching of body with powder coating for demaged parts. All
the nuts bolts & joints exposed to the air shall be covered with
suitable anti ‐ oxtidant material or as directed by the Engineer
incharge.
8) Supply and fixing all accessories and supporting structure.
9) Checking of Internal connection & wiring, operation of switches,
MCCB, MCB etc..
10) Supply of necessary tools, hardware, testing hardware, testing
equipment during testing at site.
11) Supply & fixing of 75 mm main steel [No rolling mill material
shall be allowed] MS channels for fixing the panel, alongwith all
the required civil materials required to complete the job as per the
instruction of Engineer Incharge.
12) To carry out the insulation test at site and all the readings shall
be submitted in duplicate to the consultant or engineer‐in‐charge.
13) To co‐ordinate with other agencies working at site
14) To prepare submission drawing and to take approval of
consultant at each stage.
15) To prepare & submit as‐built drawing and handing over
229 document to end user.Supply, installation, assembly, connection, 1 Each

50
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

testing and commissioning of MAIN PANEL as per Specification,


Technical Data sheet, IS & SLD

51
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

LT PANELSSupply, installation, assembling, connection, testing and


commissioning of Panels as per Specification, Technical Data
sheet, IS & relevant drawings.
All panels and DBs shall be manufacturerd CPRI approved (for
50kA in last two years) panel manufacturer with inhouse 7‐tank
process and painting facility.
The unit rate for each item shall include :
1) Supply of panels Testing of panels as per specifications at
manufacturer's works in presence of client's representative and/or
consultant.
2) Delivery of the panels / DB's to site.
3) Shifting of the panels from site store to the suitable location.
4) Assembly and wiring of component supplied separately.
5) Installation of panels as per Location arranged by site Engineer
in charge including removing packing.
6) Earthing all components, frame etc. to a common internal earth
bar.
7) Touching of body with powder coating for demaged parts. All
the nuts bolts & joints exposed to the air shall be covered with
suitable anti ‐ oxtidant material or as directed by the Engineer
incharge.
8) Supply and fixing all accessories and supporting structure.
9) Checking of Internal connection & wiring, operation of switches,
MCCB, MCB etc..
10) Supply of necessary tools, hardware, testing hardware, testing
equipment during testing at site.
11) Supply & fixing of 75 mm main steel [No rolling mill material
shall be allowed] MS channels for fixing the panel, alongwith all
the required civil materials required to complete the job as per the
instruction of Engineer Incharge.
12) To carry out the insulation test at site and all the readings shall
be submitted in duplicate to the consultant or engineer‐in‐charge.
13) To co‐ordinate with other agencies working at site
14) To prepare submission drawing and to take approval of
consultant at each stage.
15) To prepare & submit as‐built drawing and handing over
230 document to end user.Supply, installation, assembly, connection, 1 Each

52
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

testing and commissioning of G.R.S School Main Panel as per


Specification, Technical Data sheet, IS & SLD

53
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

LT PANELSSupply, installation, assembling, connection, testing and


commissioning of Panels as per Specification, Technical Data
sheet, IS & relevant drawings.
All panels and DBs shall be manufacturerd CPRI approved (for
50kA in last two years) panel manufacturer with inhouse 7‐tank
process and painting facility.
The unit rate for each item shall include :
1) Supply of panels Testing of panels as per specifications at
manufacturer's works in presence of client's representative and/or
consultant.
2) Delivery of the panels / DB's to site.
3) Shifting of the panels from site store to the suitable location.
4) Assembly and wiring of component supplied separately.
5) Installation of panels as per Location arranged by site Engineer
in charge including removing packing.
6) Earthing all components, frame etc. to a common internal earth
bar.
7) Touching of body with powder coating for demaged parts. All
the nuts bolts & joints exposed to the air shall be covered with
suitable anti ‐ oxtidant material or as directed by the Engineer
incharge.
8) Supply and fixing all accessories and supporting structure.
9) Checking of Internal connection & wiring, operation of switches,
MCCB, MCB etc..
10) Supply of necessary tools, hardware, testing hardware, testing
equipment during testing at site.
11) Supply & fixing of 75 mm main steel [No rolling mill material
shall be allowed] MS channels for fixing the panel, alongwith all
the required civil materials required to complete the job as per the
instruction of Engineer Incharge.
12) To carry out the insulation test at site and all the readings shall
be submitted in duplicate to the consultant or engineer‐in‐charge.
13) To co‐ordinate with other agencies working at site
14) To prepare submission drawing and to take approval of
consultant at each stage.
15) To prepare & submit as‐built drawing and handing over
231 document to end user.Supply, installation, assembly, connection, 1 Each

54
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

testing and commissioning of Hostel Main Panel as per


Specification, Technical Data sheet, IS & SLD

55
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

LT PANELSSupply, installation, assembling, connection, testing and


commissioning of Panels as per Specification, Technical Data
sheet, IS & relevant drawings.
All panels and DBs shall be manufacturerd CPRI approved (for
50kA in last two years) panel manufacturer with inhouse 7‐tank
process and painting facility.
The unit rate for each item shall include :
1) Supply of panels Testing of panels as per specifications at
manufacturer's works in presence of client's representative and/or
consultant.
2) Delivery of the panels / DB's to site.
3) Shifting of the panels from site store to the suitable location.
4) Assembly and wiring of component supplied separately.
5) Installation of panels as per Location arranged by site Engineer
in charge including removing packing.
6) Earthing all components, frame etc. to a common internal earth
bar.
7) Touching of body with powder coating for demaged parts. All
the nuts bolts & joints exposed to the air shall be covered with
suitable anti ‐ oxtidant material or as directed by the Engineer
incharge.
8) Supply and fixing all accessories and supporting structure.
9) Checking of Internal connection & wiring, operation of switches,
MCCB, MCB etc..
10) Supply of necessary tools, hardware, testing hardware, testing
equipment during testing at site.
11) Supply & fixing of 75 mm main steel [No rolling mill material
shall be allowed] MS channels for fixing the panel, alongwith all
the required civil materials required to complete the job as per the
instruction of Engineer Incharge.
12) To carry out the insulation test at site and all the readings shall
be submitted in duplicate to the consultant or engineer‐in‐charge.
13) To co‐ordinate with other agencies working at site
14) To prepare submission drawing and to take approval of
consultant at each stage.
15) To prepare & submit as‐built drawing and handing over
232 document to end user.Supply, installation, assembly, connection, 1 Each

56
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

testing and commissioning of Staff Quarters Main Panel as per


Specification, Technical Data sheet, IS & SLD

57
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

LT PANELSSupply, installation, assembling, connection, testing and


commissioning of Panels as per Specification, Technical Data
sheet, IS & relevant drawings.
All panels and DBs shall be manufacturerd CPRI approved (for
50kA in last two years) panel manufacturer with inhouse 7‐tank
process and painting facility.
The unit rate for each item shall include :
1) Supply of panels Testing of panels as per specifications at
manufacturer's works in presence of client's representative and/or
consultant.
2) Delivery of the panels / DB's to site.
3) Shifting of the panels from site store to the suitable location.
4) Assembly and wiring of component supplied separately.
5) Installation of panels as per Location arranged by site Engineer
in charge including removing packing.
6) Earthing all components, frame etc. to a common internal earth
bar.
7) Touching of body with powder coating for demaged parts. All
the nuts bolts & joints exposed to the air shall be covered with
suitable anti ‐ oxtidant material or as directed by the Engineer
incharge.
8) Supply and fixing all accessories and supporting structure.
9) Checking of Internal connection & wiring, operation of switches,
MCCB, MCB etc..
10) Supply of necessary tools, hardware, testing hardware, testing
equipment during testing at site.
11) Supply & fixing of 75 mm main steel [No rolling mill material
shall be allowed] MS channels for fixing the panel, alongwith all
the required civil materials required to complete the job as per the
instruction of Engineer Incharge.
12) To carry out the insulation test at site and all the readings shall
be submitted in duplicate to the consultant or engineer‐in‐charge.
13) To co‐ordinate with other agencies working at site
14) To prepare submission drawing and to take approval of
consultant at each stage.
15) To prepare & submit as‐built drawing and handing over
233 document to end user.Supply, installation, assembly, connection, 1 Each

58
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

testing and commissioning of Utility Panel as per Specification,


Technical Data sheet, IS & SLD

59
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

LT PANELSSupply, installation, assembling, connection, testing and


commissioning of Panels as per Specification, Technical Data
sheet, IS & relevant drawings.
All panels and DBs shall be manufacturerd CPRI approved (for
50kA in last two years) panel manufacturer with inhouse 7‐tank
process and painting facility.
The unit rate for each item shall include :
1) Supply of panels Testing of panels as per specifications at
manufacturer's works in presence of client's representative and/or
consultant.
2) Delivery of the panels / DB's to site.
3) Shifting of the panels from site store to the suitable location.
4) Assembly and wiring of component supplied separately.
5) Installation of panels as per Location arranged by site Engineer
in charge including removing packing.
6) Earthing all components, frame etc. to a common internal earth
bar.
7) Touching of body with powder coating for demaged parts. All
the nuts bolts & joints exposed to the air shall be covered with
suitable anti ‐ oxtidant material or as directed by the Engineer
incharge.
8) Supply and fixing all accessories and supporting structure.
9) Checking of Internal connection & wiring, operation of switches,
MCCB, MCB etc..
10) Supply of necessary tools, hardware, testing hardware, testing
equipment during testing at site.
11) Supply & fixing of 75 mm main steel [No rolling mill material
shall be allowed] MS channels for fixing the panel, alongwith all
the required civil materials required to complete the job as per the
instruction of Engineer Incharge.
12) To carry out the insulation test at site and all the readings shall
be submitted in duplicate to the consultant or engineer‐in‐charge.
13) To co‐ordinate with other agencies working at site
14) To prepare submission drawing and to take approval of
consultant at each stage.
15) To prepare & submit as‐built drawing and handing over
234 document to end user.Supply, installation, assembly, connection, 1 Each

60
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

testing and commissioning of Canteen Main Panel as per


Specification, Technical Data sheet, IS & SLD

61
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

LT PANELSSupply, installation, assembling, connection, testing and


commissioning of Panels as per Specification, Technical Data
sheet, IS & relevant drawings.
All panels and DBs shall be manufacturerd CPRI approved (for
50kA in last two years) panel manufacturer with inhouse 7‐tank
process and painting facility.
The unit rate for each item shall include :
1) Supply of panels Testing of panels as per specifications at
manufacturer's works in presence of client's representative and/or
consultant.
2) Delivery of the panels / DB's to site.
3) Shifting of the panels from site store to the suitable location.
4) Assembly and wiring of component supplied separately.
5) Installation of panels as per Location arranged by site Engineer
in charge including removing packing.
6) Earthing all components, frame etc. to a common internal earth
bar.
7) Touching of body with powder coating for demaged parts. All
the nuts bolts & joints exposed to the air shall be covered with
suitable anti ‐ oxtidant material or as directed by the Engineer
incharge.
8) Supply and fixing all accessories and supporting structure.
9) Checking of Internal connection & wiring, operation of switches,
MCCB, MCB etc..
10) Supply of necessary tools, hardware, testing hardware, testing
equipment during testing at site.
11) Supply & fixing of 75 mm main steel [No rolling mill material
shall be allowed] MS channels for fixing the panel, alongwith all
the required civil materials required to complete the job as per the
instruction of Engineer Incharge.
12) To carry out the insulation test at site and all the readings shall
be submitted in duplicate to the consultant or engineer‐in‐charge.
13) To co‐ordinate with other agencies working at site
14) To prepare submission drawing and to take approval of
consultant at each stage.
15) To prepare & submit as‐built drawing and handing over
235 document to end user.Supply, installation, assembly, connection, 1 Each

62
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

testing and commissioning of Class‐IV Quarters Main DB as per


Specification, Technical Data sheet, IS & SLD

63
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

SWITCHGEAR AND DISTRIBUTION BOARDSSupply, installation,


Testing & Commissioning of Distribution Board as per following
Description.
The distibution board shall be sheet steel clad (Fabricated / ready
made), concealed/recessed mounted, constructed from 14 SWG
sheet steel finished with rust proof red oxide coating and two
coats of paint with hinged gasketted door.
DBs shall have following features/Compliances:
1) Conforms to IS8623‐1&3,IEC61439‐1&3
2) IP‐30/43/54 :‐ Ensures DB are protected against Foreign bodies
and liquids.
3) IK‐08,09 :‐ Ensures that the DB are well protected against
Mechanical Impact
4) ROHS Compliance
5) Double door type with Reversible doors
6) Earthing facility with star washer (Per phase earthing strip)
7) Independently packed door, frame, shield cover
8) Removable Chasis
9) With Wiring kit (Insulated Busbars,Cablesties,Sticking saddles,
Blanking plates shall be provided)
10) Shall have high quality gaskets ensuring IP for life time.
11) Front shield cover with knobs and locked screws
12) Locks with padlock facility
13) Cable knockouts on all sides
14) Mark for insertion on DB
15) Cement spill cover
16) Neutral Shrouded (per phase neutral links)
17) Per phase isolation (PPI Type), Prewired up to the cnnector
strip.18) PVC insulated copper busbars with interconnections
19) Horizontal/Vertical series type Distribution boards with
MCB/MCCB as Incommer as per descriptions mentioned below:
The unit rate for each item shall include :
1) Supply of DBs
2) Delivery of the DB's to site.
3) 'Shifting of the DBs from site store to the suitable location.
4) Assembly and wiring of component supplied separately.
236 5) 'Installation of DBs as per Location arranged by site Engineer in 17 Each

64
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

charge including removing packing.


6) Earthing all components, frame etc. to a common internal earth
bar.
7) Touching of body with powder coating for demaged parts. All
the nuts bolts & joints exposed to the air shall be covered with
suitable anti ‐ oxtidant material or as directed by the Engineer
incharge.
8) Supply and fixing all accessories and supporting structure.
9) 'Checking of Internal connection & wiring, operation of
switches, MCCB, MCB etc..
10) Supply of necessary tools, hardware, testing hardware, testing
equipment during testing at site.
11) To prepare submission drawing and to take approval of
consultant at each stage.
12) To prepare & submit as‐built drawing and handing over
document to end user.
Note :The DBs shall be supplied at site to be used during civil
construction activity. It shold be supplied with proper protection
to avoid any physical damage or ingress of water /cement during
construction.Installation,Testing and commissioning of Double
door type TPN DB as per specifications, relevant IS and switchgear
quantities and specifications as below:
Incomer: 40A FP MCB (Lighting Duty)
Outgoing: 3 Nos. 40A DP ELCB (One in each phase ‐ 100 mA)
12 Nos. 6A/10A/16A/25A SP MCB (Lighting Duty)

65
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

SWITCHGEAR AND DISTRIBUTION BOARDSSupply, installation,


Testing & Commissioning of Distribution Board as per following
Description.
The distibution board shall be sheet steel clad (Fabricated / ready
made), concealed/recessed mounted, constructed from 14 SWG
sheet steel finished with rust proof red oxide coating and two
coats of paint with hinged gasketted door.
DBs shall have following features/Compliances:
1) Conforms to IS8623‐1&3,IEC61439‐1&3
2) IP‐30/43/54 :‐ Ensures DB are protected against Foreign bodies
and liquids.
3) IK‐08,09 :‐ Ensures that the DB are well protected against
Mechanical Impact
4) ROHS Compliance
5) Double door type with Reversible doors
6) Earthing facility with star washer (Per phase earthing strip)
7) Independently packed door, frame, shield cover
8) Removable Chasis
9) With Wiring kit (Insulated Busbars,Cablesties,Sticking saddles,
Blanking plates shall be provided)
10) Shall have high quality gaskets ensuring IP for life time.
11) Front shield cover with knobs and locked screws
12) Locks with padlock facility
13) Cable knockouts on all sides
14) Mark for insertion on DB
15) Cement spill cover
16) Neutral Shrouded (per phase neutral links)
17) Per phase isolation (PPI Type), Prewired up to the cnnector
strip.18) PVC insulated copper busbars with interconnections
19) Horizontal/Vertical series type Distribution boards with
MCB/MCCB as Incommer as per descriptions mentioned below:
The unit rate for each item shall include :
1) Supply of DBs
2) Delivery of the DB's to site.
3) 'Shifting of the DBs from site store to the suitable location.
4) Assembly and wiring of component supplied separately.
237 5) 'Installation of DBs as per Location arranged by site Engineer in 1 Each

66
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

charge including removing packing.


6) Earthing all components, frame etc. to a common internal earth
bar.
7) Touching of body with powder coating for demaged parts. All
the nuts bolts & joints exposed to the air shall be covered with
suitable anti ‐ oxtidant material or as directed by the Engineer
incharge.
8) Supply and fixing all accessories and supporting structure.
9) 'Checking of Internal connection & wiring, operation of
switches, MCCB, MCB etc..
10) Supply of necessary tools, hardware, testing hardware, testing
equipment during testing at site.
11) To prepare submission drawing and to take approval of
consultant at each stage.
12) To prepare & submit as‐built drawing and handing over
document to end user.
Note :The DBs shall be supplied at site to be used during civil
construction activity. It shold be supplied with proper protection
to avoid any physical damage or ingress of water /cement during
construction.Installation,Testing and commissioning of Double
door type TPN DB WITH 24 HOUR TIMER & TP CONTACTOR as per
specifications, relevant IS and switchgear quantities and
specifications as below: (For External DB)
Incomer: 40A FP MCB (Lighting Duty)
Outgoing: 3 Nos. 40A DP ELCB (One in each phase ‐ 100 mA)
12 Nos. 6A/10A/16A/25A SP MCB (Lighting Duty)

67
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

SWITCHGEAR AND DISTRIBUTION BOARDSSupply, installation,


Testing & Commissioning of Distribution Board as per following
Description.
The distibution board shall be sheet steel clad (Fabricated / ready
made), concealed/recessed mounted, constructed from 14 SWG
sheet steel finished with rust proof red oxide coating and two
coats of paint with hinged gasketted door.
DBs shall have following features/Compliances:
1) Conforms to IS8623‐1&3,IEC61439‐1&3
2) IP‐30/43/54 :‐ Ensures DB are protected against Foreign bodies
and liquids.
3) IK‐08,09 :‐ Ensures that the DB are well protected against
Mechanical Impact
4) ROHS Compliance
5) Double door type with Reversible doors
6) Earthing facility with star washer (Per phase earthing strip)
7) Independently packed door, frame, shield cover
8) Removable Chasis
9) With Wiring kit (Insulated Busbars,Cablesties,Sticking saddles,
Blanking plates shall be provided)
10) Shall have high quality gaskets ensuring IP for life time.
11) Front shield cover with knobs and locked screws
12) Locks with padlock facility
13) Cable knockouts on all sides
14) Mark for insertion on DB
15) Cement spill cover
16) Neutral Shrouded (per phase neutral links)
17) Per phase isolation (PPI Type), Prewired up to the cnnector
strip.18) PVC insulated copper busbars with interconnections
19) Horizontal/Vertical series type Distribution boards with
MCB/MCCB as Incommer as per descriptions mentioned below:
The unit rate for each item shall include :
1) Supply of DBs
2) Delivery of the DB's to site.
3) 'Shifting of the DBs from site store to the suitable location.
4) Assembly and wiring of component supplied separately.
238 5) 'Installation of DBs as per Location arranged by site Engineer in 2 Each

68
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

charge including removing packing.


6) Earthing all components, frame etc. to a common internal earth
bar.
7) Touching of body with powder coating for demaged parts. All
the nuts bolts & joints exposed to the air shall be covered with
suitable anti ‐ oxtidant material or as directed by the Engineer
incharge.
8) Supply and fixing all accessories and supporting structure.
9) 'Checking of Internal connection & wiring, operation of
switches, MCCB, MCB etc..
10) Supply of necessary tools, hardware, testing hardware, testing
equipment during testing at site.
11) To prepare submission drawing and to take approval of
consultant at each stage.
12) To prepare & submit as‐built drawing and handing over
document to end user.
Note :The DBs shall be supplied at site to be used during civil
construction activity. It shold be supplied with proper protection
to avoid any physical damage or ingress of water /cement during
construction.Installation, , Testing and commissioning of Double
door type TPN DB as per specifications, relevant IS and switchgear
quantities and specifications as below:
Incomer: 40A FP MCB (Lighting Duty)
Outgoing: 3 Nos. 40A DP ELCB (One in each phase ‐ 100 mA)
18 Nos. 6A/10A/16A/25A SP MCB (Lighting Duty)

69
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

SWITCHGEAR AND DISTRIBUTION BOARDSSupply, installation,


Testing & Commissioning of Distribution Board as per following
Description.
The distibution board shall be sheet steel clad (Fabricated / ready
made), concealed/recessed mounted, constructed from 14 SWG
sheet steel finished with rust proof red oxide coating and two
coats of paint with hinged gasketted door.
DBs shall have following features/Compliances:
1) Conforms to IS8623‐1&3,IEC61439‐1&3
2) IP‐30/43/54 :‐ Ensures DB are protected against Foreign bodies
and liquids.
3) IK‐08,09 :‐ Ensures that the DB are well protected against
Mechanical Impact
4) ROHS Compliance
5) Double door type with Reversible doors
6) Earthing facility with star washer (Per phase earthing strip)
7) Independently packed door, frame, shield cover
8) Removable Chasis
9) With Wiring kit (Insulated Busbars,Cablesties,Sticking saddles,
Blanking plates shall be provided)
10) Shall have high quality gaskets ensuring IP for life time.
11) Front shield cover with knobs and locked screws
12) Locks with padlock facility
13) Cable knockouts on all sides
14) Mark for insertion on DB
15) Cement spill cover
16) Neutral Shrouded (per phase neutral links)
17) Per phase isolation (PPI Type), Prewired up to the cnnector
strip.18) PVC insulated copper busbars with interconnections
19) Horizontal/Vertical series type Distribution boards with
MCB/MCCB as Incommer as per descriptions mentioned below:
The unit rate for each item shall include :
1) Supply of DBs
2) Delivery of the DB's to site.
3) 'Shifting of the DBs from site store to the suitable location.
4) Assembly and wiring of component supplied separately.
239 5) 'Installation of DBs as per Location arranged by site Engineer in 25 Each

70
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

charge including removing packing.


6) Earthing all components, frame etc. to a common internal earth
bar.
7) Touching of body with powder coating for demaged parts. All
the nuts bolts & joints exposed to the air shall be covered with
suitable anti ‐ oxtidant material or as directed by the Engineer
incharge.
8) Supply and fixing all accessories and supporting structure.
9) 'Checking of Internal connection & wiring, operation of
switches, MCCB, MCB etc..
10) Supply of necessary tools, hardware, testing hardware, testing
equipment during testing at site.
11) To prepare submission drawing and to take approval of
consultant at each stage.
12) To prepare & submit as‐built drawing and handing over
document to end user.
Note :The DBs shall be supplied at site to be used during civil
construction activity. It shold be supplied with proper protection
to avoid any physical damage or ingress of water /cement during
construction.Installation, , Testing and commissioning of Double
door type SPN DB as per specifications, relevant IS and switchgear
quantities and specifications as below:
Incomer: 3 Nos. 32A DP ELCB (One in each phase ‐ 100 mA)
4 Nos. 6A/10A/16A/25A SP MCB (Lighting Duty)

71
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

LT CABLES,Supply, laying, connection, testing and commissioning


of heavy duty, low voltage, XLPE (IS 7098 ‐ PART‐II) insulated,
stranded AL / Cu conductor Armoured cables as per specification
& IS.
The cable shall have inner sheeth of XLPE and outer sheath of PVC
ST2 (FRSL) type with stranded AL/Cu conductor wherever
specified.
The cable shall be laid underground in excavated trench /
prepared trench / hume pipes when laid outside the building.
Cable shall be laid throught preapred trench / cable tray / duct /
hume pipe / channel / floor trunks etc when laid inside the
building.
The scope shall include:
1) Supply of Cables.
2) Delivery of the cables at site.
3) Unloading at site store.
4) Shifting of cable from site store to place of installation.
5) Excavation in hard or soft murrem / rocky area upto required
depth, supply and laying of protection bricks, supply and
backfilling with fine sand, leveling the ground to match with the
existing condition.
6) 'Laying of cable in the excavated trench / prepared trench /
cable tray / duct / hume pipe / channel / floor trunks when laid
inside or outside the building.
7) Connection of cable.
8) Supply & fixing of cable clamps, brackets, supports, route
markers etc. where ever required to fix the cables safely.
9) Earthing the glands and armouring with earthing clamp and
jumper and also connecting to common earth bar.
10) Testing of insulation and continuity of cable and submission of
reports to the client's representative.
11) To prepare submission drawing and to take approval of
consultant at each stage.
12) To prepare & submit as‐built drawing and handing over
240 document to end user.,3.5C X 240 SQ. MM. AL XLPE 100 Mtr.

72
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

LT CABLES,Supply, laying, connection, testing and commissioning


of heavy duty, low voltage, XLPE (IS 7098 ‐ PART‐II) insulated,
stranded AL / Cu conductor Armoured cables as per specification
& IS.
The cable shall have inner sheeth of XLPE and outer sheath of PVC
ST2 (FRSL) type with stranded AL/Cu conductor wherever
specified.
The cable shall be laid underground in excavated trench /
prepared trench / hume pipes when laid outside the building.
Cable shall be laid throught preapred trench / cable tray / duct /
hume pipe / channel / floor trunks etc when laid inside the
building.
The scope shall include:
1) Supply of Cables.
2) Delivery of the cables at site.
3) Unloading at site store.
4) Shifting of cable from site store to place of installation.
5) Excavation in hard or soft murrem / rocky area upto required
depth, supply and laying of protection bricks, supply and
backfilling with fine sand, leveling the ground to match with the
existing condition.
6) 'Laying of cable in the excavated trench / prepared trench /
cable tray / duct / hume pipe / channel / floor trunks when laid
inside or outside the building.
7) Connection of cable.
8) Supply & fixing of cable clamps, brackets, supports, route
markers etc. where ever required to fix the cables safely.
9) Earthing the glands and armouring with earthing clamp and
jumper and also connecting to common earth bar.
10) Testing of insulation and continuity of cable and submission of
reports to the client's representative.
11) To prepare submission drawing and to take approval of
consultant at each stage.
12) To prepare & submit as‐built drawing and handing over
241 document to end user.,3.5C X 120 SQ. MM. AL XLPE 770 Mtr.

73
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

LT CABLES,Supply, laying, connection, testing and commissioning


of heavy duty, low voltage, XLPE (IS 7098 ‐ PART‐II) insulated,
stranded AL / Cu conductor Armoured cables as per specification
& IS.
The cable shall have inner sheeth of XLPE and outer sheath of PVC
ST2 (FRSL) type with stranded AL/Cu conductor wherever
specified.
The cable shall be laid underground in excavated trench /
prepared trench / hume pipes when laid outside the building.
Cable shall be laid throught preapred trench / cable tray / duct /
hume pipe / channel / floor trunks etc when laid inside the
building.
The scope shall include:
1) Supply of Cables.
2) Delivery of the cables at site.
3) Unloading at site store.
4) Shifting of cable from site store to place of installation.
5) Excavation in hard or soft murrem / rocky area upto required
depth, supply and laying of protection bricks, supply and
backfilling with fine sand, leveling the ground to match with the
existing condition.
6) 'Laying of cable in the excavated trench / prepared trench /
cable tray / duct / hume pipe / channel / floor trunks when laid
inside or outside the building.
7) Connection of cable.
8) Supply & fixing of cable clamps, brackets, supports, route
markers etc. where ever required to fix the cables safely.
9) Earthing the glands and armouring with earthing clamp and
jumper and also connecting to common earth bar.
10) Testing of insulation and continuity of cable and submission of
reports to the client's representative.
11) To prepare submission drawing and to take approval of
consultant at each stage.
12) To prepare & submit as‐built drawing and handing over
242 document to end user.,3.5C X 70 SQ. MM. AL XLPE 260 Mtr.

74
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

LT CABLES,Supply, laying, connection, testing and commissioning


of heavy duty, low voltage, XLPE (IS 7098 ‐ PART‐II) insulated,
stranded AL / Cu conductor Armoured cables as per specification
& IS.
The cable shall have inner sheeth of XLPE and outer sheath of PVC
ST2 (FRSL) type with stranded AL/Cu conductor wherever
specified.
The cable shall be laid underground in excavated trench /
prepared trench / hume pipes when laid outside the building.
Cable shall be laid throught preapred trench / cable tray / duct /
hume pipe / channel / floor trunks etc when laid inside the
building.
The scope shall include:
1) Supply of Cables.
2) Delivery of the cables at site.
3) Unloading at site store.
4) Shifting of cable from site store to place of installation.
5) Excavation in hard or soft murrem / rocky area upto required
depth, supply and laying of protection bricks, supply and
backfilling with fine sand, leveling the ground to match with the
existing condition.
6) 'Laying of cable in the excavated trench / prepared trench /
cable tray / duct / hume pipe / channel / floor trunks when laid
inside or outside the building.
7) Connection of cable.
8) Supply & fixing of cable clamps, brackets, supports, route
markers etc. where ever required to fix the cables safely.
9) Earthing the glands and armouring with earthing clamp and
jumper and also connecting to common earth bar.
10) Testing of insulation and continuity of cable and submission of
reports to the client's representative.
11) To prepare submission drawing and to take approval of
consultant at each stage.
12) To prepare & submit as‐built drawing and handing over
243 document to end user.,3.5C X 50 SQ. MM. AL XLPE 300 Mtr.

75
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

LT CABLES,Supply, laying, connection, testing and commissioning


of heavy duty, low voltage, XLPE (IS 7098 ‐ PART‐II) insulated,
stranded AL / Cu conductor Armoured cables as per specification
& IS.
The cable shall have inner sheeth of XLPE and outer sheath of PVC
ST2 (FRSL) type with stranded AL/Cu conductor wherever
specified.
The cable shall be laid underground in excavated trench /
prepared trench / hume pipes when laid outside the building.
Cable shall be laid throught preapred trench / cable tray / duct /
hume pipe / channel / floor trunks etc when laid inside the
building.
The scope shall include:
1) Supply of Cables.
2) Delivery of the cables at site.
3) Unloading at site store.
4) Shifting of cable from site store to place of installation.
5) Excavation in hard or soft murrem / rocky area upto required
depth, supply and laying of protection bricks, supply and
backfilling with fine sand, leveling the ground to match with the
existing condition.
6) 'Laying of cable in the excavated trench / prepared trench /
cable tray / duct / hume pipe / channel / floor trunks when laid
inside or outside the building.
7) Connection of cable.
8) Supply & fixing of cable clamps, brackets, supports, route
markers etc. where ever required to fix the cables safely.
9) Earthing the glands and armouring with earthing clamp and
jumper and also connecting to common earth bar.
10) Testing of insulation and continuity of cable and submission of
reports to the client's representative.
11) To prepare submission drawing and to take approval of
consultant at each stage.
12) To prepare & submit as‐built drawing and handing over
244 document to end user.,3.5C X 25 SQ. MM. CU XLPE 250 Mtr.

76
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

LT CABLES,Supply, laying, connection, testing and commissioning


of heavy duty, low voltage, XLPE (IS 7098 ‐ PART‐II) insulated,
stranded AL / Cu conductor Armoured cables as per specification
& IS.
The cable shall have inner sheeth of XLPE and outer sheath of PVC
ST2 (FRSL) type with stranded AL/Cu conductor wherever
specified.
The cable shall be laid underground in excavated trench /
prepared trench / hume pipes when laid outside the building.
Cable shall be laid throught preapred trench / cable tray / duct /
hume pipe / channel / floor trunks etc when laid inside the
building.
The scope shall include:
1) Supply of Cables.
2) Delivery of the cables at site.
3) Unloading at site store.
4) Shifting of cable from site store to place of installation.
5) Excavation in hard or soft murrem / rocky area upto required
depth, supply and laying of protection bricks, supply and
backfilling with fine sand, leveling the ground to match with the
existing condition.
6) 'Laying of cable in the excavated trench / prepared trench /
cable tray / duct / hume pipe / channel / floor trunks when laid
inside or outside the building.
7) Connection of cable.
8) Supply & fixing of cable clamps, brackets, supports, route
markers etc. where ever required to fix the cables safely.
9) Earthing the glands and armouring with earthing clamp and
jumper and also connecting to common earth bar.
10) Testing of insulation and continuity of cable and submission of
reports to the client's representative.
11) To prepare submission drawing and to take approval of
consultant at each stage.
12) To prepare & submit as‐built drawing and handing over
245 document to end user.,4C X 16 SQ. MM. AL XLPE 2460 Mtr.

77
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

LT CABLES,Supply, laying, connection, testing and commissioning


of heavy duty, low voltage, XLPE (IS 7098 ‐ PART‐II) insulated,
stranded AL / Cu conductor Armoured cables as per specification
& IS.
The cable shall have inner sheeth of XLPE and outer sheath of PVC
ST2 (FRSL) type with stranded AL/Cu conductor wherever
specified.
The cable shall be laid underground in excavated trench /
prepared trench / hume pipes when laid outside the building.
Cable shall be laid throught preapred trench / cable tray / duct /
hume pipe / channel / floor trunks etc when laid inside the
building.
The scope shall include:
1) Supply of Cables.
2) Delivery of the cables at site.
3) Unloading at site store.
4) Shifting of cable from site store to place of installation.
5) Excavation in hard or soft murrem / rocky area upto required
depth, supply and laying of protection bricks, supply and
backfilling with fine sand, leveling the ground to match with the
existing condition.
6) 'Laying of cable in the excavated trench / prepared trench /
cable tray / duct / hume pipe / channel / floor trunks when laid
inside or outside the building.
7) Connection of cable.
8) Supply & fixing of cable clamps, brackets, supports, route
markers etc. where ever required to fix the cables safely.
9) Earthing the glands and armouring with earthing clamp and
jumper and also connecting to common earth bar.
10) Testing of insulation and continuity of cable and submission of
reports to the client's representative.
11) To prepare submission drawing and to take approval of
consultant at each stage.
12) To prepare & submit as‐built drawing and handing over
246 document to end user.,4C X 4 SQ. MM. CU XLPE 775 Mtr.

78
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

LT CABLESCABLE END TERMINATION AND CONNECTIONSupply,


fixing, connection, testing & commissioning of single compression
brass cable glands and crimping type Bimetalic lugs / sockets with
necessary tools and equipments as specified in specifications and
IS. For outdoor installations, double compression glands shall be
considered. The glands and lugs / sockets shall be suitable for
cable size and type mentioned above. The job also includes, if
necessary, supply and fixing of extension busbar of same material
on circuit breaker or panel board terminal / connector to
connect more than one no. of parallel cables or to connect higher
size cable to lower size unit. The job also includes earthing the
glands and armour of the cable with common earth bar or flexible
247 copper mesh.,3.5C X 240 SQ. MM. AL XLPE 4 Each

79
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

LT CABLESCABLE END TERMINATION AND CONNECTIONSupply,


fixing, connection, testing & commissioning of single compression
brass cable glands and crimping type Bimetalic lugs / sockets with
necessary tools and equipments as specified in specifications and
IS. For outdoor installations, double compression glands shall be
considered. The glands and lugs / sockets shall be suitable for
cable size and type mentioned above. The job also includes, if
necessary, supply and fixing of extension busbar of same material
on circuit breaker or panel board terminal / connector to
connect more than one no. of parallel cables or to connect higher
size cable to lower size unit. The job also includes earthing the
glands and armour of the cable with common earth bar or flexible
248 copper mesh.,3.5C X 120 SQ. MM. AL XLPE 8 Each

80
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

LT CABLESCABLE END TERMINATION AND CONNECTIONSupply,


fixing, connection, testing & commissioning of single compression
brass cable glands and crimping type Bimetalic lugs / sockets with
necessary tools and equipments as specified in specifications and
IS. For outdoor installations, double compression glands shall be
considered. The glands and lugs / sockets shall be suitable for
cable size and type mentioned above. The job also includes, if
necessary, supply and fixing of extension busbar of same material
on circuit breaker or panel board terminal / connector to
connect more than one no. of parallel cables or to connect higher
size cable to lower size unit. The job also includes earthing the
glands and armour of the cable with common earth bar or flexible
249 copper mesh.,3.5C X 70 SQ. MM. AL XLPE 4 Each

81
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

LT CABLESCABLE END TERMINATION AND CONNECTIONSupply,


fixing, connection, testing & commissioning of single compression
brass cable glands and crimping type Bimetalic lugs / sockets with
necessary tools and equipments as specified in specifications and
IS. For outdoor installations, double compression glands shall be
considered. The glands and lugs / sockets shall be suitable for
cable size and type mentioned above. The job also includes, if
necessary, supply and fixing of extension busbar of same material
on circuit breaker or panel board terminal / connector to
connect more than one no. of parallel cables or to connect higher
size cable to lower size unit. The job also includes earthing the
glands and armour of the cable with common earth bar or flexible
250 copper mesh.,3.5C X 50 SQ. MM. AL XLPE 2 Each

LT CABLESCABLE END TERMINATION AND CONNECTIONSupply,


fixing, connection, testing & commissioning of single compression
brass cable glands and crimping type Bimetalic lugs / sockets with
necessary tools and equipments as specified in specifications and
IS. For outdoor installations, double compression glands shall be
considered. The glands and lugs / sockets shall be suitable for
cable size and type mentioned above. The job also includes, if
necessary, supply and fixing of extension busbar of same material
on circuit breaker or panel board terminal / connector to
connect more than one no. of parallel cables or to connect higher
size cable to lower size unit. The job also includes earthing the
glands and armour of the cable with common earth bar or flexible
251 copper mesh.,3.5C X 25 SQ. MM. CU XLPE 4 Each

82
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

LT CABLESCABLE END TERMINATION AND CONNECTIONSupply,


fixing, connection, testing & commissioning of single compression
brass cable glands and crimping type Bimetalic lugs / sockets with
necessary tools and equipments as specified in specifications and
IS. For outdoor installations, double compression glands shall be
considered. The glands and lugs / sockets shall be suitable for
cable size and type mentioned above. The job also includes, if
necessary, supply and fixing of extension busbar of same material
on circuit breaker or panel board terminal / connector to
connect more than one no. of parallel cables or to connect higher
size cable to lower size unit. The job also includes earthing the
glands and armour of the cable with common earth bar or flexible
252 copper mesh.,4C X 16 SQ. MM. AL XLPE 32 Each

LT CABLESCABLE END TERMINATION AND CONNECTIONSupply,


fixing, connection, testing & commissioning of single compression
brass cable glands and crimping type Bimetalic lugs / sockets with
necessary tools and equipments as specified in specifications and
IS. For outdoor installations, double compression glands shall be
considered. The glands and lugs / sockets shall be suitable for
cable size and type mentioned above. The job also includes, if
necessary, supply and fixing of extension busbar of same material
on circuit breaker or panel board terminal / connector to
connect more than one no. of parallel cables or to connect higher
size cable to lower size unit. The job also includes earthing the
glands and armour of the cable with common earth bar or flexible
253 copper mesh.,4C X 4 SQ. MM. CU XLPE 36 Each

83
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

CABLE TRAY & UNDER FLOOR TRUNKINGSupply, Installation, laying


and connection of G.I. Perforated, Ladder and Wired Mesh Type
cable tray with bends, tees, clamps and couplers for fixing of
cable.
The job also includes to paint the structure with two coats of red
oxide and two coats color of enamel paint of approved brands. All
material shall be Hot dip galvanised as per IS and specifications.
The structural steel supports for the trays are to be provided at
every 1.2 Mtrs. as per technical specifications.
Standard length of cable tray shall be 3 meters.300 mm. wide.,
254 perforated cable tray, side height 50 mm, thickness 1.5 mm 250 Mtr.

CABLE TRAY & UNDER FLOOR TRUNKINGSupply, Installation, laying


and connection of G.I. Perforated, Ladder and Wired Mesh Type
cable tray with bends, tees, clamps and couplers for fixing of
cable.
The job also includes to paint the structure with two coats of red
oxide and two coats color of enamel paint of approved brands. All
material shall be Hot dip galvanised as per IS and specifications.
The structural steel supports for the trays are to be provided at
every 1.2 Mtrs. as per technical specifications.
Standard length of cable tray shall be 3 meters.Providing and
erecting iron clad cable route marker duly marked with ELE.CABLE
of size 23 cms.X 12 cms. Flushed with ground in cement
255 foundation as directed by Engineer in charge. 40 Each
CABLE TRAY & UNDER FLOOR TRUNKINGHUME PIPES
Supply & installation of Pipes (NP2, RCC with collar) as per below
sizes for providing passages to lay the cables.Supply and
256 Installation of 250 mm dia RCC Hume Pipe 300 Mtr.

84
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

CABLE TRAY & UNDER FLOOR TRUNKINGHUME PIPES


Supply & installation of Pipes (NP2, RCC with collar) as per below
sizes for providing passages to lay the cables.Supply and
257 Installation of 100 mm dia RCC Hume Pipe 320 Mtr.

CABLE TRAY & UNDER FLOOR TRUNKINGEXCAVATED CABLE


TRENCH
Excavation in all sorts of soils including hard rock/ murrum for
required depth and back filling. Contractor's scope of work under
this item shall include disposal of surplus earth and shoring,
shuttering and dewatering if required. Excavation shall be done as
per directions of Engineer‐in‐charge. Necessary brick for
258 protection, sand filling.600 mm wide and 750 mm deep 200 Mtrs.

WALL MOUNTED CABLE MANAGEMENT SYSTEMS Supply and


laying of wall mounted cable management system having
protection class IP 41, fabricated from self extinguishing non‐
flammable propagating UPVC material. Trunk shall have wall
thickness of 2.5 mm and having two compartment with following
dimensions. The rate shall include supply and installation of trunks
with end caps, internal couplers, internal corners, wall plates,
bends, joints, flendge couplers etc. 100 (H) x 50 (D) mm ‐ 2
259 Compartment 200 Mtrs.

85
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

CABLE TRAY & UNDER FLOOR TRUNKINGUNDER FLOOR TRUNKING


JUNCTION BOX , Supply and installation of Hot dip galvanised, GI
fabricated floor junction boxes as per relevent IS. The job includes
aligning of boxes with the raceways and making necessary
arrangement to take the knock outs from them to lay the wires,
with all necessary accessories required to complte the job. (The
civil work like cutting of the floor to ambed in junction boxes in the
floor to be inlcuded in the rate). Top cover shall be made up from
2.5 mm thick GI steel plate. Equivalent to Legrand/MK make.350
(L) x 350 (W) x 60/75 (H) mm JB ‐ 2 mm thick (One trap & 3
260 Compartments) 0 NOs

CABLE TRAY & UNDER FLOOR TRUNKINGUNDER FLOOR TRUNKING


JUNCTION BOX , Supply and installation of Hot dip galvanised, GI
fabricated floor junction boxes as per relevent IS. The job includes
aligning of boxes with the raceways and making necessary
arrangement to take the knock outs from them to lay the wires,
with all necessary accessories required to complte the job. (The
civil work like cutting of the floor to ambed in junction boxes in the
floor to be inlcuded in the rate). Top cover shall be made up from
2.5 mm thick GI steel plate. Equivalent to Legrand/MK make.150
(L) x 150 (W) x 60 (H) mm JB ‐ 2 mm thick (One trap & 1
261 Compartments) 0 NOs

CABLE TRAY & UNDER FLOOR TRUNKINGSupply and laying of wall


mounted cable management system having protection class IP 41,
fabricated from self extinguishing non‐flammable propagating
UPVC material. Trunk shall have wall thickness of 2.5 mm and
having two compartment with following dimensions.The rate shall
include supply and installation of trunks with end caps, internal
couplers, internal corners, wall plates, bends, joints, flendge
262 couplers etc.75 (H) x 50 (D) mm ‐ 2 Compartment 0 Mtrs.

86
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

CABLE TRAY & UNDER FLOOR TRUNKINGSupply and laying of wall


mounted cable management system having protection class IP 41,
fabricated from self extinguishing non‐flammable propagating
UPVC material. Trunk shall have wall thickness of 2.5 mm and
having two compartment with following dimensions.The rate shall
include supply and installation of trunks with end caps, internal
couplers, internal corners, wall plates, bends, joints, flendge
263 couplers etc.100 (H) x 50 (D) mm ‐ 2 Compartment 0 Mtrs.

INTERNAL WIRINGWiring for Light Points Directly Controlled from


DBs
Supply, installation, connection, testing & commissioning of
following outlet points as per Specification & IS. The unit rate for
the point shall consist of the circuit wiring from LDB to outlet
point through MCB as required & including the outlet points with
connector & sockets. A point shall include in addition to phase &
neutral wire, earth continuity wire from LDB to the final
termination at outlet points. All the wiring, outlet points shall be
done in a surface / concealed manner with ISI approved medium
duty, rigid MMS PVC, ISI conduit of minimum 25 mm. dia. using
650 V FRLS copper conductor wire. Supply and installation of front
suitable plate, PVC back box with brass chromium / cadmium
plated machine screws etc. shall be part of job.Cost of MCB shall
not be considered in point rate.
Wire Size:
Phase & Neutral : 2.5 mm2 Cu FRLS flexible wire (650 V)
Earth : 1.5 mm2 Cu FRLS flexible wire (650 V)
Average Circuit Length:
From LDB to Primary Light Point : 15 MTR.
From Primary Point to Secondary Light Point: 5 MTR.Primary light
264 points controlled by one 6A MCB in LDB. 2 Each

87
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

INTERNAL WIRINGWiring for Light Points Directly Controlled from


DBs
Supply, installation, connection, testing & commissioning of
following outlet points as per Specification & IS. The unit rate for
the point shall consist of the circuit wiring from LDB to outlet
point through MCB as required & including the outlet points with
connector & sockets. A point shall include in addition to phase &
neutral wire, earth continuity wire from LDB to the final
termination at outlet points. All the wiring, outlet points shall be
done in a surface / concealed manner with ISI approved medium
duty, rigid MMS PVC, ISI conduit of minimum 25 mm. dia. using
650 V FRLS copper conductor wire. Supply and installation of front
suitable plate, PVC back box with brass chromium / cadmium
plated machine screws etc. shall be part of job.Cost of MCB shall
not be considered in point rate.
Wire Size:
Phase & Neutral : 2.5 mm2 Cu FRLS flexible wire (650 V)
Earth : 1.5 mm2 Cu FRLS flexible wire (650 V)
Average Circuit Length:
From LDB to Primary Light Point : 15 MTR.
From Primary Point to Secondary Light Point: 5 MTR.Secondary
265 light points controlled by one 6A MCB in LDB. 8 Each

88
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

INTERNAL WIRINGWiring for Light Points Controlled from Switch


Boards
Supply, installation, connection, testing & commissioning of
following outlet points as per Specification & IS. The unit rate for
the point shall consist of the circuit wiring from LDB and/or switch
board to outlet point through switch as required & including the
outlet points with connector & sockets. A point shall include in
addition to phase & neutral wire, earth continuity wire from LDB
to the final termination at outlet points.All the wiring, outlet
points shall be done in a surface / concealed manner with ISI
approved medium duty, rigid FR PVC, ISI conduit of minimum 25
mm. dia. using 650 V FRLS copper conductor wire. Supply and
installation of Modular switches with suitable plate, PVC back box
with brass chromium / cadmium plated machine screws etc. shall
be part of job.
Wire Size:
Phase & Neutral : 1.5 mm2 Cu FRLS flexible wire (650 V)
Earth : 1.0 mm2 Cu FRLS flexible wire (650 V)
Offwire size = 1.0 sqmm (P+N+E)
Average Circuit Length:
From SB to Primary Light Point: 5 MTR.
From Primary to Secondary Light Point: 3 MTR.Primary light points
266 controlled by one 6A switch 700 Each

89
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

INTERNAL WIRINGWiring for Light Points Controlled from Switch


Boards
Supply, installation, connection, testing & commissioning of
following outlet points as per Specification & IS. The unit rate for
the point shall consist of the circuit wiring from LDB and/or switch
board to outlet point through switch as required & including the
outlet points with connector & sockets. A point shall include in
addition to phase & neutral wire, earth continuity wire from LDB
to the final termination at outlet points.All the wiring, outlet
points shall be done in a surface / concealed manner with ISI
approved medium duty, rigid FR PVC, ISI conduit of minimum 25
mm. dia. using 650 V FRLS copper conductor wire. Supply and
installation of Modular switches with suitable plate, PVC back box
with brass chromium / cadmium plated machine screws etc. shall
be part of job.
Wire Size:
Phase & Neutral : 1.5 mm2 Cu FRLS flexible wire (650 V)
Earth : 1.0 mm2 Cu FRLS flexible wire (650 V)
Offwire size = 1.0 sqmm (P+N+E)
Average Circuit Length:
From SB to Primary Light Point: 5 MTR.
From Primary to Secondary Light Point: 3 MTR.Secondary light
267 points controlled by one 6A switch 490 Each

90
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

INTERNAL WIRINGWiring for Light Points Controlled from Switch


Boards
Supply, installation, connection, testing & commissioning of
following outlet points as per Specification & IS. The unit rate for
the point shall consist of the circuit wiring from LDB and/or switch
board to outlet point through switch as required & including the
outlet points with connector & sockets. A point shall include in
addition to phase & neutral wire, earth continuity wire from LDB
to the final termination at outlet points.All the wiring, outlet
points shall be done in a surface / concealed manner with ISI
approved medium duty, rigid FR PVC, ISI conduit of minimum 25
mm. dia. using 650 V FRLS copper conductor wire. Supply and
installation of Modular switches with suitable plate, PVC back box
with brass chromium / cadmium plated machine screws etc. shall
be part of job.
Wire Size:
Phase & Neutral : 1.5 mm2 Cu FRLS flexible wire (650 V)
Earth : 1.0 mm2 Cu FRLS flexible wire (650 V)
Offwire size = 1.0 sqmm (P+N+E)
Average Circuit Length:
From SB to Primary Light Point: 5 MTR.
From Primary to Secondary Light Point: 3 MTR.Two way light
268 points controlled by two 6A switch 278 Each

91
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

INTERNAL WIRINGWiring for Light Points Controlled from Switch


Boards
Supply, installation, connection, testing & commissioning of
following outlet points as per Specification & IS. The unit rate for
the point shall consist of the circuit wiring from LDB and/or switch
board to outlet point through switch as required & including the
outlet points with connector & sockets. A point shall include in
addition to phase & neutral wire, earth continuity wire from LDB
to the final termination at outlet points.All the wiring, outlet
points shall be done in a surface / concealed manner with ISI
approved medium duty, rigid FR PVC, ISI conduit of minimum 25
mm. dia. using 650 V FRLS copper conductor wire. Supply and
installation of Modular switches with suitable plate, PVC back box
with brass chromium / cadmium plated machine screws etc. shall
be part of job.
Wire Size:
Phase & Neutral : 1.5 mm2 Cu FRLS flexible wire (650 V)
Earth : 1.0 mm2 Cu FRLS flexible wire (650 V)
Offwire size = 1.0 sqmm (P+N+E)
Average Circuit Length:
From SB to Primary Light Point: 5 MTR.
From Primary to Secondary Light Point: 3 MTR.6A socket with
one 6A switch on switch board with cover plate and all required
269 accessories 251 Each

92
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

INTERNAL WIRINGWiring for Light Points Controlled from Switch


Boards
Supply, installation, connection, testing & commissioning of
following outlet points as per Specification & IS. The unit rate for
the point shall consist of the circuit wiring from LDB and/or switch
board to outlet point through switch as required & including the
outlet points with connector & sockets. A point shall include in
addition to phase & neutral wire, earth continuity wire from LDB
to the final termination at outlet points.All the wiring, outlet
points shall be done in a surface / concealed manner with ISI
approved medium duty, rigid FR PVC, ISI conduit of minimum 25
mm. dia. using 650 V FRLS copper conductor wire. Supply and
installation of Modular switches with suitable plate, PVC back box
with brass chromium / cadmium plated machine screws etc. shall
be part of job.
Wire Size:
Phase & Neutral : 1.5 mm2 Cu FRLS flexible wire (650 V)
Earth : 1.0 mm2 Cu FRLS flexible wire (650 V)
Offwire size = 1.0 sqmm (P+N+E)
Average Circuit Length:
From SB to Primary Light Point: 5 MTR.
From Primary to Secondary Light Point: 3 MTR.6A socket with
one 6A switch at convinient location with cover plate and all
270 required accessories 385 Each

93
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

INTERNAL WIRINGWiring for Light Points Controlled from Switch


Boards
Supply, installation, connection, testing & commissioning of
following outlet points as per Specification & IS. The unit rate for
the point shall consist of the circuit wiring from LDB and/or switch
board to outlet point through switch as required & including the
outlet points with connector & sockets. A point shall include in
addition to phase & neutral wire, earth continuity wire from LDB
to the final termination at outlet points.All the wiring, outlet
points shall be done in a surface / concealed manner with ISI
approved medium duty, rigid FR PVC, ISI conduit of minimum 25
mm. dia. using 650 V FRLS copper conductor wire. Supply and
installation of Modular switches with suitable plate, PVC back box
with brass chromium / cadmium plated machine screws etc. shall
be part of job.
Wire Size:
Phase & Neutral : 1.5 mm2 Cu FRLS flexible wire (650 V)
Earth : 1.0 mm2 Cu FRLS flexible wire (650 V)
Offwire size = 1.0 sqmm (P+N+E)
Average Circuit Length:
From SB to Primary Light Point: 5 MTR.
From Primary to Secondary Light Point: 3 MTR.One Fan point
controlled by one 6 A SWITCH. The cost shall include supply of
271 Modular step type Fan regulator (hum free). 469 Each

94
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

INTERNAL WIRINGWiring for Light Points Controlled from Switch


Boards
Supply, installation, connection, testing & commissioning of
following outlet points as per Specification & IS. The unit rate for
the point shall consist of the circuit wiring from LDB and/or switch
board to outlet point through switch as required & including the
outlet points with connector & sockets. A point shall include in
addition to phase & neutral wire, earth continuity wire from LDB
to the final termination at outlet points.All the wiring, outlet
points shall be done in a surface / concealed manner with ISI
approved medium duty, rigid FR PVC, ISI conduit of minimum 25
mm. dia. using 650 V FRLS copper conductor wire. Supply and
installation of Modular switches with suitable plate, PVC back box
with brass chromium / cadmium plated machine screws etc. shall
be part of job.
Wire Size:
Phase & Neutral : 1.5 mm2 Cu FRLS flexible wire (650 V)
Earth : 1.0 mm2 Cu FRLS flexible wire (650 V)
Offwire size = 1.0 sqmm (P+N+E)
Average Circuit Length:
From SB to Primary Light Point: 5 MTR.
From Primary to Secondary Light Point: 3 MTR.One Exhaust Fan
(5A plug socket) controlled by 6A switch and mounting plate with
272 necessary accessories. Supply of exhaust fan shall not be included. 86 Each

95
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

INTERNAL WIRINGWiring for Light Points Controlled from Switch


Boards
Supply, installation, connection, testing & commissioning of
following outlet points as per Specification & IS. The unit rate for
the point shall consist of the circuit wiring from LDB and/or switch
board to outlet point through switch as required & including the
outlet points with connector & sockets. A point shall include in
addition to phase & neutral wire, earth continuity wire from LDB
to the final termination at outlet points.All the wiring, outlet
points shall be done in a surface / concealed manner with ISI
approved medium duty, rigid FR PVC, ISI conduit of minimum 25
mm. dia. using 650 V FRLS copper conductor wire. Supply and
installation of Modular switches with suitable plate, PVC back box
with brass chromium / cadmium plated machine screws etc. shall
be part of job.
Wire Size:
Phase & Neutral : 1.5 mm2 Cu FRLS flexible wire (650 V)
Earth : 1.0 mm2 Cu FRLS flexible wire (650 V)
Offwire size = 1.0 sqmm (P+N+E)
Average Circuit Length:
From SB to Primary Light Point: 5 MTR.
From Primary to Secondary Light Point: 3 MTR.Providing following
type of Modular Type Accessories mounted with pvc / metallic
box, single mounting base frame covered with textured / metallic
front plate , modules erected with necessary connection. As
desired by Engineer In charge
273 (15) 32 Amps. DP switch with Indicator. Cat‐III (MASTER SWITCH) 98 Each

96
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

INTERNAL WIRINGMains Wiring for Lighting Circuits


Supply, laying, connection and testing of lighting wiring from LDB
to switch board with following wires to be laid through PVC
condiut in concealed/surface manner.
Cost of MCB and conduit shall not be considered in point rate.
Wire Size:
Phase & Neutral : 2.5 mm2 Cu FRLS flexible wire (650 V)
Earth : 1.5 mm2 Cu FRLS flexible wire wire (650 V)Supply, laying,
connection and testing of above mentioined wires from LDB to
switchboard to be laid through electrical channel / floor raceway /
274 PVC condiut. 5640 Mtr.

INTERNAL WIRINGWiring for Raw Power Points


Supply, laying, connection and testing of raw power socket wiring
from PDB to raw power point with following wires to be laid
through electrical channel / floor raceway / PVC condiut in
concealed/surface manner. (cost of Channel / raceway not to be
included in their rate.)
Cost of MCB shall not be considered in point rate.
Wire Size:
Phase & Neutral : 4.0 mm2 Cu FRLS flexible wire (650 V)
Earth : 2.5 mm2 Cu FRLS flexible wire wire (650 V)Supply ,fixing,
connection and testing of 5‐pin 16 A power plug socket alongwith
16A switch with top cover plate, PVC back box suitable for
275 modular plate with all accessories to complete the job. 163 Each

97
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

INTERNAL WIRINGWiring for Raw Power Points


Supply, laying, connection and testing of raw power socket wiring
from PDB to raw power point with following wires to be laid
through electrical channel / floor raceway / PVC condiut in
concealed/surface manner. (cost of Channel / raceway not to be
included in their rate.)
Cost of MCB shall not be considered in point rate.
Wire Size:
Phase & Neutral : 4.0 mm2 Cu FRLS flexible wire (650 V)
Earth : 2.5 mm2 Cu FRLS flexible wire wire (650 V)Supply, laying,
connection and testing of above mentioined wires from PDB to
raw power socket to be laid through electrical channel / floor
276 raceway / PVC condiut. 4660 Mtr.

98
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

LIGHT FIXTURESupply,Installation, assembling, connection, testing


& commissioning of fixtures complete with suitable rating
tubeslamps, high power factor improving capacitor, HF Electronic
Ballast , Starter and all other necessary accessories to complete
the installations.
Note : All light fixture will have Super low loss Electronics ballast
with PF>0.85 & harmonics within permissible limits specified as
per IS,
The rate shall include the following :
1) 'Unloading of light fixture at site.
2) Shifting of light fixture with all tools & accessories from site
store to the site.
3) Installation and assemble of light fixture at site.
4) 'Earthing of light fixture neutral & body.
5) 'Testing of light fixture as per IS before commissioning.
6) To prepare submission drawing and to take approval of
consultant at each stage.
7) To prepare & submit as‐built drawing and handing over
document to end user.Supply, Installation, testing and
commissioning of recessed mounted 36W LED Linear LED tubelight
Length 4ft (1200 mm) flush with difused glass. (Wall mounted /
277 Ceiling mounted) 937 Each

99
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

LIGHT FIXTURESupply,Installation, assembling, connection, testing


& commissioning of fixtures complete with suitable rating
tubeslamps, high power factor improving capacitor, HF Electronic
Ballast , Starter and all other necessary accessories to complete
the installations.
Note : All light fixture will have Super low loss Electronics ballast
with PF>0.85 & harmonics within permissible limits specified as
per IS,
The rate shall include the following :
1) 'Unloading of light fixture at site.
2) Shifting of light fixture with all tools & accessories from site
store to the site.
3) Installation and assemble of light fixture at site.
4) 'Earthing of light fixture neutral & body.
5) 'Testing of light fixture as per IS before commissioning.
6) To prepare submission drawing and to take approval of
consultant at each stage.
7) To prepare & submit as‐built drawing and handing over
document to end user.Supply, Installation, testing and
commissioning of recessed mounted 18W LED down light fixture
278 Eq. to CGL Cat No. ‐ LCDD‐18‐CDL/TL/WW 288 Each

100
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

LIGHT FIXTURESupply,Installation, assembling, connection, testing


& commissioning of fixtures complete with suitable rating
tubeslamps, high power factor improving capacitor, HF Electronic
Ballast , Starter and all other necessary accessories to complete
the installations.
Note : All light fixture will have Super low loss Electronics ballast
with PF>0.85 & harmonics within permissible limits specified as
per IS,
The rate shall include the following :
1) 'Unloading of light fixture at site.
2) Shifting of light fixture with all tools & accessories from site
store to the site.
3) Installation and assemble of light fixture at site.
4) 'Earthing of light fixture neutral & body.
5) 'Testing of light fixture as per IS before commissioning.
6) To prepare submission drawing and to take approval of
consultant at each stage.
7) To prepare & submit as‐built drawing and handing over
document to end user.Supply, Installation, testing and
commissioning of recessed mounted 40W LED down light fixture
279 Eq. to CGL Cat No. ‐ LCSFR6‐40‐CDL 10 Each

101
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

LIGHT FIXTURESupply,Installation, assembling, connection, testing


& commissioning of fixtures complete with suitable rating
tubeslamps, high power factor improving capacitor, HF Electronic
Ballast , Starter and all other necessary accessories to complete
the installations.
Note : All light fixture will have Super low loss Electronics ballast
with PF>0.85 & harmonics within permissible limits specified as
per IS,
The rate shall include the following :
1) 'Unloading of light fixture at site.
2) Shifting of light fixture with all tools & accessories from site
store to the site.
3) Installation and assemble of light fixture at site.
4) 'Earthing of light fixture neutral & body.
5) 'Testing of light fixture as per IS before commissioning.
6) To prepare submission drawing and to take approval of
consultant at each stage.
7) To prepare & submit as‐built drawing and handing over
document to end user.Supply, Installation, testing and
280 commissioning of wall / ceiling mounted 10W LED bracket lights. 218 Each

102
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

LIGHT FIXTURESupply,Installation, assembling, connection, testing


& commissioning of fixtures complete with suitable rating
tubeslamps, high power factor improving capacitor, HF Electronic
Ballast , Starter and all other necessary accessories to complete
the installations.
Note : All light fixture will have Super low loss Electronics ballast
with PF>0.85 & harmonics within permissible limits specified as
per IS,
The rate shall include the following :
1) 'Unloading of light fixture at site.
2) Shifting of light fixture with all tools & accessories from site
store to the site.
3) Installation and assemble of light fixture at site.
4) 'Earthing of light fixture neutral & body.
5) 'Testing of light fixture as per IS before commissioning.
6) To prepare submission drawing and to take approval of
consultant at each stage.
7) To prepare & submit as‐built drawing and handing over
document to end user.Providing & Erecting following Shockproof
tissino type accessories erected on 3 mm thick PC (Polycarbonate)
sheet in PVC/ Metal Box. erected on wall/ ceiling.
281 Bakelite lamp holder 218 Each

103
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

LIGHT FIXTURESupply,Installation, assembling, connection, testing


& commissioning of fixtures complete with suitable rating
tubeslamps, high power factor improving capacitor, HF Electronic
Ballast , Starter and all other necessary accessories to complete
the installations.
Note : All light fixture will have Super low loss Electronics ballast
with PF>0.85 & harmonics within permissible limits specified as
per IS,
The rate shall include the following :
1) 'Unloading of light fixture at site.
2) Shifting of light fixture with all tools & accessories from site
store to the site.
3) Installation and assemble of light fixture at site.
4) 'Earthing of light fixture neutral & body.
5) 'Testing of light fixture as per IS before commissioning.
6) To prepare submission drawing and to take approval of
consultant at each stage.
7) To prepare & submit as‐built drawing and handing over
document to end user.Half Bracket Light 24 watts to 36 watts,
Surge ‐4KV
282 (at canteen periphery) 7 Each

104
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

LIGHT FIXTURESupply,Installation, assembling, connection, testing


& commissioning of fixtures complete with suitable rating
tubeslamps, high power factor improving capacitor, HF Electronic
Ballast , Starter and all other necessary accessories to complete
the installations.
Note : All light fixture will have Super low loss Electronics ballast
with PF>0.85 & harmonics within permissible limits specified as
per IS,
The rate shall include the following :
1) 'Unloading of light fixture at site.
2) Shifting of light fixture with all tools & accessories from site
store to the site.
3) Installation and assemble of light fixture at site.
4) 'Earthing of light fixture neutral & body.
5) 'Testing of light fixture as per IS before commissioning.
6) To prepare submission drawing and to take approval of
consultant at each stage.
7) To prepare & submit as‐built drawing and handing over
document to end user.Providing street light pole bracket
comprising main Light Class MS tube of 4.2 cms. outside dia.
complete with suitable M.S. sleeve tubing of approx. 45cms.length
and suitable for 76.5mm. /80 mm or require size pole top having
sufficient fastners for fixing the brackets and having suitable rise
as per site condition as directed and spread of 2 mtr.with suitable
welded stiffener reducer and with lock nut complete painted with
one coat of Red oxide / PU base primer and two coats of
Aluminium / PU paint. Suitable for side entry fitting brackets of
283 following nos of arms Single Arm bracket 2 Mtr 7 Each

105
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

LIGHT FIXTURESupply,Installation, assembling, connection, testing


& commissioning of fixtures complete with suitable rating
tubeslamps, high power factor improving capacitor, HF Electronic
Ballast , Starter and all other necessary accessories to complete
the installations.
Note : All light fixture will have Super low loss Electronics ballast
with PF>0.85 & harmonics within permissible limits specified as
per IS,
The rate shall include the following :
1) 'Unloading of light fixture at site.
2) Shifting of light fixture with all tools & accessories from site
store to the site.
3) Installation and assemble of light fixture at site.
4) 'Earthing of light fixture neutral & body.
5) 'Testing of light fixture as per IS before commissioning.
6) To prepare submission drawing and to take approval of
consultant at each stage.
7) To prepare & submit as‐built drawing and handing over
document to end user.Supply, Installation, testing and
commissioning of 40W LED FLOOD LIGHT.
284 (On terrace of the buildings) 20 Each

106
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

LIGHT FIXTURESupply,Installation, assembling, connection, testing


& commissioning of fixtures complete with suitable rating
tubeslamps, high power factor improving capacitor, HF Electronic
Ballast , Starter and all other necessary accessories to complete
the installations.
Note : All light fixture will have Super low loss Electronics ballast
with PF>0.85 & harmonics within permissible limits specified as
per IS,
The rate shall include the following :
1) 'Unloading of light fixture at site.
2) Shifting of light fixture with all tools & accessories from site
store to the site.
3) Installation and assemble of light fixture at site.
4) 'Earthing of light fixture neutral & body.
5) 'Testing of light fixture as per IS before commissioning.
6) To prepare submission drawing and to take approval of
consultant at each stage.
7) To prepare & submit as‐built drawing and handing over
document to end user.Supply,Installation, testing &
285 commissioning of 1200mm Dia ceiling fan. 469 Each

107
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

LIGHT FIXTURESupply,Installation, assembling, connection, testing


& commissioning of fixtures complete with suitable rating
tubeslamps, high power factor improving capacitor, HF Electronic
Ballast , Starter and all other necessary accessories to complete
the installations.
Note : All light fixture will have Super low loss Electronics ballast
with PF>0.85 & harmonics within permissible limits specified as
per IS,
The rate shall include the following :
1) 'Unloading of light fixture at site.
2) Shifting of light fixture with all tools & accessories from site
store to the site.
3) Installation and assemble of light fixture at site.
4) 'Earthing of light fixture neutral & body.
5) 'Testing of light fixture as per IS before commissioning.
6) To prepare submission drawing and to take approval of
consultant at each stage.
7) To prepare & submit as‐built drawing and handing over
document to end user.Supply, Installation, testing and
286 commissioning of 300mm dia exhaust fan. 86 Each

108
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

LIGHT FIXTURESupply,Installation, assembling, connection, testing


& commissioning of fixtures complete with suitable rating
tubeslamps, high power factor improving capacitor, HF Electronic
Ballast , Starter and all other necessary accessories to complete
the installations.
Note : All light fixture will have Super low loss Electronics ballast
with PF>0.85 & harmonics within permissible limits specified as
per IS,
The rate shall include the following :
1) 'Unloading of light fixture at site.
2) Shifting of light fixture with all tools & accessories from site
store to the site.
3) Installation and assemble of light fixture at site.
4) 'Earthing of light fixture neutral & body.
5) 'Testing of light fixture as per IS before commissioning.
6) To prepare submission drawing and to take approval of
consultant at each stage.
7) To prepare & submit as‐built drawing and handing over
document to end user.Supply, Installation, testing and
287 commissioning of decorative bell push point with bell push switch 25 Each

109
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

EXTERNAL LIGHTINGSupply,eraction, assembling, checking and


testing of of decorative external light poles and high mast with
fittings and clamps as specified in Specification. The unit rate shall
also include following :
1) Fixing of pole with Sintex eq. Junction box (IP 65) of
300x200x105 mm with 8. way connector & 2 Nos. of 6 A DP MCB,
38. mm. dia., PVC cable entry & exit conduit as required.
2) Supply and laying of 3 nos. 38 mm. dia. 'B' Class G.I pipe suitable
for XLPE cable entry and exit to junction box as required.
3) Concrete coping with base plate & necessary civil works.
4) Earthing and painting.
5) Supply & connecting of wiring from junction box to the light
fixture, using 3c x 2.5 sq.mm. PVC copper conductor, flexible
cable.
6) Concrete coping with base plate & necessary civil works
7) Excavation and back fillingSupply, Installation, testing and
288 commissioning of 45W LED street light fixture. 23 Each

110
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

EXTERNAL LIGHTINGSupply,eraction, assembling, checking and


testing of of decorative external light poles and high mast with
fittings and clamps as specified in Specification. The unit rate shall
also include following :
1) Fixing of pole with Sintex eq. Junction box (IP 65) of
300x200x105 mm with 8. way connector & 2 Nos. of 6 A DP MCB,
38. mm. dia., PVC cable entry & exit conduit as required.
2) Supply and laying of 3 nos. 38 mm. dia. 'B' Class G.I pipe suitable
for XLPE cable entry and exit to junction box as required.
3) Concrete coping with base plate & necessary civil works.
4) Earthing and painting.
5) Supply & connecting of wiring from junction box to the light
fixture, using 3c x 2.5 sq.mm. PVC copper conductor, flexible
cable.
6) Concrete coping with base plate & necessary civil works
7) Excavation and back fillingSupply, Installation, testing and
commissioning of 7.5 MTR Height GI Pole (for Street Lights) as
per specification, drawing and relavent IS. Scope shall cover supply
and installation of pole, cross arm, suitable size junction box, pipe
for cable, wiring, earthing etc. to complete the job. Scope doesn't
289 cover light fixture. 23 Each

EXTERNAL LIGHTINGCABLING :
Supply, laying, testing and connecting of medium voltage cable for
290 external lighting4C X 16 SQ. MM. AL XLPE 1040 Mtr.

EXTERNAL LIGHTINGCABLE END TERMINATION:


'Supply, testing and connection of cable end termination 4C X 16
291 SQ. MM. AL XLPE 50 Each

111
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

EARTHINGEarthing Stations
Supply, installation, connection and testing of plate type / pipe
type earthing station for various electrical equipments and
systems as per IS with following.
1) Excavation in soft soil / hard marrum
2) 'Supply of copper plate electode / G.I. Pipe electrode.
3) Supply & fixing of watering 'B'Class pipe.
4) Supply of civil material and preperation of brick masonry earth
pit chamber with Heayy Duty C.I. frame and hinged covers of
suitable size as per drawing.
5) Supply and providing of charcoal and salt for filling in earth pit.
6) Supply of tools and tackles necessary for excavation to a desire
depth and doing necessary civil work etc.
7) Testing earth resistivity before earthing and electrode
resistance after completion of work.
8) Supply and fixing of Equipotential bar with housing alongwith
necessary mounting accessories.600mm x 600mm x 3.15 mm Cu
292 Plate type earthing station. 2 Each

112
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

EARTHINGEarthing Stations
Supply, installation, connection and testing of plate type / pipe
type earthing station for various electrical equipments and
systems as per IS with following.
1) Excavation in soft soil / hard marrum
2) 'Supply of copper plate electode / G.I. Pipe electrode.
3) Supply & fixing of watering 'B'Class pipe.
4) Supply of civil material and preperation of brick masonry earth
pit chamber with Heayy Duty C.I. frame and hinged covers of
suitable size as per drawing.
5) Supply and providing of charcoal and salt for filling in earth pit.
6) Supply of tools and tackles necessary for excavation to a desire
depth and doing necessary civil work etc.
7) Testing earth resistivity before earthing and electrode
resistance after completion of work.
8) Supply and fixing of Equipotential bar with housing alongwith
necessary mounting accessories.150 mm. N.B., 'B' Class 3.0 mtr.
293 long G.I. Pipe type earthing station. 14 Each

113
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

EARTHINGEarthing Conductor
Supply, laying, connection and testing bare earthing conductor for
inter‐connecting the earthing stations and various equipment in
built up trenches, walls/ceiling, buried in ground generally as
specified and shown on the drawing complete with :
1) Supply & fixing accessories like earthing clamp, saddle, etc.
2) Supply of corrosion protection of buried conductors with
bituminous coating
3) 'Supply of Test links (Copper/GI) etc.
4) Supply and installation on Equipotential bar.8 to 16 SWG. GI
294 wire 400 Mtr

EARTHINGEarthing Conductor
Supply, laying, connection and testing bare earthing conductor for
inter‐connecting the earthing stations and various equipment in
built up trenches, walls/ceiling, buried in ground generally as
specified and shown on the drawing complete with :
1) Supply & fixing accessories like earthing clamp, saddle, etc.
2) Supply of corrosion protection of buried conductors with
bituminous coating
3) 'Supply of Test links (Copper/GI) etc.
4) Supply and installation on Equipotential bar.50 X 6 MM Hot
295 dipped ( 86 micron Zinc thicness min.) GI Strip 460 Mtr

114
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

EARTHINGEarthing Conductor
Supply, laying, connection and testing bare earthing conductor for
inter‐connecting the earthing stations and various equipment in
built up trenches, walls/ceiling, buried in ground generally as
specified and shown on the drawing complete with :
1) Supply & fixing accessories like earthing clamp, saddle, etc.
2) Supply of corrosion protection of buried conductors with
bituminous coating
3) 'Supply of Test links (Copper/GI) etc.
4) Supply and installation on Equipotential bar.25 X 6 MM CU
296 Strips 60 Mtr

EARTHING,Equipotential Bar,Supply, installation, testing and


commissioning of below mentioned Equipotential bar of 500 mm
length with suitable junction box to inter connect different
earthing conductor. The bar shall be provided with six knock outs
for connecting the equipment to earthing station.50 x 10mm GI
297 Equipotential bar of 500 mm length. 7 Each

EARTHING,Equipotential Bar,Supply, installation, testing and


commissioning of below mentioned Equipotential bar of 500 mm
length with suitable junction box to inter connect different
earthing conductor. The bar shall be provided with six knock outs
for connecting the equipment to earthing station.50 x 10mm CU
298 Equipotential bar of 500 mm length. 1 Each

115
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

LIGHTNING PROTECTIONSupply, installation,testing and


commissiong of lightning protection system as per specification ,
drawings and BS : 6651 and IS : 3043 comprising of following :
1) Supply and Installation of Horizontal Air termination network on
terrace parapet.
2) Supply and Installation of Test link
3) Supply and Installation of Vertical down conductor
4) Supply, Installation, Testing and Commissioning of Earthing
Station
5) Connection to Earthing station
The rate shall include following:
Supply and installation of strip as per drawing. Route on the
external facia of the building shall be got approved from the
Architects prior to installation.
G.I. strip installation with G.I. saddles and wooden gutties as
spacers. The strip shall be connected to the air terminal rods and
to the earth stations through test links.
Earth station work shall include ground excavation and backfilling
with soft earth upto depth of 600mm for burying the portion of
conductor between earth station and building.Supplying, installing
299 and connecting hot dip galvanized iron 25mm x 4mm strip. 1800 Mtr

116
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

LIGHTNING PROTECTIONSupply, installation,testing and


commissiong of lightning protection system as per specification ,
drawings and BS : 6651 and IS : 3043 comprising of following :
1) Supply and Installation of Horizontal Air termination network on
terrace parapet.
2) Supply and Installation of Test link
3) Supply and Installation of Vertical down conductor
4) Supply, Installation, Testing and Commissioning of Earthing
Station
5) Connection to Earthing station
The rate shall include following:
Supply and installation of strip as per drawing. Route on the
external facia of the building shall be got approved from the
Architects prior to installation.
G.I. strip installation with G.I. saddles and wooden gutties as
spacers. The strip shall be connected to the air terminal rods and
to the earth stations through test links.
Earth station work shall include ground excavation and backfilling
with soft earth upto depth of 600mm for burying the portion of
conductor between earth station and building.50x10 MM GI Test
link (100 mm Long) with MS powder coated junction box (300 x
300 100 MM). 19 Each

117
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

LIGHTNING PROTECTIONSupply, installation,testing and


commissiong of lightning protection system as per specification ,
drawings and BS : 6651 and IS : 3043 comprising of following :
1) Supply and Installation of Horizontal Air termination network on
terrace parapet.
2) Supply and Installation of Test link
3) Supply and Installation of Vertical down conductor
4) Supply, Installation, Testing and Commissioning of Earthing
Station
5) Connection to Earthing station
The rate shall include following:
Supply and installation of strip as per drawing. Route on the
external facia of the building shall be got approved from the
Architects prior to installation.
G.I. strip installation with G.I. saddles and wooden gutties as
spacers. The strip shall be connected to the air terminal rods and
to the earth stations through test links.
Earth station work shall include ground excavation and backfilling
with soft earth upto depth of 600mm for burying the portion of
conductor between earth station and building.150 mm. N.B., 3.0
301 mtr.. long 'B' Class G.I. Pipe type earthing station. 19 Each

CCTV SYSTEMS ,Supply, Installation, Testing and Commissioining of


2 MP, progressive scan, CMOS image sencor, Fixed Color IR, IP
Dome Camera, 1080P resolution, POE, 2.8 or 3.6 mm, SIP enabled
302 for indoor, wall or ceiling mounted. 39 Each

118
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

CCTV SYSTEMS ,Supply & laying of the CAT‐6 cable for the CCTV
data system in rigid PVC conduit / or channel or raceway. The
same wire will be utilised to transfer data and power demand of
camera PoIP. (the cost of channel/raceway/PVC conduit not to be
303 included in the rates) 1950 Mtr
CCTV SYSTEMS ,Supply, laying, testing and commisioning of 25 mm
304 dia rigid PVC medium duty conduit. 1560 Mtr
CCTV SYSTEMS ,Supply, Installation, Testing and Commssioining of
16 Channel Duplex Color IP based Digital Video Multiplex
305 Recorder (NVR) with 2 TB HDD 3 Each

CCTV SYSTEMS ,Supply, Installation, Testing and Commssioining of


PC with 21" color LCD monitor and Software to view, display and
306 store images for above camera. 3 Each
CCTV SYSTEMS ,24 port POE switch as suitable with Optical Fiber
307 Ports 2 Each

CCTV SYSTEMS ,Supply, Installation, Testing and Connection of 0.9


mm Fiber Optic cable from data switch between buildings laid
through raceways/conduits/floor trunks/ground etc. (Rates of
308 raceways/conduits/floor trunks shall be excluded) 300 Mtr
VOICE AND DATA SYSTEM , Supply ,testing and commissioning of
309 RJ‐45 socket outlet point for Data 32 Each
VOICE AND DATA SYSTEM , Supply & connection of 3 Ft patch
310 chord for interconnections 32 Each

VOICE AND DATA SYSTEM , Supplying & erecting approved make


LAN cable of following size in existing pipe as per direction
311 [C] CAT ‐ 6 1280 Mtr

119
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

VOICE AND DATA SYSTEM , Supply, laying, testing and


312 commisioning of 25 mm dia rigid PVC medium duty conduit. 896 Mtr

VOICE AND DATA SYSTEM , Supplying & erecting Digital / PCM /


TDM EPABX System having SMT design, system with flexible
universal slots, Inbuilt Auto attendant facility, Minimum 15 Nos.
conference, Analog extension line, Calling GSM, E&M line, PRI / E1
& VOIP program me through Analog telephone digital key from
Ethernet, public address cord, shall have unrestricted
simultaneous dialling facility,
[B] No of Extension 24, No of Junctions 8, No of expandable
313 ports:96, Operators Console ‐ 01 Compatible: ISDN 2 Each

VOICE AND DATA SYSTEM , Supply and fixing of 10 pair telephone


314 tag box with KRONE terminal 3 Each

VOICE AND DATA SYSTEM , Supply and fixing of 50 pair telephone


315 tag box with KRONE terminal 1 Each

VOICE AND DATA SYSTEM , Supply, installation, testing and


316 commissioning of outlet socket for Telephone (RJ‐11) 25 Each

VOICE AND DATA SYSTEM , Supply,laying and termination of 0.5


317 mm dia tinned copper 2 pair Unarmoured telephone cable. 1250 Mtr.

VOICE AND DATA SYSTEM , Supply, laying, testing and


318 commisioning of 25 mm dia Rigid PVC medium duty conduit. 750 Mtr

VOICE AND DATA SYSTEM , Supply,laying and termination of 0.6


319 mm dia tinned copper 10 pair armoured telephone cable. 300 Mtr.

120
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

VOICE AND DATA SYSTEM , Supply,laying and termination of 0.6


320 mm dia tinned copper 50 pair armoured telephone cable. 0 Mtr.

VOICE AND DATA SYSTEM , Supplying & erecting Push button type
321 telephone instrument 0 Each

PUBLIC ANNOUNCEMENT SYSTEM ,Supply and laying of the 2c X


322 0.75 sq mm coper, stranded, shieded cable. 2440 Rmt.

PUBLIC ANNOUNCEMENT SYSTEM ,Supply, laying, testing and


323 commisioning of 25 mm dia Rigid PVC medium duty conduit. 1958 Rmt.
PUBLIC ANNOUNCEMENT SYSTEM ,Supply, Testing and assembling
of 15W ceiling/recessed mounted speaker with necessary
324 accessories,suitable for indoor applications. 122 Each
PUBLIC ANNOUNCEMENT SYSTEM ,Supply, Installation, Testing
325 and commissioning of audio system rack. 2 Each

PUBLIC ANNOUNCEMENT SYSTEM ,750w (900w MAX.) Mixing


Amplifier : High performance range of single and Dual Zone
amplifiers. Four balanced inputs for microphone or line. Selectable
priority and vox switching on microphone input 1. Optional 2‐tone
Chime to precede announcements. Separate overruling
emergency input with vox, Choice of CD, Tuner or auxiliary music
inputs. Variety of public address requirements at a surprisingly low
cost. The amplifiers shall be protected against overload and short
326 circuits 3 Each

PUBLIC ANNOUNCEMENT SYSTEM ,Supply, Testing and assembling


327 of volume controller. 2 Each

121
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

PUBLIC ANNOUNCEMENT SYSTEM ,Supply, Installation, Testing


328 and commissioning of Dynamic Hand‐Held Microphone. 2 Each

CABLE TV SYSTEM ,Supply ,testing and commissioning of RJ‐6 the


329 channel socket outlet point. 16 Each

CABLE TV SYSTEM ,Supply and laying of RG‐6 cable to be laid in 25


mm dia. Heavy duty PVC conduit. (Rates for conduit shall be
330 excluded) 240 Mtr.

CABLE TV SYSTEM ,Supply & laying of 25mm dia. Heavy duty PVC
331 conduit for laying the above cable. 240 Rmt.
CABLE TV SYSTEM ,Supply ,testing and commissioning 3 way
332 splitter. 16 Each
CABLE TV SYSTEM ,Supply ,testing and commissioning 4 way
333 splitter. 2 Each

SUBSTATION SAFETY EQUIPMENTS ,Providing printed instruction


chart both in English and Gujarati and duly framed with front
334 glasses, for treatment of person suffering from Electric shock 4 Each

SUBSTATION SAFETY EQUIPMENTS ,Supplying stand first AID box


with antiseptic cream, medicine for use on wounds due burn,
crepe bandage, gauge bandage, medicated ready to use bandage
(Band‐aid) adhesive tape for medicinal user, Scissors, anti‐septic
solution (Savlon or similar) etc. (All above contents shall be of
335 standard makes) 4 Each

122
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

SUBSTATION SAFETY EQUIPMENTS ,Supplying & erecting carbon


dioxide (CO2) fire extinguisher user of following capacity with
necessary clamps made from 50 x 6 mm M.S. Flat with nut & bolts
336 grouted in wall complete.For 4.5 Kg Capacity 30 Each
SUBSTATION SAFETY EQUIPMENTS ,Supplying rubber matting of 6
mm thickness as per IS 5424 and of required length and breadth Sq.
337 with good insulation property for 22 KV 15 Mtr.

SUBSTATION SAFETY EQUIPMENTS ,Supply of 2 x 20 W FL T/L self


338 contained emergency light with dry type maintenance free battery 4 Each

FIRE BARRIER SYSTEM ,Supply, installation, testing and


commissioning of following fire barrier systems for HT and LT
cable systems passing through shafts, trenches, ducts etc.
Providing & Fixing Fire Barrier mortar with minimum 2 hours fire
rating when tested in accordance with BS 476 part 20 nd UL 1479
for horizontal openings in fire vertical openings in walls for passing
service shafts.The mortar shall have minimum hardended of 0.8
g/cm3 .The service lines could be of various types like electrical
339 cables trays,metal pipes, GI ducts for AC. ETC. 15 Each

FIRE BARRIER SYSTEM ,Supply application of intumescent based


coating on cables/cable tray along the horizontal runs, every 5m in
case of verivcal runs and tee‐offs shall have a density in the range
of 1.2 to kg /L.The coating shall be in non toxic , asbetos and
340 halogen free and shall have good mechanical strength. 10 Each

123
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

LIASON CHARGES ,Approval Charges for obtaining approval from


S.E.B/Authority and Electrical Inspector.
SEB Liason charges to obtain LT services, 1X125 kVA DG. The job
involves submission of application, test report & other relevant
documents as may be required to SEB/statutory
authority/Electrical inspector, follow up, collection of FQ, making
necessary application payment (All statutory fees will be paid by
Client), coordnation with EB project team & getting the relevent
workdone from EB at site for obtaining power supply,Arrange visit
of Electrical Inspector, Getting necessary approvals from Electrical
Inspector.
Scope covers:
1) Preparation of documents, drawings. Documents pertaining to
SEB approval shall be provided by client/consultant.
2) Necessary hardcopy submission is in scope of contractor.
3) Follow‐up with SEB approval authority / officials, electrical
inspector is part of job.
4) All statutory fees shall be paid by Client.
5) Document submission and handing over approved documents
341 to client 1 Job

INTEGRATED DIGITAL CLASSROOM ,INTEGRATED DIGITAL


CLASSROOMIntegrated digital teaching device (wallmount) with
K12 content english solution UPS & 3 yr support
(http://mkp.gem.gov.gov_indigital‐teaching‐device/integrated‐
digital‐teaching‐device‐wallmount‐with‐k12‐content/p‐5116877‐
342 26418430470‐cat.html) 12 Each
Construction of 600mmx600 mm valve chamber 60x60 cm inside
in brick work in cement mortar 1:4 with RCC tope slab 1:2:4 with
necessary excavation, foundation concerete 1:5:10, inside
plastering with cement mortar 1:3, 12 mm thick, finished with a
343 flating coat of neat cement complete 10 Each

124
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

Constructing Manhole with R.C.C. top slab in 1:2:4 mix (1‐cement :


2‐coarse send : 4‐graded stone aggregate 20mm nominal size)
foundation concrete 1:3:6 mix (1‐cement : 3‐coarse sand : 6‐ Brick
bats 40 + 50mm size) inside plastering 15mm thick with Cement
a) With 230mm thick walls of brick masonary using brick having
crushing strength not less than 35Kg. / Sq.cm. in Cement Mortar
1:5 (1‐ Cement : 5‐ Coarse sand) (I) Inside size 900mm X
1200mm and 1.5M. deep including C.I. cover with frame size
560mm diameter total weight of cover and frame to be not less
than 128 kgs. (Wt. of cover 64 kg. and Wt. of frame 64 Kg.)
344 1) A type depth 0.90 Meter for 150 mm diameter sewer. 20 Each
Providing & Laying ( to level or Slope) and jointing reinforced
concrete Light Duty NoN Pressure I.S. Class NP2 of the following
internal diameter with collars and butt ends prepared for collar
joints including testing of joints for of
345 300 mm 200 Rmt.
Supply, Installation, testing and commissioning of 12 MTR High‐
Mast Pole as per specification, drawing and relavent IS. Scope shall
cover supply and installation of pole, suitable size junction box,
pipe for cable, wiring, earthing etc. to complete the job. Scope
346 doesn't cover light fixture. 3 Each

Supply, Installation, testing and commissioning of above 150 to


347 240 watts Cat‐III (for high mast). 12 Each

Supply, Installation and termination of 12 PORT loaded patch


348 panel (In security Cabin) 1 Each

125
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

Supply, Installation and configration data switch as per following


specifications:
1) Subtype ‐ Gigabit Ethernet
2) Ports ‐ 24 x 10/100/1000
3) MAC Address Table Size ‐ 4K entries
4) Status Indicators ‐ Collision status, port transmission speed, port
duplex mode, power, link OK, link/activity
5) Nominal Voltage ‐ AC 120/230 V
6) Frequency Required ‐ 50/60 Hz
7) Type ‐ internal power supply
8) Cabling Type ‐ Ethernet 1000Base‐T, Ethernet 100Base‐TX,
Ethernet 10Base‐T
9) MAC Address Table Size ‐ 4K entries
10) Features ‐ auto‐sensing per device
11) Compliant Standards ‐ IEEE 802.1p, IEEE 802.3, IEEE 802.3ab,
IEEE 802.3u, IEEE 802.3x
12) Switching Protocol ‐ Ethernet
13) Rack Mounting Kit ‐ included
14) Mounting Kit ‐ included
15) Min Operating Temperature ‐ ( 08 °C )
16) Max Operating Temperature ‐ ( 40 °C )
17) Humidity Range Operating ‐ 40 ‐ 95%
18) Compatibility ‐ PC

24 port 10/100/1000 Mbps RJ45 + 4 combo 1000 Base SFP, SNMP


manageable 12 port POE switch as suitable with Optical Fiber
Ports
349 (In security Cabin) 1 Each

Supply, Installation and termination of 12 PORT loaded patch


350 panel (In Hostel and school) 2 Each

126
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

Supply, Installation and configration data switch as per following


specifications:
1) Subtype ‐ Gigabit Ethernet
2) Ports ‐ 24 x 10/100/1000
3) MAC Address Table Size ‐ 4K entries
4) Status Indicators ‐ Collision status, port transmission speed, port
duplex mode, power, link OK, link/activity
5) Nominal Voltage ‐ AC 120/230 V
6) Frequency Required ‐ 50/60 Hz
7) Type ‐ internal power supply
8) Cabling Type ‐ Ethernet 1000Base‐T, Ethernet 100Base‐TX,
Ethernet 10Base‐T
9) MAC Address Table Size ‐ 4K entries
10) Features ‐ auto‐sensing per device
11) Compliant Standards ‐ IEEE 802.1p, IEEE 802.3, IEEE 802.3ab,
IEEE 802.3u, IEEE 802.3x
12) Switching Protocol ‐ Ethernet
13) Rack Mounting Kit ‐ included
14) Mounting Kit ‐ included
15) Min Operating Temperature ‐ ( 08 °C )
16) Max Operating Temperature ‐ ( 40 °C )
17) Humidity Range Operating ‐ 40 ‐ 95%
18) Compatibility ‐ PC

24 port 10/100/1000 Mbps RJ45 + 4 combo 1000 Base SFP, SNMP


manageable
351 (In computer lab at school) 1 Each

12 port POE switch as suitable with Optical Fiber Ports


352 (In GF Hostel and school) 2 Each

4 port POE switch as suitable with Optical Fiber Ports


353 (In Security cabin) 1 Each
127
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

Supply, fixing, connection of wires, testing of computer power


point with 2 Nos. 6A SOCKET + 1No. 6A SWITCH FOR
COMPUTER/TV POINT common switch along with 8 module top
cover plate, PVC back box suitable to modular plate and other
necessary accessories to complete the installation. (Approval for
the colour of the cover plate should be taken from the
354 Architect/Client) 48 Each

Supply, laying, connection and testing of above mentioined wires


from DB to raw power socket to be laid through electrical channel
355 / floor raceway / PVC condiut. 1500

Supply, Installation, testing and commissioning of decorative bell


356 push point with bell push switch 25 Each

Supply, Installation, testing and commissioning of 12 MTR High‐


Mast Pole as per specification, drawing and relavent IS. Scope shall
cover supply and installation of pole, suitable size junction box,
pipe for cable, wiring, earthing etc. to complete the job. Scope
357 doesn't cover light fixture. 3 Each

Supply, Installation, testing and commissioning of above 150 to


358 240 watts Cat‐III (for high mast). 12 Each

128
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

LT CABLES,Supply, laying, connection, testing and commissioning


of heavy duty, low voltage, XLPE (IS 7098 ‐ PART‐II) insulated,
stranded AL / Cu conductor Armoured cables as per specification
& IS.
The cable shall have inner sheeth of XLPE and outer sheath of PVC
ST2 (FRSL) type with stranded AL/Cu conductor wherever
specified.
The cable shall be laid underground in excavated trench /
prepared trench / hume pipes when laid outside the building.
Cable shall be laid throught preapred trench / cable tray / duct /
hume pipe / channel / floor trunks etc when laid inside the
building.
The scope shall include:
1) Supply of Cables.
2) Delivery of the cables at site.
3) Unloading at site store.
4) Shifting of cable from site store to place of installation.
5) Excavation in hard or soft murrem / rocky area upto required
depth, supply and laying of protection bricks, supply and
backfilling with fine sand, leveling the ground to match with the
existing condition.
6) 'Laying of cable in the excavated trench / prepared trench /
cable tray / duct / hume pipe / channel / floor trunks when laid
inside or outside the building.
7) Connection of cable.
8) Supply & fixing of cable clamps, brackets, supports, route
markers etc. where ever required to fix the cables safely.
9) Earthing the glands and armouring with earthing clamp and
jumper and also connecting to common earth bar.
10) Testing of insulation and continuity of cable and submission of
reports to the client's representative.
11) To prepare submission drawing and to take approval of
consultant at each stage.
12) To prepare & submit as‐built drawing and handing over
359 document to end user.,4C X 4 SQ. MM. CU XLPE 240

129
Gujarat Integrated Tribal Educational Project GITEP- 88 GLRS School Complex at Babarghat

CABLE TRAY & UNDER FLOOR TRUNKINGHUME PIPES


Supply & installation of Pipes (NP2, RCC with collar) as per below
sizes for providing passages to lay the cables.Supply and
360 Installation of 100 mm dia RCC Hume Pipe 300

LT CABLESCABLE END TERMINATION AND CONNECTIONSupply,


fixing, connection, testing & commissioning of single compression
brass cable glands and crimping type Bimetalic lugs / sockets with
necessary tools and equipments as specified in specifications and
IS. For outdoor installations, double compression glands shall be
considered. The glands and lugs / sockets shall be suitable for
cable size and type mentioned above. The job also includes, if
necessary, supply and fixing of extension busbar of same material
on circuit breaker or panel board terminal / connector to
connect more than one no. of parallel cables or to connect higher
size cable to lower size unit. The job also includes earthing the
glands and armour of the cable with common earth bar or flexible
361 copper mesh.,3C X 4 SQ. MM. CU XLPE 18 Each

130

You might also like