Professional Documents
Culture Documents
Energy Analysis
By Paul B. Sullivan, Daniel R. Doan, and Kenneth S. Jones
GENERALLY ACCEPTED INDUSTRY STANDARDS, SUCH for creating equipment labels, which contain arc-flash energy
as National Fire Protection Association (NFPA) 70E-2018, information, to be reviewed at least every five years, and, if
require arc-flash incident energy analysis to be updated the review identifies a change that renders the arc-flash ener-
when changes occur in the electrical power distribution gy label inaccurate, the equipment label must be updated.
system, and the analysis shall be reviewed for accuracy at The challenge for consultants and end users is to
least every five years. NFPA 70E also requires the data used determine how much of a data review is required. NFPA
RENEWAL RECOMMENDATIONS
©SHUTTERSTOCK.COM/PINYO PROMPRASERT
review of the entire system could take a year, which operating devices to allow the person to be outside the
would be costly or a large burden on resources. In this arc-flash boundary of the equipment [12]
article, the authors provide suggested guidelines for ●● changing work practices to reduce or eliminate expo-
performing the five-year review. The authors provide sure to the energized operation of equipment with
their recommended arc-flash incident energy analy- very high arc-flash incident energy
sis renewal approach that would help ensure that the ●● replacing older, low-voltage power circuit breaker trip
system labeling can be updated appropriately while units with trip units that include an energy-reducing
allowing the model to be reviewed and updated in a maintenance switch with a local status indicator [9]
reasonable amount of time. ●● adding in fiber-optic arc-flash sensing for both low-
Authorized licensed use limited to: Universidad Nacional de Colombia (UNAL). Downloaded on September 16,2022 at 14:33:53 UTC from IEEE Xplore. Restrictions apply.
current value. The calculation providing the higher level exception for calculating incident energies for 208/120-V
of incident energy was to be used as the predicted inci- panelboards. Many industrial users have 208/120-V
dent energy at that equipment. This arcing current varia- panelboards with transformers that provide greater
tion factor is different in IEEE 1584-2018 [15] and is now than 2,000 A at the secondary level. When the 2,000-A
based on electrode configuration and voltage. The factor threshold is reached, the incident energy is calculated to
is no longer a fixed percentage. Using outdated formulas be significantly higher, in the range of 4–10 cal/cm2 or
and methodology for specific configurations could lead to more. The ramifications of operator interface for these
underestimating the actual available incident energy. panels regarding PPE requirements and so must be care-
The IEEE 1584-2018 arc-flash energy calculations may fully considered.
also lead to significantly higher levels of arc-flash energy Many industrial systems’ 208/120-V transformers above
for some equipment. For example, the equipment with 30 kVA will produce more than 2,000 A of fault current.
a horizontal-electrode configuration can lead to two or Many facilities have transformers of 45–75 kVA and larger
more times the arc-flash incident energy as compared to and are quite common. The incident energy calculation
calculations for vertical electrode configuration. in the 240-V-and-below area is certainly a matter for fur-
Examples of equipment with a horizontal-electrode ther development.
configuration include low-voltage draw-out, metal-
enclosed switchgear; low-voltage, metal-enclosed busway Identifying Human Errors
with plugs; and medium-voltage, metal-clad switchgear. Electrical system modeling for incident energy calcula-
Figure 1 shows an example of a horizontal bus in a low- tions is typically done by entering electrical system data
voltage switchgear, power circuit breaker compartment. into a commercial software package. Humans make
With this style of construction, many conductors in the mistakes, so data errors can exist in the electrical system
equipment point horizontally toward a person interfac- model created in the software package. For example, it
ing with the equipment. This is especially true in circuit is easy to enter a cable length of 10 instead of 100 ft and
breaker compartments. If an arc fault occurs in this equip- for that error to go unnoticed. Updating a facility’s arc-
ment, the arc and incident energy from the arc can be flash incident energy analysis allows for a check of the
directed out of the equipment and toward the person. model to be performed to identify and correct errors in
The IEEE 1584-2002 calculations were based on a ver- the model.
tical conductor orientation for most equipment types. A
vertical electrode configuration, typically found in a panel- Lost Electrical System Model
board or switchboard, has the arc fault running off the end When starting some arc-flash incident energy analysis
of the bus to the enclosure, with it then being deflected out updates, facility owners have determined that they do not
toward the user. This creates a much longer arc path then always have the computer model of the study previously
being pointed directly out of the equipment with horizontal performed for the facility. The facility owner may have an
electrodes. The IEEE 1584-2018 calculations for incident electronic or printed copy of a report but not the actual
energy for horizontal-electrode configurations are higher electronic files that are needed to run the facility model.
than the calculations based on IEEE 1584-2002 because This problem often occurs if a facility uses a contractor
IEEE 1584-2018 more accurately includes consideration of to perform this work, and the services agreement does not
the direction of the arc and the arc energy. include a requirement for the service provider to include
Another significant area of change in the incident the actual model files. For guidance on how to specify
energy calculations is the revision to the calculations for
the equipment fed from the three-phase sources operating
at 240 V and below. In the IEEE 1584-2002 calculations,
the sources below 240 V with a single transformer source
rated at below 125 kVA could use a calculation exception
to classify the equipment as having incident energy below
1.2 cal/cm2 at a standard 18-in working distance. As fur-
ther testing has revealed, it is not as likely to sustain an
arcing fault at or below 240 V as compared to higher volt-
ages; however, it was still possible and presented a poten-
tial incident energy hazard at greater than 1.2 cal/cm2.
The IEEE 1584-2018 standard revised the exception to
the calculation to be current based. This amperage level
chosen for applying the exemption is 2,000 A. The per-
son performing the study update can use this exception
or can perform the calculations. There is a concern that FIGURE 1. A horizontal bus in a low-voltage switchgear power
many study engineers have used the IEEE 1584-2002 circuit breaker compartment.
Authorized licensed use limited to: Universidad Nacional de Colombia (UNAL). Downloaded on September 16,2022 at 14:33:53 UTC from IEEE Xplore. Restrictions apply.
Facility Tour ally installed. This is especially helpful in medium-voltage
One of the best methods to obtain updated system infor- motor starters and in medium-voltage control power or
mation is to go on a tour of the facility and visit all voltage transformer circuits as that equipment is not rou-
the parts of the power system that are (or should be) tinely available for inspection.
included in the system model. Taking printed copies of
single-line diagrams on the tour is highly recommended Data Collection Apps
as field information and changes can be recorded on the Some system-modeling software companies provide a
printed copies of the diagrams. Highlighting verified por- data collection app that can directly add data from a
tions of the diagrams helps keep track of what has and field survey to the proper equipment on the single-line
has not been verified. Figure 2 depicts the typical data to diagram. This app helps to reduce human error as the
be updated. data are entered and can be verified at the time of data
Single-line diagrams printed on 11-in × 17-in paper entry instead of recording the data at one time and then
may be easier to manage than drawings printed on larger- interpreting and entering those data into the model at a
format paper. Having a clipboard or similar hard support later time.
for the drawings provides a good surface for holding the
drawings while the marks are made. Electric Utility System Data
Electric utilities routinely make changes to their electric
Pictures transmission and distribution systems to make them more
An excellent way to quickly record field data is to take reliable and to support the growing electrical needs in
pictures of the equipment during the facility tour. Of an area. Those changes often include increasing circuit
course, the ability to take pictures depends on the poli- conductor size, installing larger power transformers,
cies in place at the specific facility where the work is and modifying system configurations. These changes
being performed. can greatly impact the available fault current and pro-
One of the authors uses the following process to docu- tection device clearing time at a utility customer’s facil-
ment equipment through pictures: ity. The authors’ experience shows that the available
1) Take a picture of the name of the
equipment.
2) Take a picture of the protective
Utility
device or other item of interest. Isc 3P 6,000 A
3) Download the pictures to a com-
puter.
P Transformer Main Bus
4) Rename each picture to include 750 kVA 480 V/WD 18 in
the name of the equipment and S 5.00 %Z-X/R 5.2 PPE Class 4/58.36 Cal/cm2
any other desired details (such as 13,800 V-480 V AF Boundary: 205 in
date taken). Prot Dev: Max TripTime at 2 s
AF Bolted Fault: 16.337 kA
The pictures provide for quickly
and accurately recording the protec-
Switch Feed Fuse Breaker 1
tion-device settings (such as all of Manufacturer Name Manufacturer Name
the settings on a low-voltage power Manufacturer Frame/Style Manufacturer Frame/Style
circuit breaker trip unit). Be sure to Trip (Size) 200 A Trip (Size) 800 A
check each picture taken to ensure LTPU (A); LTD 1 (800 A); 12
STPU 4 (3,200 A)
that it is in focus. STD 0.1 (ls T Off)
Figure 3 shows an example of a INST 2 (1,600 A)
picture of details for a circuit pro- INST or Fixed (24,000 A)
tection device. Note the amount of Switch Cable MCC Cable
details captured quickly in the pic- 1 - 3-1/C+G Number 500 kcmil THWN 2 - 3/C+G Number 750 kcmil THHN
ture. That level of detail would be Copper 100 ft Copper 180 ft
difficult to manually capture quickly,
Switch Bus MCC Incoming Bus
especially in low lighting, an awk-
480 V/WD 18 in 480 V/WD 18 in
ward location, and while wearing PPE Class 0/0.18 Cal/cm2 PPE Class 3/1.23 Cal/cm2
protective eyewear. AF Boundary: 6 in AF Boundary: 18 in
Another excellent time to take Prot Dev: Switch Feed Fuse Prot Dev: Breaker 1
AF Bolted Fault: 12.498 kA AF Bolted Fault: 13.893 kA
pictures of equipment is during
equipment commissioning and main- FIGURE 2. An example of a drawing to be reviewed. Prot. Dev.: protective device; STD: short time
tenance activities. Taking pictures of delay; LTD: long time delay; AF: arc flash; Isc: short circuit current; kcmil: 100 circular mills; MCC:
fuses helps document what is actu- motor control center; LPTU: long time pick up; STPU: short time pick up; INST: instantaneous.
Transformers
The authors have found many errors with transformer
FIGURE 3. A very detailed picture of a protection device type, model, data in the system models. Small errors in transformer
and its settings.
information can have a large impact on the arc-flash cal-
culation values. Some of those errors include
short circuit current typically increases due to utility ● wrong impedance (the typical transformer impedance
system modifications. For more information on how util- was used instead of the actual transformer impedance)
ity changes can affect arc-flash incident energy calcula- ● wrong full-load kVA (the previous model did not
flash incident energy analysis update for a facility. Some ● wrong grounding method (it was shown as solidly
utilities are slow in providing updated data, so it is impor- grounded instead of low- or high-resistance grounded)
tant to ask for updated information early in the incident ● wrong information due to the transformer being
energy analysis update process. replaced since the last model update.
The quantity of transformers in a facility is not typically
that numerous as compared to the other equipment at the
facility. The authors recommend verifying the transformer
data for every transformer in the system model. Taking
a picture of the transformer nameplate is a quick way to
capture transformer data. The picture can also be kept on
record and used for future system model verification work.
Authorized licensed use limited to: Universidad Nacional de Colombia (UNAL). Downloaded on September 16,2022 at 14:33:53 UTC from IEEE Xplore. Restrictions apply.
powered due to the level of load on readily available at the facility and
the circuit breaker or if no exter- make certain that they match the
nal trip-unit display power source The circuit breaker fuses in the system model. If they
is available. If the internal battery match, then it is likely that the facil-
is not working and the display is testing companies ity personnel will install the same
not powered from another source, often change the manufacturer, model, and amperage
the circuit breaker maintenance test fuse if an installed fuse operates so
reports may be the only source for settings on the that the system model would remain
the trip units setting the data. correct. If they do not match, a dis-
Newer LVPCB trip units may be circuit breakers to cussion should be held with facility
able to communicate through a net- allow for lower test personnel to determine how to man-
work (such as an Ethernet network) age the system model because the
or via Bluetooth and allow the set- currents to be used fuse information in the model would
tings to be read without having to be different than what is installed
directly interact with the trip unit. during the circuit in the field for the new equipment
Some LVPCBs may be behind an breaker’s primary as well as the equipment that expe-
equipment door, so the trip unit for rienced failure. Perhaps the facility
those circuit breakers may not be vis- injection testing. owner needs to establish a process
ible. When the trip-unit settings are to update the system model any time
field verified for that equipment, extra that a fuse is replaced.
job planning may be required due to When checking the fuse invento-
the exposure created when opening the equipment door. ry at the facility, be sure to verify that only the desired
The most likely time for the trip units setting the chang- fuse types are available. For example, if a facility has
es to be made is during maintenance activities on the cir- standardized using only UL Class RK1 fuses (current-
cuit breakers. The circuit breaker testing companies often limiting fuse) in their 480-V system, ensure that the
change the settings on the circuit breakers to allow for facility does not have UL Class K5 fuses (noncurrent-
lower test currents to be used during the circuit breaker’s limiting) fuses in their inventory.
primary injection testing. If that happens, the arc-flash
incident energy may be less than what would be calcu- Molded-Case Circuit Breakers
lated in the system model, but the system coordination Molded-case circuit breakers may be located throughout
may still be impacted. If the field verification of trip-unit the facility because many companies use these in motor
settings cannot be performed due to equipment design or control centers and power distribution panels. These circuit
safety concerns, the latest equipment maintenance records breakers are not typically replaced unless there is a project
could be used to perform a level of setting verification. to install a new circuit or if a circuit breaker experienced an
issue and had to be replaced. Therefore, the authors do not
Fuses feel that every molded-case circuit breaker in the system
Many electrical power systems use fuses to provide over- needs to be verified during the update of the system model.
load and short circuit protection of equipment. Fuses are During a facility tour, it may be easy to see the model
not typically replaced unless a piece of equipment has of the circuit breaker through openings in the power dis-
experienced a failure and a fuse has been operated to iso- tribution panel. Where possible, some samples of these
late the fault. Therefore, the authors do not feel that every circuit breakers should be compared to the information in
fuse in the system needs to be verified during the update the system model to ensure that they match.
of the system model. New molded-case circuit breakers installed in older
Facility personnel may know of equipment that has power distribution panels may indicate the recent addi-
failed since the last electrical system model update. Outage tion of a circuit to a panel. For these circuit breakers, the
records can be reviewed to determine if any fuses need to be system model should be checked to ensure the correct
replaced. The fuses in that equipment could be field verified molded-case circuit breaker is included in the model.
to ensure that the right fuses are modeled. This may not be
critical for smaller amperage fuses as a small change in fuse Protection Relays
size would not typically result in a change in arc-flash energy. Electromechanical- and microprocessor-based protection
Occasionally, the procurement department for a facil- relays may be located throughout the facility. The test
ity decides to switch electrical equipment suppliers reports for these devices usually provide reliable setting
due to a possible cost-savings opportunity. Sometimes information for this equipment. A sample of recent test
those changes result in a change to the default sup- reports can be compared to the system model to look for
plier of fuses for the facility. It would be a good idea to any discrepancies. A sample of electromechanical relays
check the facility storage areas to determine the fuses should be visually inspected to determine the actual relay
Authorized licensed use limited to: Universidad Nacional de Colombia (UNAL). Downloaded on September 16,2022 at 14:33:53 UTC from IEEE Xplore. Restrictions apply.
parameters, such as per-unit sub- The facility tour should help iden-
transient impedances, transient and tify whether labels are missing or are
steady-state parameters, and decre- Some generators damaged. The equipment without
ment curve. These can affect the cal- a label but that is likely to have an
culated short circuit current available
may be standby, used arc-flash hazard should be investi-
from the generator [20]. only during utility gated. The damaged labels should
A careful consideration of all the be replaced as part of the update
realistic operating scenarios is an power interruptions, work, and the labels with inaccurate
important part of the arc-flash inci- or missing information should be
dent energy analysis update. Not
while others may replaced with proper labels.
evaluating realistic scenarios can be paralleled with Occasionally, a facility may have
leave personnel underprotected from many different styles of arc-flash
arc-flash hazards in specific, expect- the utility, providing incident energy labels. This can
ed system operating conditions. happen when a facility starts an arc-
power to a part of the flash incident energy labeling pro-
Equipment and Maintenance Records site load. gram and modifies that program or
Some equipment cannot be field ver- they do not have label standards
ified because of issues with gaining and new labels are created in a
safe access to the equipment while different format than that of their
it is in service. Waiting until a maintenance outage to existing labels. Applying standardization with respect
gather information about the equipment is not always to one specific style of label is preferred. Replacing any
practical as the next maintenance may be years away nonstandard labels should be considered. For more
despite the desire to update the system model in the info on the importance of labels and best practices for
immediate future. labels, see [21].
Even if the equipment can be accessed, the settings
may be hard to see or may have a continuously adjustable Component State
range. For either of those issues, a field verification of the Some software packages can categorize the state of
settings cannot be completed. the data for a specific item. The following are exam-
Equipment specifications, manufacturer’s documen- ples of component-state categories for each item in the
tation, and equipment maintenance records can all system model:
be good sources of information for equipment design ●● incomplete
17-in paper
●● choosing certain font types, sizes, and formatting for
Authorized licensed use limited to: Universidad Nacional de Colombia (UNAL). Downloaded on September 16,2022 at 14:33:53 UTC from IEEE Xplore. Restrictions apply.
not match the equipment name on the facility single-line as “Arc Flash Risk Assessment Energy Analysis-Renewal
diagrams and/or the equipment name on the equipment. Recommendations” at the 2020 IEEE IAS Electrical Safety
Equipment-naming issues can be identified and corrected Workshop. This article was reviewed by the IIEEE IAS Elec-
when updating the electrical system model. These chang- trical Safety Committee.
es are especially easy to make when using software pack-
ages that have a data collection app. REFERENCES
[1] R. L. Doughty, T. E. Neal, and H. L. Floyd, “Predicting incident energy
to better manage the electric arc hazard on 600-V power distribution sys-
Reviewing Maintenance Practices tems,” IEEE Trans. Ind. Appl., vol. 36, no. 1, pp. 257–269, Jan./Feb. 2000.
Updating the facility electric arc-flash study regularly leads doi: 10.1109/28.821823.
to a discussion concerning the maintenance practices for [2] D. R. Doan, G. D. Gregory, H. O. Kemp, B. McClung, V. Saporita, and
C. M. Wellman, “Development of the guide for performing arc-flash haz-
the electrical power system. The study update provides ard calculations,” IEEE Ind. Appl. Mag., vol. 11, no. 3, pp. 30–29, May/
the opportunity to review the types of maintenance that June 2005. doi: 10.1109/MIA.2005.1423900.
are (or are not) being performed on the facility’s electri- [3] P. E. Sutherland, “Arc flash and coordination study conflict in an older
industrial plant,” IEEE Trans. Ind. Appl., vol. 45, no. 2, pp. 569–574, 2009.
cal power system and the frequency of that maintenance. doi: 10.1109/TIA.2009.2013597.
That review could lead to modified maintenance plans [4] T. A. Short, “Arc-flash analysis approaches for medium-voltage distri-
and frequencies that could help to improve the reliability bution,” IEEE Trans. Ind. Appl., vol. 47, no. 4, pp. 1902–1909, 2011. doi:
10.1109/TIA.2011.2153810.
of the system [22]. NFPA 70B is an excellent resource to [5] A. M. Graham, M. Hodder, and G. Gates, “Current methods for con-
use when developing or reviewing a maintenance pro- ducting an arc-flash hazard analysis,” IEEE Trans. Ind. Appl., vol. 44, no.
gram for electrical power system equipment [13]. 6, pp. 1902–1909, 2008. doi: 10.1109/TIA.2008.2006325.
[6] G. T. Homce and J. C. Cawley, “Understanding and quantifying arc
One excellent maintenance practice is to use the sys- flash hazards in the mining industry,” IEEE Trans. Ind. Appl., vol. 47, no.
tem model and print the protection-device settings for the 6, pp. 2437–2444, 2011. doi: 10.1109/TIA.2011.2169170.
equipment being maintained when planning for electrical [7] H. W. Tinsley and M. Hodder, “A practical approach to arc flash haz-
ard analysis and reduction,” IEEE Trans. Ind. Appl., vol. 41, no. 1, pp.
equipment maintenance. Maintenance personnel can then 144–154, 2005. doi: 10.1109/TIA.2004.841010.
use those settings to verify the actual settings. This is an [8] H. Wallace Tinsley, M. Hodder, and A. M. Graham, “Arc flash hazard
excellent way to regularly check the system model against calculations,” IEEE Ind. Appl. Mag., vol. 13, no. 1, pp. 58–64, 2007. doi:
10.1109/MIA.2007.265802.
the actual settings. [9] C. G. Walker, “Arc-flash energy reduction techniques: Zone-selec-
tive interlocking and energy-reducing maintenance switching,” IEEE
Conclusions Trans. Ind. Appl., vol. 49, no. 2, pp. 814–824, 2013. doi: 10.1109/
TIA.2013.2244831.
The routine updating of electric arc-flash incident energy [10] D. L. Hodgson and D. Shipp, “Arc-flash incident energy reduction
calculations is an important activity that helps ensure using zone selective interlocking,” IEEE Trans. Ind. Appl., vol. 46, no. 3,
that the electric arc-flash hazards at a facility are identi- pp. 1243–1251, 2010. doi: 10.1109/TIA.2010.2046284.
[11] J. C. Das, “Protection planning and system design to reduce arc-
fied and understood. There are many reasons to update flash incident energy in a multi-voltage-level distribution system to 8cal/
a facility’s electrical system model, with the main reason cm2(HRC 2) or less—Part II: Analysis,” IEEE Trans. Ind. Appl., vol. 47, no.
being to make certain that facility personnel are properly 1, pp. 408–420, 2011. doi: 10.1109/TIA.2010.2091378.
[12] W. S. Hopper, “One Mill’s response to a specific type of arc flash
protected from arc-flash hazards while they interact with problem,” IEEE Trans. Ind. Appl., vol. 45, no. 3, pp. 1184–1193, 2009. doi:
energized equipment. 10.1109/TIA.2009.2018983.
Updating the electrical system model and performing [13] Recommended Practice for Electrical Equipment Maintenance, NFPA
70B-2019, NFPA, Quincy, MA.
arc-flash incident energy calculations can be a significant [14] IEEE Guide for Performing Arc-Flash Hazard Calculations, IEEE
undertaking. Smaller facilities can be easily inspected and 1584-2002, IEEE, New York.
directly compared to the computer system model of the [15] IEEE Guide for Performing Arc-Flash Hazard Calculations, IEEE
1584-2018, IEEE, New York.
facility. For large and complex facilities, a different strat- [16] IEEE Guide for the Specification of Scope and Deliverable Require-
egy must be used because being able to physically inspect ments for an Arc-Flash Hazard Calculation Study in Accordance with
every component in the system is a near-impossible task IEEE Std 1584, IEEE 1584.1, IEEE, New York.
[17] Standard for Electrical Safety in the Workplace, NFPA 70E-2018,
and would be overly burdensome. A methodology for NFPA, Quincy, MA.
how the electrical system model would be updated should [18] I. Balasubramanian and A. Graham, “Impact of available fault current
be developed and agreed upon by the facility owner and variations on arc-flash calculations,” IEEE Trans. Ind. Appl., vol. 46, no. 5,
pp. 1836–1842, 2010. doi: 10.1109/TIA.2010.2058083.
the personnel performing the update. [19] P. Sullivan, D. Doan, and K. Jones, “Arc flash incident energy
analysis—Renewal recommendations,” in Proc. IEEE IAS Electrical Safety
Author Information Workshop, Mar. 2020, pp. 1–10. doi: 10.1109/ESW42757.2020.9188317.
[20] L. Grainger, D. Leschert, A. Bennett, and K. Zehr, “Arc flash consider-
Paul B. Sullivan (paul.b.sullivan@ieee.org) is with ing generator decrement curves,” in Proc. IEEE Petroleum Chemical Ind.
DuPont, Cassatt, South Carolina, 29032, USA. Daniel R. Committee, 2014, pp. 279–288. doi: 10.1109/PCICon.2014.6961893.
Doan is retired from DuPont, New Albany, Pennsylvania, [21] D. Hill, P. Ruhland, “The label says…A collection of examples from
facilities with arc-flash labeling programs,” IEEE Ind. Appl. Mag., vol. 18,
18833, USA. Kenneth S. Jones (kjones@pintegration.com) no. 1, pp. 34–37, 2012. doi: 10.1109/MIAS.2011.943101.
is with Project Integration, Inc., Spartanburg, South Caroli- [22] D. Doan, “Prioritizing circuit breaker and protective relay mainte-
na, 29301, USA. Sullivan and Jones are Senior Members of nance using an arc flash hazard assessment,” IEEE Trans. Ind. Appl.,
vol. 49, no. 2, pp. 799–802, 2013. doi: 10.1109/TIA.2013.2242818.
IEEE. Doan is a Fellow of IEEE. This article first appeared