Professional Documents
Culture Documents
INTRODUCTION
procedure
Ashworth and Hogg (2007) further posited that procurement of construction project is
vast in scope because it involves the gathering and organizing of myriads of separate
individuals, firms and companies to design manage and build construction products
such as houses, office buildings, shopping complex, roads, bridges etc. for specific
needed to design and build construction projects for a specific client. It is in a sense very
people who are brought together and organized systematically in term of their roles,
Apart from the traditional approach, there are now other “fast-tracking” or innovative
procurement
delivery. These differences have invariably affected the project performance. Project
1
undertaking”. It relates to the prescribed goals and objectives which form the project
invariably involves placing consideration on three major project elements i.e. time,
There are many other factors that determine project success, but the focus of this
research is
on the two critical parameters of project performance i.e. cost and quality. The aim of
this
delivery both in public and private sector. Since there are many different project
procurement systems, it is appropriate for the purpose of this research to limit it to the
common ones practiced here in Lagos State Nigeria i.e. traditional system, design and
organizations, and defines the various elements in the construction of a project” (Love
et al. 1998).
• Traditional (separated);
• Collaborative (relational)
2
demands. Holt et al. (2000) state that there are so many variables to each of the
nomenclature, there is a very wide range of strategies available. However, there are a
range of commonly adopted procurement system and contract methods used by public
In many countries the construction industry has however, attracted criticism for
inefficiencies in outcomes such as time and cost overruns, low productivity, poor quality
and inadequate customer satisfaction (Latham, 1994, Egan, 1998, Ericsson, 2002, Chan
et al., 2003). Practitioners, researchers and society at large have, therefore, called for a
change in attitudes, behavior and procedures in order to increase the chances for
(Love et al., 2000, Dubois and Gadde, 2002). An effective and efficient procurement
private procurement. For instance, the deficiencies led to poor public building projects
and other physical infrastructure (Akech, 2003), likewise in private procurement system.
This study tends to examine the major impact of public and private sector procurement
has however, attracted criticism for inefficiencies in outcomes such as time and cost
overruns, low productivity, poor quality and inadequate customer satisfaction (Latham,
1994, Egan, 1998, Ericsson, 2002, Chan et al., 2003). Practitioners, researchers and
society at large have therefore, called for a change in attitudes, behavior and procedures
3
in order to increase the chances for construction projects to be successfully delivered
and result in improved end products (Love et al., 2000, Dubois and Gadde, 2002). An
contributed to huge losses in public and private procurement. For instance, the
deficiencies led to poor public building projects and other physical infrastructure (Akech,
a. What are the various procurement systems employed for project delivery?
The aim of the study is to examine the impact of procurement system on construction
project delivery to achieve this aim, the following objectives are set;
The study will contribute valuable knowledge to Construction industry policy makers;
the public and private sector especially may use the study to develop or improve their
researchers will use the same in future research for literature review and for further
4
studies.
This study’s result and recommendations will contribute to improved procurement work
manual, which shall be simulated to current public and private sector procurement,
This study concentrates on the various procurement system as stipulated in the Public
and private sector identifying the impact of these systems on the delivery of
The following are the definitions of the basic technical terms used in this study:-
Procurement: Refer to the process of acquiring goods, works and services in the award
purposes) and project management success (input and output) (Bacarini, 1999).
and authorities to people and organizations, and defines the various elements in the
5
Public Sector: is that portion of an economic system that is controlled by national, state
or provincial, and local governments.(Areas of the economy controlled by the state are
Private Sector: is the part of the economy, sometimes referred to as the citizen sector,
which is run by private individuals or groups, usually as a means of enterprise for profit,
6
CHAPTER TWO
LITERATURE REVIEW
2.1 Introduction
In this chapter, the researcher reviewed work done by other researchers on the subject
under study. The chapter is organized in several broad areas, which include definitions,
contractual means of goods, construction works, and services (Hibberb, Merrifield, &
Taylor, 1990).
constructed, and/or maintained (Bacarini, 1999). In the public and private sector, this
7
has traditionally entailed the almost exclusive use of the design-bid-build system,
performance of design and construction. In recent years, however, the public and
private sector has begun experimenting with alternative methods to improve the speed
By their very nature public and private sector businesses are very different organizations
operating to fulfill different objectives. While public sector businesses are under a
mandate to operate efficiently their primary objective is public good. Conversely private
Both public sector and private sector procurement professionals share similar demands,
constraints and responsibilities such as proving value for money, being accountable for
there are several key distinctions procurement professionals identify between working
targets.
8
clients and vendors.
dealing with an increased level of red tape or rules which must be adhered to in
they are acting on behalf of the government they must be seen to be acting
ethically.
For any given project a client can adopt a collaborative strategy, such as partnering
irrespective of the procurement method used. Such a strategy has been often used by
clients who have series of projects to undertake. The performance of both contractors
and consultants can be monitored using pre-defined indicators for each of the projects
they are involved with and then compared. This approach is particularly useful to
2006). Once the primary strategy for a project has been established, then the following
commercial, technological, political, social and legal factors which influence the client
and their business, and the project team during project’s lifecycle. For example,
procuring building projects and the environment within which it operates will influence
9
the procurement strategy adopted. Client objectives are influenced by the nature and
culture of the organization. The degree of client involvement in the project is a major
consideration.
• Project characteristics – The size, complexity, location and uniqueness of the project
• Ability to make changes – Ideally the needs of the client should be identified in the
early stages of the project. This is not always possible. Changes in technology may
increase costs and time, especially they occur during construction. It is important at the
outset of the project to consider the extent to which design can be completed and the
• Cost issues – An assessment for the need for price certainty by the client should be
undertaken considering that there is a time delay from the initial estimate to when
tenders are received. The extent to which design is complete will influence the cost at
the time of tender. If price certainty is required, then design must be complete before
• Timing – Most projects are required within a specific time frame. It is important that
before construction. Assurances from the design team about the resources that are
available for the project should be sought. Planning approvals can influence the
progress of the project. If early completion is a critical factor then design and
10
A number of different procurement routes and options exist in the construction
Management Procurement
In the traditional approach, the employer accepts that design work will generally
separate from construction, consultants are appointed for design and cost control, and
the contractor is responsible for carrying out the works Davis et al., (2008). This
responsibility extends to all workmanship and materials, and includes all work by
design and construction can run in parallel to a limited extent Davis et al., (2008). Whilst
this allows an early start on site, it also entails less certainty about cost. There are three
1. Lump sum contracts - where the contract sum is determined before construction
11
completion and after re-measurement to some agreed basis.
3. Cost reimbursement – where the contract sum is arrived at on the basis of the actual
costs of labour, plant and materials, to which is added a fee to cover overheads and
profit.
Lump sum
Davis et al., (2008) stated the contractor undertakes to carry out a defined amount of
work in return for an agreed sum. This can be a fixed amount not subject to
recalculation, in which case there would be no opportunity for the employer to make
variations. The sum is likely to be subject to limited fluctuations, usually to cover tax etc
changes not foreseeable at the time of tendering. The sum may be subject to
fluctuations in the cost of labour, plant and materials – the so called fluctuations
Lump sum contracts with quantities are priced on the basis of drawings and a firm bill
Wardani (2004).
Lump sum contracts ‘without quantities’ are priced on the basis of drawings and
case the lump sum will not be itemized, or one that is detailed to the extent that the
contract sum is the total of the priceable items. The job might be more satisfactory
described as a ‘Schedule of Works’, where the lump sum is the total of the priced items.
In the latter cases, an itemized breakdown of the lump sum will be a useful basis for
valuing additional work. Where only a lump sum is tendered, then a supporting
‘Schedule of Rates’ or a ‘Contract Sum Analysis’ will be needed from the tenderer.
12
Tenders can be prepared on the basis of notional quantities, but they will need to be
replaced by firm quantities if it is intended to enter into a ‘with quantities’ lump sum
contract.
Measurement
(2008). This is where the work which the contractor undertakes to do cannot for some
good reason be accurately measured before tendering. The presumption is that it has
been substantially designed, and that reasonably accurate picture of the amount and
quality of what is required is given to the tenderer. Probably the most effective
measurement contracts, involving least risk is to the employer, are those based on
prices prepared by the employer for the tenderer to compete. This type of contract
might be appropriate where there is not enough time to prepare even approximate
quantities or where the quantity of work is very uncertain. Obviously the employer has to
accept the risk involved in starting work with no accurate idea of the total cost, and
Cost reimbursement
These are sometimes referred to as ‘Cost Plus’ contracts Davis et al., (2008). The
contractor undertakes to carry out an indeterminate amount of work on the basis that
they are paid the prime or actual cost of labour, plant, and materials. In addition, the
contractor receives an agreed fee to cover management, overheads and profit. Hybrids
• Cost-plus percentage fee – the fee charged is directly related to the prime cost. It
13
is usually a flat rate percentage, but it can also be on a sliding scale. However,
the contractor has no real incentive to work at maximum efficiency, and this
indeterminate precontract.
• Cost-plus fixed fee – The fee to be charged is tendered by the contractor. This is
appropriate provided that the amount and type of work is largely foreseeable.
agreed fee.
• Cost-plus fluctuating fee – The fee varies in proportion to the difference between
the estimated cost and the actual prime cost. The assumption is that as the
latter cost increases, the contractor’s supposed inefficiency will result in a fee
which decreases.
documents before tenders are invited. Adequate time must be allowed for this.
consultants, and it does not generally imply that the contractor has any design
contract.
and cost, they thereby retain total control over the design and quality required.
• The contractor depends heavily upon the necessary information and instructions
from the architect being issued on time. There is a risk of claims if they are
delayed.
14
• The employer decides which specialist firms the contractor is to use, although
• All matters of valuation and payment are the responsibility of the employer’s
consultants.
perfect solution: the fuller and more accurate the information, the nearer to the
Davis et al., (2008) states that with design and construct procurement a contractor
accepts responsibility for some or all of the design. There should be express reference
to this in the contract, and the extent of design liability should always be set out as
clearly as possible. Unless the contract states otherwise, it seems that the liability for
design is an absolute liability under which the contractor warrants fitness for the
purpose intended.
15
Some design and construct forms limit the design liability of the contractor to the
normal professional duty to exercise reasonable care and skill. Independent consultants
engaged by the contractor are therefore under a liability no greater than normal. An
indemnity insurance, and this is something that should be checked before a contractor
is appointed. If the contractor does not have in-house designers, which is often the case,
and the contractor uses external consultants, their identity should be established before
a tender is accepted.
The client’s requirements might be stated briefly and simply, perhaps little more than a
site plan and schedule of accommodation. On the other hand, they may be a document
of several hundred pages with precise specifications. The contractor’s input might be
restricted to taking a scheme design supplied by the client and developing details and
requirement rather than to prescribe in detail, because this leaves the responsibility for
Design and construct methods offer certainty on the contract sum and bring cost
benefits.
The close integration of design and construction methods and the relative freedom of
the contractor to use their purchasing power and market knowledge most effectively
Natasa (2007) stated that the design and construct procurement system is the main
number of the group. The principal variants are novated, direct, competitive, package
deal, develop and construct methods of procurement. With a design and construct
method, it is possible ensure a quicker start on site, and the close integration of design
16
and construction can result in more effective programming. Time, however, is needed
needed to compare and evaluate the schemes from competing tenderers. Once a
A number of variations of design and construct exist, which include (Turner, 1990):
possible competitors may be made before tendering but only one tender is
obtained.
• Competitive – tenders are obtained from documents that are prepared to enable
stage, often referred to as ‘scope design’, then competitive tenders are obtained from a
select list of contractors to develop and complete the design and construct the building.
The amount of consultant design can vary depending on the client’s needs.
• Package deal – this method is often used where the contractors competing will
use a significant part of their own or another proprietary building system or they will be
constructing variations of a repetitive theme. There is limited scope for innovation when
this method is used. Some contractors may offer to find a site, to sell, mortgage
the client.
the contractor takes over from the client a previous contract for the design work,
17
Key points to consider with design and construct procurement
responsibility. The employer therefore has the advantage of only on firm to deal
with – and one firm to blame if things go wrong. In practice, the employer’s
requirements are detailed to the extent that the contractor’s design contribution,
• The employer lacks control over the detailed design; however, this might be
acceptable where broad lines of the scheme are satisfactory and the detail
• Construction work can be started early as a great deal of detailed design can
proceed in parallel. However, it is mainly the contractor who benefits from this
operational flexibility.
• Responsibility for completing on time rests wholly with the contractor. There
should be no risk of claims because of the allegations that information from the
employer is late. This obligation on the contractor to be responsible for the flow
and construct.
responsibility for investigating site and subsoil conditions can be made entirely
the contractor’s. Any changes in the employer’s requirements can affect the
• It is always advisable to ask for information about who the contractor intends
be a requirement.
18
• The employer should be advised to appoint consultants to provide advice on the
• The requirements might include specific items or provisional sums, bit generally
• Benefits can arise from designers and estimators having to work closely together.
The contractor’s awareness of current market conditions and delivery times can
• Building is simple rather than complex is not highly serviced and does not require
technical innovation;
and
• Single organization is required to take responsibility and risk for design and
construction.
The following comments about using novation are provided (Chan, 1996): For a limited
marketplace with insufficient companies who do not have a proven record of designing
and constructing - perceived risk of taking over a design deters many would be
tenderers.
By accepting a novated design companies accept errors and omissions and other
19
potential problems including a design that may potentially prove unworkable. The
the company taking over both design and construction is free to make its own
The architect will no longer supervise quality control or exercise sanction once novation
occurs. This is difficult for many designers, as their reputation is closely associated
with their work, which may be modified in a way that could upset them.
The client looses communication links with the design team once novation occurs.
contracting, construction management and design and manage. There are some subtle
contracting, the contractor has direct contractual links with all the works contractors
is paid a fee to professionally manage, develop a programme and coordinate the design
constructability.
Management contracting
Davis et al., (2008) stated that the client appoints an independent professional team,
as adviser to the team, and during construction they will be responsible for executing
the works using direct works contracts. With this type of contract it is possible to make
20
an early start on-site and achieve early completion. Because of its flexibility, it allows the
client to change the design during construction because drawings and matters of detail
For a management contract to be successful there must be trust and good teamwork
on the part of the client, the design consultants and contractor. The contractor should
preferably be appointed no later than the outline design stage. The contractor can
advise on the design programme, tender action, delivery of materials and goods, and
construction programmes.
The management contractor will normally make a written submission which includes a
proposed management fee, and will be appointed after interviews with the client and the
design team. The fee will include for the total management service, expressed as a
percentage of the total project cost and for a service to cover pre-construction stages
The management contractor undertakes the work on the basis of a contract cost plan
prepared by a quantity surveyor, project drawings, and a project specification. The client
accepts most of the risk because there is no certainty about costs and programme.
Competitive tenders for works packages follow later and they will usually, though not
Construction management
The CIOB report (2010) stated that construction management is not a widely used
procurement method – its main reason for existence is for use on large and/or very
selection process and is paid a management fee. The basic difference is that works
21
direct between the client and works contractor. Although in a sense this gives the client
a greater measure of control, it also means that the client accepts a considerable
amount of risk. The management contractor is simply an agent, and usually cannot
A number of advantages have been identified that can be offered by the CM approach.
• Reduced confrontation between the design teams and the team responsible for
supervising construction;
packaging and splitting the construction activities into more digestible 'chunks';
• Public accountability
contracting. Under a design and manage contract, the contractor is paid a fee and
assumes responsibility, not only for works contractors, but also for the design team.
manages the work, generally for a fee and delivers the project by employing
22
• Consultant – a project designer/manager is the client’s agent, who designs and
manages the work, obtains subcontract tenders from works contractors who then
trust. There is no firm contract price before the work starts on site, and the decision to
• The management contractor is the agent of the client, and should therefore put
their knowledge and expertise are available to the design team throughout the
preconstruction period.
• Much of the detailed design work can be left to proceed in parallel with the site
operations for some work packages, thus reducing the time needed before the project
starts on-site.
• The client has a considerable degree of flexibility on design matters. The design
• The management contractor can select specialists and order materials with long
lead-in times for delivery in good time without any of the uncertainties and
• The project proceeds on the basis of a contract cost plan, but an independent
23
quantity surveyor is required for effective cost control.
• A competitive tendering element is retained for all works contracts, which usually
account for most of the overall prime cost. Tenders for works packages will
Larmour (2011) stated that public private partnership (PPP) procurement method
agreeing mutual objectives, devising a way for resolving any disputes, and committing
pains. Examples include framework agreements and joint ventures. This is a relatively
new form of procurement and although discussed in the Latham report in the 1990‟s,
has taken a long time to come into general use. It is more commonly seen within large
The CIOB report (2010) believes that this method is the “most efficient way of
undertaking all kinds of construction work including new buildings and infrastructure,
commitments showcase the real benefits of the procurement method, although short-
projects.
Under this procurement method, the client lays down a framework for the overall
administration of the project within which he/she has the discretion to use the most
appropriate of all the procurement systems contained within the other three methods.
In PPP procurement method quantity surveyors play an integral role by providing a wide
range of services, which include contractual issues; it also offers quantity surveyors an
24
opportunity to act as independent advisors within the system (Cartlidge, 2002).
The principles of this method include a decision making process, mutual objectives, and
greater understanding of how to accomplish best practice, reduce costs and attain
value for money is achieved. Partnership forms are typically used for high complex
projects. A detailed description of their characteristics and the conditions for using
According to (Stergiou, 2009) large amounts of public funds are expended to purchase
goods and services from the private sector and most of the procedures are conducted
manually, where two risks are eminent i.e. human error, which exceptionally high
considering the numerous processes and movement of documents that stretches over
a long time frame and equally potent risk of corruption during the stages of the
procurement process.
At each stage of the procurement process, there are particular risks involved;
Stage 1 risks
Stage 2 risks
25
c. Lack of access to record procedures
Stage 3 risks
c. There lack of separation of financial duties especially involving the payment process.
The United Nations (2004) article 9(2) provided that a procurement system should
ensure adequate internal control and risk management. The procurement system
should have installed an arrangement of integrated systems that link various functions
such as budgeting and planning, procurement procedures and the contract or project
implementation process
26
CHAPTER THREE
RESEARCH METHODOLOGY
3.1 Introduction
The purpose of this chapter is to address the methods used in this research study.
Items addressed include: - Research approach, research design, research population,
sampling techniques and sampling size, research instrument and measurement and
finally data analysis and presentation.
The approaches which can be used for any research work can either be quantitative,
qualitative or a mixed research method which is further explained below:
Quantitative method
Qualitative method
27
interviews, and participations/observations. The sample size is typically small, and
respondents are selected to fulfill a given quota.
Mixed method
The mixed research method is more specific in that it includes the mixing of
quantitative and qualitative data, methods in a research study or in a set of related stu
dies. In other words, mixed method is a methodology for conducting research that
involves collecting, analyzing and integrating quantitative and qualitative research. The
field of mixed methods has only been using multiple methods, just not calling them
“mixed”. Mixed methods take advantage of using multiple ways to explore a research
problem.
The methodology adopted for the purpose of this research is quantitative research
method since questionnaires will be administered to enable affective data analysis.
Survey design
Data collection
Data analysis
28
Data presentation and results
Research design refers to the overall strategy that you choose to integrate the different
components of the study in a coherent and logical way, thereby, ensuring you will
effectively address the research problem. It constitutes the blueprint for the collection,
measurement, and analysis of data. A research design will typically include how data is
to be collected, what instruments will be employed, how the instruments will be used
and the intended means for analyzing data collected.
3.4Research population
The population in focus here is the Nigeria construction industry, since it will not be
possible to reach out to the entire industry, thus the study will limit itself to clients,
contractors, consultants, professionals and other stakeholders in the industry within
Lagos state. A total population of about 100 professionals is the population of this
research area.
In this research, a random sampling technique was employed and the choice of this
technique is to be able to give equal chance to all in the population under the study. This
will be made possible through the distribution of questionnaires to firms, contractors,
clients and other stakeholders within the Nigeria construction sector.
Since it was not possible to administer questionnaire to all practicing firms in Nigeria, a
total of 80 questionnaires was administered to the randomly selected population size
which included random sample of 15 clients, 15 contractors, 20 quantity surveyors, 15
architects, and 15engineers in those selected construction firms in Lagos state via
29
personal visits and email.
The sample size was obtained using the “TAROYAMAME” formula which implies
N
n=
1+N(e)2
100
n=
1+100(0.0025)
100
n=
1+0.25
100
n=
1.25
n= 80 numbers
N = Population size
The researcher’s instrument can be described as the data collection instrument adopted
in sourcing relevant information about the project topic embarked on by the researcher.
For the efficiency of this research, a well adopted questionnaire is employed for the
project and it is structured as closed-ended in which the question are simply designed
to obtain valuable information from the respondent in order to achieve the aims and
objectives of the research work. The questionnaire is divided into four sections;
30
systems on construction project delivery.
SECTION D: Was used to gather information from respondents in selecting the most
appropriate procurement system for both private and public sector.
Primary and secondary data are collected for the purpose of this study. Primary data
comprises information derived from structured questionnaire administered on the
respondents while secondary data are information derived from textbooks, articles from
journals, magazines, internets which are relevant to the study.
Bar chart was used to determine the general particulars of the respondents in respect of
qualifications, experience, and organization. Frequency was used to analyze the
respondents opinion on the impact of procurement systems of public and private sector
on construction project delivery.
Data for the study was processed and analysed with the aid of the Statistical Packages
for Social Science (SPSS). Data measured on nominal scale were analysed using
descriptive statistics such as frequency distribution and percentages. Mean scores and
standard deviations, as well as inferential statistics will be used to analyse data
measured on ordinal scale.
Mean score = (1n1 + 2n2 + 3n3 + 4n4+ 5n5) / (n1 + n2 + n3 + n4+ n5)
31
CHAPTER FOUR
DATA PRESENTATION AND DISCUSSION OF RESULT
4.1 INTRODUCTION
In any research, data analysis occupies a central position as it gives meaningful
interpretation of the information collected from the field. It is also a way of measuring
the success of the research since it deals with the aims and objectives of the research;
The objectives of this research are
1. Identify the various procurement methods for private and public sectors projects.
32
Category of respondent
Governme 10 12.5 12.5 100.0
nt
Total 80 100.0 100.0
Majority of respondents, about 45% were consultants who at one time or the other has
procured construction projects, 24% were contracting firms, 19% were clients while
respondents from government service represented about 13% of the respondents.
Nature of organization
Frequenc Valid Cumulative
y Percent Percent Percent
Valid Building construction 45 56.3 56.3 56.3
firm
Civil engineering firm 16 20.0 20.0 76.3
33
Nature of organization
Consultancy firm 10 12.5 12.5 88.8
Others 9 11.3 11.3 100.0
Total 80 100.0 100.0
From the above findings based on the organization of respondents. It can be seen that a
high percentage of the respondent were building construction firm 56%, followed by civil
engineering firm 20%, consultancy firm 13%, and others representing just 11%
Educational qualification
Valid
Frequenc Percen Cumulativ
y Percent t e Percent
Valid OND 1 1.3 1.3 1.3
34
Educational qualification
HND 32 40.0 40.0 41.3
BSC 43 53.8 53.8 95.0
MSC 4 5.0 5.0 100.0
Total 80 100.0 100.0
35
Professional Background
Valid
Frequenc Percen Percen Cumulativ
y t t e Percent
Valid Architect 18 22.5 22.5 22.5
Builder 19 23.8 23.8 46.3
civil/structural 17 21.3 21.3 67.5
engineer
Quantity 26 32.5 32.5 100.0
surveyors
Total 80 100.0 100.0
Among the professionals who responded to the questionnaire, 33% were quantity
surveyors, 24% were builders, 23% were architects, while 21% were civil/structural
engineers.
36
Figure 5 showing the professional background of respondents
Professional body
Valid
Frequenc Perce Percen Cumulativ
y nt t e Percent
Valid NIA 12 15.0 15.2 15.2
NIOB 20 25.0 25.3 40.5
NIQS 23 28.7 29.1 69.6
NSE 11 13.8 13.9 83.5
Others 13 16.3 16.5 100.0
Total 79 98.8 100.0
Missin System 1 1.3
g
Total 80 100.0
From the table above, it will be observed that members of the Nigeria institute of
quantity surveyors were 29%, while Nigeria institute of builders were 25%, Nigeria
institute of architect were 15%, a great proportion of about 17% were not attracted to
any professional body , while nigeria society of engineers were 14%.
37
Figure 6 Showing professional qualification/body of respondents
Years of experience
Valid
Frequenc Percen Percen Cumulativ
y t t e Percent
Valid 1-6years 31 38.8 38.8 38.8
6-10years 37 46.3 46.3 85.0
11-15years 10 12.5 12.5 97.5
above 2 2.5 2.5 100.0
20years
Total 80 100.0 100.0
From the above table, 46% respondent had experience of between 6-10 years, 39% had
1- 6 years of experience, and 13% had between 11- 15 years of experience while only 3%
had above 20 years of experience.
38
Figure 7 showing the years of experience
From the table above, it can be deduced that the traditional procurement system has
the highest mean value which implies that it is widely and commonly used, important
and significant followed by design and construct procurement system, public private
partnership procurement system(PPPP) and thenmanagement procurement system.
39
SECTION C ; The impact of procurement methods to project delivery
Statistics
Measurement 80 0 4.49 2 5 4.00 5.00 5.00 5.00
method
Design and
80 0 4.09 2 8 4.00 4.00 5.00 4.00
manage method
From the table above, it can be observed that the order of impact of procurement
methods to project delivery according to their mean value is as follows; lump sum
method, measurement method, develop and construct method, public private
40
partnership method, package deal method, design and manage method, competitive
method, management contracting method, cost reimbursement method, novation
method and construction management method.
SECTION D ; The most appropriate decision criterias in selecting procurement
systems
Descriptive Statistics
Maximu
N Mean Std. Deviation Minimum m
Certainty of 78 4.54 .768 1 5
completion time
Complexity 80 4.34 .615 3 5
Design brief 80 3.71 .889 2 5
Budget limitation 80 3.75 1.025 2 5
Risk Avoidance 80 4.49 .656 3 5
Certainty of price 80 4.13 .891 1 5
Quality level 80 4.13 .753 3 5
Price competition 79 3.66 .861 2 5
Maintenance 79 3.30 1.334 1 5
Requirement
41
Observe Expecte Residua
dN dN l
Average 6 26.7 -20.7 Design brief
High 41 26.7 14.3 Observe Expecte Residua
very 33 26.7 6.3 dN dN l
high Low 7 20.0 -13.0
Total 80 Average 25 20.0 5.0
Risk Avoidance High 32 20.0 12.0
Observe Expecte Residua very 16 20.0 -4.0
dN dN l high
Average 7 26.7 -19.7 Total 80
High 27 26.7 .3
very 46 26.7 19.3 Budget limitation
high Observe Expecte Residua
Total 80 dN dN l
Low 12 20.0 -8.0
Certainty of price Average 18 20.0 -2.0
Observe Expecte Residua High 28 20.0 8.0
dN dN l very 22 20.0 2.0
very low 1 16.0 -15.0 high
Low 1 16.0 -15.0 Total 80
Average 18 16.0 2.0 Quality level
High 27 16.0 11.0 Observe Expecte Residua
very 33 16.0 17.0 dN dN l
high Average 18 26.7 -8.7
Total 80 High 34 26.7 7.3
very 28 26.7 1.3
high
Total 80
42
Price competition
Observe Expecte Residua
dN dN l
Low 7 19.8 -12.8
Average 26 19.8 6.3
High 33 19.8 13.3
very 13 19.8 -6.8
high
Total 79
Maintenance Requirement
Observe Expected
dN N Residual
very low 6 15.8 -9.8
Low 20 15.8 4.2
Average 20 15.8 4.2
High 10 15.8 -5.8
very 23 15.8 7.2
high
Total 79
From the tables above, the opinion and view of respondents shows that the decision
criterias for selecting procurement system is appropriate in the following order;
certainty of completion time, complexity, certainty of price, quality level, maintenance
requirement, budget limitation, design brief and price competition.
4.3 DISCUSSION OF FINDINGS
This research is aimed at examing the impact of various procurement system on
construction project delivery. It is true that no fail safe selection process can be defined
due to large variation in project circumstances and potential risk but the ability to select
certain options may be possible within the consideration of some decision criterias and
43
factors relating to project. This is the reason why one of these research objectives is to
identify and assess the various procurement system in the Nigeria construction industry.
The results from the analyzed questionnaire revealed that various procurement system
mostly used in Nigeria include traditional procurement system, design and construct
procurement system. While public private partnership procurement system and
management procurement system were still of low importance and underutilized in
Nigeria.
An examination of literature revealed that insufficient research had been undertaken on
selecting a procurement system for the building process, this research therefore
attempts to examine the criterias for determining the procurement system suited for
the delivery of a project .
These criterias were analyzed and ranked accordingly in order of their importance and
appropriateness in the Nigeria construction.
Therefore this research work suggests that the most appropriate criterias for selecting
any procurement system in the Nigeria construction industry is as follows; certainty of
completion time, risk avoidance, complexity of the project, certainty of price/cost and
quality level. Other decision criterias like maintenance requirement, budget limitation,
design brief and price competition are of less significance and importance.
44
CHAPTER FIVE
5.1 CONCLUSION
From this comprehensive research carried out to examine the impact of the
procurement system on construction project delivery, the following were revealed;
Traditional procurement system is still the most used and of the greatest impact in
Nigeria despite its problems and shortcomings which include long process and lots of
variations although it had a high level of dissatisfaction from user, they still prefer it to
other system because of its ability to allow professional play the full part and the fact
they are available for contractors to work it.
There is also high level of importance and satisfaction derivable from use of
procurement system like design and construct, public private partnership and then
management procurement system.
Decision criterias for selecting these procurement system in the order of their
importance are as follows; certainty of completion time, complexity, risk avoidance,
certainty of price, quality level, design brief, price competition, budget limitation and
maintenance requirement.
5.2 RECOMMENDATIONS
From the above conclusions it has been drawn out that traditional procurement system
45
is of more use and great impact to construction project delivery both for public and
private sector in Nigeria.
A simple set of criterias has been identified as being generally adequate and sufficient
procurement selection and there is a reasonable consensus on their appropriate ranking
moreover recommendation is made for a more effective procurement system.
There should be greater involvement and interaction between clients, consultants and
design team members during the selection process. Participants in the procurement
process should put aside their own objectives in a holistic manner. This can be
effectively achieved through the use of a project management which acts as a control
mechanism for the client and other participants.
All clients and consultants of the construction industry, whether from the public or the
private sector, should familiarize themselves with various procurement methods as this
will assist them in making well-informed procurement method.
The eventual choice of method should be based on the consideration of project related
factors such as certainty of completion time, complexity, risk avoidance, design brief,
budget limitations as they are of greater influence.
46
REFERENCES
A. Ashworth, and K. Hogg, “Willis's Practice and Procedure for Quantity Surveyor”,
Blackwell Publishing Ltd, Oxford, UK. 2007.
Bacarini, D. (1999). The logical framework method of defining project success. Project
Management. Project Management Journal, 30: 25-32.
Bacarini, D. (1999). The logical framework method of defining project success. Project
Management. Project Management Journal, 30: 25-32.
Chan, A., Chan, D. & Ho, K. (2003) 'An Empirical Study of the Benefits of Construction
Partnering in Hong Kong'. Construction Management and Economics, 21 (5), 523-
533.
Chan, A.P.C., Scott, D., and Lam, E.W.M. (2002), Framework of Success Criteria for
Design/Build Projects, Journal of Construction Engineering and Management,
18(3):120-128
Davis, P., Love, P., Baccarimi, D., (2008). Building Procurement Methods. Report, Project
Affiliates Curtin, University of Technology, Western Australia Department of
Housing & Work, Royal Melbourne Institute of Technology.
Dubois, A. & Gadde, L.-E. (2002) 'The Construction Industry as a Loosely Coupled
System: Implications for Productivity and Innovation'. Construction Management
and Economics, 20 (7), 621-632.
El Wardani, M., (2004). Comparing procurement methods for design-build projects. Ph.D.
thesis, Computer Integrated Construction Research Program, Department of
Architectural Engineering, The Pennsylvania State University, University Park, USA.
Hibberb, P., Merrifield, D., & Taylor, A. (1990). Key factors in constructual Relationship.
London: Royal Institution of Chartered Surveyors.
Holt, G.D., Proverbs, D., and Love, P.E.D. (2000). Survey findings on UK construction
47
procurement: Is it achieving lowest cost, or value? Asia Pacific Building and
Construction Management Journal, 5, pp.13-20.
Kenya: Enhancing democracy in the administration of aid. International law and politics,
829 868.
Larmour (2011). A study of procurement routes and their use in the commercial sector,
PhD thesis, Interdisciplinary Design for the Built Environment.
Latham, M. (1994) Constructing the Team, Department of the Environment, HMSO, UK.
Love, P., Li, H., Irani, Z. & Faniran, O. (2000) 'Total Quality Management and the Learning
Organization: A Dialogue for Change in Construction'. Construction Management
and Economics, 18 (3), 321-331.
Love, P., Skitmore, R., and Earl, G., (1998). Selecting an appropriate procurement method
for the construction process: an empirical study. Construction Management and
Economics, pp. 221-233.
Merrit, F., Loftin, M., & Ricketts, J. (1996). Standard handbook for civil engineer (4th ed.).
NewYork: McGraw Hill.
Mortledge, R., Smith, A., Kashiwagi, D.T. (2006). Building Procurement. Blackwell, Oxford,
UK.
The Chartered Institute of Building (CIOB), (2010). A report exploring procurement in the
construction industry. Understanding procurement methods in practice: An
alternative perspective, UK.
48
Turner, A. (1990). Building Procurement. Macmillan, UK.
QUESTIONNAIRE
NIGERIA.
Dear Respondent,
This questionnaire is intended to be used for gathering information for the research
work on the above topic. It is hoped that you will provide the necessary information. The
information provided will be used purely for the purpose of research and shall be treated
as confidential as possible.
49
Yours faithfully,
ADEYANJU OLUWASEYI DAVID
DEPARTMENT OF QUANTITY SURVEYING
FEDERAL POLYTECHNNIC ILARO
08163426961
Sheyzii18@yahoo.com
SECTION A: GENERAL INFORMATION OF THE RESPONDENT
1. Category of Respondent
50
1 - 6 years ( ) 6 - 10 years ( ) 11 – 15 years ( ) 16 – 20 years ( )
Above 20 years ( )
Use the following scale of 1-5 for the question in this section:
Please rate the following procurement system in order of their importance based on
your experience.
PROCUREMENT SYSTEM
5 4 3 2 1
Traditional Procurement
Management procurement
Use the following scale of 1-5 for the question in this section:
Please rate the following procurement methods in order of the impact to project
delivery to your sector.
PROCUREMENT METHODS
51
5 4 3 2 1
Measurement method
Competitive method
Novation method
Use the following scale of 1-5 for the question in this section:
Please rate the following procurement system selection criteria in order of their
appropriateness based on your experience.
SELECTION CRITERIAS
5 4 3 2 1
Complexity
Design Brief
Budget limitation
Risk Avoidance
Certainty of price
52
Quality level
Price competition
Maintenance Requirement
53