You are on page 1of 33

Value Stream PRODUCTIVITY

Mapping ACADEMY
16 Maret 2022

PRODUCTIVITY ACADEMY www.prodemyasia.com 1

Outline
Outline
Lean Thinking

Waste in Manufacture

Step-step VSM

Mapping Current State

Analyze and Future State


PRODUCTIVITY ACADEMY www.prodemyasia.com 2

1
Lean Thinking
The Relentless Elimination of Waste

PRODUCTIVITY ACADEMY www.prodemyasia.com 3


v

What is Lean ?

44

2
adalah metode sistematis guna
[Definisi] memperpendek waktu
antara order konsumen sampai dengan
Lean produk dikerjakan / dikirimkan melalui

Manufacturing penurunan sumber


pemborosan / waste
dan memberikan
nilai tambah / value

PRODUCTIVITY ACADEMY www.prodemyasia.com 5

Lean Manufacturing

Business as Usual
WASTE PRODUK
ORDER KONSUMEN
DIBUAT & DIKIRIM

Time

Lean Manufacturing

PPRODUK
ORDER KONSUMEN
DIBUAT & DIKIRIM

Time (Shorter)

66

3
Lean Thinking

Lean thinking can be summarised into five principles :

• Specify Value of specific product


• Identify Value stream for each product
• Make Value Flow without interruption
• Let the customer Pull value from the producer
• Pursue Perfection

PRODUCTIVITY ACADEMY 7
www.prodemyasia.com 7

What is Value…?
Benefit
Value =
Cost

As perceived by the Customer

8
PRODUCTIVITY ACADEMY www.prodemyasia.com 8

4
The Value Stream

Mine Reduction
Mill Smelter
Hot
Roller
Cold
Can Roller Remelter
Can Maker
Warehouse Recycle
Centre
Bottle Tesco Tesco
Bottler Home
Warehouse Warehouse Store
Value stream for Cola Cans (Lean Thinking: Womack & Jones 1996)

PRODUCTIVITY ACADEMY www.prodemyasia.com 9

Value Stream of a Cola Can


Processing time 3 hours
Storage and transportation time 11 months
Cumulative scrap 24%
(Lean Thinking: Womack & Jones, 1996)

And this is a highly developed value stream


operated by blue chip companies !

PRODUCTIVITY ACADEMY www.prodemyasia.com 10

5
Waste in Manufacture

• ” Understanding & identifying waste is the first step to reducing or


eliminating waste”

PRODUCTIVITY ACADEMY www.prodemyasia.com 11

Two Elements to Every Job

Value Adding Non-Value Adding

Valuable Effort Valueless Obvious


Effort Waste

Costs Time Costs Time


Costs Money Costs Money
Adds Value Adds No Value

VALUABLE WASTE

Where do we draw the line between Waste & Non-waste elements?

PRODUCTIVITY ACADEMY www.prodemyasia.com 12

6
Rough Guide to Waste

TOYOTA defines Waste as:


"anything other than the minimum amount of equipment, materials,
parts, and working time absolutely essential to production."

The Rough Guide to Waste is:


“Only an activity that physically changes the shape or character of a product or
assembly can add value”

Therefore: Any activity that does not change the product or assembly is waste

PRODUCTIVITY ACADEMY www.prodemyasia.com 13

Definition of Waste

✓Effort frequently does not result in changing the shape or character


of a product or assembly
• eg. moving, counting, expediting, setups, inspecting, etc

✓Changing shape or character of a product or assembly


does not necessarily add value
• eg. machining, plating, assembly, painting, heat treating, etc

✓The more waste you can see, the more you can eliminate
• If you accept activities as waste, you may devise methods to eliminate them.
YOU choose whether to tolerate the waste!

PRODUCTIVITY ACADEMY www.prodemyasia.com 14

7
PRODUCTIVITY ACADEMY www.prodemyasia.com 15

Identifikasi Waste / MUDA

PRODUCTIVITY ACADEMY www.prodemyasia.com 16

8
Value Stream Mapping
” Mapping area of waste to be eliminated ”

PRODUCTIVITY ACADEMY www.prodemyasia.com 17

Why Map ?

• Visualise individual value streams


• Uses a selection of tools to review a value stream
• Cross functional involvement & decision making
• Understand what wastes exist & where
• Enables the development of improvement plans

PRODUCTIVITY ACADEMY www.prodemyasia.com 18

9
Mapping Process
vs Value Stream Mapping?

Process Mapping Value Stream Mapping


• Internally focussed • Customer focussed
• Identifies process sequence • Identifies areas of waste
• Passive documentation • Improvement oriented

PRODUCTIVITY ACADEMY 19
www.prodemyasia.com 19

“Learning to See” Value Stream


• An approach to visualise Material and Information flows in a key
Business Process.

• All the actions required to bring a product,


• door-to-door, from raw material to the customer.

PRODUCTIVITY ACADEMY www.prodemyasia.com 20

10
21
PRODUCTIVITY ACADEMY www.prodemyasia.com

Information Flow

Material Flow

Lead Time
Timeline VA , NVA
22
PRODUCTIVITY ACADEMY www.prodemyasia.com

11
Map Layout Geography

Supplier Production Control Customer


Info. Info. Info.

Process Flow Information

Time Line

PRODUCTIVITY ACADEMY www.prodemyasia.com 23

Value Stream Mapping Steps


product family

current-state
drawing
future-state
drawing
work plan
PRODUCTIVITY ACADEMY www.prodemyasia.com 24

12
Product Family
A group of products that passes through common processing steps
and over common equipment in your downstream processes.

1 Process
3

Process Process Process


2 1 2 4 Process
5
Process
6
3

PRODUCTIVITY ACADEMY www.prodemyasia.com 25

current-state drawing
ACME Stamping Factory Layout
PRESS DEPT.
Weld II Weld I SHIPPING
200 T WELDING DEPT.
Press
Finished
Goods
Welding Storage
Inspection Welded Parts Storage
Area

Assembly I Assembly II FINAL


Stamped Parts I
Steel Coil N
Storage Storage S
P
E
ASSEMBLY DEPT. C
T
I
O
N

= WIP in Baskets = Finished Goods in Trays

PRODUCTIVITY ACADEMY www.prodemyasia.com 26

13
ACME Stamping Material Flow
1. Supplier
2.
3.
Stamping
Spot-welding Workstation #1
Door to Door
4. Spot-welding Workstation #2
5. Assembly Workstation #1 Where should we start?
6. Assembly Workstation #2
7. Shipping
8. Customer

PRODUCTIVITY ACADEMY www.prodemyasia.com 27

Value Stream Mapping Tips


• Always collect information whilst walking the pathways
• Start with quick door-to-door overview
• Begin at shipping point and work upstream
• Do your own timings and inventory counts
• (avoid “system” figures)
• Do the whole stream yourself
• Use pencil and paper - en route
• Resist the PC

PRODUCTIVITY ACADEMY www.prodemyasia.com 28

14
What data should be collected?
Customer & Shipping, Supplier Process / Production
• Company Name • Number of product variations (P/N’s)
• Quantity order per month • Machine(s) used
• Working days, shift • C/T (cycle time)
• Quantity delivery per day • C/O (changeover time)
• Frequency of delivery/trucking • Uptime (on-demand machine time)
• Order information, forecast • EPE (production sequence time)
• Number of operators (dedicated)
• Pack size
• Working time (minus breaks)
• Scrap rate
• Inventory Before and after

PRODUCTIVITY ACADEMY www.prodemyasia.com 29

Current State Map


Michigan State Street
Steel Co. Assembly

500 ft. coils This is the 18,400 pcs/mo


- 12,000 LH
- 6,400 RH
Tray = 20 pcs

Material Flow 2 shifts


920 pcs/day

Tues. +
Thurs. IN OUT 1x
Daily

Door Door
STAMPING
STAMPING I S. WELD #1 I S. WELD #2 ASSEMBLY #1
I
ASSEMBLY #2 SHIPPING
I I I
Coils 200 T 4600 L 1100 L 1600 L 1200 L Staging
5 days 2400 R 1 600 R 1 850 R 1 640 R 1

C/T = 1 seconds C/T = 39 seconds C/T = 46 seconds C/T = 62 seconds C/T = 40 seconds
C/O = 1 hour C/O = 10 minutes C/O = 10 minutes C/O = 0 C/O = 0
Uptime = 85% Uptime = 100% Uptime = 80% Uptime = 100% Uptime = 100%
27,600 sec./shift 2 Shifts 2 Shifts 2 Shifts 2 Shifts
EPE = 2 weeks 27,600 sec/shift 27,600 sec/shift 27,600 sec/shift 27,600 sec/shift

Door to Door Value Stream


PRODUCTIVITY ACADEMY www.prodemyasia.com 30

15
Add Information Flow
Acme Production Control: Icons:
• 30/60/90 day forecasts from customer PRODUCTION
• Daily firm order CONTROL
• Weekly MRP generation
MRP
• 6 week forecast to supplier
• Weekly supplier releases Daily
• Weekly build schedules Order
• Daily shipping schedule
Weekly
Schedule

PRODUCTIVITY ACADEMY www.prodemyasia.com 31

Current State Map


30/60/90 day
6-week
PRODUCTION Forecasts
Forecasts State Street
Michigan CONTROL
Steel Co. Assembly
Daily
Weekly 18,400 pcs/mo
MRP Order
500 ft. coils Release - 12,000 LH
- 6,400 RH
Tray = 20 pcs
2 shifts
Weekly Schedule
920 pcs/day

Daily Ship
Tues. + Schedule
1x
Thurs.
Daily

STAMPING
STAMPING I S. WELD #1 I S. WELD #2 ASSEMBLY #1 ASSEMBLY #2 SHIPPING
I I I I
Coils 200 T 4600 L 1100 L 1600 L 1200 L Staging
5 days 2400 R 1 600 R 1 850 R 640 R 1
1

C/T = 1 seconds C/T


C/T = 39 seconds C/T = 46 seconds C/T = 62 seconds C/T = 40 seconds
C/O = 1 hour C/O = 10 minutes C/O = 10 minutes C/O = 0 C/O = 0
Uptime = 85% Uptime = 100% Uptime = 80% Uptime = 100% Uptime = 100%
27,600 sec./shift 2 Shifts 2 Shifts 2 Shifts 2 Shifts
EPE = 2 weeks 27,600 sec/shift 27,600 sec/shift 27,600 sec/shift 27,600 sec/shift

PRODUCTIVITY ACADEMY www.prodemyasia.com 32

16
Add The Time Line
• Process lead-time is the Cycle Times (Value Added Time) for all of the
operations in the process.

• Inventory lead-time is the time it takes to work through the queues of


stock throughout the Value Stream.

Amount on Hand
Inventory Days =
Daily Customer Need

PRODUCTIVITY ACADEMY www.prodemyasia.com 33

Current State Map


30/60/90 day State Street
6-week PRODUCTION
Forecasts Assembly
Forecasts CONTROL
Michigan
Steel Co. Daily 18,400 pcs/mo
Weekly MRP - 12,000 LH
Order
Release - 6,400 RH
500 ft. coils
Tray = 20 pcs
2 shifts
Weekly Schedule 920 pcs/day

1x
Daily Ship
Daily
Tues. + Schedule
Thurs.

ASSEMBLY #1 SHIPPING
STAMPING
STAMPING
I
S. WELD #1
I
S. WELD #2
I I
ASSEMBLY #2
I
I Staging
Coils 200 T
1 1 1 1200 L 1
5 days 4600 L 1100 L 1600 L 640 R
2400 R 600 R 850 R
C/T = 1 seconds C/T = 39 seconds C/T = 46 seconds C/T = 62 seconds C/T = 40 seconds
C/O = 1 hour C/O = 10 minutes C/O = 10 minutes C/O = 0 C/O = 0
Uptime = 85% Uptime = 100% Uptime = 80% Uptime = 100% Uptime = 100%
27,600 sec./shift 2 Shifts 2 Shifts 2 Shifts 2 Shifts Production 23.6
EPE = 2 weeks 27,600 sec/shift 27,600 sec/shift 27,600 sec/shift 27,600 sec/shift =
Leadtime days
5 days 7.6 days 1.8 days 2.7 days 2 days 4.5 days
1 second 39 sec. 46 sec. 62 sec. 40 sec. Value
Added = 188 sec.
Time

PRODUCTIVITY ACADEMY www.prodemyasia.com 34

17
Identify Opportunities
• The Current State Map shows what is happening “right now.”
• It identifies wasteful steps and bottlenecks.
• It helps visualize how operations can be combined to “flow”.
• It lets you see where “pull” systems are needed
• It shows how the improvements impact the value stream.

PRODUCTIVITY ACADEMY www.prodemyasia.com 35

Current State Map


6-week 30/60/90 day
PRODUCTION
Forecasts Forecasts State Street
Michigan CONTROL
Assembly
Steel Co.
Weekly Daily 18,400 pcs/mo
Release MRP Order
500 ft. coils - 12,000 LH
- 6,400 RH
Tray = 20 pcs
Weekly Schedule 2 shifts
920 pcs/day

Daily Ship 1x
Tues. + Schedule

“flow” cell
Daily
Thurs.

pull pull
pull
STAMPING
STAMPING I I
S. WELD #2 ASSEMBLY #1
I
ASSEMBLY #2
I S. WELD #1
I SHIPPING

Coils 200 T 4600 L Staging


5 days 2400 R 1100 L
600 R
1 1600 L
850 R
1 1200 L
640 R
1
I

C/T = 1 seconds 1 = 39 seconds


C/T C/T = 46 seconds C/T = 62 seconds C/T = 40 seconds
C/O = 1 hour C/O = 10 minutes C/O = 10 minutes C/O = 0 C/O = 0
Uptime = 85% Uptime = 100% Uptime = 80% Uptime = 100% Uptime = 100%
27,600 sec./shift 2 Shifts 2 Shifts 2 Shifts 2 Shifts Production 23.6
EPE = 2 weeks 27,600 sec/shift 27,600 sec/shift 27,600 sec/shift 27,600 sec/shift
Leadtime = days
5 days
7.6 days 1.8 days 2.7 days 2 days
4.5 days Value
1 second 39 sec. 46 sec. 62 sec. 40 sec. Added = 188 sec.
Time

PRODUCTIVITY ACADEMY www.prodemyasia.com 36

18
Push vs Pull Control Systems
MRP/
Push System
Planning
System
Make to the plan/schedule
Work-To-Lists
Work-centres are independent

X Y Z Problems are hidden


eg rejects, absence, breakdowns

Information Poor linkages and communication


Material

PRODUCTIVITY ACADEMY www.prodemyasia.com 37

Push vs Pull Control Systems


Pull System = Kanban MRP/
Planning
Make to the customer demand System
Final
Work-centres are linked together Assembly
Schedule
Request
Tight linkages and close communication
Smokes out problems and issues X Y Z

Can require less inventory, giving shorter


lead-time Information
Material

PRODUCTIVITY ACADEMY www.prodemyasia.com 38

19
Kanban : A Simple Real Example
Burger
Kitchen Regulator Tills Customer

As one type of burger is consumed . . .


They are removed from the regulator . . .
And then replenished by the kitchen . . .
Not made to a forecast and pushed at the customer

PRODUCTIVITY ACADEMY www.prodemyasia.com 39

Value Stream Mapping


“Learning to See” Your Future State

PRODUCTIVITY ACADEMY www.prodemyasia.com 40

20
Future State Questions
1. Desired cycle time (Takt time)?
Demand
2. Built to a FG supermarket or direct ship ?

3. Where can we use continuous flow?


Material Flow
4. Where to use supermarket pull systems?

5. Where is “pacemaker” process?


Information Flow 6. How will you level product mix?
7. What is the increment of work to release?
Improvements 8. What must you improve to make it happen

PRODUCTIVITY ACADEMY www.prodemyasia.com 41

Future State Question #1


•What is the takt time (desired cycle time), based on the available
working time of the downstream processes that are closest to the
customer?

PRODUCTIVITY ACADEMY www.prodemyasia.com 42

21
What is Takt Time ?

Time Available (hours)


Takt Time =
Customer Demand (units)

i.e., 20 units needed today =


8 hours / 20 units = 0.4 Hours or 24 minutes

PRODUCTIVITY ACADEMY www.prodemyasia.com 43

Required Output Rate

Takt time provides the drumbeat to


ensure that output rate meets demand,
ie, 1 finished product off the line with
each beat

PRODUCTIVITY ACADEMY www.prodemyasia.com 44

22
Allocation of Resources
Required Takt time = 2.4 min

Lead-time = 1min Lead-time = 1.25min


with 5 operators with 4 operators

Lead-time = 1.7min Lead-time = 2.5


with 3 operators Source: Suzaki 1987 with 2 operators

PRODUCTIVITY ACADEMY www.prodemyasia.com 45

Future State Question #2

• Will you build to a finished goods supermarket, from which the


customer pulls, or build directly to shipping?

PRODUCTIVITY ACADEMY www.prodemyasia.com 46

23
Direct Ship or Supermarket?
Use direct ship when continuous flow, mixed model production can be
done. Withdrawal
Card Customer
Requirement

ASSEMBLY SHIPPING

Customer Schedules Assembly


PRODUCTIVITY ACADEMY www.prodemyasia.com 47

Direct Ship or Supermarket?

PRODUCTIVITY ACADEMY www.prodemyasia.com 48

24
Future State Question #3

• Where can you use continuous flow processing?

PRODUCTIVITY ACADEMY www.prodemyasia.com 49

Where Can Continuous Flow Be Applied ?

• Find the value added operations that can be combined.


• Justify equipment based on cycle time and takt time.
• Balance and improve the flow.

PRODUCTIVITY ACADEMY www.prodemyasia.com 50

25
Continuous Flow
Current Cycle Times: After Improvement:
62s.
60 56s. 56s. 56s.
45s.

ASSEMBLE
39s. 40s.
40

ASSEMBLE
ASSEMBLE 1

ASSEMB. 2

WELD
WELD 1

WELD 2

20

WELD
1s.
0 1 1 1 1 1 1 1 1
= 1 + 39 + 45 + 62 + 40 = 186 – improvement
= 187 / 60 = 3.12 Ops = 168 / 60 = 2.8 Ops
PRODUCTIVITY ACADEMY www.prodemyasia.com 51

Future State Question #4

• Where will you need to use supermarket pull systems in order to


control production of upstream processes?

PRODUCTIVITY ACADEMY www.prodemyasia.com 52

26
Where Can Supermarkets Be Placed?
Use production supermarkets when batching is necessary due to:
• Short cycle times in lead-off operations
• Multiple customer cells
• Long setup times
• Long or unreliable processes
• Distant outside supply

PRODUCTIVITY ACADEMY www.prodemyasia.com 53

Future State Question #5

• At what single point (the “pacemaker process”) in the production


chain will you schedule production?

PRODUCTIVITY ACADEMY www.prodemyasia.com 54

27
Where is the Pacemaker?
• The pacemaker process is the only one in the value stream that you
schedule.

• It sets the pace for and pulls from the upstream processes.

• Its output flows through the rest of the downstream processes.

PRODUCTIVITY ACADEMY www.prodemyasia.com 55

Selecting the Pacemaker

PRODUCTIVITY ACADEMY www.prodemyasia.com 56

28
Future State Question #6

• How will you level the production mix at the pacemaker process?

PRODUCTIVITY ACADEMY www.prodemyasia.com 57

How to Level Product Mix?


• Leveling the product mix is distributing the production of all the
products made at the pacemaker evenly over the shortest possible
time period, leading to:
• Faster customer response
• Shorter lead times
• Less supermarket inventory
• No peaks or valleys
• Less expediting
• Fewer rejects

PRODUCTIVITY ACADEMY www.prodemyasia.com 58

29
Production Mix

Normal batch scheduling would be:


1st shift 2nd Shift
LLLLLLLLLLLLLLLLLLLLLLLLLLLLLLRRRRRRRRRRRRRRRR

Level (uniform) schedule would be:


1st shift 2nd Shift
RLLRLLRLLRLLRLLRLLRLLRLLRLLRLLRLLRLLRLLRLLRLLR

Leveling Icon is: OXOX

PRODUCTIVITY ACADEMY www.prodemyasia.com 59

Future State Map

PRODUCTIVITY ACADEMY www.prodemyasia.com 60

30
Achieving the Future State

1. Breaking Implementation into Steps:

• The Pacemaker Loop

• Additional Loops upstream of the Pacemaker Loop

• You can circle these loops on your future-state map, to help you see the flow segments
that make up your value stream.

• Identify objectives and goals.

PRODUCTIVITY ACADEMY www.prodemyasia.com 61

Achieving the Future State

2. The Value Stream Plan

• Exactly what is the plan, step-by-step


• Measurable goals
• Clear checkpoints with real deadlines and named reviewer(s)

PRODUCTIVITY ACADEMY www.prodemyasia.com 62

31
Achieving the Future State

3. Value Stream Improvement is Management’s Responsibility

PRODUCTIVITY ACADEMY www.prodemyasia.com 63

Future State Map

6-week 30/60/90 day


PRODUCTION Forecasts
Michigan Forecasts State Street
CONTROL

BP #3
Steel Co. Assembly
Daily
Daily
500 ft. coils Order 18,400 pcs/mo
Order - 12,000 LH

coil Loop
- 6,400 RH
Tray = 20 pcs
2 shifts
coil Daily Order
coil

Daily 1x
Milk Run Daily

OXOX 20
batch 20
20
tote
BP #1
Loop
Coils
STAMPING WELD + ASSY.
L Pull SHIPPING

R
200 T Staging

BP #2
EPE = 1 shift
Takt = 60 sec.

Loop
C/O = < 10 min.
C/O = 0
(at the Uptime = 100%
press) 2 Shifts
Total work content
-
Production
1.5 days 1 day
< 168 sec.
2 days leadtime = 4.5 days
1 sec, 168 sec. Value
Added Time = 169 sec.

PRODUCTIVITY ACADEMY www.prodemyasia.com 64

32
Thank You
PRODUCTIVITY ACADEMY

: prodemy.global@gmail.com
: 082112235378
: Productivity Academy (PRODEMY)
: @prodemyasia

: www.prodemyasia.com

PRODUCTIVITY ACADEMY www.prodemyasia.com 65

NEXT
EVENT

Untuk mendaftar
Silahkan di klik
https://lynk.id/prodemy.asia

PRODUCTIVITY ACADEMY www.prodemyasia.com 66

33

You might also like